© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Surviving and Thriving in Turbulent Times Through Effective Project
Management
Presentation slides will be available at: TBD
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Takeaways
• Key Aspects of Effective Project Management
• Processes and Tools that can help in these challenging times
• Pathway to a successful Project Management Culture
2
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Latest Standish Group Study
• 53% of all projects are challenged (late, over budget and less than required features and functions)
• 29% Succeed• 18% Fail
Standish Group, Chaos Report 2005
3
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Project Success Factors1. User Involvement2. Executive Management Support3. Clear Business Objectives4. Optimizing Scope and
Requirements5. Experienced Project Manager6. Iterative and Agile Process7. Financial Management8. Skilled Resources9. Formal Methodology10.Standard Tools and
InfrastructuresStandish Group, Chaos Report 2005
4
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Current Economic Climate
• Limited Resources• Limited Budgets• High Stress Environments• Project failures are not an
option
5
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Today’s Agenda
• Current Situation• How can effective project
management help?• How can you as a project
management proponent provide valuable solutions?
• Q & A
6
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
What’s your specific pain ?
• People not aligned with the business strategy
• Organization loosing its competitive advantage
• Not delivering what the business needs
• Inefficient use of resources• Projects costing more than planned• Time to completion not acceptable
7
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
So, many executives and middle level managers might say: “Project management, what’s the big deal ?”
8
It’s just common sense, isn’t it ?You are either born with it or you are not…simple as that !Isn’t it just about making up a good “to do” listIsn’t good Project Software all we need ?Whadda ya mean there are best practices…just get the job done !You mean project management is a competency, a skill and can be learned ?
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
So tell me more
• There are 3 fundamental aspects to every project: A. What are we suppose to deliver, B. How much it will cost, and C. How long will it take ?
• Well…sounds simple enough, so let’s take a look
9
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
It sounds simple enough, but the big
deal is
you drop one and you loose !
Cost
10
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Project Management is about:
• The ability to plan effectively• gather requirements• negotiate with stakeholders• develop time lines & costs• determine resource
requirements
• Execute the plan• developing the team• define and manage risks• manage people
11
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
it’s about (cont’d)
• Monitoring & Controlling the Plan• Insuring quality (meeting
requirements)• effectively managing changes• reviewing progress with stakeholders• knowing when to modify the plan• looking for variance: (plan – actual),
and taking action to get back on track
12
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
In Summary, PM is About
• Consistent, Repeatable Processes
• Good Tools and Techniques• Motivating People, Creating
High Performing Teams
13
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Why is PM Importantand what it can do for you
• Deliver projects On time & within budget (delivering what you say you will deliver)
• More efficient use of people and resources (developing high performing teams)
• Better estimation of time and cost• How to deal with changes• Effectively manage unexpected events (managing risks)• Satisfied stakeholders• Creating a historical data base to track
accomplishments and improve future projects (creating organizational wisdom through a Lessons Learned data bases)
14
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
PMI’s Key Publication
• “A Guide to the Project Management Body of Knowledge” (PMBOK Guide)
• The purpose of the PMBOK Guide is to identify and describe that subset of Project Management Knowledge which is generally accepted.
• It outlines effective processes, tools and techniques
15
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
PMBOK’s 9 Knowledge Areas
16
Integration
Time Cost
Comm Risk ProcureH.R.Quality
Scope
• Umbrella– Integration
• Facilitating Processes– Quality - Risk– Human Resources - Procurement– Communication
• Core Processes– Scope– Time– Cost
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
PMBOK’s 9 Knowledge Areas
• Core Processes– Scope– Time– Cost
Integration
Time Cost
Comm Risk ProcureH.R.Quality
Scope
17
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Scope
Integration
Time Cost
Comm Risk ProcureH.R.Quality
Scope
Ensure that the project includes all the work required, and only the
work required, to complete the project successfully.
