01000 general requirements

114
09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-1 SECTION 01000 GENERAL REQUIREMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS : A. Drawings and General Provisions of the Contract. 1.02 SUMMARY OF WORK : A. Work Covered by Contract Documents: 1. Name of the project is "E.B. Lyons Interpretive Center – Sanitary Sewer Forcemain", Project No. 09-03-31-04. Drawings and Specifications are dated June 18, 2009. 2. Briefly and without force and effect upon contract documents, work of the contract can be summarized as follows: a. This project consists of constructing a sanitary sewer forcemain and a gravity sewer at the E.B. Lyons Interpretive Center. The work consists of constructing a duplex lift station along with 2600 ft. long 2.5-inch diameter forcemain that will connect the Interpretive Center to the city sewer. Project also includes approximately 316 ft. long 4-inch diameter gravity sewer connecting an existing maintenance shop to the proposed duplex lift station. All other incidental work as required by the Drawings and/or the D.N.R. Construction Inspector and as described in the Project Manual for E.B Lyons Interpretive Center, all in Dubuque County, Iowa. F. Occupancy: 1. Owner: The DNR shall have the right to enter the building or work site and store or attach such fixtures or furniture as it may elect, or to do other work providing that such storage or work will not interfere with the completion of the Contractor's work. Such occupancy by the DNR shall in no way imply final acceptance of any portion of the Contractor's work. 1.03 MEASUREMENT AND PAYMENTS : A. Measurements and payments shall be in accordance with Section 01250 of these specifications. B. Before ordering any fabricated material or doing any work, verify all measurements at the project site. No additional compensation will be allowed because of difference between actual dimensions and the measurements indicated on the drawings. Report any difference immediately to the DNR for instructions before proceeding with the work. 1.04 COORDINATION : A. Project Coordination:

Upload: others

Post on 26-May-2022

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-1

SECTION 01000 GENERAL REQUIREMENTS

PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

A. Drawings and General Provisions of the Contract. 1.02 SUMMARY OF WORK:

A. Work Covered by Contract Documents:

1. Name of the project is "E.B. Lyons Interpretive Center – Sanitary Sewer Forcemain", Project No. 09-03-31-04. Drawings and Specifications are dated June 18, 2009.

2. Briefly and without force and effect upon contract documents, work of the contract can

be summarized as follows:

a. This project consists of constructing a sanitary sewer forcemain and a gravity sewer at the E.B. Lyons Interpretive Center. The work consists of constructing a duplex lift station along with 2600 ft. long 2.5-inch diameter forcemain that will connect the Interpretive Center to the city sewer. Project also includes approximately 316 ft. long 4-inch diameter gravity sewer connecting an existing maintenance shop to the proposed duplex lift station. All other incidental work as required by the Drawings and/or the D.N.R. Construction Inspector and as described in the Project Manual for E.B Lyons Interpretive Center, all in Dubuque County, Iowa.

F. Occupancy:

1. Owner: The DNR shall have the right to enter the building or work site and store or attach such fixtures or furniture as it may elect, or to do other work providing that such storage or work will not interfere with the completion of the Contractor's work. Such occupancy by the DNR shall in no way imply final acceptance of any portion of the Contractor's work.

1.03 MEASUREMENT AND PAYMENTS:

A. Measurements and payments shall be in accordance with Section 01250 of these specifications.

B. Before ordering any fabricated material or doing any work, verify all measurements at the project site. No additional compensation will be allowed because of difference between actual dimensions and the measurements indicated on the drawings. Report any difference immediately to the DNR for instructions before proceeding with the work.

1.04 COORDINATION:

A. Project Coordination:

Page 2: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-2

1. Take out and pay for any building permit which may be required, secure and pay for all permits, certificates and licenses required to prosecute the work, and arrange and pay for all inspections required by local authorities.

2. Visit the site, compare the Drawings and Specifications with any work in place, and

verify all conditions, including other work, if any, being performed. Failure to visit the site will in no way relieve the Contractor from necessity of furnishing any materials or performing any work that may be required in accordance with Drawings and Specifications.

B. Job Site Administration: Take complete charge of work under this contract. Coordinate the

work of all trades and all phases of general, structural, plumbing, mechanical, and electrical work.

1.05 FIELD ENGINEERING:

A. Provide such field engineering services as are required for a proper completion of the work.

1. Immediately upon entering project site for the purpose of beginning work:

a. Establish actual project location with the DNR Construction Inspector. b. Establish and maintain all lines and levels.

B. Additional requirements for field engineering may also be described in other sections of these

specifications. C. Verify all figures shown on Drawings before laying out work and report all discrepancies to the

DNR Construction Inspector. Contractor will be held responsible for any error resulting from his/her failure to do so.

1.06 REGULATORY REQUIREMENTS:

A. All construction shall conform to the requirements of all national, state or building codes applicable to the project.

1.07 PROJECT MEETINGS:

A. Preconstruction Conference: Soon after award of contract and prior to the start of construction, attend a preconstruction conference with the representative of the Owner to define the requirements for contract administration and construction operation.

1. Contact the DNR Construction Inspector, who will determine the time, date and place

of the conference. B. Progress Meetings: The Contractor or the Contractor's representative shall be available at the

job site to meet with the DNR Construction Inspector, as frequently and as arranged during the preconstruction conference, to discuss work progress.

Page 3: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-3

1. Give verbal report of progress, discuss work schedule, and present all conflicts, discrepancies and other difficulties for resolution.

1.08 SUBMITTALS:

A. Provide submittals as required by the Project Engineer and/or the DNR Construction Inspector.

B. Shop Drawings: Prior to installation of any item specified as requiring submittal:

1. Submit two (2) copies for owner's use plus the number required for return to the Contractor, of manufacturer's literature containing detailed specifications and performance data, or shop drawings fully describing the items showing fabrication, layout, setting or erection details, including erection plan and details as required.

C. Shop drawings used at site must be approved by the Project Engineer.

D. Do not construe the approval of shop drawings to be a complete check.

1. This approval will indicate only that the general method of construction and detailing is satisfactory.

2. Approval of such drawings will not relieve the Contractor of the responsibility to comply with all terms and conditions of the plans and specifications.

3. The Contractor shall be responsible for the dimensions and design of adequate connections, details and satisfactory construction of all work.

1.09 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS:

A. Definitions: Specific administrative and procedural minimum actions are specified in this section, as extension of provisions in other contract documents. These requirements have been included for special purposes as indicated. Nothing in this section is intended to limit types and amounts of temporary work required, and no omission from this section will be recognized as an indication by Project Engineer that such temporary activity is not required for successful completion of the work and compliance with requirements of contract documents. Provisions of this section are applicable to, but not by way of limitation, utility services, construction facilities, security and protection provisions, and support facilities.

B. General: Establish and initiate use of each temporary facility at time first reasonably required

for proper performance of the work. Terminate use and remove facilities at earliest reasonable time, when no longer needed or when permanent facilities have, with authorized use, replaced the need.

C. Temporary Utilities: The types of services required include, but not by way of limitation,

water, sewerage, surface drainage, electrical power and telephones. Where possible and reasonable, connect to existing franchised utilities for required services; and comply with service companies recommendations on materials and methods, or engage service companies to install services. Locate and relocate services (as necessary) to minimize interference with construction operations. 1. Sanitary Facilities:

Page 4: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-4

a. Temporary Toilets: When such or permanent facilities do not exist, provide and

maintain toilets for use by workers. Keep toilets in sanitary condition. b. Temporary toilet facilities shall meet OSHA requirements.

D. Security:

1. Protection of Work and Property:

a. Place such barricades as may be necessary to prevent public access to the project site at no cost to the Owner.

