01 annual 2006-07 (1-53) with photos

110

Upload: dodieu

Post on 30-Dec-2016

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 01 Annual 2006-07 (1-53) with photos
Page 2: 01 Annual 2006-07 (1-53) with photos

CENTRAL POWER RESEARCH INSTITUTE

ANNUAL REPORT

2006-2007

NEW B.E.L. ROADSADASHIVANAGAR P.O.

POST BOX NO. 8066

BANGALORE - 560 080

Page 3: 01 Annual 2006-07 (1-53) with photos

FOREWORD

The year 2006-2007 has been a period of noteworthy achievements for CentralPower Research Institute with several advancements in the areas of appliedresearch, testing & certification and consultancy. The financial revenueperformance surpassed all previous records by reaching Rs. 42.73 crores duringthe year 2006-2007 vis-a-vis Rs.41.47 crores during 2005-2006. The Non-Planexpenditure during 2006-2007 was contained within Rs.39.26 crores to generateRs.3.47 crores revenue income over expenditure. For the ninteenth year insuccession, the Institute has not drawn any non-plan grant-in-aid from theGovernment of India.

In the year 2006-2007, testing and certification activities registered a high growth in terms of the number ofsamples tested and the number of customers serviced. A total of 46364 tests on 13931 samples were conductedduring the year. On the research front, 8 projects were successfully completed during the year. Some of thecompleted projects viz., Investigation on application of FACTS devices in Indian Power systems, Investigationof Grid Wind Turbine Interaction & Diesel Generator Interaction, Nano composites for flame retardantapplications – Exploratory Study,Studies on thermoplastic elastomers for halogen free, fire retardant lowsmoke cable compounds, Insulation diagnosis by high voltage spectroscopy, Establishment of researchfacility for communication protocol applicable to sub station automation, Estimation and analysis of radiatedelectromagnetic emission of switchgears, power equipment with augmented test facility for EMI measurement,have resulted in development of products and processes and the end results are directly available forcommercialization, thus benefitting the power industry.

CPRI continued to participate in Distribution Reforms as Advisor-cum-Consultant (AcC) for the purpose ofcapacity building in the state electricity boards/power utilities of Karnataka, Kerala and Andhra Pradeshunder the Accelerated Power Development & Reforms Programme (APDRP) of the Ministry of Power,Government of India.

Remaining Life Assessment(RLA), Renovation & Modernisation(R&M), Life Extension Studies (LES)and Consultancy have been the important activities during the financial year. The work involved conductingof remaining life assessment analysis of both mechanical and electrical components and also associatedstudies such as energy audit, forced outage analysis, capacity adequacy study and economic analysis of therun/repair/replace measures recommended.

Most of the CPRI laboratories have been acredited as per NABL 17025 standards and during the year and tohelp clientile in export of their equipment overseas. CPRI added its credentials with ASTA, IECEEB andISO 9001-2000 accreditations. Some officers of the Institute have also become ASTA observers. CPRI hasbeen awarded the full time member ship of the Short Circuit Liason (STL) at the 32nd STL ManagementCommittee Meeting, during the year.

During the year three capital schemes were completed as scheduled. The important amongst them are the

Centre for Collaborative Advanced Research and Centre for Industrial Solid Waste Utilisation and Upgradation

of Research and Testing of Power Capacitors. The former aimed at establishing infrastructure for visiting

Page 4: 01 Annual 2006-07 (1-53) with photos

scientists to take up colloborative research work at Institutes laboratories of significance to Indian PowerSector and the later is showcasing technologies of relevance for utilising industrial solid wastes like fly ash,marble slurry etc. Both these centres were inaugurated and dedicated to nation by Shri Sushil Kumar

Shinde, Hon’ble Union Minister of Power, during May 2006. Power Capacitors are very important equipment

in power system & a new test facility "Upgradation of Research and Testing of Power Capacitors" was

established in October 2006. The other notable achievement during the year is establishment of RTLKolkatta to test transformer Dielectrics with support of WBSEB. Institute is also establishingone moreunit at North Eastern range in Guwahati with co-operation of Assam State Electricity Board.

CPRI is backed up by over four decades of experience in applied research in products & processes,development, consultancy, etc. With a strong intellectual capital, CPRI has made a mark in testing andcertification and is already on the transnational frontiers looking forward to a strong global presence inresearch, development and testing in the International scene. [At CPRI, we value client satisfaction anddelight by sharing our knowledge and caring for their needs.]

A.K. TRIPATHY

DIRECTOR GENERAL

Page 5: 01 Annual 2006-07 (1-53) with photos

CONTENTS

Chapter Page

1. Organisation 1

2. Research & Development 11

3. Testing & Certification 23

4. System Studies 25 19

5. Promotion of CPRI Activities 31

6. MOUs Signed By the Institute 39 29

7. Capital Projects 40 31

8. Administrative Matters 44 34

9. Finance & Accounts 48 3

10. Use of Hindi as Official Language 52 42

Appendices

Appendix I The Governing Council 54

Appendix II The Standing Committee 55

Appendix III The Committee on Research 56

Appendix IV The Committee on Testing & Certification 57

Appendix V RSOP Expert Committee 58

Appendix VI Research Projects Undertaken 59

Appendix VII Personnel Deputed Abroad for Training / Presenting

Technical Papers, etc, during the year 2006-2007 62

Appendix VIII Membership of CPRI Officers in International/ 55

National Committees 66

Appendix IX Technical Papers Presented / Published by

Scientific / Engineering Officers 75

Appendix X Auditors Report 85 74

Page 6: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

1

1

CHAPTER - I

ORGANISATION

INTRODUCTION

The Central Power Research Institute (CPRI) was established by the Government of India in 1960 with HeadQuarters in Bangalore . The Institute was re-organised into an autonomous Society in the year 1978 under theaegis of the Ministry of Power, Government of India. The main objective of setting up the Institute was toserve as a National Laboratory for undertaking applied research in electrical power engineering besidesfunctioning as an independent National Testing and Certification Authority for electrical equipment andcomponents to ensure reliability and to innovate and develop new products.

OBJECTIVES OF CPRI

Function as a National Power Research Organisation for undertaking and/or sponsoring research anddevelopment projects in the fields of generation, transmission, distribution and operation of electricitysupply systems.

Provide necessary centralised research and testing facilities for evaluation of materials and performance ofpower equipment.

Serve as a National Testing and Certification Authority for the purpose of certification of rating andperformance to ensure availability of quality equipment for use under conditions prevalent in Indian PowerSystems.

Co-ordinate R&D activities in the various State Electricity Boards, Utilities and maintain liason with otherInstitutions engaged in research connected with power systems and/or power equipment. Act as an apex bodyfor initiating and co-ordinating the Research & Development in the field of electric power, the ResearchScheme on Power.

Evolve criteria for standards of various equipment for operation under Indian conditions and effectivelyparticipate in formulation of national standards.

Identify problems in the areas of basic and applied research and arrange such studies in-house and inacademic Institutions.

Collect information and maintain documentation in the field of power engineering and publish paper,periodical or report in furtherance of the objectives of the Institute.

Involve in Diagnostic, Renovation & Modernisation, Life evaluation and life extension studies of Thermaland Hydroelectric Power Plants.

Become an international recognised/accredidated laboratory to cater to electrical equipment manufacturers of Asia,Europe, Middle East etc.

MANAGEMENT

The management of the Institute vests in its Governing Council comprising members representingdifferent Ministries of the Government of India, Central Electricity Authority, State Electricity Boards, PowerSupply utilities, Indian Electrical & Electronics Manufacturer's Association, Academic and R&D Organizationsof national importance in Electrical Power Engineering. The Secretary, Ministry of Power and Chairperson,

Page 7: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

2

2

Central Electricity Authority are the President and Vice-President of the Governing Council respectively.Director General of the Institute is the Member-Secretary of the Governing Council. Composition of theGoverning Council is given in Appendix - I .

A Standing Committee under the Chairmanship of Member (Power Systems), Central Electricity Authority,with the Joint Secretary (T & R) and Joint Secretary (Financial Advisor), from the Ministry of Power asmembers and the Director General as Member Convener takes decisions on behalf of the Governing Councilfrom time to time on administrative and financial matters. The composition of this Committee is at Appendix- II.

Committee on Research and Committee on Testing & Certification are the two Committees constituted bythe Governing council to oversee & guide the respective activities of the Institute. The Member (Planning)& the Member (Power Systems) of the CEA are the Chairmen of these two Committees respectively. Thecomposition of these Committees is at Appendix - III & IV.

The Governing Council meets twice a year to deliberate on policy matters. The meetings of other committeesare held as and when required.

ORGANISATION

As a premier research organization in the field of power engineering, the Institute has several researchlaboratories and testing installations engaged in different specialised fields. The Head Office and its largestunit - Central Research & Testing Laboratory (CRTL) are at Bangalore. The other units are SwitchgearTesting & Development Station at Bhopal, Regional Testing Laboratory at Muradnagar, UHV ResearchLaboratory at Hyderabad, Thermal Research Centre at Nagpur and Energy Research Centre atThiruvananthapuram and RTL at Kolkatta. Details of organizational set-up of the Institute are indicated inthe Organization Chart.

The units comprise of various laboratories to cater to different fields of specialised activities.

The Central Research & Testing Laboratory, Bangalore

Centre for Collaborative & Advanced Research

Diagnostic, Cables, Capacitors Division

Dielectric Materials Division

Electrical Appliances Technology Division

Earthquake Vibration Research Centre

Energy Conservation & Development Division

High Voltage Division

High Power Laboratory (2500 MVA with Synthetic Testing Facility)

Instrumentation Division

Information Technology & Implementation Division

Materials Technology Division

Mechanical Engineering Division

Power Systems Division

Short Circuit Laboratory

Page 8: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

3

3

B.H. NARAYANA

ADDITIONAL DIRECTOR

K.N.SRINIVASAN

ADDITIONAL

DIRECTOR.

GOVERNING COUNCIL

PRESIDENT : ANIL RAZDAN

STANDING COMMITTEE

4 MEMBERS

COMMITTEE ON RESEARCH

21 MEMBERS

COMMITTEE ON TESTING & CERTIFICATIO1N

1 7 MEMBERS

DIRECTOR GENERAL

A.K.TRIPATHY

CHIEF ACCOUNTS

OFFICER

I.VENKATESWARA RAO

ORGANIZATION

CHART AS ON 31ST MARCH 2007

ADDITIONAL DIRECTOR

DIELECTRIC MATERIALS DIVISION

Dr. K. DWARAKANATH

JOINT DIRECTOR

HIGH VOLTAGE DIVISION

P.V.V. NAMBUDIRI

JOINT DIRECTOR

CIVIL ENGINEERING DIVISION

B,N. DINESH KUMAR

V.N.NANDAKUMAR

ADDITIONAL DIRECTOR

JOINT DIRECTOR

INSTRUMENTATION

MADHUSUDHANA

KADALUR

JOINT DIRECTOR

B.R. RAVISHANKAR

SHORT CIRCUIT LAB

ADDITIONAL DIRECTOR

K.B.MANJUNATH

P. MUNIYAPPA

ADDITIONAL DIRECTOR

TRC, KORADI

JOINT DIRECTOR

MATERIAL TECHNOLOGY

DIVISION

RAMAKRISHNA

CHIEF VIGILANCE OFFICER

GAUTHAM SENGUPTA

S. VIJAYAKUMARI

WOMEN WELFARE OFFICER

R.K.HEGDE

ADDITIONAL DIRECTOR

JOINT DIRECTOR

EARTHQUAKE ENGINEERING &

VIBRATION RESEARCH CENTRE

Dr. RAMESH BABU

P.K.KOGNOLKAR

DIRECTOR

ADDITIONAL DIRECTOR

Dr. S. SEETHARAMU

ADDITIONAL DIRECTOR

PLANNNING / LIBRARY

S. SRIDHAR

JOINT DIRECTOR

DIAGNOSTIC CABLES &

CAPACITORS DIVISION

A. SUDHINDRA

JOINT DIRECTOR

INFORMATION

TECHNOLOGY &

IMPLEMENTATION DIVISION

V. ARUNACHALAM

JOINT DIRECTOR

ELECTRICAL MAINTENANCE

M KRISHNAN

LIAISON OFFICER

SC/ST & OBC

P. NAGESWARA RAO

PUBLIC INFORMATION

OFFICER

S.SRIDHAR

GAUTHAM SENGUPTA

ADDITIONAL DIRECTOR

STDS, BHOPA

L

ADDITIONAL DIRECTOR

ONLINE TESTING STATION

UNHALE

JOINT DIRECTOR

REGIONAL TESTING

LABORATORY, MURADNAGAR

Dr. P.V. REDDY

N.S. MOHAN RAO

ADDITIONAL DIRECTOR

ADDITIONAL DIRECTOR

MECHANICAL ENGG.

DIVISION

P. KRISHNAMURTHY

ADDITIONAL DIRECTOR

UHV RESEARCH LAB.

B.GUNASEKARAN

Dr. SHIVAKUMARA ARADHYA

ADDITIONAL DIRECTOR

POWER SYSTEMS DIVISION

ADDITIONAL DIRECTOR

R&D CELL

M.M. BABUNARAYANAN

JOINT DIRECTOR

ENERGY CONSERVATION &

DEVPT. DIVISION

CENTRAL WORKSHOP

M. SIDDARTHA BHAT

JOINT DIRECTOR

HIGH POWER LAB.

JOINT DIRECTOR

ELECTRICAL APPLIANCES

& TECHNOLOGY DIVISION

K. MANOHARA

REGIONAL TESTING

LABORATORY, KOLKATA

OFFICIAL LANGUAGE

IMPLEMENTATION

JOINT DIRECTOR

CCAR

Dr. P.V. BALASUBRAMANYAM

JOINT DIRECTOR

ENERGY RESEARCH CENTRE

THIRUVANANTHAPURAM

Dr. K.R.C. NAIR

ADDITIONAL DIRECTOR

Dr. I.P.S. PAUL

HRD/TRAINING/SECURITY

JOINT DIRECTOR

MARKETING

SUHAS BAGALKOTKAR

ADMINISTRATION

PURCHASE &

STORES

Dr. SUJATHA SUBHASH

ENGINEERING OFFICER VI

MARKETING CCAR

Page 9: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

4

4

Switchgear Testing & Development Station, Bhopal

Direct Short Circuit Testing Laboratory (1500 MVA )

On-line Testing Station (100 MVA )

High Voltage Laboratory

Temperature Rise Testing Laboratory

Ingress Protection Testing Laboratory

Supplementary Test Laboratory

Regional Testing Laboratory, Muradnagar

Cables and Capacitors Laboratory

High Voltage Laboratory

Insulation Laboratory

Liquid Dielectrics Laboratory

Thermal Research Centre, Nagpur

Coal analysis Laboratory

Metallurgy Laboratory

Water Chemistry Laboratory

Non-destructive testing Laboratory

Condition monitoring Laboratory

Environmental Monitoring Laboratory

Mobile environmental monitoring station

UHV Research Laboratory, Hyderabad

Pollution Laboratory

Impulse Laboratory

Power Frequency Laboratory

Vibration Laboratory

RTL Kolkatta

Transformer Oil Testing Laboratory

Mobile Van

UNITS & THEIR ACTIVITIES

CENTRAL RESEARCH & TESTING LABORATORY (CRTL), BANGALORECENTRE FOR COLLABORATIVE AND ADVANCED RESEARCH (CCAR)

Centre for Collaborative and advanced research has been established in 2006 with a view to promoting advanced

research which will benefit power sector with advanced technologies.

Page 10: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

5

5

The main objectives of the centre are:

to Provide infrastructure for professionals to carry out Research in power Development

to create conducive environment for collaborative

research between R&D Institutions, Industry and

Academia.

to execute projects based on Multi - disciplinary

expertise from different institutions

dissemination of expertise through continuing

education initiative and advanced degree program.

increase interaction globally among research

organizations and groups.

Diagnostic, Cables, Capacitors Division

This division has facilities for carrying out R&D work and also for testing and evaluation of all types of

capacitors, cables, cable accessories, motor and transformer insulation, partial discharge measurement of HV

equipment as per the relevant National and International standards. Expertise is also available for diagnostic,

RLA and LE (life extension) studies on electrical equipment and for detailed investigations of specific

research and developmental problems in these areas. The division has the following laboratories:

Cables and Capacitors Laboratory

Diagnostic Laboratory

Dielectric Materials Division

This division has comprehensive testing and evaluation facilities on insulating materials and systems.

Insulating materials are evaluated and tested for electrical mechanical, physical and electro chemical thermal

properties. This division undertakes consultancy work and sponsored projects for different power utilities

& industries. This division is also involved in R&D of polymeric insulators for electric equipment. Wide range

of thermoplastics and thermosets are extensively used as insulators, bushings, etc. Polymer laboratory has

well experienced technical personnel to advise polymer industries in setting up plants, process improvement,

etc. This division has transfered technology of transformer oil reclamation to Electricity Boards and Manufacturers,

enterprenuers. The Liquid Dielectric lab has developed new technologies for D.G. Analysis. This division has

the following laboratories:

Liquid Dielectrics Laboratory

Polymer Laboratory

Insulation Laboratory

Lubricating Oil laboratory

Page 11: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

6

6

Information Technology & Implementation Division

This division is the backbone of all IT activities at CPRI which caters to both Software and Hardware needs of the

organisation. The division is built with the state of the art dedicated servers which runs on various platforms like

Sun Solaris, SCO Unix, Linux and Windows and also maintain NAS storage devices. The division also takes care

of the LAN built with fiber optic backbone and internet service. The web portal of CPRI, Digital Library and

knowledge management portals are maintained by this division.

Electrical Appliances Technology Division

The important activities of this division include performance testing and certification on low voltage

equipment. The laboratories operating under this division are:

Domestic Electrical Appliances Laboratory

Ingress Protection Laboratory

Battery Testing Laboratory

Illumination Laboratory

Fan Testing Laboratory

Flame - Proof Testing Laboratory

Rotating Machine Testing Laboratory

Refregerator testing laboratory

Earthquake Vibration Research Centre

The Earthquake Vibration Research Centre is equipped with necessary

facilities for providing testing, research and consultancy services in the area

of seismic and vibration qualification of instruments /equipment for nuclear

power plants and other generating stations as per National & International

Standards. In addition, this centre offers consultancy in checking the design

adequacy of structures/bridges models for seismic qualification.

Energy Conservation & Development Division

Energy Conservation & Development Division takes up studies & investigate problems pertaining to Energy

Audit, Energy Conservation & Field Engineering Services of Power plants. This is a virtual division created

with experts drawn from various disciplines within CPRI. This division is also providing interdisciplinary field

study packages to thermal power stations and process industries on remaining life estimation, renovation,

modernisation, upgradation and life extension of components, sub-systems and plants.

Page 12: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

7

7

High Voltage Division

This division has facilities for testing and certification of High Voltage electrical equipment & for performance,

evaluation and investigation of R&D problems in the area of HV & EHV transmission of electric power. The

following laboratories operate under this division:

High Voltage Laboratory

Mobile Field Testing Laboratory

Pollution Laboratory

High Power Laboratory

This laboratory provides facilities for development, testing and certification of EHV circuit breakers, power

transformers, current transformers, isolators, line (wave) traps, reactors, insulator strings etc., for performance

evaluation under short circuit and other switching conditions. Facilities available under this laboratory are

as follows:

Direct testing facility upto 2500 MVA, 72.5 kV, 3 phase and 1400 MVA, 245 kV, Single Phase

Synthetic Testing Facility for Extra High Voltage Circuit Breakers rated upto 400 kV, 63 kA

Instrumentation Division

This division has facilities for research and development of electronic instrumentation for power systems.This

division has the following laboratories:

Power Electronics Laboratory

Laser and Fibre Optics Laboratory

Micro Processor based Instrumentation Laboratory

Calibration Laboratory

Energy Meter Testing Laboratory

Relay Testing Laboratory

Uninterrupted Power Supply Laboratory

Materials Technology Division

This division has different laboratories for testing and

development of organic and inorganic materials, evaluation of

coal, water, etc. The laboratories operating under this

division are:

Materials Characterization and Engineering

Corrosion Laboratory.

Analytical Facilities. Power Station Technology and Field

Engineering Application

Page 13: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

8

8

Wear & Erosion and Mechanical Test Facilities.

Fuel Analysis and Combustion Research Laboratory such as Coal, sawdust etc.

Remaining Life Assessment and Renovation & Modernization.

Industrial Solid Waste Utilization.

Mechanical Engineering Division

This division is engaged in the study of Mechanical Engineering problems in the transmission systems so

as to achieve economy & reliability and also to offer solutions to the problems experienced by the Electrical

Utilities. Design and Consultancy services for evolving optimised tower design are also undertaken by the

Design Cell. In addition, this division has got the following laboratories to conduct R&D work and also to

provide testing facilities to the manufacturers of transmission towers, line components & accessories,

vibration dampers, spacer/spacer dampers, energy meters, etc. The laboratories operating under this division

are:

Prototype Tower Testing Station

Model Tower Testing Laboratory

Structural Materials Testing Laboratory

Tower Foundation Testing Centre

Vibration Laboratory

Wake Simulation Laboratory

Power Systems Division

This Division is involved in the study of various problems encountered by manufacturers and utilities in the

design, installation and operation of electric power systems, using both the mathematical and physical

models. The division has the following facilities:

Power System Simulation centre with High Voltage Direct Current (HVDC) simulator and Transient

Network Analyser (TNA)

Real Time Digital Simulator (RTDS)

Short Circuit Laboratory

This laboratory has facilities to undertake testing, certification and development of LT switchgear, fuse gear

and power system apparatus. Applied research is also undertaken to lend a helping hand in development of

indigenous products.

SWITCHGEAR TESTING & DEVELOPMENTSTATION, BHOPAL

The Switchgear Testing & Development Station, Bhopal was set

up along with the Bangalore complex in 1960. The laboratory

provides 1500 MVA SC alternator based test facilities for testing

and certification of EHV circuit breakers, power transformers,

Page 14: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

9

9

isolators, line (wave) traps, reactors, insulator strings etc., for performance evaluation under short circuit and

other abnormal conditions. In addition 100 MVA On-line Testing Station is a special facility in the station

which enables testing & certification of LT and HV switchgear, Energy Meter Testing Laboratory, 25 kA heat

run test laboratory, HV test test laboratory, Instrument transformer test laboratory and Calibration laboratory

supplements the tessts performed in H.P lab at STDS Bhopal.

REGIONAL TESTING LABORATORY, MURADNAGAR

The Regional Testing Laboratory is located in the NTPC’s Central Satellite Earth Station Campus,

Muradnagar. The laboratory undertakes testing & certification of solid insulating materials, insulating oils,

LT & HT power cables & accessories, LT capacitors and insulators, small and medium transformers used in

power equipment.

THERMAL RESEARCH CENTRE, NAGPUR

This centre situated near Koradi Thermal Power Station, Koradi is mainly intended for taking up R&D work

pertaining to Thermal Power Stations. The centre is also equipped to take up consultancy work in the area

of environmental impact assessment, investigations on fuel treatment, ignition studies, coal characteristics,

pilot scale studies for coal gassification, slurry fuels, life estimation of thermal power plant components, R&M

of Thermal Power Plants etc. Thermal Research Centre mainly undertakes RLA &RM of Thermal Power Stations

and has given consultancy to morethan twenty thermal power stations.

UHV RESEARCH LABORATORY, HYDERABAD

The UHV Research Laboratory has the necessary infrastructure to simulate actual operating voltage conditions

on an experimental line in the range of 220 kV to 1200 kV to evaluate the suitability and adaptability of UHV

systems to Indian power systems taking into account the climatic, environmental, ecological and biological

conditions prevailing in our country. The facility can evaluate corona loss, audible noise, radio & television

interference, electric field etc., under various voltage and climatic conditions. Besides, the laboratory has the

capacity to cater to electrical manufacturers for their investigatory and commercial tests of equipment rated upto

1200 kV class. This is a unique facility in this part of the world.

Page 15: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

10

10

REGIONAL TESTING LABORATORY, KOLKATA

The Regional Testing Laboratory, Kolkata is setup with a view to cater to the testing, certification and evaluation

needs of electrical power equipment manufacturing industries, utilities and consumers in the eastern region.

The laboratory is equipped with facilities to carry out testing of insulating oils in power transformers as per IS

1866-2000. The Dissolved GAs Analysis on power transformers, an important diagnostic tool is available at RTL

Kolkata for assessing the internal condition of the transformers. The laboratory has the test facilities line High

Performance Liquid Chromatography (HPLC) to evaluate Furfural content which is an important diagnistic

tool for assessing the condition of solid insulation in power transformers. The facility is also being used for

assessing the inhibitor level in the transformer oil.

Page 16: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

11

11

CHAPTER - II

RESEARCH & DEVELOPMENT

CPRI has been taking up R&D programs in various areas of electrical power generation, transmission and

distribution in its endeavor to assist utilities to supply reliable and quality power to the consumers. The broad

objectives with which the research projects are taken up in CPRI are:

1. Offering technical advise and trouble shooting

2. Product development and improvement to meet global standards

3. Bridging gap in testing and develop special testing technologies

4. Large collaborative research projects with utilities and industries.

5. Electrical products and process Improvement

While some are undertaken in collaboration with industries & utilities, while others are taken up in-house to

develop the expertise and infrastructure to serve the power sector. The project proposals are planned well in

advance keeping in mind the needs of the industry / utilities and are cleared by the Committee on Research.

The project monitoring committee was constituted for the purpose of periodical review of the progress and to

suggest measures for timely completion of the projects as per the project implementation plan.

During the year under report 23 projects with total outlay of Rs. 624.81 lakhs were investigated. Among the

projects investigated 8 projects have been completed during the year. Six new projects at a total outlay of Rs. 204

lakhs have been taken up during the year.

Some of the completed projects have resulted in development of products and processes and the end results are

directly available for commercialization, thus benefiting the power industry. List of developments are given

below:

Investigation on application of FACTS devices in Indian Power systemsObjective of the project:

(a) To investigate the control interactions of various Flexible Alternating Current Transmission System

(FACTS) devices.

