POWER PROFILE RURAL AREAS ELECTRICITY CO. RENTAL POWER PROJECT ¾ 60MW installed power to provide 40 MW base load @ 11KV for peak shaving during summer months. ¾ Synchronization with Grid. ¾ Site 900 km away from OTECO facility. ¾ 24 x 7 Operation & Maintenance. ¾ Equipment installed at site in 2010 remained at site to be hired again in 2011. ¾ Equipment: 17 x 3516, 27 x 3512 Gensets, 3.0 to 5.0 MVA Transformers, RMU’s, Synchronizing system, Portacabin, Fuel Tanks, Lube oil system etc. CUSTOMER Raeco LOCATION Oman CUSTOMER BUSINESS ISSUE Power needed to feed existing Power station for peak shaving in summer months. SOLUTION 40 MW Base load @ 11KV provided for Power plant at Salalah. YEAR / DURATION 2010 / 7 Months. 2011 / 5 Months. CAT DEALER OTECO, Muscat

Upload: others

Post on 22-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 01 Power Profile - Raeco - 60 MW - Al Baharalbahar.com/.../2014/06/01PowerProfile-Raeco-60MW.pdf2014/06/01  · PROFILE RURAL AREAS ELECTRICITY CO. RENTAL POWER PROJECT ¾ 60MW installed

POWER PROFILE

RURAL AREAS ELECTRICITY CO.

RENTAL POWER PROJECT 60MW installed power to provide 40 MW base load @ 11KV for

peak shaving during summer months. Synchronization with Grid. Site 900 km away from OTECO facility. 24 x 7 Operation & Maintenance. Equipment installed at site in 2010 remained at site to be hired again in 2011. Equipment: 17 x 3516, 27 x 3512 Gensets, 3.0 to 5.0 MVA Transformers,

RMU’s, Synchronizing system, Portacabin, Fuel Tanks, Lube oil system etc.

CUSTOMER Raeco LOCATION Oman CUSTOMER BUSINESS ISSUE Power needed to feed existing Power station for peak shaving in summer months. SOLUTION 40 MW Base load @ 11KV provided for Power plant at Salalah. YEAR / DURATION 2010 / 7 Months. 2011 / 5 Months. CAT DEALER OTECO, Muscat