18
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Integration
Time Cost
Comm Risk ProcureH.R.Quality
ScopeTime
The processes required to ensure timely completion of the project.
19
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Integration
Time Cost
Comm Risk ProcureH.R.Quality
ScopeCost
Ensure that the project is completed within the approved budget.
20
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Triple Constraint
21
Tim
e
Scope(deliverables)
Cost
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Improving Your Project Management
• Project Management is a set of skills
• Project Management skills include both
science and art - hard and soft
• Project Management skills can be assessed
- Fissure PM Capability Assessment
• Project Management skills can be learned
-through training and mentoring22
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Key Project Management Documents & Tools
23
Project CharterScope StatementWork Breakdown StructureNetwork DiagramCritical PathBar ChartRisk RegisterChange Control PlanQuality PlanResource PlanProcurement Plan
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Project Charter
• Written document containing the “contract terms” between the sponsor and the project manager.
• Provides the background, objective, and general boundaries for the project.
• Ensures scope and expected outcomes are understood by both parties.
• Should be concise.• Also called - Project Definition, Statement of
Work (SOW) or Preliminary Scope Statement.
24
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Work Breakdown Structure (WBS)
Top
1.0 2.0 3.0
1.1 1.2 1.3 1.4
1.3.1 1.3.2
1.0 ................ 1.1 ............ 1.2 ............ 1.3 ............ 1.3.1 ........ 1.3.2 ........ 1.4 ..............
2.0 ...............
3.0 ................
Level 1
Level 2
Level 3
WBS Graphical Form
WBSOutlineForm
CollectorTask
Executable Task (Work Package)
Project
25
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Using the Network Diagram
NetworkDiagram
26
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Time
2 4 6 8 10 12 14
Task
Num
ber
1.0
2.0
3.0
4.0
5.0
6.0
7.0
Project Schedule Gantt
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Analysis
Design
Prototype& Try
Implement
Mar Apr May Jun
Nu
mb
er
of
Peop
le
Schedule
Project Resource Planning
Bob
Betty
Barbara
R
Requirements
C
C
R
Design
AR
A
Resource Histogram
When Who
28
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Risk Management & Uncertainty
TOTALCERTAINTY
TOTALUNCERTAINTY
SPECIFICUNCERTAINTY
(“Unknownunknowns”)
(“KnownKnowns”)
NoInformation
CompleteInformation
PartialInformation
(“Knownunknowns”)
SCOPE OF PROJECT RISK MANAGEMENT
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Risk Management
Risk Identification
Risk Response
Identify potential risks
Plan for dealing with
the risk
Risk Management Basics (known unknowns)
Risk AssessmentAssociated
probability and impact
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Risk Register
31
Threats andOpportunities
(A)ProbabilityIt Might Happen(1-10)
(B)Impact
If ItHappens
(1-10)
(A)x(B)
Plan what youwill do on the
big ones.