(b) To explore the optimal location of selected FACTS devices in Indian system

Power system Engineers are currently facing challenges to increase the power transfer capability of the

transmission line. The proven technologies are High Voltage Direct Current (HVDC) transmission & FACTS

devices and the latter one offers an economical solution for maintaining steady state & transient stability margins.

With the recent addition of FACTS devices to Indian power system it is necessary to investigate the control

interactions of FACTS devices in the same electrical area. The frequency ranges of the different control

interactions have been classified as steady state interactions (0Hz), Electromechanical Oscillations (0-3/5Hz),

Control or small signal Oscillations (2-15Hz), Sub-Synchronous Resonance (SSR) Interactions (10-50Hz) &

High frequency interactions (>15 Hz).

Page 17: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

12

12

NREB system in India was chosen to investigate the control interactions of various FACTS devices as it comprises

of Static VAr Compensator (SVC) at Kanpur, Thyristor controlled series compensation (TCSC) on Kanpur –

Ballabgarh line and Rihand- Dadri HVDC line. Load flow analysis was carried out in SIMPOW software for the

reduced North region electricity board system and base case was finalized so that they are no steady state

interactions. Eigen value analysis was carried out and different modes of oscillations were found for this multi

machine system. Among the different electro mechanical modes it is found that one mode of 0.8Hz was most

critical. As the standard controller for TCSC is not available, controller was designed in SIMPOW using Dynamic

Simulation Language through small signal analysis. Various signals were considered for design of damping

controller as the choice of input signal was very critical to effectiveness of TCSC and Voltage across transmission

path was found to be most suitable control signal for damping the power oscillations.

Control or small signal Oscillations are investigated by plotting the impedance plots in frequency scanning

method and it is found that there is no parallel resonance. High frequency interactions were studied by considering

the 3 phase to ground faults at different buses & found that the critical inter-area mode was excited and oscillations

were damped out by TCSC damping controller. It was also found through simulation that, SVC located at

KANPUR was not effective in damping power oscillations compared to TCSC damping controller. It was also

observed that HVDC is very good in damping inter-area oscillations but excites local modes.

As critical modes identified and damped with the design of TCSC controller are not excited with the presence

of TCSC & HVDC controls in Northern Region Electricity Board (NREB) system it is concluded that there are

no control interactions in NREB system.

Achieved results:

Developed expertise to investigate application and interaction of multiple FACTS devices in Indian Power

systems.

Benefits:

Studying the controller interactions of multiple FACTS devices is a crucial in the Indian Power Systems with

multiple FACTS devices being added.

Studying the controller interactions of multiple FACTS devices is a subject of research world wide and proposed

study will contribute to the existing knowledge in this field.

This Study enhances the Research and Development strengths of the division and enables us to take up the

additional consultancy services in this area.

Investigation of Grid Wind Turbine Interaction & Diesel Generator Interaction

Objective of the project :

The objectives of the project were to study the important technical issues relevant to the interconnected operation

of different types of wind turbines with utility grid such as:

1. Modeling of different types of wind generators:

Asynchronous Squirrel cage induction generator (Fixed speed turbine)

Page 18: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

13

13

2. Dynamic performance of

Induction generators directly connected to the utility AC grid

Doubly fed induction generators connected to the utility AC grid for disturbances such as

(a) Change in wind speed

(b) Faults within the wind farm

(c) Voltage dips in the utility grid

(d) Variation in frequency in the utility grid

3. Performance of Diesel Generator integrated with wind generator

The above aspects have been studied and compared through simulation studies using MATLAB software.

Achieved results:

1. This project has helped in increasing the knowledge on the transient/ dynamic behavior of wind farm

systems and their interaction with the rest of the power system under various system contingencies.

2. The study results indicate that integrating of wind farms to the grid necessitates planning/feasibility

studies to be performed.

Benefits:

Consultancy services in this area can also be taken up by the division.

Nano composites for flame retardant applications – Exploratory StudyObjective of the project

To prepare Nanofillers in the laboratory by chemical method.

To develop composites using nanofillers for Fire Retardant Low Smoke Cable application (FRLS).

Achievements:

Combustion method was used for development of nano filler, based on alumina. The characterization of laboratory

prepared nano filler was done using Thermo-Gravemetric Analysis (TGA), Differential Scanning calorimeter

(DSC), Scanning Electron Microscope (SEM), Particle Analysis, X-ray Fluorescence Spectrometer (XRF) and

X-ray Diffracto meter (XRD) . Using Sherr’s equation the particle size of the filler was calculated and was found

to be in the range of 42 nm.

Alumina filler developed was used in Polyvinyl Chloride (PVC) formulations and comparative evaluations were

carried out in respect of mechanical, electrical and Flame retardant and low smoke properties. The new formulation

was comparable in electrical properties with composites made using commercial nanoclay.

Page 19: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

14

14

Benefits

Laboratory prepared alumina-nano filler showed superior characteristics as compared to the commercially

available nano clay.

Results indicate the superior PVC composites using the lab prepared nano filler.

Tensile strength and % Elongation were improved to a considerable extent.

Studies on thermoplastic elastomers for halogen free, fire retardant low smoke cablecompounds

Objectives of the project

To develop halofen based Low smoke Flame Retardant Wire & Cable Compounds by using Ethylene

Propylene Di-monomer (EPDM), Ethylene Vinyl Acetate (EVA), Nitrile Rubber and other thermoplastic

elastomers.

Achievements

EPDM based formulations were evaluated for oxygen index, smoke

density, halogen acid and Ultra violet (UV) stability studies. The

formulations showed excellent properties for fire retardant applications.

Trial extrusions were carried out at CIPET Mysore. During extrusion

temperature rise was observed in middle zones of extruder and

indicated the need for additional cooling in these zones for EPDM

based systems.

Benefits:

The developed compositions were satisfactory.

The base formulation developed using EPDM has been filed in the form of a patent.

Insulation diagnosis by high voltage spectroscopyObjective of the project

To characterize the extent of deterioration of dielectrics in

frequency domain with application to Power transformer

and Power Cable Systems, employing HV Dielectric

Spectroscopy.

Adaptation of this technique as a diagnostic tool for

assessing the condition of insulation in Power transformers

and MV Power cable systems in-service.

The results of the investigation to be used to formulate

guidelines on remedial measures.

Page 20: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

15

15

The condition assessment of power station equipment is fast emerging as a diagnostic tool for the maintenance

of the equipment. Most of the utilities are aware of the importance of the condition based monitoring of the

equipment. Transformers and Power cable systems play a vital role in the Power system network.

During the project, detailed investigations were carried out by measuring dielectric parameters in frequency

domain on transformers of various ratings and also on MV Power Cable systems, to evaluate the extent of

deterioration and also to categorize the type of degradation using state of art equipment, HV Dielectric

Spectroscopy. By adapting this technique, an effective diagnostic tool for assessing the condition of insulation in

Power transformers and MV Power cable systems in-service, could be established.

Experiments were carried out in the laboratory on model transformers and on representative power cable samples

of Paper Insulated Lead-Covered (PILC), Cross Linked Poly Ethylene (XLPE) & mixed power cable systems, by

subjecting them to accelerated electrical stress. At various interval of ageing, dielectric parameters like Dielectric

loss, Power Factor, Capacitance & Permittivity in frequency domain were monitored.

Transformers of various ratings and on MV Power Cable systems to assess their healthiness.

Achievements:

After analyzing the data obtained on transformer insulation, both at site and in the laboratory, it was possible to

distinguish the degradation due to each dielectric medium (oil or paper) from a single spectrum. Moisture

content in cellulosic insulation and conductivity of the oil could be estimated. It was also observed that

measurements of dielectric parameters in frequency domain yielded more information on the insulation

system,compared to those monitored at power frequency.

A pilot project was undertaken with one of the utilities to assess the condition of the Power cables in their

distribution network. During this project, a large number of MV Power cable systems with different types of

joints & terminations were monitored for their healthiness. From the analysis of the voluminous data obtained

from the laboratory studies as well as from field measurements, it was possible to estimate the moisture content

in PILC cables and identify the influence of accessories on the cable system. The study also helped to identify

the deterioration of XLPE Power cables due to presence of water trees. The power cables could be ranked based

on the extent of deterioration of the cable insulation system.

Benefits:

The analysis of the large data bank created during the investigation, by conducting measurements in the

laboratory and also on in-service Transformers & Power cable systems, has helped in suggesting guidelines on

remedial measures to be taken for maintenance & replacement strategy based on the extent of degradation of

the dielectric medium.

From this it could be established that the technique using Dielectric Spectroscopy is a sensitive diagnostic tool

to assess the healthiness of in-service Power Transformers & MV Power Cable Systems.

Page 21: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

16

16

Establishment of research facility for communication protocol applicable to sub stationautomation

Objective of the project

Electric power transmission utilities were among the first industrial

entities to embrace data telemetry and telecontrol on a wide scale.

Remote monitoring and control systems were first implemented

in the early 60’s and have progressively grown and evolved since

then. Early SCADA systems provided very rudimentary monitoring,

logging of digital chances and periodic sampling of analog data.

System integrators were confronted with a difficult challenge

whenever equipment from different vendors was integrated into a

single system. The different control protocols, parameters and operational philosophies often meant that it was

difficult and some times impossible to make the disparate components operate sensibly in a similar combinations

of equipment, their differing operational regimes and priorities sometimes prevented useful cost cutting through

sharing of design or integration information.

In the light of these difficulties, system integrators perceived the need for standardization of interfaces between

control equipment so as to reduce the cost and complexity of control system integration and testing.

Achievements:

CPRI has set up a comprehensive utility Competency Centre to address Product certification to various

protocols like IEC 61850, 60870 etc, Training utility personnel and offering consultancy services.

CPRI represents Indian Utilities’ interest at International forums regarding substation automation protocol.

Became Member in international organization like Modbus, DNP, OPC Foundation and UCA

Benefits:

CPRI conducted one International Workshop for over 350 persons.

The project has created new markets for protocol testing for utilities and manufacturers

Estimation and analysis of radiated electromagnetic emission of switchgears, powerequipment with augmented test facility for EMI measurement

Objective of the project

Development of test facilities for testing of Energy Meter for radiated electromagnetic emission test as per

the new IEC standards

Page 22: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

17

17

Obtaining data on electromagnetic radiation generated by switchgears & power equipment and analysis &

estimation of electromagnetic radiation in the vicinity of these equipments

Achievements:

Test facility for radiated electromagnetic emission in Open Area Test Site as per standard CISPR – 22 has been

developed. Experiments were carried out to obtain electromagnetic radiated emission data of various equipments

– like Motor, Industrial Drilling Machine, Moulded case circuit breaker (MCCB) , Welding Machine, Air circuit

breaker (ACB) etc.

The experiments were carried out in open area test site using the test facilities developed. The experiments

were also carried out using other methods to find out the emission from power line of the equipment. With this

it was found that the noise in most of the case of power equipment was not from the equipment itself but it was

more carried in the power line cable of the equipment. The experiments were carried out in the range of 30 MHz

to 1.0 GHz.

Benefits:

The test facility for testing of Energy Meters as per IEC 62052-11 has been developed. The old standard for

Energy meters IEC 60687 and IEC 61036 have been changed to IEC 62052-11, IEC 62053-21 and IEC 62053-22,

wherein the testing method has been changed. Therefore by developing the open area test site for radiated

emission testing we are able to comply with the new standards and also we could retain the above test in the

NABL scope of accreditation.

Data on radiated emission of various power equipments and switchgear has been obtained which gives the level

of radiation of radiated electromagnetic emission of these equipments. The data can be provided to BIS and

IEC, which could be used for deciding appropriate tests methods for these equipments.

MoP provides funds under RSOP for Applied Research / Technology development to Academic Institutions /

R&D organizations / Institutes / Utilities etc. This Research fund is managed by CPRI since the year 2001.

CPRI has advertised the scheme in several fora and also through the website so that Industry / Institutes /

Utilities can collaborate in various research activities in the area of power. Till date 62 projects are under

investigation by 20 organizations including, IISc, TNEB, ERDA, IIT-Bombay, IIT-Kanpur, IIT-Roorkee, RRL-

Bhopal, NTPC etc.

During the year 2006-07, 23 projects with an outlay of Rs. 431.16 lakhs were under investigation at sixteen

organizations like ERDA, IISc, IIT, Madras, IIT, Kharagpur, IIT, Roorkee, TNEB, KPTCL, MVIT, RVCE, CET,

BHU, IIT, Mumbai , IIIT, Hyderabad, SJVNL, PSEB etc.

Eleven projects, studied by TNEB, IIT-Kanpur, IIT-Roorkee, NTPC, ERDA, KPTCL, IIT-Mumbai, CPRI and

ERC Thiruvananthapuram, were completed during the year.

Page 23: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

18

18

RSOP PROJECTS COMPLETED DURING 2006-07

Sl.No. Title of the Project Investigating Agency

1 Performance Evaluation of LT Capacitors under Transients CPRI

2 Development of newer materials for electrical applications IISc, Bangalore

3 Design & development of 2500 MVA Master Circuit Breaker

components. CPRI-HPL

4 Study on methods of testing and condition monitoring of on

load tap charger (OLTC) in power/auto transformers TNEB

5 Study on method monitoring current transformer insulation

through tan-delta testing and to establish normal values of

tan delta for various make CT’s and age groups. TNEB

6 Comparative evaluation of different types of 6.6 kV auxiliary

circuit breakers. TNEB

7 Study on Tan-delta and capacitance value of HV transformers

bushings including, the effect of source voltage variants on

tan-delta value and arriving at acceptable limit values for

in-service bushings. TNEB

8 Study on failure of capacitor voltage transformers in

EHV sub-stations. TNEB

9 Development of active power line conditiners for power

distribution systems. IIT, KANPUR

10 Enhancement of power systems’ performance using flexible

AC transmission systems (FACTS) in competitive power market IIT, KANPUR

11 Developing and characterizing thermoplastic/thermo set-fly

as composites for technical/industrial applications. IISc, Bangalore

RSOP Expert Committee Meeting was held on 22nd January, 2007, to discuss new and ongoing RSOP Projects,

which are to be taken up during 2007-08.

Page 24: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

19

19

NATIONAL PERSPECTIVE PLAN

The Indian Power Sector is facing major challenges today with the introduction of reforms, globalization and

liberalization policy of the government. Despite our country’s the power system planners have given utmost

importance to energy sector since beginning and there being manifold increase in installed generation capacity

and transmission networks. With increase in system expansion stability and security problems have become

challenging. It is of vital importance to focus our attention now on ways and means to build expertise within the

country, to find solutions for the problems existing in the system and also for the problems that may arise in the

future. Research is urgently needed to bridge the knowledge and technology gaps, more so due to changes in

technology today at a more profound and faster pace in the new millennium.

Realizing the importance of Research & Development, The Ministry of Power constituted a Standing Committee

on R&D to frame 15 years national Perspective Plan for R&D in Indian Power Sector under the chairmanship of

Chairman, Central Electricty Authority and CPRI as member convenor. While formulating the National Perspective

Plan, it is important to critically review the growth of power sector, assess the existing R&D infrastructure in the

country and identify the crucial R&D needs for the power sector. All the key players like CEA, CPRI, NTPC,

POWERGRID, NHPC, NEEPCO, BBMB, DVC, NPTI, THDC, SJVNL, BHEL and IIT’s have participated in this

task and brought out R&D plan report.

The crucial R&D needs required to bridge the technology gaps in various subsections of power sector (Generation,

Transmission & Distribution), are identified and prioritized. The R&D needs aim at either improving design of

an individual plant component and/or evolving cost efficient overall process. R&D needs also include taking

advantage of the advances in IT, electronics and communication to improve the control & instrumentation

system, data acquisition system and monitoring of system performance parameters. The major thrust areas for

R&D are:

Thermal Power Generation: (i) Measures to improve plan availability, reliability, efficiency and safety (ii)

Beneficiation of Coal © RLA and T&M (d) Green technology approaches to thermal technology (e) Gasification

of solid and liquid fuels for power generation.

Hydro Power generation: (i) Silt erosion (ii) Measures for performance improvement © Renovation and

uprating and (iii) Hydro Environmental Interface.

Transmission: (i) Grid operation and control (ii) Transmission equipment (iii) FACTS and (iv) Advances in

HVDC transmission.

Distribution: (i) Measures to reduce losses (ii) Advanced metering (iii) Distribution Automation (iv) Custom

Power Devices (v) Demand Side Management (iv) Power sector reforms etc.

New and Renewable energy: Technologies related to Wind, Biomass, Solar are identified under this thrust

area.

Page 25: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

20

20

All the programmes under NPP are being co-ordinated by CPRI and currently the following R & D porjects are

ongoing :

1. Development of Silt Erosion Resistant Material for Turbines of Hydro generators

Nature of study : Applied Research

Project Implementing Organization : NML

Project Funding Organization : NHPC and MoP

2. National Effort to develop Technology for Custom Power Devices

Nature of study : Development and demonstration

Project Implementing Organization : C-DAC and BHEL

Project Funding Organization : C-DAC, BHEL and MoP

3. Development of Superconducting TransformersNature of study : Development and Demonstration

Project Implementing Organization : EMCO, Mumbai

Project Funding Organization : EMCO and MoP

4. To develop a prototype of 132kV Optical Current Transformer for use in the 132kV systemNature of study : Development and Demonstration

Project Implementing Organization : ERDA

Project Funding Organization : ERDA and MoP

TECHNICAL PAPERS

Dessemination of information relating to R&D work carried out in the Institute through presentation/publicationof technical papers is another important activity of the Institute. 120 technical papers including 36 Internationaltechnical papers were presented/published by Engineering/Scientific Officers at various symposia, workshopsand seminars and in technical journals (Appendix - IX). For presenting technical papers in InternationalConferences and for attending training programs, 20 officers of the Institute were deputed abroad during theyear (Appendix - VII). All officers who were sent abroad for training/presentation of papers made detailedpresentations through internal seminars/lectures to share their experience and knowledge gained abroad.

PATENTS FILED

Institute has filed the complete patent specifications in respect of the following innovations:

Patents awarded:

1. Card operated pre-paid energy meter using novel card reading technique

2. Development of digital techniques for measurement of resistive leakage current in zinc oxide arrester

3. Flame retardant low smoke compound based on pvc for cable application

Page 26: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

21

21

Complete specifications filed:1. A device for locating diametrically opposite point & measuring diameter accurately inside large,

cylindrical, spherical or conical shells

2. Stabilized zirconia plasma sprayable powder and industrial process for its manufacture

3. Thermal barrier coatings from fly ash derived cenospheres

4. Composition for polymeric high voltage insulators for outdoor applications

5. A device for carrying out inspection inside a shaft rotor bore

6. Nitrogen hetero cycle as an accelarator for curing of epoxy resin system

7. A system for measuring thermal energy gained by a water storage tank

New patent applications:1. A device for carrying out inspection inside a shaft rotor bore

2. Nitrogen hetero cycle as an accelarator for curing of epoxy resin system

3. A system for measuring thermal energy gained by a water storage tank

BRIEF NOTE ON THE NEW PATENT APPLIED

1. A DEVICE FOR CARRYING AND MANIPULATING ULTRASONIC PROBE FORINSPECTION INSIDE A SHAFT/ROTOR BORE

Inspection inside bore of a rotor is often required to assess integrity of shaft or rotor. Since approach is notgenerally available for manipulating the transducer or probe with hand, a mechanism/device is used forcarrying out required movement and other manipulations. Several devices are in use but are disadvantageous.In view of this, a new design was attempted to alleviate some disadvantages of the systems. The result is acompact device, which can perform the task. The basic kinematic arrangement is as described below.

The actuator which carried the inspection head assembly, is supported on two sets of rollers in two differenttransverse planes at ends in such a way that the actuator can slide over the rollers in axial direction. Theactuator support roller assemblies are mounted in radial directions on the flanges of a rotary carrier. Therotary carrier is supported by two roller assemblies. The carrier can rotate in circumferential direction. Thisarrangement allows the actuator to move along the axial and circumferential directions simultaneously andindependently. The carrier support roller assemblies are supported on a frame. While rotating, the entirecarrier unit is prevented to shift in axial direction by means of axial guide rollers resting on a collar extendingfrom carrier.

2. NITROGEN HETEROCYCLE AS AN ACCELERATOR FOR CURING OF EPOXY RESINSYSTEM

With an objective of developing suitable accelerator/curing agent based on nitrogen heterocycles for curingof epoxy resins used for electrical applications, the investigation on nitrogen heterocycles on cure propertiesof epoxy resins has been carried out. Epoxy resins are currently among the most intensively investigatedcompounds as electrical insulators owing to their remarkable chemical resistance, good adhesion,extraordinary toughness high mechanical strength and good heat resistance. The applications of epoxyresin depend on the nature of curing. Generally curing takes place in the presence of a hardener or a curingagent. Chemical reactions that take place during the period of curing determine the properties of the curedthermoset material. A large number of nitrogen heterocycles based on several metals and ligands have beenstudied with regards to their cure behaviour with epoxy resins used for electrical applications.

Page 27: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

22

22

The data suggests that the presence of 2-3 bis (benzimidazolyl) pyridine is effective in curing process of theepoxy resin system with appreciable reduction in the cure time of the resin system. At 1400C, it is observedthat at a concentration of 0.0625 phr of the ligand the cure time decreases from 293 minutes to 40 minutes.The reduction of cure time of epoxy resin systems in an industry at the time of manufacturing variousinsulating components is of commercial importance. It is suggested that the manufacturing industries canmake use of the newly developed accelerators, which can efficiently work in place of conventional type ofaccelerators. The effect of this ligand on the electrical properties has been studied and found that at lowerconcentrations no deterioration of the loss factor values was observed even at elevated temperatures.

3. A SYSTEM FOR MEASURING THERMAL ENERGY GAINED BY A WATER STORAGETANK

The main objective of the invention is to measure the thermal energy gained by each isothermal layer ofstorage water heating system and integrating to compute the total energy absorbed in the tank. Anotherobjective is to precisely track the energy inputs and energy outputs to the solar water heaters therebyauditing the energy flows through the system and detecting performance deterioration in thermal systems.The thermal efficiency of the system is computed using the data on solar radiation input and the energyoutput. The metering of thermal energy enables the estimation of the output energy developed by theprocess. Based on measurement of incident solar radiation and its integration and the energy output of thecollector, the thermal efficiency of the collector can be computed for a heating period.

The advantages of this meter over other meters are:

a) Static in nature with no moving parts

b) Accuracy upto 10%

c) Maintenance free

d) No costly replacements needed

Page 28: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

23

23

CHAPTER - III

TESTING AND CERTIFICATION

The performance of the Institute in the field of testing and certification during the year 2006-2007 has beenspectacular. A total of 46364 tests on 13931 samples were conducted for 3156 organisations.

The revenue realised from testing, certification and consultancy services rendered during this year increasedto Rs. 4273 lakhs as against Rs. 4147 lakhs realised during 2005-2006. The excess of income over theexpenditure (surplus) during the year was Rs.347 lakhs.

SPECIAL TESTS CONDUCTED

Some of the important testing assignments undertaken by the Institute during the year are listed below:

MCCB’s & Distribution Boards

MCC Panel Boards for M/s. Egyptian Jordanian Electrical Switch Manufacturing Company, Jordan, forASTA Certification

MCBs, Distribution Boards & CT for M/s. Middle East Electrical Meter Factory Company, Riyadh, for ASTACertification

MCCBs for Middle East Circuit Breaker Company, Riyadh, for ASTA Certification

Distribution Boards for M/s. Advanced Electro Engineering industries, Riyadh, for ASTA Certification

MCCBs for M/s. Farah Trading Company, Saudi Arabia, for ASTA Certification

Circuit Breakers

Tested Pole Mounted outdoor type 12 kV, 20 kA Vacuum Circuit Breaker for M/s. Andrewyule, Calcutta

800 kV breaker tested for the first time in UHVRL, Hyderabad

Vibration

Seismic qualification test on 36 kV & 12 kV Vacuum Circuit Breaker forM/s. Siemens Ltd., ThaneSeismic qualification test on 420 kV Circuit Breaker for M/s. CromptonGreaves Ltd., NasikVibration test on Pentographs were carried for M/s. Stone India Ltd., KolkattaFatigue Vibration test on the 220 kV, 90/120kN composite silicon rubberinsulator for the first time in CPRI for Gujarat Electricity TransmissionCompany, Gujarat (GETCO)800 kV single V suspension string consisting of glass insulatortested for M/s. Sediver, France

Transmission Towers

400 kV multi-circuit tower (4ckts) for the first time in India forM/s. Power Grid Corportion of India Ltd.Gurgaon400 kV tower tested for M/s. ONGC

Capacitors

Testing of 1000 kVAR, 525 V, 3 phase LT capacitor for the firsttime in the country for M/s.Electrical Components SDN, BHD,Malaysia

Page 29: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

24

24

High speed Automatic Transfer Switches upto 3 pole, 480 Volts, 1600 Amps for M/s. Triad Software, Ltd.,ChennaiDynamic testing of Distance & Transformer Differential relays for M/s. GE, Areva

Testing of Composite Intellegent Load Management System Controller (CILMS), for M/s. ABB, Bangalore

500 KVAR, 8.4kV (2 Nos.) ageing tests for 1000 hours under progress for M/s.ABB, Bangalore. This test wereconducted for the first time in CPRI.

200 kVAR, 7.3 kV HT capacitor for tested as per IEEE 18-2002 for M/s.Shreem Capacitors, Jaysingpur.

Temperature test and climatic test on power supply outdoor module and battery cabinet of M/s.ZTETelecome Pvt.Ltd., Mumbai for the first time.

Type tests and OVC of 500 kVAR, 8.4 kV 1 dia HT capacitor. CPRI is testing capacitors of rating 500 KVAR forthe first time for Endurance & OVC test.

Carried out Endurance test on full size capacitor of rating 500 KVAR for the first time in India as per IEC60871, Part-II – 199 for M/s.ABB Ltd.

Carried out Climatic test as per TEC’s QM 333 standard. During the climatic test, performance test andfunctional test as per M/s.ZTE Telecom Ltd. and M/s.Tata Tele Services Ltd. protocols were carried out.