E. Options and Substitutions:

1. Bid shall include all equipment, materials, and services as specified, noted on the Drawings or required for a complete and proper installation.

1.10 MATERIAL AND EQUIPMENT:

A. Transportation and Handling:

1. Provide protection against damage for all materials during delivery to and storage at the site.

2. Handle all materials and equipment to prevent damage to such material and/or equipment.

3. Replace or repair to the satisfaction of the DNR Construction Inspector, all items damaged because of failure of the Contractor to properly protect during transportation and handling, when on or off the project site, at no additional cost to the Owner.

B. Storage and Protection:

1. Protect all materials, work, and equipment against damage at all times. Store all material, which might be damaged, in storage sheds.

1.11 CONTRACT CLOSEOUT:

A. Final Cleaning:

1. Remove waste material and rubbish caused by the Work and leave all work clean and free of debris of any kind.

2. Keep the site and access road reasonably clean and free of rubbish or waste material in

order that the work may progress efficiently. Remove such rubbish or waste material entirely from the premises at each time of such cleaning.

3. When the Work is completed and ready to turn over to the Owner, leave such work

clean. This applies to all areas affected by contract work.

Page 5: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 GENERAL REQUIREMENTS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01000-5

4. On completion of the Work, thoroughly police and clean-up the work site.

B. Guarantees, Warranties and Certificates:

1. Except as otherwise stated in separate specification sections, guaranteed all Work against defects resulting from the use of inferior materials, equipment or workmanship for one (1) year from the date of final completion of the Contract, or from full occupancy of the areas by the Owner, whichever is earlier.

2. If within any guarantee period, repairs or changes are required in connection with the work which is rendered necessary as the result of using materials, equipment or workmanship which are inferior, defective or not in accordance with the Contract Documents, promptly and without expense to the Owner:

a. Correct all work which is inferior or defective.

b. Repair all damage to the building, equipment, or contents of the building.

c. Repair or replace all work disturbed in restoring defective or inferior work or equipment.

F. Final Inspection:

1. Request a final inspection in writing, at least ten days prior to the anticipated date of completion, from the DNR Construction Inspector.

2. Work will not be considered ready for final inspection until all the work has been

completed and the Contractor has certified that all items are properly operating and in strict compliance with the Contract Documents.

3. The Contractor or project supervisor shall be at the job site during the final inspection. 4. After the inspection, the DNR Construction Inspector will present the Contractor a list

of items not meeting contract requirements which must be made acceptable before final payment is made.

END OF SECTION 01000

Page 6: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MEASUREMENT AND BASIS OF PAYMENT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01250-1

SECTION 01250 MEASUREMENT AND BASIS OF PAYMENT

PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

A. Drawings and General Requirements of the Contract. 1.02 LUMP SUM / UNIT PRICE BID:

A. Bid each item on a Unit Price Bid or Lump Sum basis as required, including furnishing all labor, equipment and materials necessary to complete all the work indicated in the Contract Documents.

1.03 QUANTITIES:

A. Various estimated quantities are furnished within the Contract Documents to assist the Contractor in reviewing the Project prior to bidding. The estimated quantities are not intended to be used by the Contractor as sole basis for determining the scope and volume of the work. The Contractor is responsible for verifying all quantities necessary to submit bids for the construction of a proper and complete project.

1.04 MEASUREMENT:

A. The contractor is responsible for constructing the project to the final lines and grades shown. Owner will measure construction units only to ensure that at least minimum quantities have been properly installed.

1.05 SCOPE:

A. Each item in the Bidder's Proposal Schedule of Prices will be paid at the unit or lump sum price. The price for each item shall be considered full compensation for furnishing superintendence, overhead, bonds, insurance, mobilization, testing and profit necessary to complete the construction of the item of the project listed in the Bidder's Proposal. It is not the intent of the Bidder's Proposal to itemize each and every item and system required. Items required for project completion and not specifically mentioned in Bidder's Proposal shall be included with items which they would be considered subsidiary.

1.06 ESTIMATED QUANTITIES:

A. The items and quantities described above, as well as others listed throughout the Contract Documents, are provided for the bidder's review and consideration. The quantities listed herein are not guaranteed by the owner or the Project Engineer to be totally accurate nor to include all items of work. They are provided for the bidder's convenience to assist in the preparation of the bid. The bidder is responsible for preparing his own quantity takeoff and bid preparation.

END OF SECTION 01250

Page 7: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-1

SECTION 01300 SUBMITTALS

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and General Provisions of the contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements.

1.02 SUMMARY

A. Provide submittals required in this Section, refer to technical specification for submittal requirements for each section of the work to be performed.

1.03 PROGRESS SCHEDULE

A. Prior to the Preconstruction Conference, submit a project schedule to the IDNR for approval. Type of schedule used is at Contractor's option.

B. Prepare an approved, reproducible form and include the following: 1. Breakdown of work activities in categories so approved and segmented as necessary

to allow close monitoring of progress of the work during construction. 2. Order of the work necessary to meet time for completion. 3. Breakdown of the work schedule of all subcontractors scheduled in cooperation with

Contractor's work. 4. Anticipated monthly value for work completed. 5. Space for the additional display of actual performance on the schedule.

C. After necessary revisions have been made and approved, present one print of schedule to each

subcontractor and three copies to the IDNR.

D. Upon request, update the schedule to reflect changes required by actual conditions and indicate actual work completed. Provide same number of copies as required for original submission.

E. Payment will be withheld until progress schedule in acceptable form has been received by IDNR.

1.04 SHOP DRAWINGS

A. Shop Drawings shall be presented in clear and thorough manner, complete with respect to dimensions, design criteria, materials of construction, and like information to enable IDNR to review information as required. Details shall be identified by reference to sheet and detail, schedule or room numbers shown on Drawings.

B. Minimum sheet size: 8-1/2" by 11". C. Make submittals to IDNR promptly in accordance with approved schedule, and in such

sequence as to cause no delay in Work or in work of any other contractor.

Page 8: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-2

D. Shop Drawings: 1. Submit 3 copies of each Shop Drawing plus additional copies required by Contractor. 2. Shop Drawings not larger than 24" by 36". Copies of Drawings submitted shall be

black line on white background. 3. For printed catalog information or brochures or other multiple page documents,

submit 3 copies of each Shop Drawing plus additional copies required by Contractor.

E. Submittals shall contain: 1. Date of submission and dates of any previous submissions. 2. Project title and number. 3. Contract identification. 4. Names of:

a. Contractor. b. Supplier. c. Manufacturer. d. Identification of product, with Specification section number. e. Field dimensions, clearly identified as such. f. Relation to adjacent or critical features of Work or materials. g. Applicable standards, such as ASTM or Federal Specification numbers. h. Identification of deviations from Contract Documents. i. Identification of revisions on resubmittals. j. An 8" by 3" blank space for Contractor and IDNR stamps. k. Indication of Contractor's approval, initialed or signed, with wording sub-

stantially as follows:

"Contractor represents to IDNR that Contractor has either determined and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, or assumes full responsibility for doing so and has reviewed or coordinated each Shop Drawing Sample with requirements of Work and Contract Documents."

F. No faxed submittals will be accepted. G. Resubmission requirements: Make any corrections or changes in submittals required by

IDNR and resubmit until stamped as either "Reviewed" or "Reviewed as Noted" by IDNR. Indicate any changes which have been made other than those requested by IDNR.

1.05 PRODUCT DATA

A. Mark each copy to identify applicable products, models, options, and other data; supplement

manufacturers' standard data to provide information unique to Work. Include manufacturers' installation instructions when required by Specification section.

B. Submit the number of copies which Contractor requires, plus 3 copies which will be retained

by IDNR.

