Engineers have led the way on project management, it is now “hot and trendy”.
#1 Area of Continuing Education reported by Penn State Behrend ECE alumni.
Penn State Behrend School of Engineering Survey 2003 of Fortune 500 companies- #1 required skill for new engineers = PROJECT MANAGEMENT SKILLS
2
![Page 3: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/3.jpg)
To complete the projectOn-timeWithin budgetSo that it meets the requirements
3
![Page 4: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/4.jpg)
Work Breakdown Structure (WBS) - An ordered set of activities required to complete the project - first step in project planning
Activity - A combination of a task and its associated deliverables
5
![Page 5: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/5.jpg)
Tasks - actions that accomplish a job
Deliverables - entities that are delivered to the project upon completion of tasks - circuit design, software module,
integration and test of modules, report, presentation, approval
6
![Page 6: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/6.jpg)
From MIL-HDBK 881 A product-oriented family tree composed of
hardware, software, services, data, and facilities. The family tree results from systems engineering efforts.
A WBS displays and defines the product, or products, to be developed and/or produced. It relates the elements of work to be accomplished to each other and to the end product.
A WBS can be expressed down to any level of interest. However the top three levels are as far as any program or contract need go unless … .
7
![Page 7: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/7.jpg)
The system must Measure temperature between 0 and 200C. Have an accuracy of 0.4% of full scale. Display the temperature digitally, including one
digit beyond the decimal point. Be powered by a standard 120V 60Hz AC outlet. Use an RTD (thermal resistive device) that has an
accuracy of 0.55C over the range. The resistance of the RTD varies linearly with temperature from 100Ω at 0C to 178Ω at 200C.
8
![Page 8: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/8.jpg)
9
Digital Thermometer
AmbientTemperature
Power,120 VAC
DigitalTemperature
Display
![Page 9: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/9.jpg)
Module Digital Thermometer
Inputs - Ambient temperature: 0-200C.- Power: 120V AC power.
Outputs - Digital temperature display: A four digit display, including one digit beyond the decimal point.
Functionality
Displays temperature on digital readout with an accuracy of 0.4% of full scale.
10
![Page 10: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/10.jpg)
Problem: Create the WBS for a temperature monitoring system design
11
b0
bN-1
b1...
TemperatureConversion Unit
Power Supply
VTAmbient
Temperature
Power,120 VAC
Binary CodedDecimal (BCD)
Conversion Unit
7-Segment LEDDriver
BCD2
+/- x V DC
BCD3
BCD1
BCD0
,
Analog to DigitalConverter
![Page 11: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/11.jpg)
There are three main tasks1. The analog interface circuitry.2. The LED & digital circuitry.3. Integrate & Test.
12
![Page 12: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/12.jpg)
Activity: Design Circuitry Description: Complete the detailed
design and verify it. Deliverables/Checkpoints: 1) Circuit
schematic, and 2) Verify in simulation. Duration: 14 days. People: Jana (1), Rob (1) Resources: PC, SPICE Simulator Predecessors: none
13
![Page 13: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/13.jpg)
ID Activity Description Deliverables / Checkpoints
Duration (days)
People Resources Predecessors
1 Interface Circuitry
1.1 Design Circuitry Complete the detailed design and verify it in simulation.
Circuit schematic Simulation verification
14 Rob (1)Jana (1)
PC SPICE simulator
1.2 Purchase Components
Identify parts Place order Receive parts
10 Rob 1.1
1.3 Construct & Test Circuits
Build and test.
1.3.1
Current Driver Circuitry
Test of circuit with sensing device.
Test data Measurement of linearity
2 Jana (1)Rob (2)
Test bench Thermo- meter
1.2
1.3.2
Level Offset & Gain Circuitry
Test of circuit with voltage inputs.
Test data Measurement of linearity
3 Rob (1)Jana (2)
Test bench
1.2
1.3.3
Integrate Components
Integrate the current driver and offset circuits.
Test data verifying functionality and linearity requirement
5 Rob (1)Jana (1)
Test bench Thermo- meter
1.3.11.3.2
14
![Page 14: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/14.jpg)
PERT: Project Evaluation and Review Technique
Statistical methods to estimate project completion time.
Based on earlier studies that show that project task completion follows a Beta probability distribution.
15
6
4 bmae
tttt
![Page 15: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/15.jpg)
- a directed graph representation of the activities and dependencies between them for a project - allows for graphical visualization & quantitative analysis of a project - Use activity-on-node (AON) structure activities represented by nodes dependencies by arrows
We will use AON (Activity on Node)
16
![Page 16: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/16.jpg)
1
2
3
17
1 2
1 3
42
![Page 17: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/17.jpg)
Problem: identify the paths to completion.
18
start end
114d
28d
314d
46d
512d
![Page 18: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/18.jpg)
19
ID
Task Name Start Finish DurationJan 2005 Feb 2005
1/16 1/23 1/30 2/6 2/13 2/20 2/27
1 32d2/22/20051/10/20051: Interface Circuitry
2 14d1/27/20051/10/20051.1: Design Circuitry
3 10d2/10/20051/28/20051.2: Purchase Components
4 8d2/22/20052/11/20051.3: Construct & Test Circuits
5 2d2/14/20052/11/20051.3.1: Current Driver Circuitry
6 3d2/15/20052/11/20051.3.2: Level Offset & Gain Circuitry
7 5d2/22/20052/16/20051.3.3: Integrate Components
8 23d2/9/20051/10/20052: LED & Driver Circuitry
9 1d1/10/20051/10/20052.1 Research A/D Converters
10
7d1/19/20051/11/20052.2 Complete Hardware Design
11
10d2/2/20051/20/20052.3 Purchase LED & Driver Components
12
5d2/9/20052/3/20052.4: Construct & Test
13
7d3/3/20052/23/20053: System Integration & Test
![Page 19: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/19.jpg)
How do you complete projects within cost? Need to be able to estimate costs for
System design
Development
Manufacture
Basics presented here – complex problem that requires experience.
20
![Page 20: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/20.jpg)
Take the initial time estimates for activities and double them!
Assign a lot of time for testing and integration.
Factor in lead times for part ordering. Assign a project manager(s). Do not assign all team members to all
tasks. Track the progress versus the plan. Don’t become a slave to the plan. Experience counts.
21
![Page 21: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/21.jpg)
A Project Plan should contain Work Breakdown Structure. Identify the
activities, deliverables, responsibilities, duration, resources, and dependencies.
Gantt Chart and/or Network Diagram. Provide a graphical representation of the project plan.
Costs. Develop a tabulated list of costs and for the equipment, materials, and labor necessary to carry out the project.
22
![Page 22: Engineers have led the way on project management, it is now “hot and trendy”. #1 Area of Continuing Education reported by Penn State Behrend ECE alumni](https://reader036.vdocument.in/reader036/viewer/2022081603/56649e175503460f94b027c2/html5/thumbnails/22.jpg)
Three important objectives of project management are to complete the project On-time
Within budget
To meet the needs of the user. WBS – hierarchical breakdown of activities needed to
complete a project. Network diagram – graphical representation of
activities for project – can use for quantitative analysis of project.
Cost estimates Break-even analysis
Cost estimation models
23