Discharge current test on series capacitor 552 kVAR, 7.1 kV for the first time in the country for M/s.ABB,Bangalore.

Carried out 100 kVAR, 525 V self healing type LT capacitor test for the first time for M/s.Electrical ComponentsSdn.Bhd, Malaysia.

Environment

Environmental condition testing on PLCC of M/s.BPL, Palghat as per QM 333 specification.

NEW TEST FACILITIES CREATED

During the year under report, to keep abreast with the latest technological developments in the field, theInstitute has added the following testing facilities to cater to the growing demands of the Industry :

Ultrasonic Time of flight diffraction (TOFD) inspection facility for characterization of flaw.

Automatic test bench for MCB & MCCBs.

Chamber for 28 days test and reliability test on switchgear equipment .

Total Sulphur Analyser - for testing total Sulphur.

Mercaptan Analyser - for testing active Sulphur.

Discharge current test facility for HT series capacitors as per IEC 60143-1-2004. Tested 552.5 kVAR,7.1 kV HT series capacitor for the first time.

Disconnecting test on fuses for HT capacitors. Tested 600 kVAR, 12 kV HT capacitor for the first time.

Endurance test on full size units (2 Nos.) of rating 500 kVAR, 8.4 kV for the first time.

Rotor Reflectometer for testing of Rotor windings of turbo and hydro generators.

Transformer winding resistance measurement.

A X-ray diffractometer of Panlytical, The Netherlands, Make to determine the crystalline phases in variousmaterials and their quantification has been installed and commissioned and the same has been put to useregularly .

The magnetic barkhausen noise equipment of Stresstech, Finland Make to measure the residual stressin ferro magnetic materials has been added to the existing facility .

Page 30: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

25

25

CHAPTER - IV

SYSTEM STUDIES

Consultancy is one of the major activities of the Institute. The following are some of the importantConsultancy services rendered by the Institute during the year under report :

SPECIAL CONSULTANCY JOBS UNDERTAKEN DURING THE YEARPower System Studies

Power System Studies for M/s. Sharq Sohar Steel Rolling Mills, Sultanate of Oman

System Studies for Transco 220 kV system, Delhi Transco, New Delhi

System studies to evaluate the behaviour of HVDC controllers for ± 800 kV HVDCSystem for Power GridCorporation of India Ltd.

System studies to assess the State Level Additional Transmission requirements for Power FinanceCorpn.of India Ltd.,

System Studies for Rourkela Steel Plant

Power Evacuation Study for North Delhi Powr Ltd. (NDPL) Network, M/s. NDPL, New Delhi

System studies for Raichur Thermal Power Plant (RTPS) for M/s. KPCL, Bangalore

Load flow study of transmission & subtransmission network in Maharashtra - for Maharashtra ElectricityRegulatory Commission, Mumbai

Harmonics measurements in the existing power system at Steel Authority of India, Rourkela SteelPlant, Rourkela

Harmonic measurements and analysis at Essar Steel Limited, Hazira, Surat from M/s.IDEA, Chennai

Harmonic measurements at M/s. Roorkela Steel Plant, Roorkela

Grounding StudiesGrounding Studies, Technical Trade Links, Bangalore

Grounding Studies, M/s. Rhode & Schweitzer, Bangalore

Seismic Qualification StudiesSeismic qualification of Stack box with VRLA Battery as per UBC zone 4 of GR 63Core for M/s. HBL NIFELtd. Hyderabad

Third Party InspectionFinal inspection of 2 Nos., 100 MVA , 200kV/132 kV , 3 phase auto transformers at M/s. BharatBijalee Ltd., Thane, for HVPNL, Haryana

Pre-commissioning test on two circuits 1 x 240 sq.mm, 66kV XLPE cable at KPTCL, Hubli substationfor M/s.Easun Products of India Pvt.Ltd., Chennai.

Inspection on 100 MVA Transformer at M/s. EMCO, Thane, for Jammu & Kashmir State ElectricityBoard.

Pre-commissioning test on 33kV class XLPE power cables at M/s. Rourkela Steel Plant, Rourkela.

Pre-commissioning tests on 1 x 630 Sq.mm, 66 kV XLPE Cable at 66 kV/33 kV Substation,Himangala, Chitradurga Dist. Form/s.ENERCON, Bangalore

Page 31: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

26

26

Pre-commissioning tests on 66 kV XLPE cable was carried out for M/s.Easun Power Products, Chennai.

Witnessing of routine tests on 7 Nos. of 400 kV class CVT’s at M/s. Areva T&D Instrument TransformerIndia Pvt.Ltd., Bangalore.

Third Party Inspection was carried out to witness electrical routine tests and temperature rise tests on2 Nos. 25 MVA Transformer at M/s.Kirloskar Electric Company, Mysore.

At the request of M/s.AREVA, Bangalore, third party inspection was carried out on 220 CVT’s and 400 kVCVT’s and 9 Nos. 220 CT,s.

Third Party Inspection was carried out to witness electrical routine tests and temperature rise tests on2 Nos. 25 MVA Transformer at M/s.Kirloskar Electric Company, Mysore.

Carried out on 220 CVT’s and 400 kV CVT’s and 9 Nos. 220 CT,s. for M/s. AREVA, Bangalore

Pre-commissioning tests for four 110 kV XLPE cable circuits at M/s. TNEB, Chennai from

Pre-commissioning tests on two 66 kV XLPE cable circuits at M/s. KPTCL, Bangalore

Pre-commissioning test on 66kV XLPE cable was carried out at M/s.KPTCL substation, Bangalore

Pre-commissioning test was carried out on two circuits on 110kV XLPE cable at M/s.TNEB, Chennai.

Inspection of rewound 100 HP motor as per the requirement of M/s. Abhiman Electricals, Bangalore atWheel & Axel Factory, Yelahanka

Inspection & testing of motors for M/s. Auma India Ltd., Bangalore

Inspection & testing of motors for M/s. Trident Power Crafts Pvt., Ltd., Bangalore

Endurance test on actuator for M/s. Auma India Ltd., Bangalore

Witnessing endurance test on actuator for M/s. Auma India Ltd., Bangalore

Witnessing the testing of CFL for BIS Certification at M/s. Asian Electronics Ltd., Nasik

Witness test on Domestic Modular switches were carried out at M/s. Toyama Electric Ltd., Hoskote forM/s. Wipro Ltd., Bangalore

Final inspection of 2 Nos of 100 MVA, 200kV/132/kV, 3 phase auto transformers of /s. Bharat Bijalee Ltd.,Thane, for M/s. Haryana Vidyuth Prasaran Nigam Ltd. Haryana

Inspection of 20 MVA transformer at M/s. EMCO, thane for J&K Electricity Board

Inspection of 100 MVA Transformer at M/s. EMCO, Thane for M/s. Haryana Vidyuth Prasaran NigamLtd. Haryana

Inspection of 200 MVA transformer at at M/s. EMCO Ltd. Thane for M/s. ABB, Baroda

Inspection of 100 MVA transformer at M/s. EMCO Ltd. Thane for M/s. ABB, Baroda

Inspection of 20/25 MVA & 10/12.5 transformer at M/s. IMP Power Ltd., Mumbai

Diagnostics and Condition Monitoring StudiesDiagnostic testsPower Transformers and Instrument Transformers at Rastriya Inspant Nigam Ltd.,Visakapatnam.

AE testing on Generating Station Unit Transformer (Unit-I) 250 MVA at MTPS, Mettru Dam.

Condition Monitoring tests were carried out on 400 kV Reactor for M/s.Maharashtra State EletricityTransmission Co.Ltd., Durgapur, Maharashtra

Page 32: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

27

27

Condition Monitoring tests were carried out on Power Transformers, CT’s, CVT’s Cables and Bus barsat M/s.Jawaharlal Nehru Port Trust, Navi Mumbai

Condition Monitoring tests were carried out on Transformers at the works of M/s.Crompton GreavesLtd., Mumbai

Condition Monitoring tests on Hydro Generator (Unit # 5) at Nagarjuna Sagar Hydro Scheme,APGENCO, Nagarjuna Nagar.

Environmental conditioning tests were conducted on tail rotor blace, fluid stick damper, snubber bearingof all indigenously developed ALH (Advanced Light Helicopter) as per Centre of Excellence R&DDivision. This cyclic and temperature humidity cycles were conducted for the first time in DCCD,CPRI for HAL, Bangalore.

Diagnostic tests were conducted on 12 kV 50 MVA Short Circuit Generator and its accessories motorsat Short Circuit laboratory, CRTL, Bangalore

Diagnostic tests were conducted on 2 Nos. of 1500 MVA Short Circuit Generators and Motors (3 Nos.)STDS, Bhopal.

Diagnostic tests were conducted on 12 kV 50 MVA Short Circuit Generator and its accessories motorsat Short Circuit laboratory, CRTL, Bangalore

Diagnostic tests were conducted on 2 Nos. of 1500 MVA Short Circuit Generators and Motors (3 Nos.)STDS, Bhopal.

Condition Monitoring tests on 3 Nos. of Diesel Generators & 1 No. of Turbo Generator at CoromonadelFertilizers Ltd., Visakapatnam.

AE testing on Transformer of rating 290 MVA, 18/230 kV at M/s.ST CMS Electric Co., Neyveli forM/s.Crompton Greaves Ltd., Mumbai

ELCID test on 60MW Hydro Generators and Tan delta test on 220kV CT’s at NHPC, Baira Siul HydroStation, Surangani (H.P)

ELCID test and wedge mapping test on Short Circuit Generator No. 2 and RSO test on Rotor of ShortCircuit Generator No.1 at STDS, CPRI, Bhopal.

ELCID Wedge Mapping tests and RSO test on Rotor of short circuit generator at STDS, CPRI, Bhopal.

Page 33: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

28

28

Tan delta and FRA tests on Transformers at Kirloskar Electrical Company, Mysore.

Dielectric test on Turbo Generator of NPCIL, Kaiga.

AE testing on +/- 500 kV HVDC transformer, Pole 2 R phase at Rihand site of PGCIL, Rihand

AE testing on 315 MVA 4/220 kV transformer ICT 1 & 2 at 400/220 kV substation, Jamshedpur ofPGCIL, ERTS-I, Patna

AE testing on 315 MVA 4/220 kV transformer ICT 1, 2 & 3 at 400/220 kV substation, Biharsheriff ofPGCIL ERTS-I, Patna

Diagnostic testing on transformer bushing at Jamde Valve, Ghatnandhar substation of MSEB forM/s.Areva T&D, Bangalore

Diagnostic testing of substation equipment at WBSEB, Kolkata

Condition Monitoring tests were conducted on power house and switchyard equipment like Generators(6 Nos.), Power Transformers (21 Nos.), LA’s (60 Nos.), CT’s & CVT’s (54 Nos.) and ELCID test onStator core of Hydro Generator # 3 at NHPC, Salal Hydro Power Station, J&K

Condition Monitoring tests were conducted on substation equipment like 400 kV Shunt Reactor (1No.), 400kV Oil filled power cables (6 Nos.), CVT’s (6 Nos.) at NHPC, Uri Hydro Power Station, J&K

Condition Monitoring tests on Hydro Generators, Generator Transaformers, CT’s & LA’s at NHPC,Tanakpur Power House, Bambassa (Uttarakhanda)

AE testing on Reactor (1 No.) at Uri Hydro Power Station, NHPC, Uri

PD measurements were carried out on 13.8 kV, 100 MW Hydro Generator at Nagarjunsagar PowerHouse,, APGENCO, Hyderabad.

Diagnostic tests were carried out on 11 kV, 55 MW Steam Turbine Generator at GMR Energy Ltd.,Mangalore.

Diagnostic tests were carried out on 220/400 kV substation equipment at Zeerut substation, WBSEB,Kolkata have been completed.

Condition Monitoring test on generating and switchyard equipment is in progress at Loktak PowerStation, NHPC, Manipur.

RLA StudiesRLA study on 11kV/220kV Generator Transformers Unit # 2 and Partial Discharge tests on Unit # 4 atCaptive Power Plant, NALCO, Angul, Orissa.

Carried out RLA studies on 8 Nos. of 220 kV Power Transformers at various Substations of Assam StateElectric Transmission Corporation Ltd., Assam.

RLA studies on Generator Transformer (19 Nos.) at Hydro Generating Stations of KPCL (1st phase).

RLA studies on Generator Transformer at Vijayawada Thermal Power Station, Vijayawada.

RVM tests were conducted on 165 MVA Generator transformer at NagjhariPower Station, KPCL, Ambikanagar for M/s.Abhirami Engg. Works, Chennai

Characterisation of Flyash Cenospheres generated at NTPC, Ramagundam

Corrosion mapping studies of critical water valve boiler tubes at Tanda TPS NTPC, Tanda

Stress analysis of critical power cycle pipe lines and hanger support inspection at Tanda TPS and RihandTPS of NTPC

Page 34: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

29

29

Data analysis measurements were carried out at M/s. Haryana Vidyuth Prasaran Nigam Ltd., Karnal

Feasibility of using emulsion grade PVC resin insead of suspension grade PVC Resin at Central ExixeDepartment premises, New Delhi

Environmental StudiesTechno – Environment feasibility report on the integrated waste to energy project, Mandur, BangaloreEast, to be put up by M/s. Srinivasa Gayathri Resource Recovery Ltd., (SGRRL), in Association withBangalore Mahanagara Palike (BMP)” – M/s. SGRRL, Bangalore.

Material Characterisation StudiesStudy to assess Pozzolanic Property of Ground Fly ash (Characterization of Ground Fly ash) at SMPPNTPC , Simhadri

Establishing Correlation between Blaine’s fineness and particle size of fly ash of NTPC, TSTPP” –NTPC, Kaniha, Talcher.

Validation of Structural DesignDesign checking/analysis of 100m, 70m, 50m microwave towers for M/s. IMI Software Ltd., Hyderabad

Design approval of 2 Nos. 90m ground based microwave towers and 30m roof top tower for M/s. IMISoftwares, Ltd. Hyderabad.

Designing checking/analysis of 220/110kV M/C, Type ‘MA’ ‘MB’ ‘MC’ & ‘MD’ type broad based towersfor M/s. Reliance Energy Ltd., Mumbai.

Design of 33 kV D/C, ‘DA’ ‘DB’ ‘DC’ & ‘DD’ type towers and foundation for M/s. Sagar Power (N) Pvt.Ltd. , Bangalore.

Investighation on failure analysis of 220kV M/C, Type ‘MD’ tower for M/s. K. Ramachandra Rao Co., Ltd.,Hyderabad.

Design checking/analysis of 220/110kV M/C, ‘NA’ ‘NB’ ‘NC’ NS+12m’& ‘NS+21m’ type narrow basedtowers for M/s. Reliance Energy Ltd., Mumbai.

Design checking/analysis of 220kV D/C, ‘DA’ ‘DB’ ‘DC’ ‘DD’ DDS+9m’ type towers for M/s. RelianceEnergy Ltd., Mumbai.

Design checking/analysis of 220kV D/C, DDS+25m’ ‘BVX’ ‘BMX’ (Rever crossing towers) for M/s.Reliance Energy Ltd., Mumbai.

Accelerated Power Development & Reforms Programme (APDRP)

Central Power Research Institute (CPRI) has been functioning as Advisor-Cum-Consultant (AcC) for the purpose

of capacity building in the State Electricity Boards (SEBs) / Power Utilities of Karnataka, Kerala and Andhra

Pradesh under the ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (APDRP) of

Government of India since 2001. This prestigious consultancy appointment has been made by the Ministry of

Power, Government of India considering CPRI’s expertise in the areas of Power Transmission and distribution

studies and also similar consultancy services rendered by CPRI to Electricity Regulatory Commissions in India.

Initially, activities were confined to three distribution Circles in each of the above states in which the up gradation

of Sub-transmission and Distribution System were being carried out under the APDRP.

Page 35: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

30

30

Since May 2005, the activities of CPRI as AcC have been extended to the entire states of Andhra Pradesh,

Karnataka and Kerala in addition to the three circles per state assigned earlier since majority of towns in these

states were also included in the APDRP Scheme for up gradation.

Benefits due to implementation of APDRP:

Andhra Pradesh: Eastern Power Distribution Co. Ltd (EPDCL) of Andhra Pradesh has achieved AT&C loss of

less than 10% for the entire utility, which is an important landmark achieved for the first time by any utility in the

country.

Karnataka: Zero percent Distribution Transformer failure rate has been achieved in Bangalore Metropolitan

Area of BESCOM. Bangalore is the only city in India to achieve this milestone.

Kerala: The Distribution failure rate in the entire Kerala is less than 4.5%, which is a major achievement.

Due to the focused programme of Energy audits by CPRI in major towns of Andhra Pradesh, Karnataka &

Kerala, the need for AT&C loss reduction has gained momentum in these states.

Average Revenue Realization has increased, the power supply quality has improved, the rate of Distribution

Transformer failure is reduced, and Average Technical and Commercial Losses have consistently reduced

in all the three states.

CPRI has played an important role as AcC in assisting the utilities by monitoring continuously the implementation

of the Distribution reforms, contributing to better practices in Distribution system, Quality assurance etc.

Page 36: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

31

31

CHAPTER - V

PROMOTION OF CPRI ACTIVITIESCPRI ON INTERNET

Information on the expertise/ unique facilities available at the Institute for consultancy & quality assurancetesting and certification of power system equipment in units at Bangalore, Bhopal, Muradnagar, Nagpur,Hyderabad, Thiruvananthapuram and Kolkatta is now accessible for the benefit of power system equipmentmanufacturers and utilities in India and abroad at the following home page address:

Bangalore : http://cpri.in Hyderabad : [email protected] : [email protected] Thiruvananthapuram : [email protected] : [email protected]

WORKSHOP/SEMINARS, TRAINING PROGRAMS

The Institute organised several training programs and workshops during the year to exchange the knowledgeto Power utilities and the power system equipment manufacturers in the area of testing, research and productdevelopment etc., Following are the Workshops, Seminars, Training Programs organised by the Instituteduring the year:

INTERNATIONAL WORKSHOP ON “IEC 61850”

The Institute organized an International Workshop on “IEC 61850 Communication Networks and System inSubstations & Interoperability Demonstration”, from April 25th 2006 to 28th April 2006. More than 350 participantsattended the workshop from India and Abroad. The workshop was chaired by Shri. A. K. Tripathy, DirectorGeneral, CPRI. Shri. Rakesh Nath, Chairman C.E.A, New Delhi & Bhakra Beas management Board inauguratedthe workshop and delivered the Presidential address. Shri. R. N. Nayak, Executive Director, Power Grid Corporationof India Limited, Gurgaon delivered the Key note address.

WORKSHOP ON SESMIC QUALIFICATION OF ELECTRICAL EQUIPMENT ANDSTRUCTURES

The Institute organized a workshop on “Sesmic Qualification of Electrical Equipment and structure” to sharethe professional experience and dissemination of knowledge. Shri.C.P. Singh, Director (E, R&D), Bharat HeavyElectricals Ltd., New delhi, inaugurated the two day workshop on Thursday, 23rd November 2006. Shri. A. K.Tripathy, Director General, CPRI, presided over the function.

Page 37: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

32

32

NATIONAL SEMINAR ON “POWER CABLE TECHNOLOGY”

The national Seminar on “Power Cable Technology” was held at CPRI, Bangalore, India on 7th & 8th December

2006. About 130 participants from manufacturers, utilities, academic institutions and senior officers from CPRI

participated in the Seminar. About 12 foreign participants from countries like USA, Dubai, Germany, Switzerland,

Korea also participated in the Seminar.

There were total 32 invited research papers from the participants covering topics on latest trends and developments

in raw materials and processing techniques. Papers were also presented on recent developments in raw material

and processing techniques. Papers were also presented on recent developments in fire retardant cables, installation,

operation & maintenance and failure analysis of power cable accessories and diagnostic testing.

Shri. M. K. De, IAS, Chairman, West Bengal State Electricity Board inaugurated the seminar. Shri. A. K. Tripathy,

Director General, CPRI briefed the participants about the facilities available in CPRI on testing and evaluation of

power cables and accessories.

SEMINAR ON “NEW DIRECTIONS IN CERAMICS”

Central Power Research Institute (CPRI) and Indian Ceramic society – Bangalore Chapter (ICS- BC), jointly

organised a seminar titled “New Directions In Ceramics” on 17th March 2007. Shri. A. K. Tripathy, Director

General CPRI inaugurated the seminar. Five technical papers were presented by invited speakers from various

R&D organizations. A total of 70 delegates representing CGCRI, BHEL- EPD, NAL, CUMI, CPRI, ceramic

experts and consultants took part in the seminar. The delegates evinced keen interest in the seminar and

participated in the discussions.

WORKSHOP ON POLYMER COMPOSITES

Workshop on “Advanced Polymer Composite Materials Technology including the development of cenosphere

based polymer composites for the power sector”. organized at the Institute. About 85 deligates representing

BHEL (EPD), IISc (CED), MICO, Fiberglass Industries, ADA, Graphite India Ltd., Farcom Cables, Mehar

Capacitors Pvt. Ltd., Lakshmanan Isola Pvt. Ltd., KPCL and Academic Institutes participated actively in the

discussions during the workshop.

Page 38: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

33

33

INTERNATIONAL CONFERENCE AND TUTORIALS ON POWER SYSTEMPROTECTIONThe Institute organised a International Conference and Tutorialson Power system Protection during 20- 23 February 2007. TheConference, slated for the first two days, was attended by around 55participants including academicians, Personnel from Utilities andmanufacturers. The conference and workshop was inaugurated byShri. Veeraraghavan, General manager, Electronic Division, BHEL,Bangalore and Prof. P. K. Dash, Director, Bubaneshwar College ofEngineering delivered the key note address. The Tutorial was wellappreciated by the participants.

TRAINING PROGRAMSTRAINING TENAGA NASIONAL BERHAD ( R) QA INSPECTORSThe Central Power Research Institute bagged a prestigious contract for training of M/s. Tenaga Nasional Berhad(Research) QA Inspectors at Kuala Lumpur, Malaysia. The training was organized in the area of Meteringequipment and Enhancement of QA Process. The training on metering equipment was held from 17th to 25th

April 2006. Eleven participants attended the programme. The training on enhancement of QA process was heldfrom 17th to 22nd April 2006 and was attended by 22 participants. Seven Officers from CPRI delivered lecturescovering metering and QA topics. The programme was well appreciated by Tenaga Nasional Berhad (Research).

TRAINING PROGRAM ON PIPING AND HANGER INSPECTIONThree day training programme on “Testing and Inspection of Pipe and Hanger components of Thermal PowerStations” for the NTPC executives was organized on 26-27 April, 2006.

TRAINING PROGRAM ON ENERGY METERSThe Institute has conducted “Training program on energy meters” for officials of M/s. Bhuthan Power CorporationLtd., Thimphu: Bhutan from 8th June 06 to 14th June 06. Ten deligates attended the program. The topic coveredduring courses are principles of energy meters, components and their behavior, quality aspects, testing, standards,terminology, advanced metering aspects, AMR & Prepaid meter,Protocol and tampering prevention. A study tour to Larsen &Toubro, Mysore was also arranged during training period.

TRAINING PROGRAM ON POLLUTION LEVELMEASUREMENT AND HIGH VOLTAGE TESTINGTECHNIQUES FOR PGCIL ENGINEERS AT CPRI

The Institute conducted two days training programme in twobatches from 8th June 2006 to 9th June 2006 and 24th August, 2006 to25th August 2006 for the Engineers of PGCIL. The High VoltageDivision of CPRI conducted this programme for the benefit ofPGCIL Engineers working on NER- NR HVDC TransmissionSystem between Kemang HEP and lower Subansiri HEP. Thefollowing topics were covered in the Training Programme.

Design of External Insulation from the point of view of pollution and pollution test methods.

Pollution monitoring in high voltage transmission system and remedial measures.

Polymeric insulators in HV transmission system.

Page 39: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

34

34

TRAINING PROGRAM ON TEST FACILITIES

Five day training program on “Test Facility at CPRI” wasorganized at the Institute from 24 -28 July 2006. Shri. A.K.Tripathy, Director General, CPRI Inaugurated the five daytraining program on 24 July 2006 at the Auditorium ofcentre for Colloborative Advanced Research Centre, CPRI.Thirty three delegates from RITES- Mumbai andHaryana, TNEB- Chennai, KPTCL – Bangalore,APTRANSCO – Hyderabad, KPCL – Bangalore, PSEB –Patiala, KSEB – Thiruvananthapuram, BHEL – New Delhi,NABL - New Delhi, UPRVUNL – Uttar Pradesh, IndianRegistrar of Shipping – Bangalore and Saravana Insulators Ltd., Cuddalore. Participated in the training programTechnical lectures and laboratory visits were arranged during the course of programme.

Shri. A. K. Tripathy, Director General, CPRI awarded certificates to all participants during the valedictoryfunction held on 28th July 2006.

TRAINING PROGRAMME FOR TNB RESEARCH SDN BHD, MALAYSIA ON SELECTEDEQUIPMENT USED BY ELECTRICAL SUPPLY INDUSTRY

The Training Programme for TNB Research Sdn Bhd, Malaysia on main equipment used by electrical supplyindustry was held in Shah Alam from 7th August to 18th August 2006. The training for the 5th Batch of QualityAssurance Inspectors of TNB organized by TNB Research Sdn Bhd (“TNRD”). 36 participants attended theprogram. The program was inaugurated on 7th August 2006 by Dr. Salim Sairan, Managing Director of TNRD andclosed on 18th August 2006 by Senior General Manager of TNRD, En Azmi Omar. The subject covered by thetraining program were on Power Distribution Transformers, Circuit breakers and switches (air insulated), Powercables and accessories, Gas insulated switchgear (GIS), Surge arrestor and insulators and High voltage and highpower laboratories.

Participants were evaluated before and after the completion of the training programme to assess the extent ofutilization of the programme. This evaluation showed a marked improvement in the knowledge acquired byparticipants during training program.