Response Plan
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Defining Risk Priorities
High Probability Risk will Occur
Low Probability Risk will Occur
High Impact if Risk Occurs
Low Impact if Risk Occurs
Need to have plan
Ignore - “Don’t Worry, Be Happy”
May need a plan
May need a plan
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Valuable Solutions
• Establish a baseline of current PM competency, tools and techniques
• Level set of knowledge, process and terminology
• Cultural change within the organization to establish project management excellence
33
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Establish a baseline of current PM competency
• Conduct an assessment to establish a baseline
• Determine short and long-term goals for moving from the baseline to PM competency
• Create short and long-term plans• (Fissure PM On-line Assessment tool and
improvement planning framework)
34
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Level set of knowledge, process and terminology
• Establish a common set of terminology and processes enabling team members and management to effectively communicate and work across the organization
• Enables strategic level analysis of all projects
• (Accomplished through various levels of training and mentoring support)
35
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Cultural change within the organization
Cultural change requires:• Buy-in from the top• Buy-in from the PMs and team members• Willingness to learn a new set of skills• A set of effective PM tools and
processes • A long-term commitment to PM
competency
36
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
• A study on the effects of project management improvement was done by The Center for Business Practices and reported in the December 2001 issue of Business Finance. The study was of 103 executives who after implementing major PM initiatives reported:
• 49.23% increase in project Performance vs. Schedule
• 49.96% increase in Project Performance vs. Budget• 22.14% increase in customer retention• 33.44% increase in customer satisfaction• • Another study (done in 2002) and quoted in the same
publication, was of 100 Sr. level PM practitioners, they said after implementing major PM initiatives companies could expect an average of:
• 50% improvement in Process Execution• 54% improvement in Financial Performance • 36% improvement in Customer satisfaction
37
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
Fissure Project Management
Capabilities and Offerings
38
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
NTL (National Training Laboratory) Institute For Applied Behavioral Science - Study on Learning Retention Rates Findings
Students retain on average:
39
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09 40
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Webinar June 09
• Business Analysis, Project Management and Leadership training and development company that trains internationally
• Standard and tailored offerings• IIBA Endorsed Education Provider• Global Charter PMI Registered Education Provider • 20 years of turning knowledge into performance using computer simulation training• We partner with our clients to ensure they meet
their objectives in a timely and cost effective manner
Who is Fissure
41
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Fissure Certification Workshops
PMP® Certification Track:• Project Management SPL® Workshop – 3 days
• Advanced PM SPL® Workshop – 3 days• PMP Exam Preparation – 1 day
PMP® Certification Track:• Project Management SPL® Workshop – 3 days
• Advanced PM SPL® Workshop – 3 days• PMP Exam Preparation – 1 day
CBAP™ Certification Track:• Business Analysis SPL® Workshop – 3 days
• Eliciting and Modeling Project Requirements Workshop – 3 days• CBAP™ Certification Exam Preparation – 3 days
CBAP™ Certification Track:• Business Analysis SPL® Workshop – 3 days
• Eliciting and Modeling Project Requirements Workshop – 3 days• CBAP™ Certification Exam Preparation – 3 days
42
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Other Fissure WorkshopsProject Management:• Project Management SPL® Lite Workshop – 2 days• Microsoft Project Professional – 1 day• Project Estimation – 1 day• Risk Management – 1 day• Project Manager as Coach – 2 days
Project Management:• Project Management SPL® Lite Workshop – 2 days• Microsoft Project Professional – 1 day• Project Estimation – 1 day• Risk Management – 1 day• Project Manager as Coach – 2 days
Leadership and Leading Successful Change Track:• Leadership and Change Management SPL® Workshop – 2 days• Leading Successful Change SPL® Workshop – 2 days• Managing Change Workshop or online training – 1/2 day
Leadership and Leading Successful Change Track:• Leadership and Change Management SPL® Workshop – 2 days• Leading Successful Change SPL® Workshop – 2 days• Managing Change Workshop or online training – 1/2 day
43
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
2009 Fall ScheduleMilwaukee
Sep Oct
Project Management SPL
29-Oct.1
Advanced PM SPL 13-15PMP Exam Prep Prep 14
Pricing
• Three Day Workshops - $1,595• One day class - $495
• Please contact NH WI for current discounts & onsite pricing
44
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Next Steps!
• Discuss your specific requirements with your New Horizons Training Consultant
– Schedule Conf Call / Meeting with NH & Fissure?– Public Class Schedule or Private / Custom / On-site?– New Horizons Training Consultant will handle entire enrollment
process!– Take advantage of the available discounts!
• Next Stop – Comments like this….– “This was a Five Star event – we learned more in three DAYS than
we have in the past three YEARS!” – PG Hartford Life– “The Simulation was engrossing and a great way to drive home
the lessons…I learned a lot about teamwork from this experience – S.L Ecolab
45
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
For More Information
Scott DalyPresident – New Horizons
46
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
PM Simulation June 09
Questions / Open DiscussionThank you for attending