0 overview of fukushima-accident analysis ermsar 2012, cologne (germany) march 21 – 23, 2012 jnes...
TRANSCRIPT
1
Overview of Fukushima-Accident Analysis
ERMSAR 2012, Cologne (Germany)
March 21 – 23, 2012
JNES
Masanori FUKASAWA
2
Contents
1. 1F 1※ Accident Analyses (Plant behavior) at JNES
2. Plant Behavior Analysis using MELCORA) Results at IAEA Ministerial Conference (June 2012) and Problems
B) Revised Analysis
3. Primary System Behavior during IC operation
4. Hydrogen Mixing and Explosion in Reactor Building (R/B)
5. Conclusions
※1F: Fukushima Daiichi
3
Published Analyses and Evaluations ”Report of Japanese Government to the IAEA Ministerial Conference on
Nuclear Safety,” June 2011. (June Report), JNES-RE-2011-0002.Documents of Hearings at Nuclear Safety Commission (NSC) and Nuclear
and Industrial Safety Agency (NISA).Analyses and Evaluations submitted to NISA (published on JNES web).
Accident Analysis Plant Behavior FP Release•Getting chronology information together
•Event tree analysis of the accident
•Possibility of recriticality•Reactivity constraint by sea water
•Time before fuel damage in SFP
•Salt precipitation
•MELCOR analysis•Primary system behavior during IC operation
•Hydrogen mixing and explosion
•MCCI in case water injection stops
•Possibility of PCV failure by H2 deflagration
•H2, O2 concentration
•FP release and dose evaluation
• Influence in case water injection stops
•FP release and EPZ •Estimation of FP release and dose based on monitoring data
•FP release in case of venting
1. 1F Accident Analyses (Plant behavior) at JNES
4
Analytical configuration:
Code: MELCOR1.8.5
2. Plant Behavior Analysis using MELCOR
6 volumes of primary system4 volumes of containment5 volumes of reactor building
to simulate FP transfer.Junctions of S/R valves,
vacuum breaker, PCV leak, W/W vent
Further (not depicted), activated cooling systems and assumed leak to simulate transports of steam, coolant and FP. 1F1: IC1F2: RCIC1F3: RCIC, HPCI
Objectives: To figure out plant behaviors of 1F1 – 3 and enhance safety measures.
Primary boundarySecondary boundary
Pedestal
蒸気ドーム
下部プレナム
Upper plenum
Core
Bypass
Do
wncom
er
RPV
FHB
4F
3F
2F
1F
Environment
Blowout panelPCV
Vent pipe
W/W
RPV failure
W/W
vent
ADS
S/RV
Vacuu
m
breaker
R/B
Leakag
e
SGTS
D/W
Steam dome
Lower plenum
Primary boundarySecondary boundary
Pedestal
蒸気ドーム
下部プレナム
Upper plenum
Core
Bypass
Do
wncom
er
RPV
FHB
4F
3F
2F
1F
Environment
Blowout panelPCV
Vent pipe
W/W
RPV failure
W/W
vent
ADS
S/RV
Vacuu
m
breaker
R/B
Leakag
e
SGTS
D/W
Steam dome
Lower plenum
5
①IC stop、② water injection、③W/W vent open、④W/W vent close、⑤ Sea water injection、⑥Increase of PCV leakage
1F1: Lower coolant injection caseWater injection (fire pump, F/P) by 3/15 is 88 m3
2.A) Result of June Report and Problems (1F1)
IC actuation is limited and water level decreases at an early stage.Core melts before alternate water injection.RPV failure is calculated at 5 hrs.Most core is calculated to melt and slump to PCV floor. RPV failure timing (MELCOR default model calculates early failure.)Actuation of W/W vent at 1st attempt (3/12 10:17).
Analytical results
Problems
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
-4000
-2000
0
2000
4000
6000
0 12 24 36 48 60 72 84 96
(M
Pa)
炉圧
(m
m)
水位
(h)経過時間
(○,△ )実測値1F1
炉圧
TAF
RPV水位
3/ 12 3/ 13 3/14
実時刻
① ② ③
④
⑥⑤
W/W vent
Date
Wat
er le
vel (
mm
)
P/S
pre
ssur
e (M
Pa)
Time (hr)
○,△:Measured dataP/S Pressure
Water level
P/S pressure and water level
6
1F2: In case PCV confinement maintains
D/W pressure could not be reproduced in case PCV confinement maintained.→PCV leakage was assumed.