Page 40: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

35

35

TRAININING PROGRAM ON TESTING AND DIAGNOSTICS OF LUBRICATING OIL

The Dielectric Materials Division of the Institute organized a Training Program on “Testing and Diagnostics ofLubricating Oil” from 7th and 8th December 2006 for the first time. The training program was inaugurated byShri. K. P. S. Varma, ED/M&C, RDSO, Lucknow on 7th December 2006. Seventeen participants from variousorganizations attended the two day programme. Technical Lectures were delivered by the officers of DielectricMaterial Division and other organizations from India and abroad. The demonstrations on various lubricating oiltest were arranged during the period. Shri. A. K .Tripathy, Director General, CPRI awarded the certificates to theparticipants at the valedictory function held on 8th December 2006.

TRAINING OF DISTRIBUTION ENGINEERS UNDER THE DRUM PROGRAM

The Distribution Reforms and Upgradation Management (DRUM) under the Ministry of Power, Govt. of India& USAID is aimed at training and capacity building at the management, operational and technical level of Stateutilities targetting junior and middle level officials of the distribution utilities. CPRI organised 5 day trainingprogrammes for utility engineers in the areas of :

Best practices in distribution loss reduction.

Disaster management, Electrical safety procedures and accident prevention.

Demand side management.

The Institute has entered into an MoU with BESCOM for training its engineers on the above subjects. Engineersfrom other ESCOMs of Karnataka like MESCOM, GESCOM, HESCOM, CHESCO, etc., are also being trained.Till date CPRI has conducted 16 training programs and trained around 400 engineers under the DRUMprogramme co-ordinated by the Energy Conservation & Development Division.

TRAINING PROGRAMME ON ENERGY METERS AND PROTECTIVE RELAY

The Instrumentation Division of the Institute organized a 5-day Training programme on Energy and ProtectiveRelays for Senior officials of Punjab State Electricity Board from February 20th to 26th, 2007 at the CCAR Seminar

Hall. 13 persons participated in the Training Programme. Technical presentations on Energy meters protective

relays were made during the Programme by officers of CPRI including supplementary test facilities. Industrial

visits to M/s. Larsen Toubro, Mysore, M/s. Easun Reyrolle, Hosur and M/s. Conzerv, Bangalore were arranged as

a part of the programme.

Page 41: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

36

36

TRAINING TNBR (QA) ENGINEERS, MALAYSIA

Training program on type Testing of Power Equipment, was

organized for the eight TNBR (QA) Engineers in CPRI from 12th

March 2007 to 23rd march 2007. The program was inaugurated on

12th March 2007 by Shri. A. K. Tripathy, Director General, CPRI.

Technical Lectures Laboratory demonstrations and training on type

testing of equipments were organized during the period.

TUTORIAL ON POWER SYSTEM GROUNDINGPRACTICES

Power System Division of the Institute organized a two day “Tutorial on Power System Grounding Practices” on

16th and 17th November 2006 with an objective of providing theoretical and practical knowledge on economic

design and maintenance of grounding system and their applications. 56 participants from 36 organizations from

all over the country and Bhutan participated. Practical demonstration was given to the participants on use of

CPRI’s GMAT software for earth mat design and on measurement of Soil resistivity and Grounding resistivity.

TUTORIAL ON “REAL TIME DIGITAL SIMULATION “ AT IIT, ROURKEE (NPSC 2006)

The fourteenth National Power Systems Conference (NPSC 06) was organised at Indian Institute of Technology,

Rourkee during 26-29, December 2006. The conference was preceeded by four tutorials on 26th December 2006

by invited experts in the power sector covering power system protection, HVDC & FACTS, Distribution systems

and Real time digital simulation.

CPRI conducted the tutorial on ‘Real Time Digital Simulation’ at IIT, Rourkee jointly with Prof. A. Gole of

University of Manitoba, Canada on 26th December 2006. The tutorial was attended by more than 75 delegates

from academic institutions, industries and consulting organizations.

TUTORIAL ON “MODERN TRENDS IN EARTHING PRACTICES” AT KSEB

The Institute conducted a 2-day Tutorial on “Modern Trends in Earthing Practices” for engineers of Kerala State

Electricity Board in Thiruvananthapuram during 8-9 February 2007. The tutorial was organized by the Research

wing of KSEB and inaugurated by Shri. T. M. Manoharan, Chairman, KSEB. 45 participants drawn from different

wings of KSEB attended the programme. The main topics covered at the Tutorial included (i)

Computer- aided design of HV / EHV earthing systems (ii) measurements of soil resistivity & earth resistance

and (iii) system earthing aspects. There was also a demonstration of the GMAT software developed by CPRI for

design of grounding systems.

EIGHTEENTH JAWAHARLAL NEHRU MEMORIAL LECTURE

The eighteenth Jawaharlal Nehru Memorial lecture on “Measuring and Assessing Science” was delivered by

Prof. P. Balaram, Director, Indian Institute of Science, Bangalore. Shri. Santhosh Kumar, Member (Grid Operation

& Distribution) Central Electricity Authority, New Delhi, presided over the function and delivered the presidential

address. Shri. A. K. Tripathy, Director General, welcomed the gathering. Large number of distinguished invitees,

officers, staff and retired officials of CPRI attended the program. The staff and their family members turned out

in large number to view the variety entertainment programme performed by the employees and their children

and the CPRI Colony Ladies Club members.

Page 42: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

37

37

The institute kept open all its laboratories for general public/research and educational Institutions. The

continuous stream of visitors went round the laboratories wetting their intellectual appetite. It was heartening

sight to see that majority of the people were students from various schools and colleges.

EXHIBITIONS

CPRI PARTICIPATED IN GULF COUNCIL CO-OPERATION CIGRE EXIBITION

CPRI participated in the recently held GCC CIGRE exhibition at Abu Dhabi, UAE. The exhibition cum CIGREConference was held on 29th and 30th of November 2006. The CPRI stall attracted more than 250 visitors duringthe two days including many high level dignitaries of local utilitiesin the Middle East and Africa. H E Minister of Energy of UAE alsopaid a visit to CPRI stall and showed keen interest in the activities ofCPRI. During this visit CPRI officials made a presentation aboutCPRI facilities and international accreditations to the senior officialsof Abu Dhabi Water and Electricity Authority (ADWEA). CPRIofficers also met senior officials of Dubai Electricity and WaterAuthority (DEWA) and appraised them about CPRI’s facilities andinternational accreditations.

CPRI PARTICIPATED IN INDIA INTERNATIONALTRADE FAIR 2006

The institute participated in India International Trade Fair 2006(IITF) held at Pragati Maidan, New Delhi from 14th – 27th November2006. CPRI stall was in the Ministry of Power pavilion. Many visitorsevinced keen interest in the field of Research, Testing &Consultancy, field Engineering services and third party inspectionservices of CPRI. By participating in IITF 2006, CPRI showcased itsstrength to support power utilities in particular and general publicat large. Shri. Suhas. S. Bagalkotker, Dr. P. V. Reddy Join Directors,Shri. K. Ravikumar, Scientific Officer & and other officers mannedthe stall.

Page 43: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

38

38

CPRI PARTICIPATED IN EL- ASIA 2007

The institute participated in ELASIA 2007 Exhibition from 23rd – 26th February 2007 held at Palace Grounds inBangalore. Shri. Ramachandra Gowda, Hon’ble Minister for Science & Technology, Govt. of Karnataka, inauguratedthe exhibition. All leading electrical equipment manufactures, multinationals and PSU’s participated in theevent. The exhibition attracted over 10,000 visitors over the four days.

CPRI stall attracted large number of visitors who evinced keen interest in the field of Research, Testing &Consultancy, field measurements and third party inspection services of CPRI. CPRI officials delivered a shortpresentation on short circuit and energy meter test facilities to a large group of Engineers who visited theexhibition.

CPRI PARTICIPATED IN GRIDTECH -2007

The Institute participated in the Gridtech 2007 at Pragati Maidan, New Delhi, during 5th & 6th February 2007.The theme of the exhibition was New Technologies in Transmission, Load Despatch & Communication. TheCPRI exhibits consisted of charts covering the Centre for Advanced and Collaborative Research, KnowledgeManagement portal of CPRI, 800 kV tower testing for M/s PowerGrid, Real Time Digital Simulation Facility,Facilities for implementation of Energy labelling scheme in India, CPRI’s contribution to mission drivenprojects of Govt. of India, UHV Research Facilities, Products developed by High Voltage Laboratory etc.

The CPRI stall received about 200 visitors which included several overseas deligates.

Page 44: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

39

39

CHAPTER - VI

MoU's SIGNED BY THE INSTITUTEInstitute has entered into memoranda of understanding with the following organizations:

1. M/s. Asea Brown Boveri (ABB) India, for joint power evaluation studies for MPEB system

2. M/s. Power Grid Corporation of India Ltd., New Delhi, for long term co-operation in respect of R&Drelated to High Voltage Transmission System.

3. M/s. FARCOM Cables Systems Pvt. Ltd. for jointly working in the development of Fire Resistant LowSmoke (FRLS) cable and sheathing material.

4. KPTCL - Training of KPTCL personnel, RLA and Diagnostic Studies, special tests on distributiontransformers, CT's PT's, transformer oil, uprating and upgrading of transmission lines, T&D NetworkPlanning & loss evaluation, failure analysis of power equipment etc.

5. Agreements for conducting Third Party Inspection Services (a) Uttara Haryana Bijli Vitaran NigamLtd. (b) Dakshin Haryana Bijli Vitaran Nigam Ltd. (c) Haryana Vidyut Prasaran Nigam Ltd. (d) J&KBoard.

6. Joint studies with BHEL in the areas of power systems studies on 765 kV systems, testing of EHV CBs as perIEC etc.

7. Thirdparty inspection of Energy Meters with BSES

8. BARC for Seismic tests on piping with internal pressure

Page 45: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

40

40

CHAPTER - VII

CAPITAL PROJECTS

During 2006- 07 the following Capital projects were under implementation in the institute:

1. Augmentation of engineering services for Plant performance Monitoring & Improvement (PMI), renovation& Modernization (R&M) and Life Extension (LE) facilities

2. Establishing capacitor current switching facility at STDS Bhopal

3. Establishing Comprehensive energy efficiency testing facility for Refrigerators and Air conditioners atBangalore

4. National and International accreditation for CPRI laboratories

5. Establishment of test facility at eastern & north eastern regions

6. Rotor System with Exciter for motor of the 2500 MVA s/c generator at Bangalore

7. Upgradation of the static frequency converter for 1500 MVA s/c generator at Bhopal

8. Augmentation and modernization of CPRI labs

9. Relocation of Regional Testing Laboratory from Muradnagar to Noida

The project outlays and expenditure during the year 2006- 07 are given below:

(all figures Rs. In lakhs)

Sl. No Title of the project Project outlay CumulativeExpenditure

1. Augmentation of engineering servicesfor plant Performance Monitoring & Improvement(PMI) Renovation & Modernization (R&M) and lifeextension (LE) facilities 255.00 230.00

2. Establishing capacitor current switching facilityat STDS Bhopal 435.00 433.87

3. Establishing Comprehensive energy efficiencytesting facility for Refrigerators and Air conditionersat Bangalore 495.00 337.71

4. National and International accreditation for CPRIlaboratories 160.00 093.93

5. Establishment of test facility at eastern & northeastern regions 320.00 248.76

6. Rotor System with Exciter for motor of the2500 MVA s/c generator at Bangalore 200.00 187.00

Page 46: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

41

41

7. Upgradation of the static frequency converterfor 1500 MVA s/c generator at Bhopal 270.34 200.00

8. Augmentation and modernization of CPRI labs 2729.50 582.10

9. Relocation of Regional Testing Laboratory 869.00 494.42

10. R&D 300.00 315.13

11. RSOP 200.00 146.25

Total 6233.84 3269.17

Physical Progress of the Capital Projects:

1. ESTABLISHMENT OF ENGINEERING SERVICES FOR PLANT PERFORMANCE MONITORING &IMPROVEMENT(PMI), RENOVATION & MODERNISATION AND LIFE EXTENSION (LE).

Keeping the various requirements of the Power Generation Sector, it was proposed to strengthen andconsolidate the facility and capability for Plant Performance Monitoring & Improvement (PMI), Renovation& Modernization and Life Extension (RM & LE) and through this CPRI will provide a more focused andmeaningful service to the power plants. This project sanctioned at a cost of Rs. 255 lakhs is underimplementation and will be completed by August 2008.

2. ESTABLISHING CAPACITOR CURRENT SWITCHING FACILITY AT STDS BHOPAL

The project sanctioned at a cost of Rs.435 lakhs to study behavior of MV switchgear with interruptingcapacitive currents upto 400 Amps and to assist the product development for the Indian industry. All the civilworks have been complete and the equipments are in various stages of commissioning and the project will beoperational from May 2007.

3. ESTABLISHING COMPREHENSIVE ENERGY EFFICIENCY TESTING FACILITY FORREFRIGERATORS AND AIR CONDITIONERS AT BANGALORE

The project sanctioned at a cost of Rs. 495 lakhs to help the Bureau of Energy Efficiency in their energylabeling programme. Facilities are being established for testing Air Conditioners & Refrigerators under thisscheme. During the year the Refrigerator test facility become fully operational and the equipment for testingAir conditioner facility has been ordered and the facility will be fully operational by end of 2007.

4. NATIONAL /INTERNATIONAL ACCREDITATION FOR CPRI LABORATORIES

In view of the globalization, the Institute is making forays into the markets of African, Middle East andSoutheast Asian nations towards meeting the test & certification and also consultancy in the area of powerengineering. The globalization of the world market has also brought in lot of avenues for the Indian electricalindustry to market their services overseas. IEEMA which is an agency in India looking after the interest ofthe Indian power industry had requested several times in the past to have accreditation by the Institutewhich makes International acceptability for their goods manufactured in India. Towards meeting this endand to make the Institute as a regional testing laboratory it is proposed in the scheme to go in for several

Page 47: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

42

42

international accreditation and membership of world renowned bodies. The project sanctioned at a cost ofRs.160 lakhs is under implementation. Some of the major accreditation obtained under this scheme includeASTA - BEAB, UK certification. STL membership and ISO- 9001- 2000 certification for R&D and consultancyactivities.

5. ESTABLISHMENT OF TEST FACILITY FOR EASTERN/ NORTH EASTERN REGION

Under this proposal it is planned to create

Dielectric tests facility and

Mobile transformer oil testing facility

The Diagnostics of Power/Distribution Transformers through oil tests is planned, which will help the powerutility to maintain the transformers and also know the health of transformers. Some remedial action dependson the nature of fault can also be carried out. The Mobile laboratory so established would be able to covervast area in West Bengal, Orissa, Bihar, Assam, Manipur, Meghalaya, Arunachal Pradesh etc. Approximately,1500 Transformers could be monitored in one year. Later based on the demand and also the requirement ofthe power utility other facilities would be planned in a phased manner. The project sanctioned at a cost ofRs.320 lakhs is under implementation. The Regional Testing Lab at Kolkata is operational and at Guwahatiis in final stages.

6. ROTOR SYSTEM WITH EXCITER FOR THE MOTOR OF 2500 MVA SHORT CIRCUITGENERATOR OF C.P.R.I, BANGALORE

The 2500 MVA short circuit generator of High power Laboratory is driven by synchronous motor. Thissystem was commissioned in 1988. Since then, Generator system is working with out standby driving motor.In recent past several problems in driving motor rotor, exciter viz Cracks in motor shaft, Failure of Exciterof the driving motor, Abnormal noise, vibration while starting and running of the motor have been experienced.Though these problems are attended by M/s Alsthom Projects, Vadodara & M/s Converteam, France, stillproblems are persisting. The non availability of this generator is causing inconvenience to electrical industries.Hence it is proposed to procure a new complete rotor system for the driving motor from the original supplierfrom France. The project is under implementation at a cost of Rs.200 lakhs. The Rotor System has beenordered and likely to be installed in 2007- 08.

7. UPGRADATION OF THE STATIC FREQUENCY CONVERTER USED FOR DRIVING THE 1500MVASHORT CIRCUIT GENERATOR OF 1500MVA SHORT-CIRCUIT TESTING LABORATORY(STATION-1) OF CPRI, BHOPAL.

1500 MVA Short Circuit Generator at STDS,CPRI Bhopal is facing problems in Generator driving motorcontrol system on control cards causing loss of testing time and lot of inconvenience to electrical industriesto test their products. Original suppliers of generator themselves suggested to replace present drive systemwith modified motorless drive system with latest technology for smooth running of short circuit generator.Hence it is proposed to up grade the static frequency converter used for driving the 1500MVA short circuitgenerator of short circuit testing laboratory (station-1) of C.P.R.I., Bhopal at a cost of Rs.270.34 lakhs orderhas been placed for supply of SFC and will be installed in 2007- 08.

Page 48: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

43

43

8. AUGMENTATION & MODERNIZATION OF CPRI LABORATORIES

The Testing, Research & Consultancy activities require the laboratories to be accredited and all equipmentcalibrated to carryout testing as per National/ International standards. Since most of the test equipment isoutdated, operation & maintenance of these equipment calls for very high expenditure. Many of the originalmanufacturers/suppliers of the equipment either did not exist or the companies have got merged with othercompanies, it is generally observed that spares and services are not available form the equipment suppliers,hence it is proposed to Augment & modernize some of the CPRI laboratories at a cost of Rs. 2329.5 lakhs.Several laboratories like, The High Voltage, Short Circuit, High Power Lab. Material Technology have beenaugmented and also the Rejuvenation of physical infrastructure is being carried under the scheme.

9. RELOCATION OF REGIONAL TESTING LABORATORY, MURADNAGAR, U.P. TO NOIDA

At present only CPRI has the necessary comprehensive capital intensive testing facilities under one roof fortesting & certification of electrical equipment. There has been persistent demand from manufacturers ofpower apparatus to establish Regional Testing Laboratories to cater to the testing needs of industriessituated in the respective regions of the country. Clients are facing lot of difficulties at present in sendingthe equipment from one end to the other for certification needs. The other important aspect has been thatlack of such adequate testing facilities in the regions to meet the demand which naturally force the useragencies to use untested equipment which may, not only introduce hazards to working personnel, but alsomake the system unreliable with frequent failures. Considering the above aspect and also realising theimportance of the demand of power industry for proper testing facility in the regions, there was a need andurgency for providing such regional test facilities for the benefit of manufacturers of power equipment.To cater to the northern Indian utilities, the Regional Testing Laboratory was started in 1992 at Muradnagar(near Ghaziabad) of UP. The inaccessibility of the testing Lab and worsening power situation has forced toshift the test lab to NOIDA. The project sanctioned at a cost of Rs.869 lakhs is under implementation. TheNOIDA authorities have allotted land near Ghaziabad and the civil works are likely to commence soon.

Page 49: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

44

44

CHAPTER - VIII

ADMINISTRATIVE MATTERS

Shri Anil Razdan, Secretary, Ministry of Power, New Delhi vice Shri R.V.Shahi became the President of the CPRI

Governing Council and Society.

The following Officers became the Members of the CPRI Governing Council and the Society during the year

under report:

Shri Harish Chandra, Joint Secretary (Thermal), Ministry of Power vice Shri Gireesh B. Pradhan, Joint Secretary

(T) vice Shri U.N.Panjiar, Additional Secretary vice Shri Gireesh B Pradhan, Shri V.K.Goel, Technical Advisor

(Boiler), Ministry of Industry, New Delhi vice Dr. D.R.Chawla, Shri D.J.Ramesh, President - IEEMA vice Shri

A.K.Dhagat, Shri Rajib Ranjan, Chairman, Chattisgarh State Electricity Board, Raipur vice Shri S.K.Rakesh,

Secrerary (Power), Government of Tripura, Agartala, Shri T. Nandakumar, Chairman, Jharkhand State Electricity

Board, Ranchi vice Lt. Gen. (Retd.) O.S. Lohchab, Chairman, Haryana Vidyut Prasaran Nigam Ltd., Panchkula,

Haryana, Shri S.C.Srivastava, Dean (R&D), Indian Institute of Technology, Kanpur vice Director, Bhabha Atomic

Research Centre, Mumbai, Prof. J. Nanda, Emeritus Professor, Indian Institute of Technology, New Delhi vice

Prof. S.S.Prabhu, Bangalore, Dr. V.K.Aatre, Emeritus Professor, Indian Institute of Science vice Prof. P.S. Satsangi,

IIT(Retd.) New Delhi, Dr. Ajay Mathur, Director General, Bureau of Energy Efficiency, New Delhi vice Shri

V.S.Verma.

During the year, the Governing Council met once on 20th September 2006. The Society held its Annual General

Body meeting on 20th September 2006. The Standing Committee met thrice on 7th October, 19th October 2006

and 8th January 2007.

Vigilance

The vigilance activities of the Institute are looked after by a part time Chief Vigilance Officer Shri. Sengupta,

Additional Director, who is appointed upon the approval by the Chief Vigilance Commission. The Chief Vigilance

Officer reports to the Director General and is assisted by the Administration Section in all vigilance matters.

Preventive vigilance relates to every area of the Institute’s activity, viz., Purchase (Contracts for supply of goods),

Civil works & maintenance works (Contracts for supply of services), R&D function, Testing & Certification,

Consultancy, and Memorandum of Understandings entered into with others, scrutiny of the Annual Property

Returns (APR) of officers/ staff, inspections to detect the system failures and existence of corruption or

malpractices; etc.

As per the directions of the Central Vigilance Commission, Boards have been displayed prominently at all the

Units/ Divisions of the Institute for wide publicity among Public, Contractors and Customers about the availability

of Chief Vigilance Officer / Head of the Organisation. It is facilitated such that instances and information on

corruption in the Institute by affected parties can be brought to the notice of Head of the Organisation or to the

Chief Vigilances Officer at the addresses mentioned in the Boards. Timely Returns of vigilance activities

containing the requisite in formations are filed with the appropriate authorities bringing out the latest position

in this regard.

Page 50: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

45

45

SC/ST/OBC LIASION OFFICE ACTIVITIES

Coordinated in conducting 115th Birth Anniversar y of

Dr. B.R. Ambedkar on 25th May 2006. Conducted annual inspection

of the roaster maintained in the organization with a view to

ensuring proper implementation of the reservation orders during

the year. Assisted in consolidating and verifying the annual returns

relating to representation of SC/ST’s and forwarded it to Ministry,

Department of Public Enterprise and National commission State

office. Literacy is the foundation for the society. In the modern

education system matriculation or the tenth standard is the

minimum for one to be called “LITERATE” The three layer implementation strategy as the essence of

Ambedkar’s philosophy, EDUCATE, ORGANISE AND AGITATE. For the first time in the history of CPRI,

this office has liaison with management of CPRI to institute “Dr. B.R. Ambedkar Merit award” for children of

CPRI Employees who topped in tenth standard under different schemes.

The officer in charge had liaison with the management to resolve the issues of CPRI SC/ ST Employees

regarding promotion and transfers etc. Other grievances were resolved amicably by bringing in awareness on

the merit of the grievance. Elections for the office bearers of CPRI SC/ST’s employees welfare association

conducting for the first time in CPRI.

RIGHT TO INFORMATION ACT

The Institute has implemented the Right to Information Act – 2005. The Public Information Officer & Assistant

Public Information Officer has been nominated as per the guidelines. Information is being disseminated and

the system has been established for maintenance of records. CPRI has also created a website http://cpri.in and

provides general information about various testing laboratories, facilities & services rendered. During the year,

the Information Officers conducted an Internal Audit to check the adequacy of the system for dissemination of

information in accordance with the stipulations of the Act. The Institute received seven nos. of requests seeking

information on various activities and requested information has been submitted to all the applicants

WELFARE ACTIVITIES

The Women Employees Cell is operative since 1997, for the welfare of female employees and to meet their

grievances. Creche for the employees children is operational successfully over the last six years for the benefit of

working couples in the Institute.

The following were the activities of the Women’s Cell during 2006-2007 :

Maintenance and Smooth functioning of the Creche as per framed guidelines, Opening of bank account

in the name of ‘Women’s Cell’, Managing all grants and expenditure through the account, Solved complaints

of two women employees.

Employment situation of Women Employees in various post(s) in CPRI as on 31.03.2007 is as follows.

Page 51: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

46

46

STAFF POSITION OF CENTRAL POWER RESEARCH INSTITUTE

Sl. Post(s) No. of No of Women %age of women

No. Employees Employees Emps to total No

01 Director General 01 - -

02 Director 01 - -

03 Additional Director 18 01 5.55

04 Joint Director 56 06 10.71

05 Scientific/ Engineering Officers 169 22 13.01

06 Scientific/ Engineering Assistants 20 01 5.0

07 Non- Technical Officers 16 03 18.75

08 Office Staff/ Stenographers 122 43 35.24

09 Library Staff 03 03 100

10 Technicians 69 - -

11 Technical Attendants/ Attendants 158 04 2.53

12 Drivers/Cook-cum-Caretaker 23 - -

13 Watchmen 57 - -

14 Safaiwala 21 04 19.04

Total 734 87 11.85

No. of Physically Challenged employees in the Institute as on 31-03-07

Sl. Post (s) No. of employees No. of physically

No. challenged employees

01 Director General 01 -

02 Director 01 -

03 Additional Director 18 -

04 Joint Director 56 02

05 Scientific/ Engineering Officers 169 02

06 Scientific/Engineering Assistants 20 03

07 Technicians 69 -

08 Technical Attendants/ Attendants 158 06

09 Non-Technical Officers 16 -

10 Office Staff / Stenographers 122 03

11 Library Staff 03 -

12 Drivers/ Cook-cum-Caretaker 23 -

13 Security Staff 57 -

14 Safaiwala 21 -

Total 734 16

Page 52: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

47

47

STAFF STRENGTH

The staff strength at the end of the financial year 2006 - 07 was as under:

Director General : 01

Director : 01

Additional Director : 18

Joint Director : 56

Chief Administrative Officer : 00

Chief Accounts Officer : 01

Scientific/Engineering Staff : 189

Technical Staff : 69

Administrative & other Supporting Staff : 241

Technical Supporting Staff : 158

Total 734

REPRESENTATION OF SCHEDULED CASTES AND SCHEDULED TRIBES

Details of employees belonging to scheduled caste/tribe & others on the rolls of CPRI as on 31.3.2007 are

summarised below:

Category Total No. of No. of SC No. of ST Othersemployees employees employees (including OBC)

Group A 241 34 09 198

Group B 102 24 11 67

Group C 337 109 45 183

Group D 33 04 07 22

Safaiwalas 21 16 02 03

Total 734 187 74 473

% - 25.47 10.08 64.44

LIBRARY & INFORMATION SERVICES

The Institute has well established Libraries at Bangalore and Bhopal to provide adequate library and

information services for the research work and for updating employees' knowledge in Scientific advancement.

