DESCRIPTION
EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE. The EUSO-BALLOON AIT-Development plan. Sylvie Dagoret-Campagne LAL, Orsay , Baptiste Mot, IRAP , Toulouse. - Purpose - Main sequences - Resources (manpower and GSE), including location - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/1.jpg)
- Purpose
- Main sequences
- Resources (manpower and GSE), including location
-Main activities of the assembly and integration of the subsystems
-Final integration and tests
E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E
Sylvie Dagoret-CampagneLAL, Orsay,Baptiste Mot,IRAP, Toulouse
The EUSO-BALLOON AIT-Development plan
1
![Page 2: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/2.jpg)
CDR – 18.12.2012
AIT Development plan and GSE 2
EUSO-BALLOON, a Highly Modular instrument
4 subsystems :• « electrical » (DP,PDM,DP)• 1 mechanical,
DP : 11 components (boards),PDM : 5 components (boards),PWP : 1
Each component under the responsibility (design, fabrication, procurement) of different laboratories world wide spread.
Phase B Phase C&D • Need AIT/AIV procedures• Need resource evaluation• Need time evaluation (planning)
![Page 3: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/3.jpg)
AIT Development plan and GSE 3
Main sequences of Integrations
CDR – 18.12.2012
EC-Unit Integration: MATRA-LAL
Electronic Integration:
LAL
Data processing Integration:INFN-Naples
PDM integration:APC
Optics Tests:RIKEN-JP/UAH-
US tests
Full electronics intgration:
APCInstrumentIntegration:B.I.S CNES
Mechanics assembly:
B.I.S CNES
FinalTests:B.I.S CNES
time
![Page 4: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/4.jpg)
AIT Development plan and GSE 4
Manpower for AIT
Full Instrument AIT
:B. Mot/IRAP
Mechanical AIT : G. Roudil/IRAP
Electronic AIT : M Dupieux/IRAP
Optical AIT : C. Catanalo/IRAP
AQ AIT : TBD / IRAP
CDR – 18.12.2012
PDM-AIT : P. Barrillon/S. Dagoret /LAL
H. Miyamoto/L
ALS. Blin/LAL C.
Moretto/LAL APC Team
DP AIT : G.
Osteria/INFN
Naples-INFN
Rome-INFN BARI-INFN IAAT-
Tuebingen
Full integration :
Subsystem/ electronic integration :
DP integration :
![Page 5: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/5.jpg)
AIT Development plan and GSE 5
GSE-PDM
CDR – 18.12.2012
![Page 6: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/6.jpg)
AIT Development plan and GSE 6
GSE-CAL
CDR – 18.12.2012
![Page 7: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/7.jpg)
AIT Development plan and GSE 7
GSE-DP and GSE-Opt
CDR – 18.12.2012
![Page 8: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/8.jpg)
AIT Development plan and GSE 8
ComponentPre-assembly
Component test
EC-Unit
HVPS
EC-ASIC
PDM-B
Pre-Integration Assembly
IntegrationTests &Validation
PAECM2
PAECM1
THV1
THV2
TECA2
TECA1
TPD1..N
IEC1
IEC2
IEC3
IEL1
IEL2
AP1
AP2
AP3
CAPHEEC1
TrigPDM
CAKIEC1
CDR – 18.12.2012
PDM AIT activities sequence
![Page 9: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/9.jpg)
AIT Development plan and GSE 9
PDM AIT activities list
CDR – 18.12.2012
Test name component comment duration location whocomponent pre-assembly
PAECM1 MAPMTPhoton collection efficiency and gain measurement for each channel 1 month for 36 units APC APC & LAL
PAECM2 MAPMT Sorting to fit an EC 1 hour APC APCTHV1 HVPS cable reference THV2 HVPS HV tuning (depending on PMT gains) APC APCComponent Tests
TECU1 EC-Unit static test under HV, normal air pressure 1 hour LAL LALTECU2 EC-Unit static test under HV, low pressure 12 hours APC LALTECA1 EC-ASIC visual inspection 1 hour LAL LALTECA2 EC-ASIC electronic test bench 1 week for 6 units LAL LAL
TPD1 PDM-BElectrical mechanicalcompatibilitie 1 day Korea SKKU
TPD2 PDM-B Power supply tests 1 day Korea SKKUTPD3 PDM-B ASIC configuration 1 day Korea SKKUTPD4 PDM-B ASIC readout TBD Korea SKKUTPD5 PDM-B Trigger functionality tests TBD Korea SKKUTPD6 PDM-B HVPS switch control tests TBD Korea SKKUTPD7 PDM-B DP (or CCB) interfaces TBD Korea SKKUTPD8 PDM-B HK logic and interface tests TBD Korea SKKUPre-Integration
IEC1 EC-Unit+HVPS static test under HV, normal air pressure 1 hour per EC unit APC APC&LALIEC2 EC-Unit+HVPS statistic test under HV, low pressure 12 hour / EC-Unit APC APC&LAL
IEC3 EC-Unit+HVPS+EC-ASIC light on EC-Unit+ EC-ASIC red by Test-EC-ASIC10 days assembly+15 days tests APC APC&LAL
IEL1 PDM PDM-B readout external computer LAL APC&LALIEL2 PDM+DP link CCB+PDM-B 1 week LAL APC&LAL
![Page 10: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/10.jpg)
AIT Development plan and GSE 10
PDM-AIT Activities list
CDR – 18.12.2012
Test name component comment duration location whoAssembly
AP1 9 EC-Units+PDM-Framemechanical integration and screwing 1 day APC LAL
AP29 EC-Units+6 EC-ASIC+PDM-Frame
mechanical integration and screwing 1 day APC LAL
AP39 EC-Units+6 EC-ASIC+HVPS+PDM-Frame cabling 1 week APC APC