C. No faxed submittals will be accepted.

1.06 IDNR DUTIES A. Review required submittals with reasonable promptness and in accord with schedule, only for

general conformance to design concept of Project and compliance with information given in Contract Documents. Review shall not extend to means, methods, sequences, techniques, or procedures of construction or to safety precautions or program incident thereto. Review of a separate item as such will not indicate approval of assembly in which item functions.

Page 9: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-3

B. Affix stamp and initials or signature, and indicate requirements for resubmittal, or review of

submittal. IDNR’s action on submittals is classified as follows: 1. Reviewed: Submittal has been reviewed and appears to be in conformance to design

concept of Project and Contract Documents. Contractor may proceed with fabrication of work in submittal.

2. Reviewed As Noted: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by IDNR. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by IDNR.

3. Resubmit: Submittal has been reviewed and appears not to be in conformance to design concept of Project or with Contract Documents. Contractor shall not proceed with fabrication of work in submittal, but instead shall make any corrections required by IDNR and resubmit for review.

4. Returned without Review: Submittal is being returned without having been reviewed because: 1) not required by Contract Documents; 2) grossly incomplete; 3) indicates no attempt at conformance to Contract Documents; 4) cannot be reproduced; 5) lacks Contractor's completed approval stamp; or 6) lacks design professional's seal when required by law or Contract Documents. If submittal is required by Contract Documents, Contractor shall not proceed with Work as detailed in submittal, but instead shall correct defects and resubmit for review.

5. For Information Only: Submittal has not been reviewed but is being retained for informational purposes only.

C. Return submittals to Contractor. D. IDNR’s review of submittals shall not relieve Contractor from responsibility for any

deviations from Contract Documents unless Contractor has, in writing, called IDNR's attention to such deviation at time of submission, and IDNR has given written concurrence pursuant to Contract Documents to specific deviation, or shall any concurrence by IDNR re-lieve Contractor from responsibility for errors or omissions in submittals.

1.07 SAMPLES

A. Submit in Duplicate:

B. Provide samples of sufficient size to permit an accurate appraisal of color, texture, finish, workmanship, and other appropriate characteristics.

C. Submit samples with shop drawings when both are required.

1.08 QUALITY ASSURANCE

A. Coordination of Submittals: 1. Prior to submitting required material, carefully review and coordinate all aspects of

each item being submitted. 2. Verify that each item and its submittal conform in all respects with the specified

requirements. 3. Prior to sending submittals to IDNR, the stamp and sign each submittal, certifying

that they conform in all respects with the specified requirements.

B. Substitutions:

Page 10: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-4

1. Contract is based on the standards of quality established in the Contract Documents. Substitutions will be considered only when listed with the IDNR prior to the bid date, and when substantiated by Contractor's submittal of required data within 35 calendar days after award of contract.

2. The following products do not require further approval except for interface within the work: a. Products specified by reference to standard specifications such as ASTM or

similar standards. b. Products specified by manufacturer's name and catalog model number for

which another product is not substituted. 3. Do not substitute materials, equipment or methods unless such substitutions have

been specifically approved in writing.

C. Or Equal: 1. Where the phrase "or equal," or "or equal as approved by the IDNR," occurs in the

Contract Documents, do not assume that the materials, equipment or methods will be approved as equal unless the item has been specifically approved for this work by the IDNR.

2. IDNR's decision shall be final.

1.09 DISTRIBUTION OF SUBMITTALS AFTER REVIEW

A. IDNR will distribute copies of shop drawings and product data, after review, to: 1. IDNR Construction Inspector (1 copy). 2. IDNR Construction Bureau (1 copy). 3. Reserved (1 copy). 4. General Contractor (remaining copies).

1.10 CONTRACTOR RESPONSIBILITIES

A. Review shop drawings, product data, and samples prior to submission to the next level of control.

B. Verify: 1. Field dimensions. 2. Field construction criteria. 3. Catalog numbers and similar data.

C. Coordinate each submittal with requirements of:

1. The work. 2. The contract documents. 3. The work of other contractors.

D. Contractor's responsibility for errors and omissions and deviations from Contract Documents

in submittals is not relieved by IDNR’s review of submittals.

E. Notify IDNR, in writing, of proposed deviations in submittals from contract requirements, prior to or at the time of submission.

F. Do not begin any work which requires submittals without having IDNR’s stamp and initials or signature indicating review.

Page 11: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-5

1.11 RECORD DRAWINGS

A. Provide and maintain at the project site, one complete set of prints of the project drawings. Keep drawings in good, clean and readable condition.

B. Project site drawings shall have neatly inscribed all changes in work including relocation of lines, valves and fixtures, change in type of materials, etc. Changes shall be noted with red pencil or red ink.

C. Submit a copy of corrected prints monthly with request for payment. Non-submittal of corrected prints is grounds for withholding payment.

D. Submit final corrected prints at time of final acceptance and prior to final payment. Note all data and changes on these record drawings in sufficient detail and clarity and provide information necessary for preparation of "record” drawings.

E. Final payment will be withheld until a set of corrected prints of the record drawings has been received by the IDNR Construction Inspector.

1.12 GUARANTEES, WARRANTIES AND AFFADAVITS

A. Refer to Section 01700.

1.13 OPERATING AND MAINTENANCE INSTRUCTIONS

A. Submit all operating and maintenance instructions to the IDNR prior to final payment.

B. Refer to Section 01730.

1.14 CHANGE ORDER PRICE QUOTES

A. Contract unit prices will be used for changes. Work substantially out of scope of contract will be addressed by change order.

B. In the event of the need for change order, the IDNR Construction Inspector will request a price quote from the Contractor for proposed changes to the contract.

C. For evaluation purposes, the Contractor's quote shall be broken down to show the costs of labor and materials for each proposed category of work included with the change, along with the total cost for Contractor's overhead, profit and bond for the proposed change.

D. All contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.

1.16 TEST REPORTS

A. Refer to Section 01400.

1.17 DELIVERY TICKETS

A. Submit to the IDNR Construction Inspector one legible copy of each delivery ticket for all material delivered to the construction site.

Page 12: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMITTALS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01300-6

B. Delivery tickets shall show brand name, catalog number and number of items received.

END OF SECTION 01300

Page 13: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 QUALITY CONTROL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01400-1

SECTION 01400 QUALITY CONTROL

PART 1 - GENERAL 1.01 RELATED DOCUMENTS:

A. Drawings and General Provisions of the contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements.

1.02 SCOPE:

A. Supplementary tests and reports required in this section with any tests, reports, and other information that may be required additionally in any section of the specifications.

B. Inspection, sampling, and testing is required, but not limited to, the following: 1. Section 02316 - Trenching, Backfilling and Compacting. 2. Section 03300 - Cast-in-Place Concrete.

1.03 TESTS BY INDEPENDENT TESTING LABORATORY:

A. Testing Laboratory: 1. Select and pay for an independent testing laboratory, acceptable to the IDNR, to

perform specified services required by the contract. 2. Employment of testing laboratory will in no way relieve Contractor's obligations to

perform work in accord with the contract. 3. Include in unit prices the cost for all testing services required.

a. No separate payments will be made for testing. b. Include all associated costs in the various appropriate bid items. c. IDNR Construction Inspector will direct all tests. d. Contractor shall pay the testing firm.

B. Contractor:

1. Make available at no cost, all material to be tested. 2. Provide labor necessary to supply samples and assist in making tests. 3. Advise laboratory of the identity of material sources and instruct suppliers to allow

inspections by laboratory. C. Testing laboratory shall:

1. Submit written report promptly, covering each inspection and test to the IDNR, including: a. Date issued. b. Project title and number. c. Testing laboratory name and address. d. Name and signature of laboratory technician. e. Date of inspection and sampling. f. Record of temperature and weather. g. Date of test. h. Identification of product and specification section. i. Location of project. j. Type of inspection or test.