Several books and periodicals are added to the library at Bangalore and Bhopal During the year 2006-2007. The

expenditure incurred on books and periodicals during the year at both Bangalore and Bhopal was Rs.16.98 lakhs.

Computerisation of Library facility at Bangalore unit was taken up. All the books and publications were coded

for creating a data base which would be accessible to all users over the LAN.

Page 53: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

48

48

CHAPTER - IX

FINANCE & ACCOUNTS

The Institute has done well in its financial performance during the year 2006-2007 and earned an all time

high revenue of Rs.4272.91 lakhs.

Revenue earnings during the past five years:

Year Revenue Percentage increase

(Rs. lakhs) (Base year 2002-2003)

2006-2007 4273 38.95

2005-2006 4146 34.82

2004-2005 3651 18.73

2003-2004 3600 17.07

2002-2003 3075

Increased services rendered to the utilities and Industries are well reflected in the financial performance

raising the revenue earnings from Rs.3075 lakhs in 2002-03 to Rs.4273 lakhs during the current year. During

the year under report, as against the revenue realisation of Rs.4273 lakhs, the expenditure on non-plan

activities stood at Rs.3926 lakhs only and thereby it has been possible to generate a surplus of Rs.347 lakhs.

For the 19th year in succession, the Institute has not drawn any non-plan grant-in-aid from the Government.

During the year, the expenditure under various heads has been as follows:

Non-plan Expenditure : Rs. 3925.63 lakhs

Plan R&D Expenditure : Rs. 318.25 lakhs

Plan Capital Expenditure : Rs. 1436.09 lakhs

RSOP : Rs. 146.06 lakhs

The Institute received grants-in-aid (Plan) of Rs.3302.00 lakhs from the Government of India during the

year. The details along with the Auditors Report are furnished in Appendix - X

With many new laboratories commissioned and opened for commercial testing, it is hoped that the trend

of increased earnings of revenue will continue. As at the end of March 2007, the capital investment by the

Government of India at the Institute has been Rs. 41012.33 lakhs.

Page 54: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

49

49

Page 55: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

50

50

Page 56: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

51

51

Page 57: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

52

52

CHAPTER - X

USE OF HINDI AS OFFICIAL LANGUAGE

Requirement under section 3/3 of the Official Language Act were fully complied with. All office orders, circulars,

reports etc., were issued bilingually.

Discussions Programme with Parliamentary Committees Drafting and Evidence subCommittee:

Drafting and evidence sub committee of discussion Programme of committee of parliamentary with Director

General, CPRI and Chairman, TOLIC and Heads of 15 member offices was held on 30th December 2006. Activities

of TOLIC, prizes received and the magazine ‘ Kaveri’ were appreciated by H’ble members.

HINDI PUBLICATIONS

The fourteenth edition of ‘ Kaveri’, the journal of TOLIC was published.

Technical articles competition

Annual technical articles competition under the auspices of TOLIC sponsored by the Institute was organized

and the best three articles were awarded prizes on Hindi Divas celebrated at CPRI.

Organizing Managerial Lecture

A Managerial Lecture on “Goal Setting” by Smt Sneha Sharma, Assistant Manager, United India Insurance Co.

Ltd was organized for the officers and employees of the Institute on 24th May 2006.

Official Language Orientation Programme by Dr.H.S.Rana, ChiefManager (Rtd) NTC Ltd was organized on 23rd

August 2006 for all the Additional Directors and Joint Directors of the Institute.

TENDERS IN HINDI ON WEB SITE

Tenders in Hindi were posted on the website along with English ones. The website of the Institute is available

in Hindi.

Page 58: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

53

53

HINDI MONTH

Hindi month was organized and 10 competitions were conducted separately for Staff, Proficient and those with

working knowledge of Hindi.

HINDI DIVAS

Hindi Divas was celebrated on 14th September 2006. The Chief Guest Shri. Ashwini Kumar Rai, Dy Regional

Director, Atomic Minerals Directorate gave away the prizes to the winners of competitors held during Hindi

month, technical articles competition under TOLIC and incentive schemes in Vogue in the Institute.

ACTIVITIES OF TOWN OFFICIAL LANGUAGE IMPLEMENTATION COMMITTEE

The Director General, CPRI continued to be the chairman of TOLIC and the Senior Hindi Officer the member

secretary. 13 inter organizational competitions were organized under TOLIC sponsored by various organizations

from 13th to 30th November 2006 and 6 prizes were awarded for each competition. Officers Conference,

Kavi Sammelan and Technical Seminars were organized on 13th, 23rd, and 27th November 2006 respectively.

Page 59: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

54

54

APPENDIX - I

THE GOVERNING COUNCIL AS ON 31 MARCH 2007

PRESIDENT

Shri Anil RazdanSecretary

Ministry of Power, Govt. of IndiaNew Delhi

VICE-PRESIDENTShri Rakesh Nath

ChairmanCentral Electricity Authority

New Delhi

M E M B E R S

Shri Ajit K. Gupta Shri Harish ChandraAdvisor & Head (Power Group) Additional Secretary/Advisor (T&R)Ministry of Non-Conventional and Ministry of PowerRenewable Energy Sources, New Delhi. New Delhi.

Shri K. Ravikumar Shri D.J. RameshDirector (Power) President - IEEMABharat Heavy Electricals Ltd. MumbaiNew Delhi.

Shri V. Ramakrishna Shri M. SahooMember (Power Systems) Joint Secretary & FACentral Electy. Authority Ministry of PowerNew Delhi New Delhi.

Shri Chandan Roy Shri G.N. MathurDirector (Operation) SecretaryNTPC Ltd. Central Board of Irrigation & PowerNew Delhi. New Delhi

Shri V. S. VermaMember (Planning) Ministry of Science & TechnologyCentral Electy. Authority Technology BhavanNew Delhi New Delhi.

S. Majumdar Shri Rajib RanjanDirector (Projects) ChairmanPower Grid Corpn. of India Ltd. Chattisgarh State Electy. BoardNew Delhi Raipur

Page 60: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

55

55

Shri T. Nandakumar Dr. V.K. AatreChairman Emeritus Professor - ECE Deptt.Jharkand State Electy. Board Indian Institute of ScienceRanchi Bangalore

Shri V.K. Goel Dr. S.C. SrivastavaTechnical Advisor (Boiler) Dean R&DDeptt. Indl. Policy & Promotion Indian Institute of TechnologyMinistry of Industry Kanpur.New Delhi.

Prof J. Nanda Shri Ajay MathurEmeritus Professor - Deptt. of Electrical Engg. Director GeneralIndian Institute of Technology Bureau of Energy EfficiencyNew Delhi. New Delhi.

Shri A.K. Tripathy-Member SecretaryDirector GeneralCentral Power Research InstituteBangalore.

APPENDIX - II

THE STANDING COMMITTEE AS ON 31 MARCH 2007

CHAIRMAN

Shri V. Ramakrishna

Member (Power Systems)

Central Electricity Authority

New Delhi

M E M B E R S

Shri Harish Chandra Shri M. Sahoo Shri A.K. Tripathy- Member Convenor

Additional Secretary/ Joint Secretary & FA Director General

Advisor (T&R) Ministry of Power Central Power Research Institute

Ministry of Power New Delhi Bangalore

New Delhi

Page 61: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

56

56

APPENDIX - III

THE COMMITTEE ON RESEARCH AS ON 31 MARCH 2007

CHAIRMAN

Shri V. S. VermaMember (Planning)

Central Electy. AuthorityNew Delhi

M E M B E R S

Shri Santhana Gopalakrishnan Shri G. N. MathurChief Engineer (R&D) SecretaryTamil Nadu Electy. Board Central Board of Irrigation & PowerChennai New Delhi

Dr. U.C. BhaktaDirector (Technology) N.T.P.C. Ltd - R&D CentreG.E. Power Controls (I) Pvt. Ltd. NoidaBangalore

Shri Jashwant PatelChief Engineer (Trg. & R&D) Head (R&D)Maharastra State Electy. Board Asea Brown Boveri Ltd.EKLAHARE Baroda

Shri V.K. Agarwal Shri D.J. RameshAsstt. General Manager ChairmanPower Grid Corpn. of India Ltd. M/s. Vijaya ElectricalsBangalore Hyderabad

Dr. A.A.Natarajan Dr. B.P. SinghPrincipal General Manager (HGI)Sastha Institute of Engineering & Technology Corporate R&D, BHELChennai Hyderabad

Smt. Sarala Vichur Shri D.K. RoySuptd. Engineer (Elec./R&D Centre) Chief EngineerKPTCL West Bengal State Electy. BoardBangalore Kolkata

Dr. A. Lahiri Shri K. SudheendraAdviser - DSIR Supertending Engineer(Elec.)Min. of Science & Technology R&D centreNew Delhi Karnataka Power Corporation Ltd.

Bangalore

Shri A.K. Tripathy - Member ConvenorDirector GeneralCentral Power Research InstituteBangalore

Page 62: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

57

57

APPENDIX - IV

THE COMMITTEE ON TESTING & CERTIFICATIONAS ON 31 MARCH 2007

CHAIRMANShri V. Ramakrishna

Member (Power Systems)Central Electy. Authority

New Delhi

M E M B E R S

Prof. G.R. Nagabhushana Shri S.V. MurthyDept. of High Voltage Engg. Executive Director (SR)Indian Institute of Science NTPC Ltd.Bangalore Secunderabad

Shri S.M. Zafrulla Shri A.R. RaoDirector General Manager (E.P. Dvn.)Karnataka Power Corpn. Ltd Bharat Heavy Electricals Ltd.Bangalore Bangalore

Shri V.K. Kulkarni Shri P. Narasimha MurthyHead (Product Development) Retd. Chairman - KEBSiemens India Ltd. BangaloreThane

Shri Sunil MoreExecutive Director (SRTS II) Secretary General- IEEMA, WorliPower Grid Corpn. of India Ltd. MumbaiBangalore

Shri Anil Pandit Shri A.K. Tripathy - Member Convenor

Business Technology Leader Director GeneralGE PCTDC, John F. Welch Technology Centre Pvt LTD Central Power Research Institute.Whitefield, Bangalore Bangalore

Shri P. SenguptaDirectorBureau of Indian StandardBangalore

Dr.S.GopalVice PresidentMWB (India)Ltd.,Bangalore

Shri Samba MurthyGeneral ManagerVijay Electricals Ltd.Hyderabad

Shri Mrinal Kanti RayMember (Commercial & HRD)West Bengal State Electy. BoardKolkata

Page 63: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

58

58

APPENDIX - V

RSOP EXPERT COMMITTEE

CHAIRMAN

Shri A.K. TripathyDirector General

Central Power Research InstituteBangalore

M E M B E R S

Dr. Naresh Kumar SahajpalHead R&D Planning DivisionDept. of Electrical EngineeringCouncil of Industrial ResearchNew Delhi

Shri Gajendra BehariDirector (R&D)Central Electricity AuthorityR.K. PuramNew Delhi

Dr. Thukaram. DProfessorDeptt. of Electrical EngineeringIndian Institute of ScienceBangalore

Dr. V. Rao Aiyagiri, FNAEHead SERC Division & Scientist GDeptt. of Science & TechnologyTechnology Bhavan, New Delhi

Shri M.C. BhatnagarAGM, (R&D)PGCIL, Corporate R&DNew Delhi

Dr. Y.V.L. Narasimha MurthyGeneral Manager, Corporate R&DBHEL, Corporate R&D DivisionHyderabad

Shri P.P. WahiDirector (IT)Central Board of Irrigation & PowerNew Delhi

Smt. Sarala VichurSuperintending Engineer (Elec.)R&DK.P.T.C.LCauvery BhavanBangalore

Shri Virender SinghChief Engineer/HRDPunjab State Elecricity BoardPatialaPunjab

Dr. K. DwarakanathJoint Director, DMDCentral Power Research InstituteBangalore

Dr. R.S. Shivakumara AradhyaJoint Director, Power Systems Dvn.Central Power Research InstituteBangalore

Shri M.M.Babu Narayanan-Member ConvenorJoint Director, R&D Co-ordination DivisionCentral Power Research InstituteBangalore

Page 64: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

59

59

CENTRAL RESEARCH & TESTING LABORATORY, BANGALORE

INSTRUMENTATION DIVISION

2.1.46 Effects of Harmonic influence on 06 12/07 27.00 OngoingEnergy meters

POWER SYSTEM DIVISION4.1.27 Investigation of Grid – Wind 09/04 08/06 12.00 Completed

turbine & D G interaction.

4.1.28 Investigation on application of 09/04 05/06 22.00 CompletedFACTS devices in Indian Power systems

4.1.29 Study of dynamic performance 11/05 10/06 22.00 Ongoingof relays using Real Time Power

MATERIAL TECHNOLOGY DIVISION5.2.14 Establishment of electromagnetic 04/06 07/07 22.00 Ongoing

method of stress assessment tobenchmark structural soundness inturbine and other plant components

5.2.15 Damage tolerance of cenosphere 04/06 09/07 45.00 Ongoingbased coatings and compositesin plant condition

DIAGNOSTICS,CABLES &CAPACITORS DIVISION6.1.29 Insulation diagnosis by high 10/03 9/06 48.00 Completed

voltage spectroscopy

6.1.31 Dielectric Diagnosis of HV rotating 09/04 08/07 20.00 Ongoingmachine insulation based on structural changesof the insulation due to ageing

DIELECTRIC MATERIALS DIVISION

5.4.44 Studies on thermoplastic elastomers 07/02 07/06 32.60 Completedfor halogen free, fire retardant lowsmoke cable compounds

5.4.48 To study the effect of corrosive 11/05 08/07 25.00 Ongoingsulphur on transformer components

5.4.49 Polymer Ceramic composites with 11/05 10/07 25.00 Ongoinghigh dielectric constant forElectrical applications

APPENDIX - VI

RESEARCH PROJECTS UNDERTAKEN DURING THE YEAR 2006-2007

Proj. Title of the Project Start Close Outlay RemarksIdn. mm/yy mm/yy (Rs.inNo. lakhs)

Page 65: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

60

60

5.4.50 Development of polymer nanocomposite for electrical applications 11/05 10/07 20.00 Ongoing

6.1.32 Nano composites for flame 11/05 10/06 2.00 Completedretardant applications –Exploratory Study

HIGH POWER LABORATORY

13.2.09 Evaluation of shunt reactor current 01/04 09/07 28.00 Ongoingswitching capability of MVvacuum circuit breaker

13.2.11 Study on enhancement of capability 11/05 09/07 48.00 Ongoingof conducting capacitor currentswitching test on 240kV circuit breakerfrom voltage factor of 1.2 to 1.4

ENERGY CONSERVATION & DEVELOPMENT DIVISION

15.1.4 Showcasing of Energy Conservation 04/06 07/07 39.00 Ongoingmeasures in an office building– CPRI H O

INFORMATION TECHNOLOGY & IMPLIMENTION DIVISION

16.1.14 Establishment of research facility for 09/04 01/07 50.25 CompletedCommunication protocol Applicableto sub station automation

EARTH QUAKE ENGINEERING &VIBRATION RESEARCH CENTRE

17.1.1 Microzonation for Power 11/05 10/07 15.00 OngoingProjects

CENTRE FOR COLLABORATIVE AND ADVANCED RESEARCH

18.1.1 Building up Research 04/06 09/07 50.00 OngoingInfrastructure

THERMAL RESEARCH CENTRE, NAGPUR

10.1.13 Performance evaluation and 9/03 8/06 20.50 Completedlife improvement of boiler tubecomponents through plasmasurface coating

10.1.14 Condition Assessment of 11/05 10/07 8.00 Ongoingcomplex geometry Power Plantcomponents by Ultrasonic TOFDtechnique.

Proj. Title of the Project Start Close Outlay RemarksIdn. mm/yy mm/yy (Rs.inNo. lakhs)

Page 66: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

61

61

ULTRA HIGH VOLTAGE RESEARCH LABORATORY, HYDERABAD

11.1.20 End-of-life Estimation of RTV 09/04 08/07 8.46 Ongoingcoated insulators under pollutionconditions

SWITCHGEAR TESTING AND DEVELOPMENT STATION, BHOPAL

9.1.13 Estimation and analysis of radiated 01/04 06/07 35.00 Completedelectromagnetics on switchgears,power equipment with augmentedtest facility for EMI measurement

Proj. Title of the Project Start Close Outlay RemarksIdn. mm/yy mm/yy (Rs.inNo. lakhs)

Page 67: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

62

62

APPENDIX - VII

PERSONNEL DEPUTED ABROAD FOR TRAINING/PRESENTINGTECHNICAL PAPERS, ETC. DURING THE YEAR 2006-2007

Sl.No. Name Country visited period & sponsoring authority

1. N.S. Mohan Rao Dubai, UAE Attending Middle East Electricity CPRIRiyad, Saudi Arebia Exhibition & Conference and organising

CPRI meet at Riyadh, Saudhi Arabia

2. Suhas S. Bagalkotkar Dubai, UAE Attending Middle East Electricity CPRIExhibition & Conference at Dubai

3. A.K. Tripathy Sultanate of Oman Preliminary Discussion on PowerSystem Netrole in Sohar Indl. Areaat Sultanate of Oman with the officersof M/s. Sharq Sohar Steel Rolling MillsOman

4. Dr. Sujatha Subhash Sultanate of Oman Preliminary Discussion on PowerSystem Netrole in Sohar Indl. Areaat Sultanate of Oman with the officersof M/s. Sharq Sohar Steel Rolling MillsOman

5. B.R. Ravishankar Rugby Warwickshire Attending the Interview towardsappointment of CPRI personnel asASTA observer

6. M.K. Wadhwani Rugby Warwickshire Attending the Interview towardsappointmentof CPRI personnel asASTA observer

7. A.K. Tripathy Malayasia, Kaulalampur Inauguration, Faculty for Transformerand Circuit Breaker at the training organisedfor TNBR Engineers at Malayasia

8. N.S. Mohan Rao Malayasia, Kaulalampur Inauguration, Coordination Faculty forTransformer and interviewing organisationsto represent CPRI

9. U.R. Sheshagiri Rao Malayasia, Kaulalampur Faculty for Insulators, Arrester andQA & module training organisedfor TNBR Engineers at Malayasia

10. Suhas S Bagalkotkar Malayasia, Kaulalampur Coordination for QA Module presentationand interviewing organisations to representCPRI

11. A. Sudhindra Malayasia, Kaulalumpur Faculty QA module, training organisedfor TNBR Engineers at Malayasia

Page 68: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

63

63

12. C.P. Jayaram Malayasia, Kaulalampur Faculty QA module, training organisedfor TNBR Engineers at Malayasia

13. B.A. Sawale Malayasia, Kaulalampur Faculty Meter, training organisedfor TNBR Engineers at Malayasia

14. K.B. Manjunath Malayasia, Kaulalampur Faculty Meter,, training organisedfor TNBR Engineers at Malayasia

15. Madhusudhan Kadalur Malayasia, Kaulalampur Faculty Meter,, training organisedfor TNBR Engineers at Malayasia

16. N. Murugesan Malayasia, Kaulalampur Faculty Metering Protocol,, trainingorganised for TNBR Engineers atMalayasia

17. A.K. Tripathy Netherlands/France To meet the management of KEMAKEMA Netherlands and to attend the Short Circuit

Liason (STL) Management/STLACommittee Meeting was held at EDFR&D Laboratories, France

18. P.K. Kognolkar Netherlands/France To meet the management of KEMAKEMA Netherlands and to attend the Short Circuit

Liason (STL) Management/STLACommittee Meeting was held at EDFR&D Laboratories, France

19. Dr. P.V. Reddy Delware, USA Advanced application training at TAInstruments, Delware, USA

20. P.K. Kognolkar Malayasia, Kaulalampur Faculty for Transformer and CircuitBreaker at the training program organisedfor TNBR Engineers, KaulalampurMalayasia

21. N.S. Mohan Rao Malayasia, Kaulalampur Inauguration, Coordination Faculty forTransformer and interviewing organisationsto represent CPRI

22. B.R. Ravishankar Malayasia, Kaulalampur Faculty for Transformer at the trainingprogram organised for TNBR Engineers,Kaulalampur, Malayasia

23. V.S. Nandakumar Malayasia, Kaulalampur Faculty for Circuit Breaker & Switches atthe training program organised for TNBREngineers, Kaulalampur, Malayasia

24. R. A. Deshpande Malayasia, Kaulalampur Faculty for Gas Insulated Switchgear atthe training program organised for TNBREngineers, Kaulalampur, Malayasia

Sl.No. Name Country visited period & sponsoring authority

Page 69: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

64

64

Sl.No. Name Country visited period & sponsoring authority

25. K.N. Srinivasan Malayasia, Kaulalampur Faculty for High Voltage & High PowerLaboratories at the training programorganised for TNBR Engineers,Kaulalumpur, Malayasia

26. S. Ramaprasath Malayasia, Kaulalampur Faculty for Cables & Accessories at thetraining program organised for TNBREngineers,Kaulalampur, Malayasia

27. K.P. Meena Malayasia, Kaulalampur Faculty for Cables & Accessories at thetraining program organised for TNBREngineers,Kaulalampur, Malayasia

28. U.R. Sheshagiri Rao Malayasia, Kaulalumpur Faculty for Insulators, Arrester andQA module training organisedfor TNBR Engineers at Malayasia

29. S. Ramaprasath Paris Attending 41st CIGRE Session 2006

30. B.M. Mehra Rugby Warwickshire Attending the Interview towards appointmentof CPRI personnel as ASTA observer

31. Anupam Awasti Rugby Warwickshire Attending the Interview towards appointmentof CPRI personnel as ASTA observer

32. B.R. Vasudeva Murthy Rugby Warwickshire Attending the Interview towards appointmentof CPRI personnel as ASTA observer

33. N. Murugesan Austria Attending Training on CommunicationProtocol Systems at M/s. OmriconElectronics Ltd. Austria

34. M. Pradish Austria Attending Training on CommunicationProtocol Systems at M/s. OmriconElectronics Ltd. Austria

35. Gautam Sen Gupta Korea Attending 4th Asian Meteing of High PowerLaboratories, Kawasaki, Japan and forhaving discussions with KERI, ChangwonCity, Korea

36. V.S. Nandakumar Berlin, Germany Attending 54th Short Circuit Liason (STL)Technical Committee Meeting, at BerlinGermany

37. S. Vynatheya Netherlands Training on Operation and Maintenance ofX-ray Diffractions System at PA Nalytical,Almelo Tech, Netherlands

38. K. Suryanarayana Berlin, Germany Attending 54th Short Circuit Liason (STL)Technical Committee Meeting, at BerlinGermany

Page 70: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

65

65

39. P.K. Kognolkar Dubai, Abudhabi Follow up work with Dewa Authoritiesfor consultancy projects and for holdingone day workshop each at Dubai andAbudhabi, UAE

40. N.S. Mohan Rao Dubai, Abudhabi Follow up work with Dewa Authoritiesfor consultancy projects and for holdingone day workshop each at Dubai andAbudhabi, and participating GCC Seminar& Exhibition at Abudhabi, UAE

41. N.S. Mohan Rao Dubai, Abudhabi Follow up work with Dewa Authoritiesfor consultancy projects and for holdingone day workshop each at Dubai andAbudhabi and participating GCC Seminar& Exhibition at Abudhabi, UAE

42. M. Janardhana Finland Training and operation & maintenanceof digital magnetic Barkhasess NoiseAnalyser, at Stresstech Oy, Finland

43. B. Nageswar Rao San Fransisco, USA Attending & presenting paper atFire & Materials 2007 Conference,San Fransisco, USA

44. Dr. C. Jayarama Naidu Texas, USA Training on operation and maintenance ofsulphur in oil Analyser at PetroleumAnalyser Co., Houston, Texas, USA

45. A.K. Tripathy Malayasia Attending IEEE Region 10th Meeting

Sl.No. Name Country visited period & sponsoring authority

Page 71: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

66

66

1 A.K. Tripathy Member - Fellow of Institution ofDirector General Engineers India

Member - Senior Member and ChairmanBangalore Section of IEEE

Member - Technical Committee ofInternationalAssociation onElectricity Generation,Transmission & Distribution (Afro-Asian Region), New Delhi

Member - Transformer SectionalCommittee ofBureau of Indian Standards, New Delhi

Member - Governing Council of Sardar SwaranSingh National Institute ofRenewable Energy, Jalandhar

Member - Governing Council of MahathmaGandhi Institute of RuralElectricity Development

Member - Fellow of National Academy of EngineeringMember - Project review committee of DSIR

2. P.K.Kognolkar Principal - ET0-8 High Voltage Switchgear &Director Member Controlgear Sectional Committee

-do- - ET-16, Transformers-do- - ET-39, FusesMember - Institution of EngineersMember - CIGRE technical committee on High

VoltageSwitchgear & ControlgearSectional Committee, ET 08

Member - Expert Committee constituted byBHEL for vetting of the Design/Development of500 MVA, 765kV Single Phase Autotransformer in the specific fieldof High Voltge Engineering / Short

Circuit stress.

3. R. K. Hegde Member - BIS ET13- Equipment for ElectricalAdditional Director Energy measurement & control

Principal Member - BIS Wind EnergySub-committee ME04-

Principal Member - ET-28 Committee on "Solar PV

Energy System of BIS

APPENDIX - VIII

MEMBERSHIP OF CPRI OFFICERS IN INTERNATIONAL/NATIONAL COMMITTEES

Sl.No. NAME NAME OF THE COMMITTEE

Page 72: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

67

67

4. B.H. Narayana Invited Member - To take part in the meeting of

Additional Director "CREEP PANEL" an devisat

committee to Central Boiler Board

Member - Task force on Thermal Generation

(including Gas & Nuclear

Standing Committee on R&D MOP.