①RCIC manual actuation②SBO
③ Change of RCIC water source from CST to S/P
④RCIC stop⑤Sea water injection⑥S/R valve1 open⑦S/R valve open⑧explosion
D/W pressure increases due to temperature rise of S/P.
Water source of RCIC is switched from CST to S/P.
Assumption of analysis in June Report
2.A) Result of June Report and Problems (1F2)
D/W pressure
0.0
0.2
0.4
0.6
0.8
1.0
0 12 24 36 48 60 72 84 96
M
Pa
圧力
()
(h)経過時間
D/ W (○)圧力実測値
D/ W圧力( )破損無し
2Pd
1Pd
実時刻
①②
③ ④ ⑥⑤
⑧⑦
3/ 120:00
3/ 130:00
3/ 140:00
3/ 150:00
Date
D/W
pre
ssur
e (M
Pa)
Time (hr)
○:Measured data
7
2.A) Result of June Report and Problems (1F2)
1F2: Lower coolant injection case with PCV leakage Water injection (F/P) by 3/15 is 213 m3
D/W pressure is well simulated on assumption of PCV leakage (50 cm2) at an early stage.
RPV failure is calculated at 80 hrs because water injection by F/P is not enough.
Higher FP release due to assumed early PCV leakage
Analytical results
0.0
0.2
0.4
0.6
0.8
1.0
0 12 24 36 48 60 72 84 96
M
Pa
圧力
()
(h)経過時間
D/ W (○)圧力実測値2Pd
1Pd
実時刻
①②
③ ④ ⑥⑤
⑧⑦
D/ W圧力
3/ 120:00
3/ 130:00
3/ 140:00
3/ 150:00
D/W pressure
①RCIC manual actuation, SBO, ② ③ Change of RCIC water source from CST to S/P,
④RCIC stop, Sea water injection, S/R valve1 open, ⑤ ⑥⑦S/R valve open, explosion⑧
Date
D/W
pre
ssur
e (M
Pa)
Time (hr)
○:Measured data
D/W Pressure
8
2.A) Result of June Report and Problems (1F2)
0.0
0.2
0.4
0.6
0.8
1.0
0 12 24 36 48 60 72 84 96
M
Pa
圧力
()
(h)経過時間
D/ W (○)圧力実測値2Pd
1Pd
実時刻
①②
③ ④ ⑥⑤
⑧⑦
D/ W圧力
3/ 120:00
3/ 130:00
3/ 140:00
3/ 150:00
D/W pressure
①RCIC manual actuation, SBO, ② ③ Change of RCIC water source from CST to S/P,
④RCIC stop, Sea water injection, S/R valve1 open, ⑤ ⑥⑦S/R valve open, explosion⑧
Date
D/W
pre
ssur
e (M
Pa)
Time (hr)
○:Measured data
Measured D/W pressure does not increase even S/R valve opened. On the other hand, pressure increases in calculation.
D/W pressure at this stage is not simulated due to assumed PCV leakage.
Some heat removal (instead of PCV leakage) possibly occurred by then.
Problems
1F2: Lower coolant injection case with PCV leakage Water injection (F/P) by 3/15 is 213 m3
D/W Pressure
9
1F3: Lower coolant injection caseWater injection (F/P) by 3/17 is 369 m3
Much H2 is produced due to water level decrease when S/R valve opens.
RPV failure is calculated at 79 hrs because sea water injection is not enough.
FP is released to environment through W/W vent.
Analytical results
①RCIC actuation、② RCIC stop, HPCI actuation, HPCI ③ ④stop, S/R valve open, W/W vent open, water injection, ⑤⑥W/W vent close, W/W vent open, Sea water injection, ⑦ ⑧⑨W/W vent close, water injection、⑩~⑭W/W vent open⇔close
2.A) Result of June Report and Problems (1F3)
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
-4000
-2000
0
2000
4000
6000
0 24 48 72 96 120 144
(M
Pa)
炉圧
(m
m)
水位
(h)経過時間
(○ △ )、 実測値
1F3
炉圧
TAF
RPV水位
実時刻L-2 L-8と の間で推移
① ②③
⑤ ⑨~
⑩ ⑭⑪ ⑫ ⑬④
3/ 12 3/13 3/14 3/15 3/16 3/17 3/18
S/R Valve open
P/S pressure and water level
Date
Wat
er le
vel (
mm
)
P/S
pre
ssur
e (M
Pa)
Time (hr)
○,△:Measured data
P/S Pressure
Water level
10
During RCIC operation, D/W pressure is underestimated. (inverse trend to 1F2)
Measured pressure drops when HPCI actuates.
