WHAT THE TASK FORCE COMMITTEE DID? WHY DOES ANDOVER NEED A NEW TOWN YARD? WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING? WHAT ARE THE BENEFITS OF FINDING A HIGHER AND BETTER USE AT THE CURRENT IN TOWN SITE? WHAT ARE THE PROJECTED COSTS AND BENEFITS OF BUILDING AT A NEW SITE? 1 ANDOVER TOWN YARD TASK FORCE

Upload: arabella-atkinson

Post on 26-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

WHAT THE TASK FORCE COMMITTEE DID?

WHY DOES ANDOVER NEED A NEW TOWN YARD?

WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?

WHAT ARE THE BENEFITS OF FINDING A HIGHER AND BETTER USE AT THE CURRENT IN TOWN SITE?

WHAT ARE THE PROJECTED COSTS AND BENEFITS OF BUILDING AT A NEW SITE?

1

ANDOVER TOWN YARD TASK FORCE

Page 2: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS
Page 3: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Erected in 1965 – Temporary 10 Year Buildings.

Town Population then 20,000, Now 33,000. Close to $100,000 spent in the last two years

for repairs, emergency maintenance and time to keep the existing buildings in operation.

Recent Investigation - Major Structural Issues. Functions are in Nine Different Locations. Buildings are too Small & Obsolete – 1/3 Size. Equipment rusting being stored outside.

Page 4: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

4

Page 5: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

5

Page 6: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

6

Page 7: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

7

Page 8: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS
Page 9: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

9

Page 10: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

10

Page 11: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

11

Page 12: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

12

Page 13: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

13

Page 14: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

14

Page 15: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

15

Page 16: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Forestry Division (P&F) Highway Division (DPW) Fuel Depot and Fleet: 150 + Vehicles &

Equipment Parks & Grounds Division (P&F) Vehicle Maintenance Division (P&F) Water & Sewer Division (DPW) Building Division (P&F) Mechanical/Electrical Division (P&F)

Page 17: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Support of all Town and School Infrastructure:

$10+ Million Vehicle and Equipment Fleet 1.4 Million Sf. Town and School Buildings 2.75 Million Sf. of Fields 1.4 Million Sf. Lawn Areas 215 Miles of Roadways 180 Miles of Water Mains 100 Miles of Sewers

Page 18: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Why not rebuild at the present location?

Page 19: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

19

Page 20: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Site3+acresExisting Town YardTY11 Taxes = 0

Potential Sale = $2 - $3 million Residential (158 units)

237,000 sf 63 Market Ownership 16 Income Restricted 63 Market Rental 16 Income Restricted

Commercial 47,000 sf

Potential Tax Revenue from redevelopment = $ 561,194

20

Page 21: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

For Andover Taxpayers:

• Rare opportunity to actually expand downtown • Increased Tax Revenues• Redevelopment of adjoining parcels becomes advantageous• Increases the value of adjoining parcels• Development Costs are at a cyclical low now

For Andover Shoppers and Its Business Community:

• Expansion under 40R will allow Town to retain its character, upgrade its shopping opportunities and increase business and tax revenues.

Increase variety of storesExisting center is too small (1/2)Neighboring towns have expanded along our bordersProvide new housing opportunitiesProvide increased commuter parkingImprove property values throughout TownImprove our “Sense of Place”Creates new jobsImprove Traffic Conditions

Page 22: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

• 158 Residential Units - Average selling price between $125,000 - $250,000

• Approx assessed value = $33,390,000

• Approx new tax revenue generated from residential development = $471,467

• Approx assessed value of retail/office development assuming a value of $85 per sf- 47,000 square feet x $85 = $3,927,000

• Approx new tax revenue generated from retail/office development = $89,727

• Approx new tax revenue generated = $561,194

• Existing tax revenue = $0

Page 23: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

PRIOR ASSESSMENT BY TASK FORCE

NEW REQUEST FOR PROPOSALS for PHASE 1DEVELOPMENT OF 59,000 SF

FOUR PROPONENTS REVIEWED BY COMMITTEE

PHASE 1 SINCE VALUE ENGINEERED TO PRE-ENGINEERED CONSTRUCTION OF57,500 SF

Page 24: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Financial Assessment: Site•24 acres•274,400 square feet•FY2011 Taxes = $212,687

Purchase = $13.9 millionRetrofit = $10.7 million

Total Project Cost $24.6 million

Page 25: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Financial Assessment: Site• 16 + approximate acres• FY2010 Taxes = $33,725 (loss of tax revenue)

Land and ConstructionTotal Project Cost: $17.8 million to $18.4

Page 26: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

26

Page 27: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

ADDITIONAL BENEFITS TO THE TOWN FOR THIS LOCATION:

PUBLIC ACCESS TO THE MERRIMACK RIVER

Page 28: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Conservation Land

5 Campanelli Drive

Page 29: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

29

Page 30: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

Add HERRON slides

30

Page 31: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

31

Page 32: WHAT THE TASK FORCE COMMITTEE DID ?  WHY DOES ANDOVER NEED A NEW TOWN YARD?  WHAT ARE THE COST IMPACTS OF NOT DOING ANYTHING?  WHAT ARE THE BENEFITS

NEXT STEPS:

1. REVIEW DESIGN

2. REVIEW DEVELOPMENT COSTS WITH WESTON & SAMPSON ENGINEERS

3. NEGOTIATE LAND PURCHASE

4. PRESENT TO OTHER TOWN BOARDS

5. PREPARE FOR SPRING TOWN MEETING