Life Member - Indian Society of non destructive

testing

5. N.S.Mohan Rao Member - Statelevel committee forAdditional Director Standardisation &Quality systems.

Fellow - Indian Society of Light EngineerMember - BIS Committee ETD-32

Member - CIGRE National Study Committee

Convener Working group 22-overhead lines

- CIGRE-CPRI group II,Section II,

study committee on "Condition Monitoring"

Member - Electrical Tractor Equipment

Sectional Committee -ET 27

6. K.N.Srinivasan Principal - BIS Sectional Committee ET06 on

Additional Director Member Electrical insulators and accessories

Principal - State Level Committee for

Member Standardistion of Quality System.

Alternate Member - BIS Sectional Committee ET30 on

Surge Arresters

7. V.N. Nandakumar Member - CIGRE NationalStudyCommittee- D2

Additional Director onInformationSystems&

Telecommunication System

Member - BISET13 Section Committee of

Equipment forelectrical

measurements &Load Control

8. Dr. Sujatha Subash Member - ET 40 - HVDC power system

Additional Director BIS sectional committee.

Alternate - ET 01 - Basic electro technical

Member Standard of sectional committee

-do- - ET 40/P3- Dynamic performance of

HVDC Systems.

-do- - ET 40/P2 - DC measuring devices

Member - Engineering committee of National

FACTS Project

Sl.No. NAME NAME OF THE COMMITTEE

Page 73: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

68

68

Member - Executive Committee of ECONElectricity consumersorganisation formed by KERC

Member - Technical advisory group of ECON

Member - Task Force on R&D in Grid Managementformed by POWER GRID

Member - Task force on Transmission set upby the Standing Committee on R&D,Ministry of Power.

9. Dr. S. Seetharamu Member - Expert Committee KPCL for

Additional Director procurement of proprietary items

under the KTPP Act 1999

Member - Indian Society of non Destructive

testing

Member - Tribological Society of India

Member - Expert member capital projects,

technology for engineering

assessment, CSIR

Vice Chairman - Indian Instituteof Plant Engineers,

Member - Working committee on R&D, Siddaganga

Institute of technology Tumkur & SJCIT,

Chikkaballapur

Member - BIS, light metals & their alloys,

Sectional Committee MTD7

Expert Member - KTPP Act Expert Committee KPCL

Member - Indian Society of Analytical

Scientists,Mumbai

10. P. Muniyappa Member - Technical committee16, relating toAdditional Director Standing Committee of Experts to

investigate the failure oftransmission towers

Member - Sub-committee CED 7:1of BIS New Delhi

Use of Structural steel in overhead

tansmissionline towers and

switchyard structures

Member - Conductor & accessories for overhead

lines,Section Committee ETD - 37 of

BIS New Delhi

11. Gautham Sengupta Chairman - Low voltage Switchgear & Controlgear

Additional Director Sectional Comittee, ET 07

Member - BIS ET 39- Fuses Sectional Committee

-do- - National Sub-committee of CIGRE

No.13 on switching equipment.

Sl.No. NAME NAME OF THE COMMITTEE

Page 74: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

69

69

-do- - CIGRE, India National Study Committee

on Transformers

Alternate - ETD07, Low Voltage Switchgear `

Member Sectional Committee

Alternate - ETD08, High Voltage Switchgear

Member & Controlgear Sectional Committee

12. S. Sridhar Chairman - ET-03,Committee on Electrotechnical fluids

Additional Director Principal member - ET 02, Bureau of Indian Standards

Member - Indian Society for AnalyticalScientists of

the Bhabha Atomic Research Centre, Mumbai

Lead Assessor - NABL13.M.M.Babunarayanan Member - ETD 40/P3 -Dynamic performance ofAdditional Director HVDC transmission systems.

-do- - ETD 40/P2 - AC/DC Harmonics &Interactions.

-do- - ETD 40/P14- HVDC ground electrodes.

Member - CBIP National sub-committee ofCIGRE study committee NSC-38 onPower System Analysis and Techniques.

-do- - Technical Advisory Panel(TAP)on Computers, Govt.of Karnataka

Alternate - ETD 40/P5Member - DC measuring devices.Member - FACTS devices committee of

PGCIL, New DelhiMember - Committee for finalize software

for distribution system studiesunder APDRP constituted by MOP

14.Dr. R.S.Shivakumara Alternate member - BIS Committee, Surge Arrester

Aradhya Sectional Committee ET 30

Additional Director Alternate member - BIS Committee, Circuit Breakers

Alternate Member - CIGRE - India working group

for surge arresters

Member - CIGRE National Sub Committee NSC

36 on "Power System Compatibility"

Alternate Member - BIS Sectional Committee on HVDC

System ETD-40

15.B. Gunasekaran Chairman - High Voltage Engineering Sectional

Additional Director Committee, ET-19, BIS

Sl.No. NAME NAME OF THE COMMITTEE

Page 75: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

70

70

16. K. Manohara Member - BIS Sectional Committee ETD-05 fan

Joint Director - BIS Sectional Committee ETD-22

for flame proof

17. S.Vijaya Kumari Principle Member - ETD 03, Committee on

Joint Director Electrotechnical fluids of the

Bureau of Indian Standards

Member - Indian Society for Analytical

Scientists of Bhabha Atomic Research

Centre, Mumbai

18. A.Sudhindra Member - NABL Accreditation Committee

Joint Director Alternate - State level Committee for Standard-

Member disation & Quality systems.

Lead - National Accreditation Board for

Assessor Testing & calibration of

laboratories Govt.of India, DST.

Assessor - NVTquality certification Pvt. Ltd.

(KEEMA registered quality India)

19. B. V. Ragavaiah Member - ET 07 BIS Technical committee

Joint Director - Low Voltage Switchgear andcontrolgear Sectional committee

Alternate Member - BIS Electro Technical Sectional Committee

on Transformers ET - 16

20. V. Arunachalam Principal Member - ET 35 committee on powersystem

Joint Director relays

Principal Member - BIS LTD 25 committee on power system

control and associated communications

Member - UCAIUG (Utility Communication Architecture

International Users Group)

21. P.V.V. Nambudiri Principal - Surge Arrester Sectional

Joint Director Member Committee, BIS ET - 30

22. K.B.Manjunath Member - Studying IEC Document ETD 37/p.1

Joint Director relating to overhead conductors and

accessories in BIS-ET Sectional

Committee

23. Dr. Ramesh Babu Member - CIGRE National Study Committee

Joint Director Working group B2.4 overhead lines

24. P. V. Balasubramanyam Member - Power System Transmission

Joint Director Planning Committee of PGCIL, New Delhi,

Hyderabad.

Sl.No. NAME NAME OF THE COMMITTEE

Page 76: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

71

71

25. Ramakrishna Associate Member - Institute of Chemists, KolkataJoint Director Life Member - Society of Analytical Scientists, Mumbai

26. R.A. Deshpande Alternate - Transformer Sectional Committee

Joint Director Member BIS ET14

27. M. Siddhartha Bhatt Member - Project review committee on Technopeneur

Joint Director promotion programme of DSTR, Min. of

Scientific & Indl. Research. Govt. of India

Convenor - International Renewable Energy Congress

Energy Conservation Solar Energy

Society of India

External Examiner - BVB College of Engineering, Post Graduate

Dept. Visveswariah Technical University,

Hubli

Guest Faculty - Environmental Sciences Deptt.

Bangalore University, Bangalore

Guest Faculty - PSTI, Bangalore

Life Member - Solar Energy Society of India

Life Member - Energy Conservation Society

28. B.R. Ravishankar Alternate Member - BIS Sectional Committee on LV Switchgear

Joint Director & Controlgear

Member - IEEE

29. Dr. K.N. Ravi Principal - BIS High Voltage Sectional

Engg. Officer Gr.5 Member Committee, ET 19

Alternate - Basic Electro technical

Member standards BIS - ET-01

30. C.P. Jairam Lead Assessor - NABL New Delhi

Engg. Officer Gr.5 Principal Member - BIS ET 34, Instruments Transformers

31. S.Ramprasath Chairman - BIS ET 09, Sectional CommitteeEngg. Officer Gr.5 on Power Cables

Member - Working Broup B1-HV Insulated cables ofCIGRE Paris

Member - IT Cable 07 - International Scientific& Technical Committee

32. Dr. D. Devendranath Member - External Board of Studies Electronics &

Engg. Officer Gr.5 Electrical Engg. Deptt. Usmania University,

33. B.M. Mehra Alternate Member - BIS Technical Committee Instrument

Engg. Officer Gr.5 Transformer, ETD-34

Principal Member - Standing Committee of Experts to

investigate failure of equipments

220kV & above substations

Sl.No. NAME NAME OF THE COMMITTEE

Page 77: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

72

72

Sl.No. NAME NAME OF THE COMMITTEE

34. M.K. Wadhwani Member - Institution of Engineers

Engg. Officer Gr.5

35. P. Sampathkumaran Member - Tribological Society of India

Scientific Officer Gr.5

36 B.S. Ramesh Member - CBIP Experts Committee

Engg. Officer Gr.5

37 K. Mallikarjunappa Member - CIGRE - India National Sub-Committee

Engg. Officer Gr.5 A1(NSC A1) on Rotating Machine

38 B. Nageswara Rao Member - CIGRE - India National Study Committee

Engg. Officer Gr.5 on Rotating Machine

39. Dr. H.N. Nagamani member - BIS ET-29,Sectional Committee

Engg. Officer Gr.5 on Power Capacitors

Member - IEEE

40. K.S.Meera Member - CIGRE NSC-B5- Power System Protection

Engg. Officer Gr.5 and local controls

Member - EMTP users Group, New Delhi

Corresponding - WG B5. 17 - Relay Software models

Member - for use with EMTP

41. T. Raghunatha Alternate Member - Studying IEC Document ETD 37/p.1

Engg.Officer Gr.5 relating to overhead conductors and

accessories in BIS-ET SectionalCommittee

42. D. Revanna Member - Technical Committee16, relating to

Engg. Officer Gr. 4 Standing Committee of Experts to

investigate the failure of

transmission towers

Alternate Member - Sub-committee CED 7:1of BIS New Delhi

Use of Structural steel in overhead

tansmissionline towers and

switchyard structures

Member - Panel of experts on manual on transmission

lines, CBI&P

43. M.D. Anantha Babu AlternateMember - Conductor & accessories for overhead lines,Engg. Officer Gr.4 Section Committee ETD - 37 of BIS

New Delhi

44. J. Sundara Rajan Member - CIGRE(India)NationalSub-Engg.Officer Gr.5 committee on Materials for

Electro Technology

Page 78: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

73

73

Sl.No. NAME NAME OF THE COMMITTEE

45. A. Amruthakala Alternate - ET 35 Committee on Power System RelayEngg. Officer Gr. 5 Member

46. S. Ganga Member - Technical Adviser Panel (TAP) onScientific Officer Gr. 5 Computers Govt. of Karnataka

47. B.M. Mehra Alternate - Technical committee of low voltage switch-Engg. Officer Gr.4 Member gear & Controlgear ET-07, BIS sectional

committee

48. K.S. Madhusudan Member - BIS ET 13 Sectional Committee of EquipmentJoint Director of Electrical Measurement & Load Control

49. B.A. Sawale Member - Expert committee of CBIP on Energy metersEngg. Officer Gr.4 Member - BIS Technical Committee ET-13

50. K.P. Meena Alternate Member - BIS ET-09 Power Cables Section CommitteeEngg. Officer Gr.4

51. Dr. P.V.Reddy Member - Expert group for Specification of enclosuresJoint Director for energy meters” Constituted by CBI&PMember - BIS ET 02 Technical CommitteeMember - Board of Standards in Polymer Science,

Mysore UniversityMember - Institution of Chemists

52 . V.S. Nandakumar Life time member - ET08 Electro technical sectional committeeEngg. Officer Gr.5 of HV Switchgear & Control gear

53. V.V.Pattana Shetty Alternate member - ETD 03, Committee onScientific Officer Gr. 5 Electrotechnical fluids of the

Bureau of Indian Standards

54. D. Ravindra Alternate Member - ETD 03, Committee onScientific Officer Gr. 4 Electrotechnical fluids of the

Bureau of Indian Standards

55. V. Saravanan Alternate member - Combustion Institute Pittsburg, USAEngg. Officer Gr.4

56. M. Janardhana Member - Indian Society of Non-Destructive TestingEngg. Officer Gr.4

57. K.Karunakara Principal member - Current Harmonic CommitteeEngg. Officer Gr.3 formulated by CBIP, New Delhi

58. R.SudhirKumar Alternate Member - ET-28 Committee on "Solar PVEngg.Officer Gr.3 Energy System of BIS

59. S.Bhavani Shankar Alternate Member - BIS ET-29 Sectional Committee on PowerEngg. Officer Gr.3 Capacitors

60. Rajshekar P. Mandi Life Member - Indian Science Congress,Engg. Officer Gr.3 Calcutta

Associate Member - Institution of Engineers (I) Kolkata

Page 79: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

74

74

61. N. Murugesan Principal Member - BIS LTD 25 committee on power systemEngg. Officer Gr.3 control and associated communications

Member - CIGRE Study Committee B5-Protection andAutomation

Member - UCAIUG (Utility Communication ArchitectureInternational Users Group)

Member - DLMS US, GenevaMember - MODBUS ORG, USAMember - DNP, CanadaMember - OPC foundation, USAChairman - Standards Committee, ISA (USA)

Bangalore Chapter

62. M.G. Anandkumar Life Member - Indian Ceramic SocietyEngg. Officer Gr.3

63. S. Vynatheya Member - Indian Society of Analytical ScientistsEngg. Officer Gr.3

64. M. Selvaraj Alternate Member - Panel of experts on manual on transmissionEngg. Officer Gr.3 lines, CBI&P

65. Yugal Agarwal Member - Institution of EngineersEngg. Officer Gr.3

66. S. Jothi Basu Alternate Member - BIS Wind Energy Sub-committeeEngg. Officer Gr.2 ME 04-4

Member - Society of Energy Engineers and Managers

67. N. Rajkumar Life Member - Solar Energy Society of IndiaEngg. Officer Gr.2

68. K. Suryanarayana Associated Member - Institution of Engineers (India)Engg. Officer Gr.2

69. M.Pradish Member - UCAIUG (Utility Communication ArchitectureEngg. Officer Gr.2 International Users Group)

70 . K. Suryanarayana Member - Institution of Engineers (India)Engg. Officer Gr.1

Sl.No. NAME NAME OF THE COMMITTEE

Page 80: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

75

75

1 Influence of load on the friction P.Sampathkumaran, Published in the CPRI reviewedand wear behavior in glass- S. Seetharamu, Journal, 3,1,Sept. 2006, 51-57epoxy composite system C.H Sathisha,

B. Suresha andG. Chandramohan

2 Compatibilization of biodegradable R.R.N. Sailaja Published in the CPRI reviewedtapioca starch/LDPE blends to S. Seetharamu Journal, 3, 1, Sept. 2006, 45-50obtain products to be used forshort term packaging applications:Dealing with waist poltethylenefrom the power sector

3 Friction and Slide wear P.Sampathkumaran Published in Indian Journal ofcharacteristics of glass- epoxy S. Seetharamu, Engineering and Materialand glass- epoxy filled with Vartha Venkateswarlu sciences, 13, Dec.2006,SiCp composites B. Suresha and 535-541

G. ChandramohanP.R. Sadananda Rao

4. Friction and Wear characteristics P.Sampathkumaran Published in the Journal ofof carbon- epoxy and glass- S. Seetharamu Reinforced Plastics andepoxy woven roving fiber compo- S. Vynatheya Composites, 25, 7, 2006, 771-sites B. Suresha 782.

G. Chandramohan

5. Investigation of the Friction and P.Sampathkumaran Published in the Journal ofWear behavior of glass- epoxy S. Seetharamu Reinforced Plastics andcomposite with and without B. Suresha Composites 26, 5, 2007, 81– 93.Graphite filler G. Chandramohan

6. Three – body abrasive wear P.Sampathkumaran Published in the Internationalbehavior of carbon and glass S. Seetharamu Journal of Material Science andfiber reinforced epoxy composites B. Suresha and Engineering A., A443, 2007,

G. Chandramohan 285- 291.Siddaramaiah

7. Influence of SiC fillers addition P.Sampathkumaran publication in the Internationalon abrasive wear of glass- S. Seetharamu Journal of Material science andepoxy composite system B. Suresh Engineering

G. ChandramohanKishore

8. Mechanical and Thermal R.R.N. Sailaja Publication in the Internationalproperties of LDPE- Cellulose S. Seetharamu journal of Applied Polymeracetate phthalate blend- Effect Scienceof Maleic anhyhride grafted LDPECompatibilizer

APPENDIX -IX

PAPERS PRESENTED/PUBLISHED IN SEMINARS/WORKSHOPS/SYMPOSIA/JOURNALS

BY THE ENGINEERING/SCIENTIFIC OFFICERS OF CPRI DURING THE YEAR 2006-2007

Sl.No Title of the Paper Authors Presented/Published in Journal

Page 81: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

76

76

9. Manufacture of value added K. Suryanarayana Workshop on Fly Ash Utilization,products from fly ash- Enterpreneur M. Shekar Kumar Engineering Staff College of ndia,Oppurtunities. Hyderabad, October 2006.

10. End use Oriented Characterization M. Shekar Kumar Workshop on Fly Ash Utilization,of Fly Ash K. Suryanarayana Engineering Staff College of India,

Hyderabad, October 2006.

11. Ash Microspheres – Potential K. Suryanarayana Workshop on new directions inApplications M. Shekar Kumar, Ceramics, jointly organized by

S. Vynatheya Indian Ceramic society andM.G. Ananda Kumar. CPRI, Bangalore, March 2007.

12. Utilization of Fly ash in the M. Shekar Kumar Workshop Fly ash based Buildingmanufacture of value added K. Suryanarayana Products, organized bybuilding Products TNEB, Erod, March 2007.

13. Utilization of Fly ash in concret K. Suryanarayana and Workshop Fly ash based BuildingM. Shekar Kumar Products, organized by TNEB,Erod, March 2007

14. Effect of material characteristics P.Sampathkumaran Proceedings of National confer-on the acoustic emission parameter P.Sampathkumaran ence on emerging trends in

C. Ranganathaiah in Chromium Manganese ironsPhysics, Electronics andEngineering sciences at JSSCollege of Arts, Commerce andScience, Mysore, 25-26 Sept. 2006

15. Abrasive Wear of Glass fabrics/ P. Sampathkumaran International conference onparticulate filled polymeric S. Seetharamu Industrial Tribology- 2006composite systems B. Suresha and held at Indian Institute of Science,

G. Chandramohan Bangalore, Nov- Dec.,2006.

16. Ash microsphere- potencial K. Suryanarayanana presented a paper in a seminarapplications. on New directions in ceramics

jointly organized by CPRI andIndian ceramic society, Bangalorechapter on 17 march 2007 atCCAR, CPRI, Bangalore

17. Abrasive Wear of Glass fabrics/ P.Sampathkumaran International conference onparticulate filled polymeric S. Seetharamu Industrial Tribology- 2006 held atcomposite systems B. Suresha and Indian Institute of Science,

G. Chandramohan Bangalore, Nov- Dec.,2006.

18. Three – body abrasive wear of P.Sampathkumaran 16th International Conference ontwo and three dimensional glass S. Seetharamu composite materials to be heldfabric reinforced vinyl ester B. Suresha in Japancomposites. G. Chandramohan

Siddaramaiah

Sl.No Title of the Paper Authors Presented/Published in Journal

Page 82: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

77

77

19. New Trends in assessing the Fire B. Nageswar Rao At the National Seminar on Powerbehavior of Power Cables R. Arunjothi Cable Technology held in CPRI,

A.R. Srinivasan Bangalore during 7 – 8 DecemberP. Rajasekaran 2006.A. Sudhindra

20. Standard requirements for testing P. Rama Prasath At the National Seminar on Powerof Power Cables & Accessories K.P. Meena Cable Technology held in CPRI,

Thirumurthy Bangalore during 7 – 8 DecemberG.K. Raja 2006A. Sudhindra

21. Pre-qualification tests on EHV Cables S. Rama Prasath At the National Seminar on PowerK.P. Meena Cable Technology held in CPRI,Thirumurthy Bangalore during 7 – 8 DecemberA. Sudhindra 2006

22. Failure of Power Cables & Accessories S. Rama Prasath At the National Seminar on Power– An overview K.P. Mena CCable Technology held in CPRI,

Thirumurthy Bangalore during 7 – 8 DecemberG.K. Raja 2006A. Sudhindra

23. Condition Monitoring of Medium Voltage K. Mallikarjunappa At the National Seminar on PowerPower Cables – CPRI Experience P.K. Poovamma Cable Technology held in CPRI,

Thirumurthy Bangalore during 7 – 8 DecemberB.S. Manjunath 2006C.D. KeriV. VaidhyanathanA. Sudhindra

24. Flow Electrification Phenomena in P.K. Poovamma 5th International Conference ofLarge Power Transformers A. Sudhindra French Society of Electrostatics,

Afzal Ahmed Grenoble, France during 30 – 31August 2006.

25. Diagnostic Testing for Insulation K. Mallikarjunappa At International Conference on LargeCondition Assessment of Power C. D. Keri Power Transformers Modern Trend

P.K. Poovamma Transformers in Service in ApplicaA. Sudhindra tion, Installation, Operations,

Maintenance held at New Delhiduring 12 – 13 October 2006.

26. Heat Release Measurements on B. Nageswar Rao At Fire and Materials 2007 Confer-FRLS Cables using Cone Arunjothi ence at San Francisco, USA duringCalorimeter P. Rajasekaran 29-31 January 2007.

A. Sudheendra

27. Static Var Compensator Sizing for A.K.Tripathy IPST Conference 2007Electric Arc Furnace Application – Sujatha Subhash was held during 4-7 June 2007.A case Study. K.S.Meera,

J.SreedeviM.Murali, MI Patel

Sl.No Title of the Paper Authors Presented/Published in Journal

Page 83: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

78

78

Sl.No Title of the Paper Authors Presented/Published in Journal

28. Harmonic Filter Design for High J.Sreedevi National Workshop on PowerPower Arc Furnace Installations – K.S.Meera Electronics (NWPE-2006) heldA Case Study Dr. Sujatha Subhash during 30.10.2006 to 1.11.2006

A.K.Tripathy at IIT,Kanpur.

29. Energy Metering for Distribution R.S.Shivakumara Aradhya National Power System ConferenceLoss Estimation – Problems and R.K.Hegde (NPSC) during December 2006solutions. S.Shyamsundar at IIT,Roorkee.

K.Devender RaoJ.SreedeviRaghunatha

30. Transient Response of Grid K.S.Meera IEEB International Conference onconnected Wind Electric Generators Vinodh Kumar Power Electronics Drives &

Sasi K.Kothayil Energy System for IndustrialGrowth-2006.

31. Closed Loop Performance Evaluation Shivakumara Aradhya 6th International R&D Conferenceof Protection Scheme for Fixed Series K.S.Meera organized by CBIP, New DelhiCapacitor Sachin Srivastav held at Lucknow during 13-16

Khoday February 2007Pallavi

32. Transient Response of Grid connected K.S.Meera IEEE International Conference onWind Electric Generators Vinodh Kumar Power Electronics Drives &

Sasi K.Kothayil Energy System for IndustrialGrowth-2006.

33. Transformer Differential Relay testing J.Sreedevi International Conference onusing Real Time Digital Simulator C.Prabhakar , “Power System Protection”

R.S.Shivakumara Aradhya held during 21-23 FebruaryDr. Sujatha Subhash 2007 at CPRI, Bangalore.K.S.Meera

34. Relay Co-ordination Studies for Power C.Prabhakar International Conference onDistribution Network of a Sea Port K.S.Meera “Power System Protection” held

R.S.Shivakumara Aradhya during 21-23 February 2007 atDr. Sujatha Subhash CPRI, Bangalore.K.R. Sudhakar

35. Dynamic Performance of Distance K.S. Meera International Conference onRelays using Real Time Digital A. Amruthakala “Power System Protection”Simulator C. Prabhakar held during 21-23 February

2007 at CPRI, Bangalore.

36. Damping of inter-area oscillations G.P. Vijayakumar Sixth National Power Systemsin Northern Region Electricity Board J. Sreedevi Conference, held at IIT, RoorkeeSystem

37. Seismic Qualification of Bamboo Ramesh Babu National Institute of TechnologyBuilding System Prof Katta Venkataramana Karnataka, Surathkal Research

Bulletin, Volume 15, Number 2,December 2006

Page 84: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

79

79

Sl.No Title of the Paper Authors Presented/Published in Journal

38. Presentation on Mitigation of Ramesh Babu DRUM training Programme heldEarthquake Hazards Disaster on June 2006 at CPRI, BangaloreManagement, Electrical Safetyand Accident prevention

39. Seismic Qualification of Substation Ramesh Babu Two day workshop on “SeismicEquipment’. Qualification of Electrical

Equipment and structures”23-24 November 2006

40. Vibration and Shock Qualification V. Srinivasa Murthy Two day workshop on “Seismictests on equipment’ Qualification of Electrical

Equipment and structures”23-24 November 2006

41. Seismic Qualification by Impulse Prabhakar Hegde Two day workshop on “SeismicHammer Technique Qualification of Electrical

Equipment and structures”23-24 November 2006

42. Seismic Qualification of Electrical R.Panneer Selvam Two day workshop on “SeismicEquipment by Shake Table tests’ Qualification of Electrical

Equipment and structures”23-24 November 2006

43. Seismic Qualification for Power R.Ramesh Babu All India Seminar on EnvironPlants mental Considerations in

Planning and Design of PowerProjects” organized by theInstitution of Engineers (India),Uttaranchal State Centre heldat Dehradun on 9th & 10th

November 2006.

44. Response Evaluation of Reinforced Chethan.K National seminar & ExhibitionConcrete Structures under Ramesh Babu on Recent Developments inEarthquake Loading Design & Construction Tech-

nologies, 18th, 19th & 20th

January 2007, organized byAssociation of Consulting CivilEngineers (India), BangaloreCentre held at Bangalore.