During HPCI operation, water level is not clear.
Amount of produced H2
Explosions of 1F3 and 1F4 are possibly attributed to H2 produced in 1F3
2.A) Result of June Report and Problems (1F3)
D/W pressure
Problems
0.0
0.2
0.4
0.6
0.8
1.0
0 12 24 36 48
M
Pa
圧力
()
(h)経過時間
D/ W (○)圧力実測値
D/ W圧力
2Pd
1Pd
実時刻
① ②③
④ ⑥ ⑨~
3/ 120:00
3/ 130:00
3/ 1212:00
3/ 1312:00
⑤
Date
D/W
pre
ssur
e (M
Pa)
Time (hr)
○:Measured data
D/W Pressure
11
RCIC steam exhaust pipe
Hot water
Hot water flow
Major problems; D/W pressure underestimation during RCIC operation and pressure drops after HCPI actuation.
Latest information and examination RCIC continuous operation using
return line to CST.→Assume S/P thermal stratification by
RCIC exhaust steam. (see Figs.)• Simulated by upper/lower S/P nodes and RCIC exhaust to the upper.
• HPCI initiated, steam exhausted to lower node assuming lower temp. of the water near HPCI exhaust pipe.
PCV spray during HPCI Similar pressure transition between
P/S and S/C after 42.4 hrs. →Assume RPV failure at this time.
2.B) Revised Analysis (1F3: Analytical Conditions)
12
Improved matching with measured data
D/W pressure increases during RCIC operation
Depressurization due to S/C spray ( No depressurization if thermal stratification not considered because of lower spray flow rate)
Remained problemsModeling of S/P thermal
stratification; investigation using CFD
Further investigation is needed for PCV leakage and W/W vent, which have large influence on FP release.
0
2
4
6
8
0.0
0.2
0.4
0.6
0.8
1.0
0 10 20 30 40 50 60
(MPa
)原
子炉
圧力
PCV
(MPa
)圧
力
(h)経過時間
原子炉圧力
D/ W圧力→
実時刻3/ 120:00
3/ 130:00
3/ 140:00
2.B) Revised Analysis (1F3: Analytical Result)
Date
D/W
Pre
ssur
e (M
Pa)
P/S
pre
ssur
e (M
Pa)
Time (hr)
P/S Pressure
D/W pressure
○:Measured data
P/S and D/W pressures
S/C Spray
13
2.B) Revised Analysis (1F2: Analytical Conditions)
Major problems; D/W pressure after S/R valve open. (Some heat removal instead of PCV leakage)
Latest information and examination Tsunami water flooded at a depth of boots length in RCIC room
(same level as S/P torus room) at 1:00, 3/12 and increased at 2:00.*
→Assume S/P heat removal by flooding water• 60% heat of RCIC exhaust steam is removed.
Early PCV leakage is not assumed. Instead;• Small leakage at 70 hrs because measured D/W pressure
slightly decreases. • Enlargement of leakage at 90 hrs when large pressure drop
is measured. RCIC injection rate is adjusted to simulate time when water
level comes down to TAF. Assume S/P thermal stratification (Same as 1F3).
*TEPCO, “Report regarding factual information related to the investigation results of the accident situation at Fukushima Daiichi Nuclear Power Plant,” Dec. 22, 2011.