Page 14: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 QUALITY CONTROL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01400-2

k. Observations regarding compliance with Contract Documents.

2. Promptly notify IDNR of irregularities or deficiencies of work which are observed during performance of services.

3. Perform additional services required by the IDNR Construction Inspector. D. Laboratory is not authorized to:

1. Release, revoke, alter or enlarge on, contract requirements. 2. Approve or accept any portion of work. 3. Perform any duties of the Contractor.

E. Conduct tests in accordance with the requirements of the designated specifications or, where

not specified, the latest appropriate standard of the American Society for Testing and Material.

1.04 LABORATORY SERVICES AND TESTS REQUIRED:

A. Compacted Soils:

1. Secure samples of fill proposed for use and test for proper gradation (sieve analysis) in accordance with applicable sections of these specifications.

2. Establish optimum moisture-density relationship in accordance with ASTM D 698 (Standard Proctor).

B. Concrete:

1. Secure samples of aggregates Contractor proposes to use and test for compliance with specifications.

2. Certify compliance with specification of cement proposed for use by the Contractor. 3. Review concrete design mix proportions for the required concrete strengths using

materials Contractor proposes to use on the project. a. Incorporate specified admixtures and not less than amount of cement

specified. b. Perform appropriate laboratory tests, including compression tests of cylinders

and slump test to substantiate mix designs. c. Submit one copy of report to the IDNR, one copy to the IDNR Construction

Inspector, and one copy to the Contractor, clearly indicating the results of the mix design review.

4. Test Cylinders:

a. Each test shall consist of a set of three cylinders provided by the Contractor. b. Provide a minimum of one set of test cylinders each day concrete is placed. c. Provide one set of test cylinders for every 20 cubic yard of concrete placed

and any fraction thereof. d. Contractor shall make and cure test cylinder in conformity with ASTM C 31. e. Note on record drawings placement locations represented by test cylinders.

5. Perform compression tests in accordance with Section 03001. 6. Identify all test cylinders with symbols to indicate location on the job where concrete

tests were made. Note on record drawings. C. Aggregate gradation and compaction as per applicable specifications.

Page 15: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 QUALITY CONTROL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01400-3

1.05 CONTRACTOR'S RESPONSIBILITIES: A. Furnish product mix design to meet or exceed Contract Documents. B. Cooperate with laboratory personnel and provide access to work, as well as to manufacturer's

operations. Monitor each inspection, sampling and test. C. Provide to laboratory, preliminary representative samples of material to be tested, in specified

quantities. D. Furnish copies of mill test reports. E. Furnish verification of compliance with contract requirements for material and equipment. F. Furnish casual labor and facilities:

1. To provide access to work to be tested. 2. To obtain and handle samples at site. 3. To facilitate inspections and tests. 4. For laboratory's exclusive use for storage and curing of test samples.

G. Notify laboratory sufficiently in advance of operations to allow for assignment of personnel

and scheduling of tests. 1. Notify IDNR Construction Inspector when work is ready for testing. 2. Schedule testing after approval of the IDNR Construction Inspector.

H. Correct work which is defective or which fails to conform to the Contract Documents in

accordance with the general condition. Do not delay the project schedule or the work of other contractors with corrective work, unless approved by the DNR Construction Inspector.

I. Pay all cost of retesting when test results indicate non-compliance with contract requirements. J. Patch all surfaces and areas disturbed by testing operations.

END OF SECTION 01400

Page 16: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY FACILITIES AND CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01500-1

SECTION 01500 TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and General Provisions of the contract, including the General Covenants and

Provisions, Supplementary Covenants and Provisions and General Requirements. 1.02 WEATHER PROTECTION

A. General:

1. Provide necessary protection against weather to maintain all materials, apparatus, fixtures, and work free from damage whether in shipment, in storage, or in place.

2. Do not perform wet work when temperature is below 40 degrees F or is forecast to be below 40 degrees F within the ensuing 48 hours, except when work is properly protected and sufficient heat is provided.

B. Heat Provision:

1. When heat is required for proper weather protection, provide temporary enclosures of work and acceptable means to provide sufficient heat to maintain a temperature of not less than 50 degrees F. Provide higher temperatures when required by these specifications.

2. Use only heating apparatus and fuels of approved safe types. Keep equipment and surroundings in a clean, safe condition. Use flame resistant tarpaulins and other materials for temporary enclosure of space. Use vented heaters only.

1.03 TEMPORARY UTILITIES

A. Electricity, Lighting and Heating:

1. Provide such temporary electric service as may be required for construction purposes with required distributing facilities and meter. Electric service components shall conform to NEC and local codes.

2. Pay the cost of all electrical energy used on this part of the project until completion of the contract. If partial occupancy by the IDNR occurs prior to completion, the IDNR will pay proportional share of electrical energy used.

3. Provide light bulbs required for all temporary construction lighting and replace when necessary. Temporary lighting shall provide illumination levels at, or higher, levels than required by OSHA.

4. Use no temporary service material in permanent system without written approval of the IDNR. When temporary electrical lines are no longer required, remove them and restore any parts of buildings or grounds damaged by such removal to original condition.

5. Provide and maintain temporary lighting at barricades as required for safety. 6. Provide any heating required by these specifications.

B. Water:

1. Provide, protect, and maintain an adequate water supply for use on the project for construction purposes, either by means of the permanent water supply line or by installing a temporary waterline.

Page 17: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY FACILITIES AND CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01500-2

2. Install, valve, maintain, and protect such water supply lines as may be required. 3. Remove temporary lines when they are no longer required. Restore to original

condition any part of grounds or buildings damaged by removal. 4. Pay the cost of all water used on this portion of the project until final completion of

the contract. C. Toilets:

1. Provide and maintain suitable, weather tight, painted sanitary toilet facilities for all workers during construction period. When toilet facilities are no longer required, promptly remove from site. Disinfect, clean or treat the area as required.

2. Provide and maintain facilities in accordance with requirements of applicable local and state health authorities and OSHA.

3. Keep all toilet facilities clean and supplied with toilet paper at all time. 1.04 OPERATION AND STORAGE AREAS

A. All operations of the Contractor (including storage of materials) upon premises shall be confined to areas authorized or approved by the IDNR.

B. Premises adjacent to the construction will be made available for use by the Contractor

without costs whenever such use will not interfere with other uses or purposes. C. Do not enter on or occupy with personnel, tools, equipment, or material any ground outside

the IDNR's property without the written consent of the IDNR of such ground. D. Other contractors and employees or agents of the IDNR may for all necessary purposes enter

upon the work and premises used by the Contractor, and the Contractor shall conduct his work so as not to impede unnecessarily any work being done by others on or adjacent to the site.

E. Provide and maintain weather tight storage sheds for own use. F. Provide storage sheds with substantial floors raised a minimum of six (6) inches above the

ground. G. Locate all storage sheds as approved by the IDNR Construction Inspector. H. Completely remove from site after completion of work.

1.05 PROTECTION AND RESTORATION

A. Protect all structures, including walks, pipelines, trees, shrubbery, and lawns during the

progress of the work; remove from the site all debris and unused materials; and, upon completion of the work, restore the site as nearly as possible to its original condition, including the replacement, at the Contractor's sole expense, of any facility or landscaping which has been damaged.

1.06 ACCESS ROADS

A. Temporary Roads and Storage Areas:

Page 18: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY FACILITIES AND CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01500-3

1. Lay down equipment and supplies only in areas indicated by DNR. 2. Construct and maintain all temporary access roads and storage areas required. Locate

and construct all roads, ramps, mats, storage areas, and similar items in a manner approved by the IDNR and provide overall management of available site areas.