45. Seismic Qualification of Electrical Ramesh Babu Presentation in the 6th Interna-Equipment R.K. Hegde tional R&D Conference jointly

organized by CBIP and Power,Irrigation & Energy Depart-ment, Govt. of Uttar Pradeshon “Sustainable Developmentof Water & Energy Resources– Needs & Challenges” during13-16 February 2007.

Page 85: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

80

80

Sl.No Title of the Paper Authors Presented/Published in Journal

46. Testing of power transformer K.R .Dashrathy IEEMA Journal Dec 2006 .and analysis of results- Statistical K.G. Venkateshfailure rates of transformer of varied U. R. Sheshagiri Raoratings K. Badari narayanan

R.K. Gajendra

47. Performance evaluation of N.Vasudev Powergrid corporation of India ltdpolymer insulator used in K.N.Ravi New Delhi400 kv ac and +/_ 500 kv P.V.V NambudiriHV DC line Anantha Babu

P.N. DixitM.C. Bhatnagar

48. Design of external insulation from N.Vasudev Seminar on “silicone compositethe point of view of pollution insulators” organized by depart-

ment of scientific & industrialresearch (dsir), Ministry ofScience & Technology at NewDelhi 2nd August 2006

49. Polymeric insulators in Indian N. Vasudev Presented at workshop ontransmission system advanced Polymer composite

material technology for thepower sector held atCCAR,CPRI, Bangalore on 27Feb 2007.

50. Effect of fiber ratio on mechanica Maya Jacob Journal of Polymers andand thermogravimetric properties K.T. Varughese Polymer Compositesof lignocellulosic fiber reinforced Sabu Thomasrubber composites”

51. Durability and ageing characteristics Maya Jacob International Journal ofof hybrid bio-fiber reinforced natural K.T. Verughese Biobased Materials andrubber biocomposites Sabu Thomas Bionergy

52. Viscoelastic and thermal properties Maya Jacob Textile Research Journalof woven sisal fabric reinforced natural K.T. Verugheserubber composites Sabu Thomas

53. Dynamic mechanical analysis of Maya Jacob Journal of Polymersisal/oil palm fibre reinforced natural Bejoy Francis compositesrubber composites K. T. Verughese 27(2006)6 71-680

Sabu Thomas

54. Stress relaxation and thermal Maya Jacob Journal of Reinforced Plasticsanalysis of Hydro Biofiber Seno Jose and CompositesReinforced Rubber Biocomposites Sabu Thomas 25 (18)2006

K.T. Verughese 1903-1917

55. Dielectric characteristics of hybrid Maya Jacob Journal of Material Sciencebio-fibre reinforced natural rubber Sabu Thomas 41(17)2006composite K.T. Verughese 5538 - 5547

Page 86: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

81

81

Sl.No Title of the Paper Authors Presented/Published in Journal

56. The effect of Silance coupling agents Maya Jacob Journal of Micromolecuaron the viscoelastic properties of Sabu Thomas Material Engineeringbiofibre reinforced natural rubber K.T. Verughese 291(2006)1119-1126composites

57. Moisture absorption characteristics Maya Jacob Journal of Applied Polymerin woven sisal fabric reinforced natural Sabu Thomas Science, 102(2006)416-423rubber composites : A study K.T. Verughese

58. Failure properties of Thermoplastic J George Journal of Applied PolymerElastomers from High Density N.R. Neelagantan Science 100(4)2006Polyehylene.Nitrile rubber blends: K.T. Verughese 2812 - 2829Effect of blend ratio, dynamic S. Thomas

59. Novel woven sisal fabric reinforced Maya Hacob Journal of Compositenatural rubber composites : Tensile K.T. Verughese Materials 40 (2006)and swelling characteristics S. Thomas 1471-1485

60. Investigation on problem ofPT due to Corrosive Sulphur J.Sundara Rajan Double conference JanuaryC.J. Naidu 18 held at Beroic

K.DwarakanathA.K. Tripathi

61. Benzimidazole derivatives Dr. P.V. Reddy Journal of Applied Polymerand their complexes as Sakuntala Samuelson Scienceaccelleratos for curing of N.M. Nanje Gowdsepoxy resin D.N. Sathyanarayana

62. Estimation of AT&C Losses in R.Sudhir Kumar Presented at 22nd Nationala typical town in Kerala M.M Babu Narayanan Convention of Electrical

Engineers at Kochi on 24th,25th Nov 2006

63. Modernization of Distribution M.M Babu Narayanan Presented at 14th NationalSystem – Role of APDRP Power System Conference

NPSE during 27-28 Dec 2006

64. Investigation of Surge Voltage J. Santosh presentation at INDUCTICAbuild during switching of traction K.N. Srinivasan – 2006 Conference whichtransformer under no load V.S. Nandakumar was held in Berlin,

Germany from May 30th to1st June 2006

65. Remote Meter Reading using Power V. Shivakumar IEEE International Sympo-Line Carrier Communication V. Arunachalam , sium on Power Line

V.N.Nandhakumar Communications and itsJothy Gopalakrishnan, Applications – ISPLC 2007,Madhusudan Kadloor organized by IEEE/COMSOC,K.B. Manjunath

Page 87: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

82

82

Sl.No Title of the Paper Authors Presented/Published in Journal

66. Interpretation of Transformer Pradeep M Nirgude NPSC December,Frequency Response Data by P Ashok Raju 2007 IIT Rurkeetransfer function estimation & R. Sireeshaapplication of ANN technique

67. Condition monitoring of insulation T. Mallikharjuna Rao IIM, Mumbai, .of plant equipments using Thermo- 19 December 2006graphy maintaining insulation ofboilers & turbine.

68. Condition Assessment & remaining M. Venkateshwara Rao IIM, Mumbai, Life assessment for performance 18 December 2006improvement of boilers including criticalpiping.

69. High temperature corrosion (Oxidation) M. Venkateshwara Rao IIM, Mumbai,damage mechanism in boiler tubes and 19 December 2006techniques for condition assessment &remaining life estimation.

70. Condition assessment & remaining M. Venkateshwara Rao IIM, Mumbailife assessment for performance . 18 December 2006improvement of turbine.

71. Condition assessment of condensers M. Venkateshwara Rao IIM, Mumbai,& heat exchangers. 19 December 2006

72. Boiler tube failure mechanisms and M. Venkateshwara Rao VNIT, Nagpur 19.01.07preventive measures.

73. Influence of Short time over current S.K. Das Training program on energytests and tests of resistance to heat meters and relays,and fire on Energy Meters Bangalore 1 Sept. 2006

74. Studies on EPDM for low smoke flame Dr. P.V. Reddy National Seminar on Powerretardant applications Cable Technology, Dec. 2006.

at CPRI, Bangalore

75. Development of a new technique M.Siddhartha Bhatt B.H.Narayanafor measurement of coal flow B.H.Narayana C pp. 1-10.

76. Performance enhancement of M.Siddhartha Bhatt Journal of Scientific & Industrialnatural circulating, storage Research, Vol.66, 2007,type solar water heaters

77. Energy conservation in refrigeration S.Jothibasu Cooling India, Vol.2, No.2, Mayand air conditioning systems –June 2006, pp. 84-86.

78. Integration of solar PV – R.P. Mandi Journal of the Institution ofDiesel Hybrid Power System V.S. Kumar Engineers(India) Vol 87 May 29,

2006,pp. 14 – 20.

79. Effect of water side deposits on the M.Siddhartha Bhatt Energy Conversion &energy performance of coal fired Management, Vol. 47 (9-10),thermal power plants June, pp. 1247-1263.

80 The interrelationship between energy M.Siddhartha Bhatt Energy, 2007efficiency and energy consumption

Page 88: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

83

83

Sl.No Title of the Paper Authors Presented/Published in Journal

81. Effect of air ingress on the energy M.Siddhartha Bhatt Energy Conversion &performance of coal fired thermal Management, Vol. 47, 2007power plants

82. Safety requirements & safety systems M.Siddhartha Bhatt One day Seminar on Safety inin construction sites construction, 25th May 2006 at

ISRO, Bangalore

83. Lighting energy audits-case studies M.Siddhartha Bhatt National Workshop on Energyefficiency in lighting, Society ofEnergy engineers & managers,Mysore 9-11 August 2006.

84. Energy conservation in Boilers M.Siddhartha Bhatt Program on energy conservationin thermal plants, BMS Collegeof Engg., Bangalore, Sep. 132006

85. Efficiency and performance monitoring M.Siddhartha Bhatt Program on energy conservationof steam turbines in thermal plants, BMS College

of Engg., Bangalore, Sep. 13,2006

86. Combined cycle and gas based M.Siddhartha Bhatt PSTI, Bangalore on 12th Octoberpower stations 2006.

87. Electric Power –Demand & supply M.Siddhartha Bhatt One Day Seminar on Energy,Jointly organized by RotaryClub of Mysore, West & Indian

Nuclear Society, 20th January

2007

88. Energy Conservation technologies M. Siddartha Bhatt National Symposium on

- advances and trends Advanced Energy Conservation

Technologies, ManipalInstitute of Technology,

Manipal, 23 March 2007

89. Energy Conservation Techniques Rajashekar P. Mandi Seminar on emerging trends

in energy conservation, on

20 May 2006, organised bySambaram Institute of

Technology, Bangalore

90. Energy Conservation meassures in Rajashekar P. Mandi Seminar on EnergyElectrical Equipment in process Conservation, at Malnad

Industries College of Engineering

Hassan, organised by KREDL,Bangalore on 27 June 2006

Page 89: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

84

84

91. Factors affecting the short circuit B.V. Raghavaiah Conference on “Large Power

Performance of Transformers and M.K. Wadhwane Transformers - Modern trendsfailure analysis- A CPRI experience Manoher Singh Takher in Application, Installation,

Yugal Agarwal Operation, Maintenance

12-13 October 2006 at NewDelhi, organised by CBI&P

and CIGRE India, New Delhi

92. Market & Publicise the testing K. Manohara Seminar on “Energy Efficiencyfacilities on lighting in CPRI M. Naganna in Lighting” conducted at

Mysore on 10-11 August 2006,

organised by Society of EnergyEngineers and Managers

93. Market & Publicise the testing K. Manohara Seminar on “Energy Saving andfacilities on lighting in CPRI M. Naganna Efficient Street Lighting”

conducted by Indian Society of

Lighting Engineers, on 16thFebruary 2007, Bangalore

94. Concept of tower design and testing M. Selvaraj NPTI, Bangalore on 5th and

18th September 2006,

95. Concept of tower deisign and testing M. Selvaraj PSTI, Bangalore, on

19 October 2006

96. Design and testing of transmission M. Selvaraj PSTI, Bangalore, on

line towers 19 October 2006

97. Vibration aspects of conductors, M. Selvaraj PSTI, Bangalore, on

Insulators & line components 20 November 2006

98. Concept of tower design and testing M. Selvaraj PSTI, Bangalore, on5 March 2007

Sl.No Title of the Paper Authors Presented/Published in Journal

Page 90: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

85

85

AUDITOR'S REPORT

We have audited the enclosed Balance Sheet of CENTRAL POWER RESEARCH INSTITUTE,

BANGALORE as at 31st March 2007, and the Income and Expenditure Account and Receipt & Payments

Account of the said Society registered under the Karnataka Societies Act, 1960 for the year ended on that date

and report that:-

1. These financial statements are the responsibility of the societies management. Our responsibility is to

express an opinion on these financial statements based on our audit.

2. We conducted our audit in accordance with auditing standards generally accepted in India. Those

standards require that we plan and perform the audit to obtain reasonable assurance about whether the

financial statements are free of material misstatements. An audit includes examining, on a test basis,

evidence supporting the amounts and disclosure in financial statements. An audit also includes

assessing the accounting policies used and significant estimates made by management as well as

estimating the overall financial statement presentation. We believe that our audit provides a reasonable

basis for our opinion and we further report that:-

a) We have obtained all the information and explanations which to the best of our knowledge and

belief were necessary for the purpose of our audit.

b) The Balance Sheet, Income & Expenditure Account and Receipt & Payments Account dealt with by

this report are in agreement with the books of account maintained by the Society.

c) In our opinion and to the best of our information and according to the explanation given to us, the

said accounts read together with the notes thereon give a true and fair view.

Subject to non-provision of Depreciation on Fixed as stated in point No 1 of Schedule 16 - Notes to

Accounts and point no 2.3 of Schedule 17-Accounting Policies of the said accounts. Had depreciation

been provided, the excess of income over expenditure for the year would have been lower by

Rs. 10,39,86,274/-.

APPENDIX - X

'POORNIMA', No. 25,

State Bank Road, Bangalore - 560 001

Karnataka, India

Phone : 080-25587385, 25586814

Fax : 080-25594661

Grams : 'SUREAUDIT'

E-mail : [email protected]

: [email protected]

K. P. RAO & COCHARTERED ACCOUNTANTS

K. P. RAO, K. VISWANATH

VINAY G. RAO M.G. VINAYA SIMHA

K. SURYA PRAKASH RAVINDRANATH. P

CONSULTANT

SADASHIV RAO

Page 91: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

86

86

For K. P. RAO AND COMPANY

CHARTERED ACCOUNTANTS

Sd/

(M.G. VINAYA SIMHA)

PARTNER

MM No: 208874

Place : Bangalore

Date : 15.06.2007

Subject to non provision of Fringe Benefit Tax as stated in point no 5 of Scheduling 16 - Notes to

Accounts. As the amount has not been qualified by the management, we are un able to comment on

the impact on the income and expenditure account.

i) In case of Balance Sheet of the state of affairs of the Society as at 31st March 2007.

ii) In the case of Income and Expenditure Account, of the excess of Income over Expenditure for

the year ended on that date.

And

iii) In the case of Receipts and Payments Account, of the surplus being excess of receipt over

payments for the year ended on that date.

Page 92: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

87

87

CENTRAL POWER RESEARCH INSTITUTE BANGALOREBALANCE SHEET AS AT 31st MARCH 2007

BangaloreDate: June 15, 2007

Capital Fund and Liabilities Schedule Current Year Previous Year

Capital Reserve representing Assets acquiredfrom Grant-in-Aid from Government of India and Others 1 450,69,41,117 432,96,64,407

Reserves and Surplus 2 22,59,95,898 24,93,53,821Earmarked and Endowment Funds 3 71,79,65,920 59,81,23,956Grants from Government of India 4 17,06,61,929 3,41,00,694Unsecured Loans & Borrowings 5 3,16,00,000 3,76,00,000Current Liabilities and Provisions 6 14,54,85,362 12,74,89,317

Total 579,86,50,226 537,63,32,195 AssetsFixed Assets 7 453,16,91,845 435,26,01,939

Investments from Earmarked & Endowment Funds 8 62,41,47,960 55,83,23,956

Current Assets, Loans and Advances 9 64,28,10,421 46,54,06,300

Total 579,86,50,226 537,63,32,195 Notes on Accounts & Contingent Liability 16Significant Accounting Policies 17Schedules 1 to 9 and 16 & 17 form part of Balance Sheet

CENTRAL POWER RESEARCH INSTITUTE, BANGALOREINCOME AND EXPENDITURE ACCOUNT FOR THE YEAR ENDED 31ST MARCH 2007

INCOME Schedule Current Year Previous Year

Income from Test Fee & Consultancy 10 39,36,03,547 38,83,07,658

Fees 11 86,28,955 34,25,175

Interest Earned 12 1,94,75,756 1,86,25,198

Other Income 13 55,83,043 42,91,622

Total (A) 42,72,91,300 41,46,49,653

Expenditure

Establishment Expenses 14 20,13,98,805 19,69,43,380

Other Administrative Expenses 15 19,11,64,504 18,29,45,717

Total (B) 39,25,63,309 37,98,89,097

Balance being excess of Income over Expenditure (A-B) 3,47,27,991 3,47,60,556

Balance being surplus carried to General Reserve 3,47,27,991 3,47,60,556

Notes on Accounts & Contingent Liability 16

Significant Accounting Policies 17

Schedules 10 to 15 and 16 & 17 form part of Income & Expenditure Account

(Amount in Rupees)

As per Our Report of Even Datefor K. P. RAO & CO

Chartered Accountants

Sd/(M.G. VINAYA SIMHA)

Partner

Sd/(A. K. TRIPATHY)

Director General

Sd/(I. VENKATESWARA RAO)

Chief Accounts Officer

Page 93: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

88

88

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET AS AT 31ST MARCH 2007

Current Year Previous Year

Capital Reserve representingAssets acquired fromGrant-in-Aid fromGovernment of India and Othersa) Under Plan Capital 395,76,24,307 3,795,707,493

Addition during the year 14,36,08,821 410,12,33,128 161,916,814 3,957,624,307b) Under R&D Plan 16,11,09,953 147,770,549

Addition during the year 2,32,27,828 18,43,37,781 13,339,404 161,109,953c) Under Non-Plan 7,25,66,429 72,405,217

Addition during the year 1,42,096 7,27,08,525 161,212 72,566,429d) Assets acquired out of General Reserve 5,43,36,159 45,668,291

Addition during the year 12,61,380 5,55,97,539 8,667,868 54,336,159e) Assets acquired out of

Sponsored Schemes 7,29,80,985 69,006,157 -Addition during the year 10,03,958 7,39,84,943 3,974,828 72,980,985

f) Assets acquired out of RSoPManagement Fund 11,46,574.00 1,146,574 -Addition during the year 32,627 11,79,201 - 1,146,574

g) Capitalisation of Assets acquired 99,00,000 -out of LoanAddition during the year 80,00,000 1,79,00,000 9,900,000 9,900,000

Total 450,69,41,117 - 4,329,664,407

(Amount in Rupees)

SCHEDULE -1

Current Year Previous Year

Reserves and SurplusA) General Reserve

As per last Account 18,00,28,246 163,996,770 -Addition during the year 3,47,27,991 34,760,556 -Less:- Transfer to Superannuation Fund 6,00,00,000 -Less:- Assets directly acquired

out of General Reserve 12,61,380 8,667,868 -Less:- Assets acquired

transferred to Capital Reserve 1,42,096 161,212 -Less:- ICICI Loan Repayment 80,00,000 9,900,000 -

Net Balance - I 14,53,52,761 - 180,028,246

B) Maintenance, Renewal &Obsolescence ReserveOpening Balance 6,93,25,575 50,000,000 -Add:- Intrest earned & accrued duing the

year 35,44,184 -Add:- Provision during the year 3,50,00,000 35,000,000 -Less:- Amount spent from MRO Fund 2,72,26,622 15,674,425 -Net Balance - II 8,06,43,137 - 69,325,575

Total 22,59,95,898 - 249,353,821

SCHEDULE -2

BangaloreDate: June 15, 2007

Page 94: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

89

89

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET AS AT 31ST MARCH 2007

(Amount in Rupees)

Earmarked & Endowment FundsA) Superannuation Fund

Opening Balance 45,66,44,553 413,493,220Add:- Receipts from other organisations 31,484 68,537 -Add:- Transfers from General Reserves 6,00,00,000 -Add:- Provision during the year 3,46,00,000 39,800,000 -Add:- Interest received and accrued 3,67,18,576 29,655,720 -Add:- Retention Money received 14,000 25,000 -Less:- Utilisation for pension payments 2,52,67,701 26,397,924Net Balance - I 56,27,40,912 - 456,644,553

B) Provident FundOpening Balance 13,83,80,124 121,727,467Add:- Subscriptions & Repayments 3,06,92,223 29,484,297 -Add:- Interest credited to PF members 1,11,71,022 9,998,558 -Less:- Withdrawals 2,77,67,773 22,830,198 -

Total 15,24,75,596 - 138,380,124Opening Balance (Additional Interest) 29,32,495 3,786,175 -Less:- Utilisation towards shortfall in

Interest earned over Interestcredited to PF Accounts(Rs.1,03,45,207 - 1,11,71,022) (8,25,815) (853,680) -

Total 21,06,680 2,932,495

Net Balance - II 15,45,82,276 - 141,312,619C) New Pension Scheme Fund

(i) Opening Balance(employees contribution) 81,672 -Add:- Subscriptions / Employees’

Contribution 2,22,008 - 81,672 -Add:- Interest on Employees’ Contribution 17,686 1,720 -

(Cumulative)(ii) Opening Balance(employees contribution) 81,672 -Add:- Employers

Contribution 2,22,008 - 81,672 -Add:- Interest on Employees’ Contribution 17,686 1,720 -

(Cumulative)Net Balance - III - 6,42,732 166,784

Total (I+II+III) - 71,79,65,920 - 598,123,956

SCHEDULE - 3 Current Year Previous Year

BangaloreDate: June 15, 2007

Page 95: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

90

90

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET AS AT 31ST MARCH 2007

Current Year Previous Year

Grants from Government of India

a) Under Plan Capital

Opening Balance 2,48,91,137 93,807,951 -Add:- Grant received during the year 27,30,00,000 93,000,000 -Less:- Grant utilised during the year 14,36,08,821 161,916,814 -Grant Balance 15,42,82,316 - 24,891,137

b) Under R&D Plan

Opening Balance 39,04,952 7,658,363 -Add:- Grant received during the year 3,00,00,000 16,000,000 -Less:- Grant utilised during the year 3,18,24,705 19,753,411 -Grant Balance 20,80,247 - 3,904,952

c) Under RSoP Scheme

Opening Balance 53,04,605 5,710,502 -Add:- Grant received during the year 2,00,00,000 12,300,000 -Less:- Grant utilised during the year 1,46,25,239 12,705,897 -Grant Balance 1,06,79,366 - 5,304,605

d) Under NPP SchemeOpening Balance - -i) Add: Grant received during the year 72,00,000 - less: Grant utilised during the year 72,00,000 -Grant Balance - -

ii) Opening Balance - - Add : Grants received from Sponsors 55,00,000 - Less : Grant utilised during the year 18,00,000 -

grant Balance 36,20,000 -Total 17,06,61,929 3,41,00,694

(Amount in Rupees)

SCHEDULE -4

BangaloreDate: June 15 2007

Unsecured Loans & BorrowingsUnsecured Loan:-Loan from ICICI Bank Ltd.Opening Balance 3,76,00,000 - 30,000,000Add:- Additional Fresh Loan drawn - - -

during the year 20,00,000 17,500,000 -Less:- Repayment of Loan

during the year 80,00,000 9,900,000 -Loan Balance 3,16,00,00

Total - 3,16,00,000 - 3,76,00,000

SCHEDULE - 5 Current Year Previous Year

Page 96: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

91

91

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET AS AT 31ST MARCH 2007

Gross Block

A. Fixed Assets1) Land

Freehold 17,689,090 - - 17,689,090 17,689,0902) Buildings

On Freehold Land 47,45,06,582 97,804 5,30,69,239 52,76,73,625 47,45,06,5823) Plant, Machinery &

Equipment 3,630,921,438 2,42,17,883 2,68,86,419 368,20,25,740 3,630,921,4384) Vehicles 49,30,869 2,06,288 - 51,37,157 49,30,8695) Furniture & Fixtures 5,768,892 64 50,42,977 1,08,11,933 5,768,8926) Library Books & Film 1,22,21,881 1,41,892 - 1,23,63,773 1,22,21,8817) Machinery & Equipments -

(Sponsored Projects) 7,52,88,607 10,03,958 - 7,62,92,565 7,52,88,6078) Buildings on Freehold Land

(ICICI) 22,44,336 - 29,315 22,73,651 22,44,3369) Plant, Machinery & -

Equipment (ICICI) 3,05,93,196 69,818 97,14,063 4,03,77,077 3,05,93,196

Total 425,41,64,891 2,57,37,707 9,47,42,013 437,46,44,611 425,41,64,891

B. Capital Work-in-Progress 9,84,37,048 14,36,08,821 (8,49,98,635) 15,70,47,234 9,84,37,048C. Capital Work-in-Progress

(ICICI) - 97,43,378 (97,43,378) - -

Grand Total 435,26,01,939 17,90,89,906 - 453,16,91,845 435,26,01,939

SCHEDULE - 7

Cost/valuation Additions Transfer As at the As at theAs at during the from WIP Current year Previous year

beginning year end endof the year

Current Year Previous Year

Current Liabilities and ProvisionsA. Current Liabilities1) Sundry Creditors

a) For Supplies & Services 42,65,151 4,335,895 -b) For Expenses 1,55,73,813 15,328,208 -c) For Salaries 1,41,29,230 12,008,669 -d) For Others 24,30,408 1,599,340

3,63,98,608 33,272,1122) Deposits Received

(Test Fee & Consultancy) 8,11,59,302 - 70,509,7673) Statutory Liabilities 93,58,434 - 5,665,5064) EMD, Security Deposits & Others 1,61,49,681 - 14,386,4425) Sponsored Scheme Deposits 24,19,337- 3,655,490

Total - 14,54,85,362 - 12,74,89,317

(Amount in Rupees)

SCHEDULE -6

BangaloreDate: June 15, 2007

Page 97: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

92

92

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET AS AT 31ST MARCH 2007

Investments from Earmarked/Endowment Funds

A. Superannuation Fund Investment Account

1) In Government Securities -

2) Bonds 17,90,00,000 11,68,45,000

3) Term Deposits with Banks & Financial Institutions 14,41,59,749 15,01,59,749

4) Post office Time Deposits 12,65,52,000 12,65,52,000

5) Interest Accrued on Superannuation Fund Investments 1,44,30,794 1,65,66,738

6) Receivables 11,48,134 13,86,720

7) Cash at Bank (S.B Account No.10356553751) 36,32,275 53,34,346

Total - 1 46,89,22,952 41,68,44,553

B.Provident Fund Investment Account

1) In Government Securities - -

2) Bonds - 6,40,000

3) Term Deposits with Banks & Financial Institutions 7,04,35,189 6,54,35,189

4) Post office Time Deposits 6,85,71,000 6,85,71,000

5) Interest Accrued on PF Investments 49,17,619 2,138,827

6) Receivables 3,79,747 477,352

7) Cash at Bank (S.B Account No.10356553740) 1,02,78,721 4,050,251

Total - 2 15,45,82,276 141,312,619

C. New Pension Scheme Fund Investment Account

1) Cash at Bank (S.B Account No.30019323462) 6,42,732 1,66,784

Total - 3 6,42,732 1,66,784

Total Investments (1+2+3) 62,41,47,960 55,83,23,956

(Amount in Rupees)

