© mcr, llc mcr proprietary - distribution limited earned value management application, guidance,...
TRANSCRIPT
© MCR, LLC MCR Proprietary - Distribution Limited
Earned Value Management Application, Guidance, and Education
Neil F. AlbertPresident/CEOMCR, [email protected]
2010 Corporate RidgeSuite 350
McLean, VA 22102703.506.4600
www.mcri.com
© MCR, LLC MCR Proprietary - Distribution Limited
EVM in the Acquisition Life Cycle
Pre
-Sys
tem
s A
cqu
isit
ion
Pla
nn
ing
Sys
tem
s S
ust
ain
men
t
Sys
tem
s A
cqu
isit
ion
Operational/FunctionalConcept
PM
EVM
Cost Analysis
SystemsEngineering
RequirementsDefinition
ConceptDefinition
AoA
Life CycleCost Estimate
WBS
Risk Analysis
•Cost•Schedule•Technical
•Cost•Schedule•Technical
AcquisitionPlan
Integrated BaselineReview
Surveillance
WBS
Performance Measurement
Baseline
AcquisitionCost Estimate
Risk Analysis
•Cost•Schedule•Technical
•Cost•Schedule•Technical
•Cost•Schedule•Technical
•Cost•Schedule•Technical
Risk Analysis
•Cost•Schedule•Technical
Risk Analysis
•Cost•Schedule•Technical
Risk Analysis
•Cost•Schedule•Technical
© MCR, LLC MCR Proprietary - Distribution Limited
ANSI/EIA-748 Earned Value Management Systems
• Contains guidelines for establishing and applying an integrated management system for cost, schedule, and technical performance
• Contains 32 guidelines, grouped into five major categories:
– Organization – Planning, Scheduling, and Budgeting – Accounting Considerations– Analysis and Management Reports – Revisions and Data Maintenance
• NDIA Intent Guide for Earned Value Management Systems
– Provides additional insight into the 32 guidelines
– Describes the typical attributes and objective evidence that support compliance with a given guideline
Management ProcessesOrganization
WBS top level clearly describes one end product or deliverable The WBS represents the entire scope of work and represents products and not
budget categories, organizations, personnel, tasks, functions, or project phases Each WBS subordinate element has only one parent Each subcontracted effort is assigned to a single WBS element (unless
subcontractor is responsible for multiple components) Work Packages are not identified as WBS elements; CA is the point of MANAGEMENT CONTROL and ANALYSIS
Planning, Scheduling, and Budgeting All tasks have unique names, with milestones representing key events Work Packages average less than < 90 days Planning Packages are usually < one year and most often are tied to a Rolling Wave;
the Rolling Waves are tied to significant project events Methods selected to measure work accomplished against plan must be objective
and meaningful Schedule tasks are derived from a product-based WBS Schedule networks are created by linking lowest level tasks only Each schedule task has at least one predecessor and at least one successor
(Exceptions: first and last task or external milestones) Use of schedule lags/leads is minimal; a lag/lead may be injected into the schedule
network only for a specific purpose, not as shortcuts to identifying logical sequences of events or to override event sequencing
Use of task constraints (Must Start On, etc.) is minimal, usually only for key contractual milestones
Stakeholders validate Schedule Scope, Task Logic, and Durations Baseline is set, then an Intergraded Baseline Review (IBR) is conducted Network critical path (+some float) focus of schedule/SPI analysis Track schedule metrics to assess goodness of schedule, include start/finish slips,
tasks near critical path, float/slack, etc Pessimistic/Most Likely/Optimistic estimates are made for costs and time MR is based on risks and opportunitiesAccounting Considerations WBS lowest elements are broken down into convenient ‘packages’ which are used
to group, summarize/monitor elements of cost (i.e., labor, material, ODCs Estimated actuals are utilized to assure realistic actual costs in a timely manner
Analysis and Management Reports Reporting is at lowest WBS level necessary for effective management LOE is extracted when evaluating actual progress and performance Cost, Schedule, Performance along with risks and opportunities are tracked Variances are analyzed, they are neither good or bad, but variations that
indicate areas that might need management action EAC analysis is based on time/cost estimates adjusted for risks/opportunity Project MR ‘burn down’ rates with assumptions regarding potential distribution
Revisions and Data Maintenance CCB approval is required for changes to scope, schedule or budget Develop
realistic CA EACs integrated with tech, cost, and schedule risks/opportunities. Establish Risk baseline (see Risk/Opp Index)
Mitigation plans have triggers, are included in PMB and tied to metrics PM may Re-plan as necessary within scope or Reprogram to new scope
MCR
© MCR, LLC MCR Proprietary - Distribution Limited
Pre-Systems Acquisition
Systems Acquisition
EVM ApplicationANSI/EIA-748
Compliant EVMS
Systems Sustainment
EVM ApplicationANSI/EIA-748Scalable EVMS
ANSI/EIA-748
EVMS
Organization and Supplier processes
integrated with EVM capability and documented
Contract or Project
