© graham m winch riding the project life-cycle1 11 : managing the programme to watch the time, and...
TRANSCRIPT
Riding the Project Life-cycle 1© Graham M Winch
11 : Managing the Programme
to watch the time, and assign things by time, to devote oneself to business and never lose an
hour of timeLeon Battista Alberti
Riding the Project Life-cycle 2© Graham M Winch
Managing the Programme
• the programme planning hierarchy• the critical path method• resourcing the project• the critical chain method• reducing task duration variability
– last planner
• programming reciprocal processes• 4D planning
3© Graham M Winch
Planning Programme Hierarchy
tender programmeclient’s strategic
programme
summary programme
architects design programme
master programme
target construction programme
tender restraints programme
works contractor’s programme
parcel documents programme
procurement programme
contract restraints programme
Riding the Project Life-cycle 4© Graham M Winch
Critical Path Method
• the notion of task dependency– technical– organisational– spatial
• a way of thinking about programme
Riding the Project Life-cycle 5© Graham M Winch
The Critical Path
• establishing the network of dependencies• identifying the critical path
– the longest path through the network
• developing a robust programme– shortest achievable programme– buffering– PERT and Monte Carlo
• a critical path with buffers
Riding the Project Life-cycle© Graham M Winch
Critical Path with Buffers
X
FB
PB
X = shared resourcesFB = feeding bufferPB = project buffer
X
X
X
FB
FB
FBX
Riding the Project Life-cycle 7© Graham M Winch
Resourcing the Project
• the infinite resource assumption– the reliance on spot contracts
• types of resources– plant– labour– space (the 28m2 rule)
• resource levelling– using slack to smooth resources
Riding the Project Life-cycle 8© Graham M Winch
Limitations of the Critical Path Method
• the inverted logic– not applying the rolling wave
• an historically orientated control tool– deterministic– client led– difficulties of on-site up-dating
• task duration estimates– uncertainty– opportunism
Riding the Project Life-cycle 9© Graham M Winch
The Critical Chain Method
• the theory of constraints• critical chain as the longest path through the resource
constrained network• task execution durations
– normally distributed– padded by safety time
• gaining control over safety time• not punishing overruns
– benefiting from your luck
• the critical chain
Riding the Project Life-cycle 10© Graham M Winch
The Theory of Constraints
• Identify the constraint• Exploit the constraint• Subordinate to the constraint• Elevate the constraint• Identify the new constraint
Riding the Project Life-cycle© Graham M Winch
Critical Chain with Buffers
X
FB
PB
X = shared resourcesFB = feeding bufferPB = project buffer
X
X
X
FB
FB
FB X
FB
Riding the Project Life-cycle 12© Graham M Winch
Reducing Task Duration Variability
• multi-tasking• Parkinson’s law• student syndrome • partnering with the resource bases• shielding production
Riding the Project Life-cycle 13© Graham M Winch
Shielding Production : Last Planner
• managing task execution, not contracts• quality assignments
– precedent tasks really completed– resources required really available
• a weekly planning cycle• a tactical tool• combining critical chain and last planner
Riding the Project Life-cycle 14© Graham M Winch
Last Planner and Critical Chain Combined
projectprogramme
criticalpath
qualityassignment
low duration
variability
elevatethe
constraint
latest start date
consummatetask
execution
last planning process
criticalchain
perfunctorytask
execution
highduration
variability
Riding the Project Life-cycle 15© Graham M Winch
Programming Reciprocal Processes• assumption of sequential information flows
– dependencies
• planning problem and reciprocal flows– interdependencies
• the dependency structure matrix– identify interdependencies– prioritise the matrix– cluster the interdependent tasks
• applying DSM to solving the design problem?– the problem of iterative flows
Riding the Project Life-cycle 16© Graham M Winch
4D Construction Planning
• 3D + t• constructing the product model• advantages
– communication– clash detection
• disadvantages – constructing the PBS not WBS– initial product model set-up
Riding the Project Life-cycle 17© Graham M Winch
4D Construction Planning