SCHEDULE -8 Current Year Previous Year

BangaloreDate: June 15, 2007

Page 98: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

93

93

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF BALANCE SHEET FOR THE YEAR 31ST MARCH 2007

Current Year Previous Year

Current Assets, Loans & Advances

A Current Assets1 Inventories

a) Stores and Spares 93,260 93,260 94,562 94,5622 Sundry Debtors

a) Debts Outstanding for a periodexceeding six months 3,47,34,622 32,941,643 -

b) Debts Outstanding for a periodnot exceeding six months 4,71,91,822 8,19,26,444 30,526,180 63,467,823

3 Cash balances in hand(including cheques/drafts and imprest) 2,08,594 144,699 144,699

4 Deposits & Bank Balancesa) Deposits with Scheduled Banks

(includes margin money) 19,69,38,946 215,131,623 -b) Savings Accounts 26,57,59,937 46,26,98,883 96,393,513 31,15,25,136c) Deposits of Maintenance,

Renewal & Obsolescence Reserve 4,00,00,000 3,47,50,000 -d) Savings Bank Account of Maintenance,

Renewal & Obsolescence Reserve 27,23,433 1,05,435 -e) Accrued Interest on MRO Fund 29,19,704 4,56,43,137 12,39,579 3,60,95,014

B Loans, Advances & Other Assets

a) Deposits with GovernmentDepartments & Others 1,53,89,507 - 18,222,080 -

b) Advances to Employees 2,26,31,094 - 25,227,785 -c) Prepaid Expenses 12,29,645 - 916,345 -d) Accrued interest 90,87,810 - 6,814,317 -e) Claims Receivable 29,70,082 - 1,161,822 -f) Other Advances 9,31,965 5,22,40,103 1,736,717 54,079,066

Total - 64,28,10,421 - 465,406,300

(Amount in Rupees)

SCHEDULE - 9

BangaloreDate: June 15, 2007

SCHEDULES FORMING PART OF INCOME & EXPENDITURE FOR THE YEAR ENDED 31ST MARCH 2007

Income from Test Fee & Consultancy

a) Test Fee 30,41,09,491 312,254,608

b) Consultancy Service Charges 8,94,94,056 76,053,050

Total 39,36,03,547 388,307,658

SCHEDULE -10 Current Year Previous Year

Page 99: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

94

94

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF INCOME & EXPENDITURE FOR THE YEAR ENDED 31ST MARCH 2007

(Amount in Rupees)

BangaloreDate: June 15, 2007

Interest Earned

1) Interest on Term Deposits with Banks & Financial Institutions # 1,88,75,921 17,370,601

2) Interest on Loans & Advances to Employees 5,99,835 1,254,597

Total 1,94,75,756 18,625,198

# Tax Recovered on Interest from Bank Deposits and Investments is Rs.37,615/- for the year 2006-07

SCHEDULE -12 Current Year Previous Year

Other Income

1) Fees for Miscellaneous Services

a) Sale of Publications 15,600 14,300

b) Library Receipts - 2,166

2) Miscellaneous Income

a) Application fee on recruitment 27,600 73,025

b) Private use of vehicles 29,747 22,690

c) Sale of Tender forms 1,44,916 235,099

d) Rent Receipts 15,39,739 1,393,791

e) Sale of Scrap 6,55,492 264,669

f) Others 31,69,949 2,285,882

Total 55,83,043 42,91,622

SCHEDULE - 13 Current Year Previous Year

Establishment Expenses

a) Salaries and Wages including Bonus 15,19,03,206 142,254,585

b) Staff Welfare Expenses 67,26,684 5,285,565

c) Expenses on Employees’ Retirement and Terminal Benefits 3,48,32,162 39,957,233

d) Expenses on Medical Facilities 79,36,753 9,445,997

Total 20,13,98,805 196,943,380

SCHEDULE - 14 Current Year Previous Year

Fees

1) Training Fee 27,68,972 911,100

2) Seminar Fee 58,59,983 2,514,075

Total 86,28,955 3,425,175

SCHEDULE -11 Current Year Previous Year

Page 100: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

95

95

CENTRAL POWER RESEARCH INSTITUTE, BANGALORESCHEDULES FORMING PART OF INCOME & EXPENDITURE FOR THE YEAR ENDED 31ST MARCH 2007

(Amount in Rupees)

Other Administrative Expenses

a) Electricity and Power 4,21,90,767 41,971,765

b) Water Charges 9,94,094 859,020

c) Office Expenses 1,01,54,049 9,895,012

d) Repairs and Maintenance 7,76,32,959 69,823,646

e) Rent, Rates and Taxes 3,08,197 308,197

f) Vehicles Running and Maintenance Expenses 28,77,723 2,358,207

g) Postage, Telephone and Communication Charges 43,13,486 5,111,979

h) Printing and Stationery 13,81,128 1,503,905

i) Travelling and Conveyance Expenses 89,94,750 10,371,722

j) Expenses on Seminar & Workshops 33,62,356 2,643,623

k) Subscription Expenses 79,092 78,070

l) Expenses on Fees 35,058 44,420

m) Auditor’s Remuneration 1,00,000 75,000

n) Professional Charges 6,20,036 455,273

o) Library Expenses 16,97,594 613,768

p) Training Expenses 6,54,144 724,950

q) Publication Expenses 24,650 154,778

r) Advertisement and Publicity 7,44,421 952,382

s) Provision for MRO Fund 3,50,00,000 35,000,000

Total 19,11,64,504 182,945,717

SCHEDULE - 15 Current Year Previous Year

BangaloreDate: June 15, 2007

Page 101: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

96

96

Schedule – 16

Notes on Accounts & Contingent Liability attached to and forming part of Balance Sheet as at 31st March 2007, AND

Income & Expenditure Account AND Receipts & Payments Account for the year ended on that date

Background:- The Institute, an autonomous body under Govt. of India, Ministry of Power incorporated through a

resolution vide No.33(14)/74-Policy, dated 21/10/1974 is totally focused on Power Research. The Institute has been recognized

by Ministry of Science & Technology as an S&T Institution. The Institute has been further recognized as Scientific and

Industrial Research organization by Government of India, Ministry of Science and Technology vide their letter No.11/68/88-

TU-V, dated 5/4/2005 and valid upto 31.03.2008. The Institute as a legal entity is registered with the Registrar of Societies. The

basic objectives of the Institute is to serve as a National Testing & Certification Authority and act as an apex body for initiating

and coordinating Research and Development in the field of electric power. The Government of India is supporting the

activities thro’ grants. Additionally, the Institute is generating funds through other sources and thro’ test fees and professional

services rendered to Government organizations/Electricity Boards/Commercial organizations etc.

Institute is notified by the Government of India, Ministry of Finance, Department of Revenue vide notification No.178/2007

(F.No.203/38/2006/ITA-II), dated 24.05.2007 in the category of 'other institution' partly engaged in research activities for the

purpose of Clause (ii) of subsection (1) of section 35 of the Income Tax Act 1961read with rule 5C & 5D of the Income Tax

Rules, 1962 effective from 1.4.2005 onwards. Accordingly, the income of the Institute will be exempt from Income Tax as

provided under Section 10(21) of Income Tax Act, 1961.

1. Fixed Assets and Depreciation:- Hitherto, the Institute capitalized all costs relating to the acquisition and installation of all

fixed assets. From the year 2002-03 onwards, the Institute has changed its policy for accounting capital assets as under

All assets acquired under Capital Projects, R&D Plan, Sponsored Schemes, RSoP Schemes are

capitalized with all costs relating to their acquisition.

All assets acquired out of Non-Plan (Revenue) expenditure of the Institute are charged off to the

Income & Expenditure account during the year. The value of such assets is Rs.115.11 lakhs for

2006-07 (Rs.149.31 lakhs for the year 2005-06). Total value of assets charged off from 2002-03 tillnow,

is Rs. 518.52 lakhs.

Since the infrastructure is created by drawal of grants from Government of India, depreciation is not provided in the

books of accounts. Depreciation not provided as per the rates prescribed under the Income Tax act under the Written

Down value method till the period ended 31.3.2007 is Rs.3,68,51,00,064/-(Depreciation upto 31.03.2006 was

Rs.3,58,11,13,790/-) and Depreciation for the year is Rs.10,39,86,274/- (Depreciation for 2005-06 was Rs. 10,32,57,217/

-). The fixed assets are stated only at cost.

2. Government Grant:- Grants received from the Government of India and other organisations towards specific

projects are shown as capital/sponsored grants. The Institute conforms compliance of all the conditions of the grant.

The Institute consistently has followed the procedure of showing the assets procured from such grants under the

Fixed Assets.

Page 102: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

97

97

3. Retirement Benefits:- The liability on account of Pension, Gratuity & Leave Encashment for the period ending

31.3.2007 evaluated through M/s.India Life Hewitt on the basis of actuarial valuation amounts to Rs. 5627.00 lakhs.

As the Superannuation Fund as on 31.03.2007 is only Rs.4681.00 lakhs, further requirements of funds is to the tune

of Rs.946.00 lakhs of which Rs.346.00 lakhs is charged to Income & Expenditure Account and the balance amount

of Rs. 600.00 lakhs is being provided from General Reserve Fund.

4. The Institute has created and operating Maintenance, Renewal & Obsolescence (MRO) Fund from 2004-05.

During the current year, Rs.272.26 lakhs has been utilized from MRO Fund towards major repairs in High Power

Laboratory & Sub Station and a provision of Rs.350.00 lakhs is made during 2006-07.

5. Finance Act 2005 has introduced Fringe Benefit Tax (FBT) w.e.f 1.4.2005. The Institute is recognized as “S & T

Institution” by Department of Science & Technology, and is also recognized as “Scientific & Industrial Research

Organisation” by Department of Scientific & Industrial Research.

The rules and regulations regarding service matters of employees of the Institute are in accordance with the CCS

Rules as an extended arm of Government Department. The Institute is receiving complete support for Capital and

Research & Development Projects.

The Institute had been notified as a Research & Development organization and had been approved by Central

Government for the purpose of Section 35(1)(ii) had been exempt from Income Tax. A letter was also addressed to

Ministry of Power for seeking exemption from Ministry of Finance, from payment of FBT. In view of the above,

FBT is not paid nor provided.

6. The total Land in the possession of the Institute is as under :

a) Freehold Land - 281.12 acres

b) Leasehold Land - 33.00 acres

Total 314.12 acres

7. Contingent Liabilities:-

(a) On account of Letter of Credit opened and remaining to be honoured – NIL (excepting Letter of credits

with 100%margin) (NIL for 2005-06).

(b) Estimated amount of liability on account of capital contracts – Rs. 1576.31 lakhs (Rs.540.67 lakhs for 2005-

06).

(c) Claims not acknowledged as debts by the Institute – Nil.

(d) Bank Guarantees furnished to various clients by the Institute is of the value of Rs.100.39 lakhs for 2006-07

(Rs.127.06 lakhs for 2005-06)

Page 103: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

98

98

(e) With the inclusion of Scientific & Technical consultancy as one of the taxable services under Service Tax

Rules with effect from 16th July 2001, the Institute has registered with Service Tax authorities and collecting

& remitting service tax to Central Excise Department. However the Service Tax Department treating CPRI

as a ‘Consulting Engineer’ had passed an order-in-Appeal demanding payment of Service Tax amounting to

Rs. 512.00 lakhs on the value of taxable services for the period 7.7.1997 to 15.7.2001. The matter has been

disputed as CPRI cannot be construed as ‘Consulting Engineer’. An appeal was filed before the Customs,

Excise and Service Tax Appellate Tribunal (CESTAT) (South Zone Bench), Bangalore, and the Hon’ble

Division Bench set aside the impugned Order by allowing the appeal during the final hearing on 18th May 2006.

The Commissioner of Service Tax is proposing to appeal against the Order of CESTAT and has filed an

application with Committee on Disputes (COD) Cabinet Secretariat, New Delhi.

(f) There is a dispute between the Institute and M/s. A.S.Iyer & Co., Nagpur regarding construction of quarters

at CPRI, Nagpur. As per the arbitration award made by the Arbitrator, CPRI is liable to pay Rs.17.80 lakhs to

M/s. A.S.Iyer & Co., Nagpur alongwith 18% Interest P.A to the point of judgement which works out to

Rs.40.25 lakhs. The Institute filed an appeal before High Court of Karnataka who have granted Interim Order

staying the execution of the decree passed against CPRI subject to CPRI depositing Rs.20.00 lakhs in the

Court. Accordingly, Rs.20.00 lakhs was deposited in High Court of Karnataka during 2004-05.

8. The Institute has a system of Internal Audit conducted by a firm of Chartered Accountants.

9. The grant balances shown at Schedule-4 are exclusive of margin money utilized for L.C establishment towards the

committed Liability for import of equipments. The margin money deposits at the end of 31.3.2007 are Rs.673.93

lakhs (Rs.145.10 lakhs at the end of 2005-06).

10. Figures for the previous year have been regrouped wherever necessary to conform with the presentation of this year.

BangaloreDate : June 15, 2007

As per Our Report of Even Datefor K. P. RAO & CO

Chartered Accountants

Sd/(M.G. VINAYA SIMHA)

Partner

Sd/(A. K. TRIPATHY)

Director General

Sd/(I. VENKATESWARA RAO)

Chief Accounts Officer

Page 104: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

99

99

Schedule – 17Significant Accounting Policies attached to and forming part of Balance Sheet as at 31st March 2007 AND Income & ExpenditureAccount AND Receipts & Payments Account for the year ended on that date.

1. Method of Accounting:

1.1 The Accounts have been prepared on the historical cost concept, based on the accrual method of Accounting,in accordance with the generally accepted Accounting Principles, unless otherwise stated.

2. Fixed Assets:

2.1. Fixed Assets acquired under Capital Projects, R & D Plan, Sponsored Schemes and loans are stated at theiroriginal cost of acquisition. The funds provided for acquisition of these Fixed Assets under Grant-in-Aidfrom Government of India/other Agencies are reflected as contra under Capital Reserve.

2.2. Fixed Assets acquired other than referred to 2.1. are charged off as revenue expenditure during the yearw.e.f. 2002-03.

2.3. The Institute is a non-profit organization and therefore depreciation is not provided in the accounts.

2.4. Capital work-in-progress includes expenditure on Civil Works of projects which have not been completedas at the end of the year.

3. Investments:

3.1. Investments are valued at cost.

4. Inventories:

4.1. Inventories of stores and spares are valued at cost, and cost includes expenses incurred for procuring the same.

5. Research and Development:

5.1. Revenue expenditure on Research and Development are adjusted against the receipt of research grants. Capitalexpenditure on Research & Development are treated in the same manner as expenditure on other fixed assets.

6. Foreign Currency Transaction:

6.1. Transactions in Foreign Currency are recorded at the rate of Exchange prevailing at the beginning of financialyear.

6.2. Realised gains and loses on Foreign Currency transactions other than those relating to fixed assets are recognizedin the Income and Expenditure Account. Gain or Loss on transactions in respect of liabilities incurred toacquire fixed assets are adjusted to the carrying cost of such fixed assets.

7. Revenue Recognition:

7.1. The Revenue in respect of Test Fees and Consultancy charges are accounted on completion of the work.

8. Retirement Benefits:

8.1. Retirement liabilities to staff/employees in respect of Gratuity, Leave Encashment, Superannuation benefits areprovided in the accounts based on actuarial valuation.

As per Our Report of Even Datefor K. P. RAO & CO

Chartered Accountants

Sd/(M.G. VINAYA SIMHA)

Partner

Sd/(A. K. TRIPATHY)

Director GeneralBangaloreDate : June 15, 2007

Sd/(I. VENKATESWARA RAO)

Chief Accounts Officer

Page 105: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

100

100

CENTRAL POWER RESEARCHRECEIPTS AND PAYMENTS FOR THE PERIOD

RECEIPTS Current Year Previous Year

I Opening Balances

a. Cash in Hand 144,699 3,364,957

b. Bank Balances

i) Savings accounts 106,050,330 106,401,368

ii) In Short-term deposits 53,806,323 89,934,596

iii) In Long-term deposits 161,325,300 72,672,300

iv) PF Investments 134,646,189 113,194,402

v) SAF Investments 393,556,749 377,385,749

vi) MRO Fund Investments 34,750,000 30,000,000

II Grants Received

a. Capital Grants from GOI 273,000,000 93,000,000

b. R&D Grants from GOI 30,000,000 16,000,000

c. RSoP Grants from GOI 20,000,000 12,300,000

d. NPP Grants from GOI 7,200,000

e. NPP Grants from Sponsorers 5,500,000

f. Deposits from Sponsored Projects 3,329,800 5,307,000

g. ICICI Funds 1,997,613 17,500,000

III Receipts on Endowment Funds

a. Receipts on SA Funds 31,484 15,798,867

b. Interest received in PF 7,566,415 17,020,564

c. Interest received in SA 38,854,520 31,966,161

d. GPF Subscription & Repayments 30,687,223 29,484,297

e. NPS Subscription 484,704 166,784

IV Receipts on Maintenance, Renewal, Obsolescence Reserve

V Interest Received

a. On Bank deposits 21,258,124 23,497,852

b. On Loans & Advances to employees 177,979 224,163

VI Revenue Receipts

a. Receipts from Clients 454,688,668 462,549,384

b. Royalty & Technology Transfer 0

c. Publication Sales 15,350 14,300

d. Seminars & Conferences Fees 7,312,692 3,425,175

e. Rent Receipts 912,553 751,531

f. Transport Charges 7,025 84

g. Sale of Tender Forms 176,212 235,099

h. Miscellaneous Receipts 3,162,471 1,687,497

Page 106: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

101

101

INSTITUTE, BANGALORE1ST APRIL 2006 TO 31ST MARCH 2007

PAYMENTS Current Year Previous Year

I Expensesa. Establishment Expenses

132,495,719 133,835,505b. Administrative Expenses

163,225,415 158,431,818II Payments made against funds for various Projects

a. Plan Capital Expenditurei) Machinery & Equipments under Erection 70,909,824 96,071,952ii) Civil works 18,123,295 45,398,184iii) Purchase of Land at Noida 42,211,673iv) Miscellaneous Expenses 7,584077 13,264,847

b. R&D Expenditurei) Fixed Assets 21,167,412 12,993,570ii) Research Activity Expenses 8,694,681 6,375,288

c. Sponsored Project Expenditurei) Fixed Assets 946,467 1,171,610ii) Research Activity Expenses 3,427,085 1,392,083

d. RSoP Schemesi) Fixed Assets 32,627ii) Management Expenditure 76,778 184,791iii) Disbursements 14,509,367 12,461,733

e. NPP Schemesi) NPP Grants disbursement 7,200,000ii) NPP Grants disbursement (Sponsorers) 1,880,000

f. ICICIi) Fixed Assets 9,520,557 6,774,527ii) Civil Works 28,472 4,472iii) Misc. Expenses 49,244 5,510

g Payment out of General ReserveIII Payments on Endowment Funds

a. GPF Advances/ Withdrawals 27,767,773 22,830,198b. Retirement Settlements 24,471,660 25,471,393

IV Assets Acquired out of General Reservea. Library Books, etc. 141,892 54,979b. Vehicles 0 -c. Assets acquired 1,060,564 6,962,760

V Payments on MRO Fundi) Fixed Assets 25,303,111 15,666,415ii) Misc. Expenses 1,864,059

(Amount in Rupees)

Page 107: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

102

102

CENTRAL POWER RESEARCHRECEIPTS AND PAYMENTS FOR THE PERIOD

RECEIPTS Current Year Previous Year

VII Advances Refund & Deposits

a. Advances to Suppliers 548,953 414,011

b. Loans & Advances to employees (Recovery) 5,310,970 4,673,261

c. EMD & Security Deposits 10,421,924 4,437,289

d. Withdrawal of Deposits from Telephones, etc. 13,008,162 248,336

e. Stores 0 645

VIII Recoveries for Remittances

a. Statutory Recoveries for Remittances 11,906,392 13,736,632

b. Recoveries from salaries for Remittances 6,408,680 6,879,085

c. Group Savings Linked Insurance Scheme 536,642 817,945

d. Accident Insurance Scheme 171,645 607,907

Total 1,838,955,7911,555,697,241

As per Our Report of Even Datefor K. P. RAO & CO

Chartered Accountants

Sd/(M.G. VINAYA SIMHA)

Partner

Sd/(A. K. TRIPATHY)

Director General

Sd/(I. VENKATESWARA RAO)

Chief Accounts OfficerBangaloreDate: June 15, 2007

Page 108: 01 Annual 2006-07 (1-53) with photos

ANNUAL REPORT 2006-2007

103

103

INSTITUTE, BANGALORE1ST APRIL 2006 TO 31ST MARCH 2007

PAYMENTS Current Year Previous Year

VI Other Payments

a. Advances to Suppliers 7,39,128 10,843,248

b. Advances to Employees 8,393,941 13,613,659

c. Refund of EMD & Security Deposits 10,200,070 5,194,877

d. Sundry Debtors for Tests, Consultancy & Others 17,638,523 3,650,942

e. Deposits for Telephones & Electricity, etc. 8,982,381 4,239,440

VII Remittances of Recoveries

a. Remittances of Statutory Recoveries 52,539,910 51,688,493

b. Remittances of Salary Recoveries 47,623,352 21,186,251

c. Group Savings Linked Insurance Scheme 1,003,592 1,049,275

d. Accident Insurance claims & payments 240,566 599,831

VIII Closing balances

a. Cash in Hand 208,566 144,699

b. Bank Balances

i) Savings accounts 283,037,098 106,050,330

ii) In Short-term deposits 94,616,646 53,806,323

iii) In Long-term deposits 102,322,300 161,325,300

iv) PF Investments 1,39,006,189 134,646,189

v) SA Investments 449,711,749 393,556,749

vi) MRO Fund Investment 40,000,000 34,750,000

Total 1,838,955,791 1,555,697,241

(Amount in Rupees)

As per Our Report of Even Datefor K. P. RAO & CO

Chartered Accountants

Sd/(M.G. VINAYA SIMHA)

Partner

Sd/(A. K. TRIPATHY)

Director General

Sd/(I. VENKATESWARA RAO)

Chief Accounts OfficerBangaloreDate: June 15, 2007

Page 109: 01 Annual 2006-07 (1-53) with photos

Cen

tral

Pow

er R

esea

rch

In

stit

ute

, B

anga

lore

Sch

edu

le o

f Fix

ed A

sset

s an

d D

epre

ciat

ion

on

Fix

ed A

sset

s as

at 3

1.3.

2007

1)

Lan

d17

,689

,090

017

,689

,090

0%0

00

17,6

89,0

9017

,689

,090

2)B

uild

ings

on

Free

hold

Lan

d47

,45,

06,5

825,

31,6

7,04

352

,76,

73,6

2510

%28

,62,

86,3

562,

41,3

8,72

731

,04,

25,0

8318

,82,

20,2

2621

,72,

48,5

42

3)P

lant

& M

achi

nery

363,

09,2

1,43

8

5,

11,0

4,30

236

8,20

,25,

740

* 1

5%32

0,10

,30,

013

7,21

,49,

359

327,

31,7

9,37

242

,98,

91,4

2540

,88,

46,3

68

4)Ve

hicl

es49

,30,

869

2,06

,288

51,3

7,15

7*

15%

28,4

1,04

93,

44,4

1631

,85,

465

20,8

9,82

019

,51,

692

5)Fu

rnit

ure

& F

ixtu

res

57,6

8,89

250

,43,

041

1,08

,11,

933

10%

45,0

2,46

76,

30,9

4751

,33,

414

12,6

6,42

556

,78,

519

6)L

ibra

ry B

ooks

1,19

,96,

728

1,41

,892

1,21

,38,

620

33.3

3%1,

16,5

4,94

51,

61,2

091,

18,1

6,15

43,

41,7

833,

22,4

66

7)Fi

lms

(Doc

umen

tary

)2,

25,1

530

2,25

,153

10%

1,96

,655

2,85

01,

99,5

0528

,498

25,6

48

8)M

achi

nery

& E

quip

men

ts(S

pons

ored

)7,

52,8

8,60

710

,03,

958

7,62

,92,

565

* 1

5%6,

45,2

7,17

717

,64,

808

6,62

,91,

985

1,07

,61,

430

1,00

,00,

580

9)B

uild

ings

on

Free

hold

Lan

d (I

CIC

I)22

,44,

336

29,3

1522

,73,

651

10%

4,26

,023

1,84

,763

6,10

,786

18,1

8,31

316

,62,

865

10)

Pla

nt,

Mac

hine

ry &

Equ

ipm

ent

(IC

ICI)

3,05

,93,

196

97,8

3,88

14,

03,7

7,07

7*

15%

96,4

9,10

546

,09,

196

1,42

,58,

301

2,09

,44,

091

2,61

,18,

776

Tota

l42

5,41

,64,

891

12,0

4,79

,720

437,

46,4

4,61

135

8,11

,13,

790

10,3

9,86

,274

368,

51,0

0,06

567

,30,

51,1

0168

,95,

44,5

46

12

34

56

78

91

0

* T

he

Rat

e of

Dep

reci

atio

n o

n P

lan

t an

d M

ach

iner

y is

rev

ised

from

25%

to 1

5% a

nd

on

Veh

icle

s fr

om 2

0% to

15%

w.e

.f. 2

005-

06.

Fix

ed A

sset

s

Gro

ss B

lock

Dep

reci

atio

nN

et B

lock

Op

enin

gB

alan

ce a

s on

1.4.

2006

Ad

dit

ion

sd

uri

ng

the

year

200

6-07

Clo

sin

g B

alan

ceas

on

31.3

.200

7( 2

+ 3

)

%P

rogr

essi

veu

pto

1.4.

2006

For

the

year

2006

-07

( 9 +

3 )

x 5

Cls

oin

gB

alan

ceas

on

31.

3.20

07( 6

+ 7

)

upto

31.3

.200

6up

to31

.3.2

007

( 4 -

8 )

(Am

oun

t in

Ru

pee

s)

Ban

galo

re

Dat

e : J

un

e 15

, 200

7

Page 110: 01 Annual 2006-07 (1-53) with photos