B. Public Access:

1. Provide public access at all times to park roads. 2. Maintain one lane of traffic on park roads at all times.

C. Laws and Regulations:

1. Observe all laws and regulations of the local, county, and state authorities in the use of all public roads and highways for the transportation of materials and equipment in connection with work on the project. Observe all overhead construction, bridges, cables, and the like. Repair damage to roads, highways, overhead construction and similar off-site items, resulting from operations in connection with this project.

1.07 WATER CONTROL

A. Carry on construction work in a manner that will direct surface water away from the

structures and away from adjoining property. B. Provide own means of pumping, well pointing or otherwise maintaining excavations free

from groundwater encountered. Provide means of properly conveying such water off the construction site.

C. Prepare and follow construction erosion control plan.

1.08 PARKING

A. Make necessary provisions for parking of all employees on the project within the site limits.

Include necessary access roads and maintenance of all roads and parking areas during construction period.

B. Park vehicles to avoid interference with normal construction activities and to avoid

interference with IDNR's operation. 1.09 SAFETY

A. Provide at least one non-freezing-type fire extinguisher in each workshop and shed used for

storage of materials on the premises. Place in readily accessible location. B. Provide and maintain a basic first aid kit.

1. Provide first aid supply commensurate with size of project with items necessary for first aid treatment of all injuries.

2. Advise workers of the location of first aid supplies. 3. Post telephone numbers of nearest hospital or ambulance service and fire station in

conspicuous location. Advise all workers of location of telephone numbers.

D. Conform to federal, state, and local safety laws and regulations.

Page 19: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY FACILITIES AND CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01500-4

1.10 BARRIERS

A. Provide as required to prevent public entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide barriers around trees and plants designated to remain. Protect against vehicular

traffic, stored materials, dumping, chemically injurious materials, and puddling or continuous running water.

1.11 SECURITY

A. Provide security program and facilities to protect Work, existing facilities, and IDNR's operations from unauthorized entry, vandalism, and theft. Coordinate with IDNR's security program.

PART 2 - PRODUCTS - NOT USED PART 3 - EXECUTION 3.01 PROTECTION OF LAND RESOURCES

A. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, top soil, and land forms without special permission from the IDNR.

B. Do not fasten nor attach ropes, cables, or guys to any trees for anchorage unless specifically authorized.

C. Where such special emergency use is permitted, provide effective protection for land and vegetation resources at all times as defined in the following subparagraphs.

3.02 PROTECTION OF MONUMENTS AND MARKERS

A. Protect monuments and markers before and during construction operations. B. Where construction operations are to be conducted during darkness, the markers shall be

visible. C. Contractor shall convey to his personnel the purpose of marking and/or protection of all

necessary objects. 3.03 PRESERVATION AND RECOVERY OF HISTORICAL, ARCHEOLOGICAL AND CULTURAL RESOURCES

A. Existing historical, archeological and cultural resources within the Contractor's work area will be so designated by the Department and precautions taken to preserve all such resources as they existed at the time they were pointed out to the Contractor.

B. Install protection and assume responsibility for the preservation of these resources as

designated on the Drawings, or if not designated as necessary for their preservation.

Page 20: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY FACILITIES AND CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01500-5

C. Report any unusual items that might have historical or archeological value, found or observed during construction activities as soon as practicable to the IDNR Construction Inspector.

3.04 PROTECTION OF FISH AND WILDLIFE RESOURCES:

A. Keep construction activities under surveillance, management and control to minimize

interference with, disturbance to and damage of fish and wildlife. B. List species that require specific attention along with measures for their protection prior to

beginning of construction operations.

END OF SECTION 01500

Page 21: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY ENVIRONMENTAL CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01560-1

SECTION 01560 TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 - GENERAL 1.01 SUMMARY

A. Section includes furnishing all labor, material and equipment for the control and prevention of environmental pollution and damage as the result of construction operations under this Contract and for those measures set described herein, as indicated on the Drawings, specified herein, and as required for the construction of all work of this Contract. 1. Control of environmental pollution and damage requires consideration of air, water,

and land, and includes management of visual aesthetics, noise, solid waste, radiant energy and radioactive materials, as well as other pollutants.

2. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract.

3. Confine activities to areas defined by the Drawings and Specifications. 1.02 DEFINITION

A. Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to man; or degrade the utility of the environment for aesthetic, cultural and/or historical purposes.

1.03 QUALITY ASSURANCE

A. Establish and maintain quality control for environmental protection of all items set forth herein. 1. Record on daily reports any problems in complying with laws, regulations and

ordinances and corrective action taken. 2. Assure compliance of subcontractors with this Section.

B. Regulatory Requirements:

1. IDNR Construction Inspector will notify the CONTRACTOR in writing of any observed noncompliance with the aforementioned Federal, state or local laws, or regulations, permits and other elements of the CONTRACTOR's environmental protection plan.

2. After receipt of such notice, inform the IDNR Construction Inspector of proposed corrective action and take such action as may be approved.

3. If the CONTRACTOR fails to comply promptly, IDNR Construction Inspector may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions shall be granted such suspension.

C. National Pollutant Discharge Elimination System (NPDES): Provide a Notice of Intent (Form

1415) for application of a General Permit for Storm Water Discharge and prepare and file all necessary Forms and Drawings with the applicable Bureau of the IDNR, and pay necessary application fees. (Required for sites of one acre or more) For Storm Water General Permit Assistance: Contact 515-281-7017 or 515-281-8693 for information.

Page 22: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY ENVIRONMENTAL CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01560-2

D. Pollution Control Training: Train personnel in all phases of environmental protection.

Include methods of detecting and avoiding pollution, familiarization with pollution standards, both statutory and contractual, and installation and care of facilities to insure adequate and continuous environmental pollution control.

1.04 PROJECT/SITE CONDITIONS

A. Protection of Land Resources: Prior to beginning construction, the CONTRACTOR shall

identify all land resources to be preserved within the CONTRACTOR's work area.

1.05 MAINTENANCE OF POLLUTION CONTROL FACILITIES

A. Maintain all constructed facilities and portable pollution control devices for the duration of the contract or for that length of time construction activities create the particular pollutant.

PART 2 - PRODUCTS 2.01 MATERIAL AND EQUIPMENT

A. Provide and maintain material and equipment necessary to perform the specified work. PART 3 - EXECUTION 3.01 EXAMINATION

A. Prior to beginning construction, the CONTRACTOR shall identify all land resources to be preserved within the CONTRACTOR's work area.

B. Limits of Work Area:

1. Mark the areas that are not required to accomplish work to be performed under this contract.

2. Mark or fence isolated areas within the general work area that are to be saved and protected.

3.02 PROTECTION OF LAND RESOURCES

A. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and land forms without special permission from the IDNR.

B. Do not fasten nor attach ropes, cables, or guys to any trees for anchorage unless specifically

authorized. C. Where such special emergency use is permitted, provide effective protection for land and

vegetation resources at all times as defined in the following subparagraphs. 3.03 PROTECTION OF MONUMENTS AND MARKERS

A. Protect monuments and markers before and during construction operations.

Page 23: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY ENVIRONMENTAL CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01560-3

B. Where construction operations are to be conducted during darkness, the markers shall be visible.

C. CONTRACTOR shall convey to his personnel the purpose of marking and/or protection of

all necessary objects. 3.04 PROTECTION OF LANDSCAPE

A. Clearly identify trees, shrubs, vines, grasses land forms and other landscape features to be preserved by marking, fencing, or wrapping with boards, or any other approved techniques.