14
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
-4000
-2000
0
2000
4000
6000
0 20 40 60 80 100
(MPa
)炉
圧
(mm
)コ
ラプ
スト水
位
(h)経過時間
(○,△ )実測値
炉圧
TAF
ダウンカマ水位
実時刻3/ 150:00
3/ 120:00
3/ 130:00
3/ 140:00
BAF
E[2]
G[5]
F[3]
C
A,B
D[1]
H[10]
P/S pressure and water level
A:RCIC manual actuation, B:SBO, C:Change of RCIC water source from CST to S/P, D[1]:RCIC stop, F[3]Sea water injection, E[2]:S/R valve1 open, G[5]:S/R valve open, H[10]explosion
2.B) Revised Analysis (1F2: Analytical Result)
P/S pressure is also simulated by adjusting RCIC injection rate
Date
Wat
er le
vel (
mm
)
P/S
pre
ssur
e (M
Pa)
Time (hr)
P/S Pressure
Water level
○△:Measured data
15
0.0
0.2
0.4
0.6
0.8
1.0
0.0
0.2
0.4
0.6
0.8
1.0
0 20 40 60 80 100
(MPa
)炉
圧
D/W
(MPa
)圧
力 (h)経過時間
(○,△ )実測値
炉圧
D/ W圧力
実時刻3/ 140:00
3/ 130:00
3/ 120:00
3/ 150:00
0.6 cm2 of leakage
Enlargement of leakage (32 cm2)
2.B) Revised Analysis (1F2: Analytical Result)
P/S and D/W pressures
High D/W pressure is reproduced.
Calculated pressure increase becomes lower and consistent with measured data.Steam through S/R
valve flows to lower level of S/P, whose temperature is lower due to thermal stratification.
Date
Wat
er le
vel (
mm
)
D/W
pre
ssur
e (M
Pa)
Time (hr)
P/S Pressure
D/W pressure
○△:Measured data
16
3. Primary System Behavior during IC operation
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
3/ 11 14:45 3/ 11 15:00 3/ 11 15:15 3/ 11 15:30 3/ 11 15:45 3/ 11 16:00 3/ 11 16:15
DAY
Rx P
ress
(MPa
,g)
RELAP5RecorderChart
EarthquakeSCRAM
IC start
IC stop
IC manualoperation
SR/ V
Isolation Condenser (IC) is a unique system for reactor cooling in unit-1, and worked at the initial stage of the accident. (ceased due to AC/DC valve power loss by the tsunami)
RELAP5/mod3 analyses were performed to investigate the IC behavior. IC functioned properly to the original design. (Not impaired by the earthquake) Sensitivity analysis shows that the core uncovery could have been avoided by
continued operation of IC after the tsunami.
IC system (Unit-1)Initial stage of the accident (after earthquake)
Assuming IC continued operation
Reactor pressure
-6000
-4000
-2000
0
2000
4000
6000
8000
3/1114:30
3/1115:00
3/1115:30
3/1116:00
3/1116:30
3/1117:00
3/1117:30
3/1118:00
3/1118:30
3/1119:00
3/1119:30
DAY
Abo
ve T
AF (m
m)
EarthquakeSCRAM
Assuming IC continuedoperation after tsunami Feed seconary
coolant
Water level above TAF
17
Hydrogen gas concentration
4. Hydrogen Mixing and Explosion in R/B
JNES is conducting analyses of hydrogen gas mixing and detonation in Reactor Buildings (R/Bs) for investing explosion phenomena during Fukushima accident.
MELCOR for hydrogen source evaluation , FLUENT(CFD code) for hydrogen gas transport and mixing, and AUTDYN for structural analysis of detonation
The objectives are to better understand the phenomena that took place in Unit 1 and Unit 3, and assess and improve the methods and tools.
CFD model of Reactor Building Mixture gas velocity
18
Some results from the analysis of detonation at unit 3
4. Hydrogen Mixing and Explosion in R/B
Debris Velocity R/B Pressure
The amount of hydrogen gas leaked into R/B is estimated to be approximately 1 ton.
If it is assumed that the leakage took place at S/C or D/W’s penetration, overall detonation behavior is well reproduced.
With initial velocity 70 m/s debris is supposed to reach at about 250 from the top of R/B at 7.1 seconds.
This photo is quoted from Fukushima-chuo TV This photo is quoted from TEPCO web
19
• JNES has been conducting various analyses of the Fukushima accident.
• Plant behavior analysis using MELCOR improved by assuming S/P thermal stratification and latest information for 1F2 and 1F3.
• P/S behavior analysis of 1F1 using RELAP5/mod3 shows IC functioned properly to the original design. (Not impaired by the earthquake)
• Detonation analysis with the assumption that leakage took place at S/C or D/W’s penetration well estimates overall R/B behavior of 1F3.
5. Conclusions