Page 1: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013
Page 2: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

PRESENTATIONPRESENTATION

SSA management Meeting SSA management Meeting

Date: 24/10/2013Date: 24/10/2013

Vigilance Activity Period from Vigilance Activity Period from 07/2013 to 09/201307/2013 to 09/2013

Page 3: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

COMPLAINTS AND DISPOSAL

Total Written Complaints Received :1611 complaints were regarding unsatisfactory working of Telephone. Vigilance has taken up the cases and closed the cases after proper restoration of service. Remaining 5 were against the staff which were investigated by the Vigilance and reported as below:

1.Misbehavior of staff at Kakayangad Xge. :The Complaint is mainly attributed to delay in reconnection of NPD number. Observation after Investigation: i). There was no abnormal delay in reconnecting number. ii) Alleged misbehavior is on the basis of family rivalry . However TM has been recommended to caution so that such complaint should not be come up in future against him.

Page 4: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

COMPLAINTS AND DISPOSAL continued ….

2. Unauthorised blocking of SIM:

After a preliminary investigation, the case has been forwarded to Mobile Vigilance for further investigation The Data received from Mobile Vigilance shows that the reason behind the incident is mismanagement of CSR Pass word. The investigation could not be completed by SSA Level. Hence the case referred to Circle vigilance for further direction in this case.

Suggestion: Security in CSR password has to be ensured by the CSR in charges.

Page 5: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

COMPLAINTS AND DISPOSAL continued ….3. Complaint of M/s K.K. Builders

regarding hacking of BB.Party changed the rental modem and

connected Wi.Fi modem without setting security code at their own Risk. Hence BSNL staff can not be blamed for non setting of Password.

Page 6: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

COMPLAINTS AND DISPOSAL continued

Recommendation:

Customer has to bear the amount for any misuse /hacking. However Customer being CIS who pay to BSNL >1.5 lakhs per month towards rental/usage charges on our products through their different establishment; the case is recommended for settling under BB special relief Scheme “Samdhan”

4. Delay in attending fault. Complaint against JTO Cheruvathur.

Investigation showed that the delay is due to breakage of cable consequent of heavy flow of water through drainage in the cable route and subsequent scarcity of cable to relay the same. Communication restored by pulling drop wire from cable breakpoint to party’s premise.. Party satisfied with the restoration of service. No action Recommended in this case

Page 7: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

COMPLAINTS AND DISPOSAL continued.

5. Private Complaint against staff at Kasaragod for involving in anti social activities.

Inquiry showed that no material evidence available to substantiate the above charge against the official . Hence complaint disposed by recommending to keep a watch on the official in his dealings in future.

6. Complaint of Callous and arrogant attitude of BSNL staff towards a subscriber at Panoor Xge.

The case is investigated and report submitted for taking further action in this case.

Page 8: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

INSPECTIONSSURPRISE:43PREVENTIVE TECHNICAL INSPECTION : 35CASES OF IRREGULARITIES NOTICED DURING

INSPECTION:45

Main irregularities observed:1. FAULT REPAIR: As per TRAI benchmark for QOS , the MTTR

is to be <8 hours and rental rebate has to be paid to customer for fault pending >3 days. But MTTR in some of Exchanges are >300. It was reported that Main reason for huge MTTR is torrential rain and shortage of manpower. They would take care of lowering MTTR in future.

2. Suggestion: Responsibility has to be fixed in such cases.

Page 9: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

OBSERVATION Continues>>>

3. Energy Saving measures in CDOT/5ESS Switches:

It is observed that in many of the switches the working connections are very less against the equipped capacities. Hence much energy can be saved by rearranging the ports and switching off the frames which stands idle thereafter. Reports has been submitted to GM with copy to respective DEs in charges after identifying the stations.

Compliance is awaited.

Page 10: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

4. Exchange Batteries:

In 5 Main stations including Kannur, the Battery condition is very critical. Batteries are also life expired. Reports submitted to GM with copy to the respective DEs to arrange immediate replacement of these life expired Batteries to avoid any catastrophe.

OBSERVATION Continues>>>

Page 11: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Weak and damaged cells are to be replaced in 6 stations.

5.Engine Alternators:

In 5 stations profuse oil leak is observed . In 2 stations Engines are kept idle for want of starting Batteries. Cases are reported to SSA for arranging rectifications.

6.Air conditioners: There are defective AC units (No proper cooling ) in 10 stations. Electrical wing has to

OBSERVATION Continues>>>

Page 12: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Carry out proper AMC maintenance in this connection.

7.Building Problems. In 2 stations the department building are

heavily leak which has to be attended by Civil Wing . Report submitted to GM with copy to Civil section.

OBSERVATION Continues>>>

Page 13: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

8. Scrapping of unserviceable items: A large quantity of AB posts, Window type

units, Engine Alternators , Power Plant units ,IFWT instruments etc are kept idle in various Xges which are to be scrapped and disposed for earning Revenue.

9. Unutilized cable laying in Xge premises.

These cable has been brought to the notice of Planning wing for taking in stock of inventory for reissue .

OBSERVATION Continues>>>

Page 14: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Inspection of CSCs As per kannurnet the closing balance is much

more than actual cash balance on hand found during inspection. It was reported that the amount to be recovered from DSA/Shoppe were also accounted as cash balance .Hence the difference.

Suggestion: More Efforts have to be taken to collect maximum amount on the same day of issue of cash cards/Ctop up to shoppe/DSA itself.

Page 15: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Circle vigilance has badly commended about the high cash balance shown in the net.

Inspection of CSCs Continues >

Page 16: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

VERIFICATION OF STOCK OF VERIFICATION OF STOCK OF SIM/CASH CARDS IN CSRs SIM/CASH CARDS IN CSRs

Stock of SIM/Cash cards are not tallying with the SSA figure. CSRs are asked to tally the balance with SSA figure before the next inspection.

Page 17: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Verification of IPR statements

It is reported that a few Executive staff are yet to be submit the IPR for the year 2012.

AGM Admn has to give letter to such staff for early submission failing which disciplinary actions are to be initiated against such off .

Total verified 146 as on date

Page 18: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013

Disciplinary cases &Monthly Review with SSA head.

Sri.M.P.Satheesan TM Perla is continuously absent for more than 8 months. Vigilance has recommended for starting Disciplinary proceeding against him under Rule-36 of CDA rule 2006. Charge sheet is framed and handed over to the Disciplinary Authority for further action in the case.

Disciplinary authority (DGM KSZ) has to start the disciplinary proceeding early.

Page 19: PRESENTATION  SSA management Meeting  Date: 24/10/2013  Vigilance Activity Period from 07/2013 to 09/2013