3.05 LOCATION OF FIELD OFFICES, STORAGE AND OTHER CONTRACTOR FACILITIES

A. Place field offices, staging areas, stockpile storage, and temporary buildings in areas approved by the IDNR Construction Inspector.

B. Do not temporarily move or relocate CONTRACTOR facilities unless approved by the IDNR

Construction Inspector. 3.06 DISPOSAL OF SOLID WASTES

A. Place solid wastes in containers to be emptied on a regular schedule. 1. Conduct handling and disposal to prevent contamination. 2. Transport all solid waste off state property and dispose of in compliance with

Federal, state, and local requirements for solid waste disposal. 3.07 DISPOSAL OF CHEMICAL WASTE

A. Store chemical waste in corrosion resistant containers; remove from the work area and dispose of in accordance with Federal, state and local regulations.

3.08 DISPOSAL OF DISCARDED MATERIALS

A. Handle discarded materials other than those that can be included in the solid waste category as directed by the IDNR.

3.09 PROTECTION OF WATER RESOURCES

A. Keep construction activities under surveillance, management and control to avoid pollution of surface and ground waters.

B. Implement applicable management techniques to control water pollution in accordance with

the listed construction activities that are included in this contract. C. Comply with Drawings for temporary erosion control procedures to be performed on this

Project. 3.10 PROTECTION OF AIR RESOURCES

Page 24: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 TEMPORARY ENVIRONMENTAL CONTROLS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01560-4

A. Keep construction activities under surveillance, management and control to minimize pollution of air resources. Perform or operate activities, equipment, processes, and work to accomplish the specified construction in strict accordance with the State of Iowa and all Federal emission and performance laws and standards.

B. Implement special management techniques as set out below to control air pollution by

construction activities. 1. Control of Particulates: Control dust particles, aerosols, and gaseous by-products

from all construction activities at all times, including weekends, holidays and hours when work is not in progress. a. Maintain all work areas within or outside the project boundaries free from

particulates which would cause the applicable air pollution standards to be exceeded or which would cause a hazard or a nuisance.

b. Sprinkling, chemical treatment of an approved type, light bituminous treatment, baghouse, scrubbers, electrostatic precipitators or other methods will be permitted to control particulates in the work area.

c. Sprinkling, to be efficient, must be repeated at such intervals as to keep the disturbed area damp at all times. CONTRACTOR must have sufficient competent equipment available to accomplish this task.

d. Perform control of particulates as the work proceeds and when ever a particulate nuisance or hazard occurs.

2. Control hydrocarbons and carbon monoxide emissions from equipment in accordance

with Federal, State and local allowable limits at all times. 3. Control odors at all times for all construction activities. 4. Assume responsibility for monitoring of air quality throughout the entire areas

affected by the construction activities. 3.11 PROTECTION OF SOUND INTRUSIONS

A. Keep construction activities under surveillance and control to minimize noise. 3.12 CLEANING

A. Post Construction Clean Up: Cleanup all areas used for construction. B. Restoration of Landscape Damage: Restore all landscape features damaged or destroyed

during construction operations outside the limits of the work areas, in accordance with a plan submitted for approval by the IDNR.

END OF SECTION 01560

Page 25: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MATERIAL AND EQUIPMENT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01600-1

SECTION 01600 MATERIAL AND EQUIPMENT

PART 1 - GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and General Provisions of the contract, including the General Covenants and

Provisions, Supplementary Covenants and Provisions and General Requirements. 1.02 MATERIAL

A. All materials, equipment, and other items incorporated in the work of this project must be new,

and both materials and workmanship of best grade of their respective kinds. B. To assure ready availability of materials, parts, or components for repair, replacement or future

expansion purposes, all materials, equipment, and related components must be obtained from sources which maintain a regular, domestic stock.

C. Throughout all sections of these specifications, provide other material not specifically

described but required to provide IDNR with a complete and proper installation of all phases of the work of this contract. Select these materials subject to the approval of IDNR Construction Inspector.

1.03 IDNR-FURNISHED MATERIALS, SUPPLIES, AND EQUIPMENT

A. IDNR will not furnish any materials, supplies, or equipment concurrent to this contract.

1.04 TRANSPORTATION AND HANDLING

A. Provide protection against damage for all materials during delivery to and storage at the site. B. Handling of all materials and equipment shall be such as will prevent damage to such material

and/or equipment. C. Replace or repair to the satisfaction of the IDNR Construction Inspector, all items damaged

because of Contractor's failure to properly protect during transportation and handling, when on or off the project site, at no additional cost to the IDNR.

1.05 STORAGE AND PROTECTION

A. Protect all materials, work, and equipment against damage at all times. B. Refer to Section 01500 for requirements for storage sheds. Store all materials that might be

damaged within storage sheds.

END OF SECTION 01600

Page 26: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 PROJECT CLOSEOUT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01700-1

SECTION 01700 PROJECT CLOSEOUT

PART 1 - GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and General Provisions of the contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements.

1.02 CLEANING UP

A. Keep premises free of accumulation of surplus materials and rubbish from contractor and subcontractor operations.

B. Remove rubbish weekly and at other times as required by the IDNR Construction Inspector.

C. Immediately prior to final inspection: 1. Clean site; sweep paved areas, rake clean other surfaces. 2. Remove waste and surplus materials, rubbish, and construction facilities from Project

and from site.

1.03 GUARANTEES, BONDS AND AFFIDAVITS A. Submit all written guarantees, bonds and affidavits required to the IDNR prior to final

payment. B. Guarantees shall extend the full period of the required guarantee period after:

1. Replacement of work found defective during guarantee period. 2. Repair of inoperative items or adjustments to proper working conditions of items not

operating properly at time of inspection at final completion. 1.04 RECORD DRAWINGS

A. Required prior to final payment. Refer to Section 01300. Submit to IDNR Construction

Inspector. 1.05 SHOP DRAWINGS

A. Refer to Section 01300.

1.06 TESTS

A. Complete all tests required to prove actual operating performance of equipment and systems

incorporated into the project. Refer to Section 01400. B. Submit reports of all tests to the IDNR prior to final payment.

1.07 MAINTENANCE AND OPERATING

A. Refer to Section 01730.

Page 27: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 PROJECT CLOSEOUT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01700-2

1.08 DAMAGE TO EXISTING STRUCTURES

A. Prior to final acceptance by the IDNR, repair or otherwise return to original condition any parts of the existing facilities which have been damaged during construction.

1.09 FINAL INSPECTION

A. Request a final inspection in writing, at least ten days prior to the anticipated date of completion, from the IDNR Inspector.

B. Work will not be considered ready for final inspection until all the work has been completed

and the Contractor has certified that all items are properly operating and in strict compliance with the contract documents.

C. The Contractor or his project supervisor shall be present at the job site during the final

inspection. IDNR Inspector will present the Contractor, after the final inspection, a list of any items not meeting contract requirements. This list will be confirmed in writing and all items listed must be made acceptable before final payment will be made.

END OF SECTION 01700

Page 28: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 OPERATION AND MAINTENANCE DATA E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01730-1

SECTION 01730 OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL 1.01 SUMMARY

A. Aid the instruction of operating and maintenance personnel. Provide a source of information

regarding the systems incorporated into the Work. Furnish and deliver the data described in this section and in pertinent other sections of these specifications. Additional data requirements may be described in individual sections.

B. Related Sections: Drawings and General Provisions of the contract, including the General

Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements.

1.02 SUBMITTALS

A. Comply with pertinent provisions of Section 01300. B. Submit six copies of a preliminary draft of the proposed manual or manuals to the IDNR for

review and comments. C. Unless otherwise directed in other Sections or in writing by the IDNR, submit five copies of

the final manual to the IDNR Construction Inspector. 1.03 QUALITY ASSURANCE

A. In preparing required data, use only personnel thoroughly trained and experienced in operation and maintenance of the described items, completely familiar with this section's requirements, and sufficiently skilled in technical writing to communicate the essential data.