AP4
9 EC-Units+6 EC-ASIC+HVPS+PDM-B+PDM-Frame
mechanical integration and cabling 1 week APC LAL
Calibration
CAPHEEC1 EC-Units+EC-ASIC
Photon counting calibration (Test-EC-ASIC) 3 weeks APC APC&LAL
CAKIEC1 EC-Units+EC-ASICKI channels calibration (Test-EC-ASIC) 3 weeks APC APC&LAL
Validation
TrigPDM PDM + light sourceapply a fast moving light spot few days APC APC&LAL
SWLOG PDM + light sourceapply a variable light source few days APC APC&LAL
![Page 11: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/11.jpg)
AIT Development plan and GSE 11
DP-Activities sequence
CDR – 18.12.2012
![Page 12: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/12.jpg)
AIT Development plan and GSE
DP-AIT Activities list
ID512
Test name component comment duration location who
ID1 LVPS+HK+CPU
1-2 monthes Naples
IAAT and INFN
(NA-BA-Roma2)
and Korea
ID2 LVPS+HK+CPU+GPS+CLK SPI tests
ID3LVPS+HK+CPU+GPS+CLK+CCB
ID4LVPS+HK+CPU+GPS+CLK+CCB CCB through SPI
ID5LVPS+HK+CPU+GPS+CLK+CCB
CCB through Spacewire
ID6LVPS+HK+CPU+GPS+CLK+CCB+PDM-B
…ID1 ID5
CDR – 18.12.2012
![Page 13: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/13.jpg)
AIT Development plan and GSE 13
ComputerPDM board
EC-ASICboard
Power supply Logic
analyzer
NI(PC interface)
Multimeter
Charge injection
EC-ASIC board
ASIC
PDM board
Pre-Integration EC-ASIC and PDM-B
CDR – 18.12.2012
![Page 14: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/14.jpg)
AIT Development plan and GSE 14
PDM-B-DP Pre-Integration
CDR – 18.12.2012
![Page 15: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/15.jpg)
EC-HV
EC-DYNODE
HVPS2
HVPS1
MA
PMT
EC-ANODE
EC-ASIC
PDM-B
IR-CAM
Batteries
PWP
LVPS
-DP1
LVPS
-DP2
LVPS-PDM
LVPS
-HK
HK
CCB
CLKB
GPSR
CPU
DST
SIREN
CNES Telemetry
EXT
Bat Controller
TLS
Sensors
Motors
SPACEWIRE/PCI
EC-Front
EC-Back
DPINTERFACES TESTED UP TO NOW FOR HARDWARE
DP PDM
![Page 16: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/16.jpg)
AIT Development plan and GSE 16
Optical AIT Activities list
Test name component comment duration location who
TOP1 Lenses 1,2,3 acceptance tests 1 week/lens IKEGAMI RIKEN
TOP2 Lenses 1+2+3 performances tests 1 month Alabama UAH
TOP3 Lenses 1+2+3
validation tests for integrated instrument TBD CNES IRAP
TOP 1 TOP 2
CDR – 18.12.2012
![Page 17: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/17.jpg)
AIT Development plan and GSE 17
PWP Activities sequence
CDR – 18.12.2012
![Page 18: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/18.jpg)
CDR – 18.12.2012
AIT Development plan and GSE 18
Activities- Task forms
• All activities are referred by an acronym,
• Each activity is performed in a sequence of AIT-AIV of a subsystem of of the instrument
• They are tracked in activity forms by AIT managers
• Description :• Component,• Configuration,• GSE,• Task details, procedures, results
Example of description of a task
![Page 19: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/19.jpg)
AIT Development plan and GSE 19
Final AIT-AIV
Resp : IRAP location : CNES 1. Overview of Integration Phases 2. Sequence of integrations3. Global tests4. Transport and flight campaign preparation5. Flight campaign #1
CDR – 18.12.2012
![Page 20: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/20.jpg)
AIT Development plan and GSE 20
1.SEQUENCE FOR INTRUMENT INTEGRATION
CDR – 18.12.2012
Preliminary
+ IR-CAM Assembly
![Page 21: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/21.jpg)
AIT Development plan and GSE 21
2.GLOBAL TESTS
CDR – 18.12.2012
Preliminary
![Page 22: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/22.jpg)
AIT Development plan and GSE 22
3.TRANSPORT AND FLIGHT-CAMPAIGN PREPARATION
CDR – 18.12.2012
Preliminary
![Page 23: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/23.jpg)
AIT Development plan and GSE 23
Flight campaign #1
CDR – 18.12.2012
Preliminary
![Page 24: - Purpose - Main sequences - Resources (manpower and GSE), including location](https://reader036.vdocument.in/reader036/viewer/2022062410/568163ef550346895dd56a73/html5/thumbnails/24.jpg)
AIT Development plan and GSE 24CDR – 18.12.2012
Conclusions
• Main phases of AIT identified :• Subsystems• Instrument (Final),
• Many activities identified for subsystem AIT and their component integration,• Test procedures assessed,• Some activities can be done in parallel, some in sequences.• Merging points.
• Activities are inserted in a sequence of AIT of the subsystems,• Types of activities:
• Component tests, pre-integration, assembly, integration, tests and validation, calibration.
• Resources in manpower for AIT distributed, location of the activities, including the management.
• Resources in GSE listed,• Timing estimated,• Activities follow-up:
• AIT-AIV will be controlled and tracked by the AIT managers using activities forms.