EVMS EVMS Surveillance
Implementation
ANSI/EIA – 748 EVMS Application
© MCR, LLC MCR Proprietary - Distribution Limited
National Defense Industrial Association (NDIA)
Program Management Systems Committee (http://www.ndia.org)
• EVM ANSI/EIA-748 Subject Matter Experts • Developed Guides as documented in OMB A-11, Part 7
– ANSI/EIA 748 Intent Guide – maintains the explanations as to the purpose and attributes expected for ANSI/EIA 748 compliance
– Application Guide - describes for all organizations implementing the ANSI/EIA-748, the importance of planning the EVM application through all phases of the acquisition life cycle
– System Acceptance Guide – evaluates whether the EVMS is capable of meeting the intent of ANSI/EIA-748 and obtain EVMS compliance recognition that will meet current and future requirements for an approved EVMS
– Integrated Baseline Review Guide - identifies the IBR Process and integrates the IBR with risk management within the framework of the IBR Process
– Surveillance Guide - defines a standard industry surveillance approach to effective surveillance, encourages efficiencies through the use of a uniform process, and gives consistent guidance for companies implementing the ANSI/EIA 748 EVMS guidelines
• Joint Government/Industry EVM Working Groups – focusing on Industry input to
the revised DoD and OMB EVM Policy and related requirements, including interpretation and guidance
© MCR, LLC MCR Proprietary - Distribution Limited
Integrated Program Management Document Framework
Performance Baseline
Performance
Measurement RiskManagement
Integrated
Plan
Surveillance Guide
PM Guide to IBR Process
ANSI/EIA
748
Inte
nt G
uide
Application Guide
Evaluating:ContractingSystems EngineeringRisk Management
© MCR, LLC MCR Proprietary - Distribution Limited
Acquisition Life Cycle Acceptance Authority or Customer
EVM System Owner or Supplier
Pre-Systems Acquisition Approval or Award
Recognize:Application GuideSystem Acceptance Guide
Document and Assessment:Application GuideIntent Guide
Systems Acquisition Approval or Award
Accept:Intent Guide & Surveillance GuideIBR Review:IBR GuideSurveillance:Surveillance Guide
Implement:Intent Guide & Surveillance GuideIBR Review:IBR GuideExecution and Surveillance:Surveillance Guide
NDIA Guidance
© MCR, LLC MCR Proprietary - Distribution Limited
Project Management Institute – College of Performance Management
(PMI-CPM)
Internationally recognized forum for Earned Value Management and project planning and control,
standards, research, and education(www.pmi-cpm.org)
Objectives• Promote Earned Value Management and Project Planning and Control
– Recognition and use of earned value management and other project planning and control techniques as integrating processes for project management
• Disseminate Information– Provide opportunities for the exchange of ideas, information, solutions and
applications • Improve Community of Practice
– Encourage and enable the advancement of theory and application through research, standards, and education
• Professional Growth– Provide membership with growth opportunities through leadership,
education, networking, professional certification, and other benefits of a professional association
© MCR, LLC MCR Proprietary - Distribution Limited
Project Management Institute – College of Performance Management
(PMI-CPM)
• Two conferences annually– Spring: Annual CPM Conference “EVM World”– Fall: Integrated Program Management
International Conference (Co-Sponsor w/SCEA and NDIA)
• Training Seminars– Special Topics– Education Program (EVM Certificate)
• Certification– Endorse AACEI – Earned Value Professional
(EVP)
© MCR, LLC MCR Proprietary - Distribution Limited
Project Management Institute – College of Performance Management
(PMI-CPM)
• Measurable News
• PMI-CPM Forum
• Electronic Library
• EVM Practice Standard
• Research
• Scholarships
© MCR, LLC MCR Proprietary - Distribution Limited
EVM Federal - Community of Interest (EVM CoEye)
• Founded in 2005 by volunteers in the PMI-CPM and Civilian Agency Leads (www.fedevm.org)
• Provide information on EVM to workers in the civilian agencies of government.
• EVM-based project management now a mandatory requirement of the US government
– CoEye supports more than 400 people on its distribution list, consisting of public servants and contractors from more than 60 government offices
• Complements formal government organizations by creating a network of well-informed people
– Helps agencies change the focus of their mission-oriented acquisition systems to EVM-based project management systems
• Meets monthly at sponsoring agency location
• Discusses issues in OMB guidance for EVM, including policy, implementation and validation
© MCR, LLC MCR Proprietary - Distribution Limited
Other Related Educational Opportunities
• Project Management Institute– www.pmi.org
• Society of Cost Estimating and Analysis– www.sceaonline.org
• Defense Acquisition University– https://acc.dau.mil/evm
• Federal Acquisition Institute– http://www.fai.gov/resource/educate.asp
© MCR, LLC MCR Proprietary - Distribution Limited
Questions?