1.04 SERVICE REPRESENTATIVE

A. Contractor shall provide qualified Service Representative(s), as necessary to:

1. Inspect equipment after it is installed to assure that all details of installation are correct and that equipment is prepared for operation in accordance with manu-facturer's instructions and recommendations.

2. Check connections to equipment and adjust, or supervise adjustment of, control and indicating devices after equipment has been installed and connected.

3. Fully instruct IDNR's operating personnel in operation and maintenance of equipment.

4. Provide IDNR with duplicate copies of final alignment and clearance measurements on all rotating or reciprocating equipment. Measurements shall clearly identify each piece of equipment.

5. Supervise preliminary operation of equipment and necessary adjustments.

B. Presence of Service Representative will in no way relieve Contractor of any responsibility assumed under Agreement. 1. Contractor shall furnish materials, tools, and labor necessary to start up each item of

equipment or system. 2. Comply with manufacturer's procedures in starting up each item of equipment.

Page 29: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 OPERATION AND MAINTENANCE DATA E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01730-2

C. Work and abilities of Service Representative shall be subject to review of IDNR. If IDNR determines that any Service Representative is not properly qualified, Contractor shall replace Service Representative upon written notification by IDNR.

D. Contractor shall provide continuity in assignment of Service Representative to Work. In

event substitution of Service Representative is made which is not at request of IDNR, substitute's time for "familiarization" shall be at Contractor’s expense.

PART 2 - PRODUCTS 2.01 INSTRUCTION MANUALS

A. Where instruction manuals are required to be submitted under other sections of these

specifications, prepare in accordance with the provisions of this Section. B. Format:

1. Size: 8-1/2" by 11." 2. Paper: White bond, at least 20 lb. weight. 3. Text: Neatly written or printed. 4. Drawings: 11" in height preferable; bind in with text; foldout acceptable; larger

drawings acceptable but fold to fit within the manual and provide a drawing pocket inside rear cover or bind in with text.

5. Flysheets: Separate each portion of the manual with neatly prepared flysheets briefly describing contents of the ensuing portion; flysheets may be in color.

6. Binding: Use heavy-duty plastic or fiberboard covers with 3-ring binders. All binding is subject to the IDNR's approval.

7. Measurements: Provide all measurements in U.S. standard units: feet-and-inches, lbs., and cfm.

C. Provide front and back covers for each manual, using durable IDNR's approved material,

clearly identified on or through the cover with at least the following information:

OPERATING AND MAINTENANCE INSTRUCTIONS ( name and address of work )

( name of contractor ) ( general subject of this manual ) ( space for approval signature of ) ( the IDNR and approval date )

D. Contents include at least the following: 1. Neatly typewritten index near the front of the manual, giving immediate information

as to location within the manual of all emergency information regarding the installation.

2. Detailed list of subcontractors, including address, phone number and product or equipment installed.

3. Complete instructions regarding operation and maintenance of all equipment involved, including start-up and shut-down, procedures, troubleshooting, lubrication, disassembly, and reassembly.

4. Complete nomenclature of all parts of all equipment. 5. Complete nomenclature and part number of all replaceable parts, name and address

of nearest vendor, and all other data pertinent to procurement procedures.

Page 30: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 OPERATION AND MAINTENANCE DATA E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01730-3

6. Copy of all guarantees and warranties issued. 7. Manufacturers' bulletins, cuts, and descriptive data, where pertinent, clearly

indicating the precise items included in this installation and deleting, or otherwise clearly indicating, all manufacturers' data with which this installation is not concerned.

8. Such other data as required in pertinent sections of these specifications. 9. Written text, as required to supplement product data for particular installation.

a. Organize in consistent format under separate headings for different procedures.

b. Provide logical sequence of instructions for each procedure. PART 3 - EXECUTION 3.01 INSTRUCTION MANUALS

A. Preliminary:

1. Prepare and submit 6 preliminary draft copies of each proposed manual at least 60 days prior to final inspection and acceptance.

2. Show general arrangement, nature of contents in each portion, probable number of drawings and their size, and proposed method of binding and covering.

3. Secure the IDNR's approval prior to proceeding. B. Final: Complete the manuals in strict accordance with the approved preliminary drafts and the

IDNR's review comments. Submit 6 copies of final manual within 10 days after final inspection and acceptance.

C. Revisions: Following the instruction of operation and maintenance personnel, review all

proposed revisions of the manual with the IDNR Construction Inspector.

3.02 INSTRUCTION AND TRAINING OF IDNR’S PERSONNEL

A. In addition to start-up and initial operation checkout and at separate training session, CONTRACTOR shall provide qualified Service Representative to fully instruct IDNR's operating personnel on proper operation and maintenance of each piece of equipment. Training shall include as a minimum the following: 1. General familiarization and review of O & M manual. 2. Complete nomenclature for equipment and its parts. 3. Procedures for disassembly, repair, and reassembly. 4. Function, normal operating characteristics, and limiting conditions. 5. Procedures for alignment, adjustment, and checking. 6. Procedures for routine maintenance such as changing oil, replacing seals, and

lubrication. 7. Start-up, break-in, and routine operation. 8. Procedures for regulation, control, stopping, shutdown, and emergency operation. 9. Summer and winter operation. 10. Procedures for safe operation and identification of potential hazards of equipment. 11. Special operating instructions. 12. Procedures for "trouble-shooting equipment" problems. 13. Recommended spare parts inventory.

Page 31: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 OPERATION AND MAINTENANCE DATA E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 01730-4

B. Operator training shall include both classroom and "hands-on" instruction. C. Training shall be supplemented with displays, demonstrations, films, exercises, and

proficiency tests as necessary to develop operator proficiency. D. Operator training may be recorded by IDNR on video recording equipment for future

reference, retraining, and training of new personnel. E. Training schedule shall be coordinated with IDNR to avoid conflicts and to provide logical

sequence of instruction and training. Training sessions shall be held in accordance with IDNR-approved schedule.

F. Contractor shall provide necessary labor for hands-on training and adjustments.

END OF SECTION 01730

Page 32: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-1

SECTION 02200 EARTHWORK

PART 1 - GENERAL

1.01 SUMMARY:

A. Section Includes: The work covered by this section consist of site clearing, grading, general and building excavation, disposal of debris and spoils, dewatering preparation of subgrade, foundations, borrow, embankment, structural and general backfill, restoration, and cleanup necessary to construct the project, all as shown on the drawings and as specified herein.

B. Related Sections: Drawings and General Provisions of the Contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not limited to, the following:

Section 02930 - Lawns and Grasses Section 03100 - Concrete Formwork Section 03300 - Cast-In-Place Concrete

1.02 QUALITY ASSURANCE:

A. Codes and Standards: Perform all excavation work in compliance with applicable requirements of governing authorities having jurisdiction.

B. Safety: All excavation work and methods of construction shall conform to the state of Iowa Bureau of Labor and all OSHA Standards.

1.03 JOB CONDITIONS:

A. Site information shown on the Drawings regarding existing conditions is of a general nature. Visit the site and become familiar with existing conditions.

B. Observe weather conditions. Attempt no work in frozen conditions without the approval of the DNR Construction Inspector.

1.04 PROTECTION OF PERSONS AND PROPERTY:

A. Protect from damage existing buildings, walks, paving, fencing, sod, and other items noted to remain. Maintain benchmark, monuments, property stakes, and other reference points.

B. Protect existing underground utilities to remain.

1. Notify the DNR Construction Inspector of underground utilities or structures encountered but not indicated on drawings.

