004 site & project evaluations.pdf
TRANSCRIPT
1
Site & Project Evaluation;Project Consideration;and Geometric Design
PW Lesson 4
RM Chapter 2: Sections 2.6 to 2.8
Lesson 4 – Learning Outcomes
Participants will be able to:
• List typical MSEW & RSS exploration requirements
• List agency MSEW project criteria
• Discuss geometric design considerations of facing types
Soil and Site Investigation
• A MSE Wall is not an embankment
• A MSE Wall is a structure
2
Article 10.4.2 (AASHTO, 2007)
• Subsurface explorations shall be performed to provide the information needed for design and construction. . .
• Borings should be in sufficient number and depth to establish a reliable longitudinal and transverse substrata profile . . . .
Site Evaluation Elements• Evaluate existing subsurface information
• Field reconnaissance
• Subsurface exploration– Drilling and Sampling, SPT, CPT, bulk samples– Borings spaced @ 100 ft along wall, 150 ft back
– Geophysics to reduce uncertainty between borings and planning of subsurface exploration
• Laboratory testing– Mechanical properties, grain size, index tests– Strength properties, shear (frictional)– Electrochemical properties, pH, resistivity, etc.
Typical Boring Layout
Wall boring1-2H
200 ft
100 ft150 ft
3
Soil and Site Exploration• Flexibility has limitations
• Evaluate site stability
• Settlement/bearing resistance of foundation soils
• Location of ground water
• Need for drainage
• Availability of reinforced wall fill
Subsurface Exploration Requirements
Foundation Soil
Limits of Excavation
Reinforced Zone
Drainage
Retained
Backfill
Retained Backfill
Natural Soil
Primary Causes of Substructure Movement
• Post construction settlement of approach embankment or foundation soils
• Instability of foundation soils
• Loss of support due to lateral squeeze
4
Foundation Soils Control Overall Stability
e.g., Bearing Capacity
Foundation Improvement Techniques
• Normal consolidation
• Surcharging w/ or w/o wick drains
• Stone columns
• Dynamic compaction
• Lightweight fill
• Deep foundations (e.g., piles &
drilled piers)
OWNER/AGENCY’S RESPONSIBILITY!
Ground Improvement
Testing• Identify & classify
– Mechanical properties, grain size, index tests
• Shear strength– Drained, undrained
• Consolidation
• Electrochemical
5
Shear Strength of In-Situ Soils
• Laboratory Tests including triaxial (UU, , and CD) and direct shear
• In-situ tests including CPT and field vane test
• Consider appropriate drainage condition in the field and sample disturbance
CU
Reinforced Fill Properties• Gradation• Reinforced fill top size• Plasticity• Moisture – density relations• Shear strength• Soundness• Corrosion/Degradation
– Electrochemical (metals)– Durability (geosynthetics)
See RM - Chapter 3 and PW - Lesson 5
Retained Backfill Properties• Gradation• Plasticity• Moisture – density relations• Shear strength
See RM - Chapter 3 and PW - Lesson 5
6
Selection Factors• Subsurface conditions
– bearing capacity
– settlement considerations
• Aesthetics – type of structure, MSEW or RSS
• Environmental conditions– aggressiveness of site
• Size of structure– ROW, technical limitations
• Risk
• Cost
Establishment of Project Criteria• Consider all possible alternatives
• Choose a system (MSEW or RSS)
• Choose facing system
• Identify performance criteria
• Assess environmental conditions
Performance Criteria• Load Factors
• Resistance Factors
• Lateral Deflection
• Embedment
• Design Life
• Joint Width
• Other (see manual)
7
MSEW Load & Resistance Factors
• Strength Limits – see RM Chapter 4, PW Lessons 8, 9, and 10
• Serviceability Limits – see RM Chapter 4, PW Lessons 8, 9, and 10
• Extreme Limits – see RM - Chapter 7, PW Lesson 13
Nominal Reinforcement Strength
• Nominal steel tensile strength
• Nominal geosynthetic strength
• See RM Chapter 3, PW Lesson 7
RSS Factors of Safety
• PW Lessons 13 and 14, see RM Chapters 8 & 9
8
Typical Deformation for 0.7H & H = 10’
Metallic reinf. ¾Geogrids reinf. 1.5Geotextiles 3
Lateral Deformation During Construction (Empirical) (RM Figure 2-15)
Project Criteria
Limits of Excavation
Wall EmbedmentSlope in Front of Wall
Minimum to Top of Leveling Pad
Horizontal (walls) H / 20
Horizontal (abutments) H / 10
3 Horiz : 1 Vert H / 10
2 Horiz : 1 Vert H / 7
3 Horiz : 2 Vert H / 5
• H is the total height of wall (for slopes can use H = hexposed + 2 ft)
• For sloping ground provide a bench 4 ft bench in front of wall
• Embed at least 2 ft below anticipated scour depth
• Embed below frost depth
9
LevelingPad
Facing
Reinforcement (typ.)
Reinforced Fill
RetainedBackfill
Reinforced Zone
H
ds
dh
4 ft min.
dh-min = 2 ft
Required Design Life
Structure Classification Design Life (years)
Permanent structures 75
Abutments and critical applications
100
Temporary walls < 3
See RM Chapter 3, PW Lesson 7
Limiting Differential Settlements for MSEW Facing Systems
Type of Facing Limiting Differential Settlement
Joint Width
Precast ( 30 ft2) 1 / 100 ¾-inch
Precast(30 ft2 to 75 ft2)
1 / 200 ¾-inch
Precast Full-height 1 / 500 ¾-inch
Drycast MBW 1 / 200 N/A
Welded Wire 1/50 N/A
10
Manifestation of Differential Settlements
Manifestation of Differential Settlements
Lesson 4 – Learning Outcomes
Participants will be able to:
• List typical MSEW & RSS exploration requirements
• List agency MSEW project criteria
• Discuss geometric design considerations of facing types