Microsoft Project 2010 Step 1 Set working folder 1) Create a folder on your Desktop and name it My Projects -Right click on your desktop and select New->Folder 2) Create one folder for each project. Today we will create a folder named Uthen 001

Upload: lamanh

Post on 29-Aug-2019

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Microsoft Project 2010

Step 1 Set working folder

1) Create a folder on your Desktop and name it My Projects-Right click on your desktop and select New->Folder

2) Create one folder for each project. Today we will create a folder named Uthen 001

Page 2: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Step 2 Set default behaviors

1) Open Microsoft Project2) File->Close3) File->Options

a. On Schedule tab Week starts on: Monday New tasks created: Auto Scheduled

Page 3: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

b. On Save tab Change Default File location: Desktop\My Projects Check Auto save every:15 minutes Select Save active project only Check Prompt before saving

Page 4: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

c. On Advanced tab Check Open last file on startup Uncheck Advice from Planning Wizard (because it’s often incorrect or misleading)

Page 5: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Step 3 Open new project and set project options

File->New->Blank project

Set project start date by going to Project->Project Information

Page 6: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Change header font by right click on info image->Text Styles… , and select font and size

Page 7: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

View->check Details and select Task Form

Tools->Project Options Decimal digits: 0 Currency: THB Calendar Type: Thai Buddhist Calendar (if you want)

Page 8: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 9: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Select Display tab and change Date format: ….”to anything you want”

Page 10: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Project Start Date by going to Project->Project Information-> Start Date

Page 11: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Example

Task Name Predecessors DurationA 10B A 8C A 3D B, C 10E D 5F D, E 6

Make sure Details option is checked.

For Activity A, input following data in Task Form

Name: a Duration: 10 days Uncheck Manually Schedule

For Activity B, do the same as Activity A and

Select Predecessor name

Page 12: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Create task summary for activities B and C by

1. Insert new activity before B

Page 13: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 14: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Format Bar Styles to show more info on Gant chart

1. Right click on the Gant chart and select Bar Styles

2. Find Critical activity and click Text3. Type Name as shown in the picture below

Page 15: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 16: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 17: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 18: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 19: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 20: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

View->Calendar

+

Page 21: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Go back to Gantt chart by View->Grant Chart icon

Double click at activity a and change calendar to Standard Thai Calendar

Page 22: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 23: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 24: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name
Page 25: chachrist.files.wordpress.com€¦ · Web viewto show more info on Gant chart. Right click on the Gant chart and select Bar Styles. Find Critical activity and click Text. Type . Name

Make sure the following options are checked

Project Summary Task Summary Tasks