2. Contractor responsibilities: correcting damage caused to existing construction, utilities, surfacing, and other items noted to remain at no additional expense to the Owner.

C. Barricade open excavations occurring as part of this work and provide warning lights.

Page 33: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-2

1.05 EXPLOSIVES:

A. The use of explosives is not permitted.

PART 2 - PRODUCTS

2.01 GENERAL FILL AND EMBANKMENT MATERIAL:

A. Materials to be incorporated in the top 12 inches of earth embankment or general fill shall be earthy materials, free from stones larger than 2 inches, broken concrete, roots, or other materials that would significantly affect scarifying, compacting and finishing the subgrade.

B. It is anticipated that the majority of excavation material from the building excavation will be acceptable for this use.

C. Obtain approval of fill material prior to any placement from the DNR Construction Inspector.

2.02 STRUCTURAL BACKFILL MATERIAL:

A. Structural backfill material shall consist of a natural sand or a mixture of sand with gravel, crushed stone, or other broken fine material to fill all voids in coarser material.

1. The maximum size of any gravel, stone, or broken or fragmented material shall be of such size that 100 percent passes a 6-inch sieve.

2. The liquid limit of the material shall not be greater than 25 and the plasticity index shall not be more than 6.

3. The portion of the material, which passes a No. 4 sieve, shall conform to the following requirements:

Percentage By Sieve Size Weight Passing

No. 4 100 No. 40 Not more than 75 No. 100 Not more than 15 No. 200 Not more than 8

B. The material shall be capable of being compacted to 95 percent maximum density without undue weaving and heaving as defined by ASTM D698, Method D.

C. Obtain approval of fill material prior to any placement from the DNR Construction Inspector.

2.03 GRANULAR DRAINAGE FILL MATERIAL:

A. Granular drainage fill for use under concrete slabs and walks where shown on the Drawings shall consist of granular free-draining material; consisting of clean bank run gravel or crushed stone of full range of sizes.

Page 34: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-3

B. Maximum size of aggregate shall be 3/4 inch. 15 to 50% of that portion of weight of fill shall be passing the No. 4 sieve.

2.04 TOPSOIL:

A. Topsoil: Friable clay loam surface soil reasonably free of subsoil, clay lumps, stones and other objects over two inches in diameter, and without weeds, roots and other objectionable materials.

PART 3 - EXECUTION

3.01 SITE CLEARING:

A. General: Remove all vegetation, improvements, or obstructions interfering with installation of new construction.

1. Removal includes digging out of stumps, roots, boulders and any other necessary items, the removal of which is not covered in the work of another section.

B. Clearing and Grubbing: Clear site of trees, shrubs, and other vegetation, except those indicated or directed to be left standing.

1. Completely remove stumps, roots, boulders and other debris protruding through the ground.

2. Use only hand methods for grubbing inside drip line of trees indicated to be left standing.

3. Depressions: Fill depressions caused by clearing and grubbing operations with satisfactory soil materials, unless further excavation work is required or indicated.

3.02 LAYING OUT WORK:

A. Commission surveyor to locate new construction, set slope and grade stakes, and otherwise fully lay out work.

1. Provide grade staking to maintain proper grades and control.

2. Check existing grades at site against grades or contours indicated on Drawings, and report any differences to Architect before starting of grading.

3. Stake out building and verify location before start of grading.

B. Preserve stakes and markers.

1. Replace at no cost to the Owner’ stakes or markers carelessly or willfully damaged by operation.

2. Assume responsibility for accuracy of lines, grades, and dimensions.

3.03 STRIPPING AND SALVAGING OF TOPSOIL:

Page 35: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-4

A. Preparation: Mow or otherwise remove weed grass and other vegetation on entire area expected to be disturbed by the work of this section.

B. Sod: Shred sod by shallow plowing, blading or disking throughout the entire area.

C. Excavation of Topsoil: Excavate topsoil throughout the entire prepared area to a depth of 12 inches and stockpile where designated by DNR Construction Inspector.

3.04 DEWATERING:

A. Dewatering System: Provide, maintain and operate sufficient well points, headers, pumps, trenches, and sumps to keep all excavations for structures free from water at all times. Submit proposal to the DNR Construction Inspector for review prior to construction.

B. Surface Runoff: Control grading around the excavation to prevent surface water from running into the excavations for the structure.

C. Saturated Foundations: Prior to placing any concrete for foundations, remove soils in footing excavation that have become saturated with surface water.

3.05 EXCAVATION - GENERAL:

A. General: General excavation consists of removal of materials of whatever nature, including boulders smaller than 1 cubic yard in volume, required for the construction of structures, roads, and walks.

1. The method of excavating shall be at the Contractor's option, exercising great care to leave the final grade in an undisturbed condition.

2. If final grade is disturbed, restore to requirements and satisfaction of the DNR Construction Inspector/Architect.

3. Prior to placing any concrete for footings and foundation work, notify the DNR Construction Inspector to inspect the excavation and obtain approval to proceed with the placement.

B. Frozen Ground: Provide frost protection for all structural excavation work and do not place concrete for foundation work on frozen ground.

C. Protection of Existing Work: Protect existing work, including underground utilities and piping, from damage caused by excavation work.

1. Repair any damage to existing work, utilities, or piping at Contractor's expense.

D. Storage of Fill Materials: Store suitable excavated fill material away from excavations to avoid slides.

1. Deposit excess earth on site, where directed by DNR Construction Inspector.

Page 36: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-5

E. Removal of Unsuitable Materials: The DNR Construction Inspector may find that changes to cross-sectional dimensions and depths shown on Drawings are necessary to secure foundations free from soft, weathered, shattered and loose materials or other objectionable materials.

1. Remove unsuitable material encountered and replace with granular materials from established pits satisfactory to the DNR Construction Inspector.

2. Compact granular materials to at least 95 percent of maximum density.

3. When the excavation of unsuitable materials and replacement with granular fill material directed by the DNR Construction Inspector is found to be above normal expectations, it will be paid for at the unit prices listed in the Contractor's submitted cost breakdown.

a. What constitutes normal expectations will be determined by the Architect.

b. The Architect's decision will be final.

F. Disposal of Excavated Materials: Materials free from sticks, roots, and other objectionable material may be used on site as directed by the DNR Construction Inspector.

1. Remove excavated materials not suitable for fill as directed by the DNR Construction Inspector.

3.06 STRUCTURAL EXCAVATION:

A. Excavate to elevations and dimensions indicated on the Drawings; allow additional space as required for construction operations and inspection.

B. Remove all existing construction, encountered within the excavation, to a depth of 6 inches below the indicated elevation of footings and subgrades, to receive floor slabs, walks, and paving.

C. If suitable bearing for foundations, is not encountered at depth indicated on the Drawings, immediately notify the DNR Construction Inspector.

1. Do not proceed until instructions are given and necessary measurements made for the purpose of establishing additional volume of excavation.

D. Excavate last 4 inches by hand, if machines are used for excavation.

E. Fill with concrete, at Contractor's expense, unauthorized excavation carried below bottom of foundation levels shown.

F. The DNR Construction Inspector will inspect and approve the bottoms of all excavation prior to concrete placement.

3.07 STRUCTURAL BACKFILL:

A. Start backfill around foundations not less than 24 hours or more than seven (7) days after application of waterproofing.

Page 37: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-6

1. Backfill walls and piers to about the same elevation on each side to equalize pressure.

B. Compacted structural backfill to 95 percent of its maximum density.

1. Compact to density and construction requirements as determined by ASTM D698, Method D or by AASHO Method T-180 (Modified Proctor Density).

C. Compact subgrade to receive structural backfill to 95 percent density.

3.08 DRAINAGE FILL UNDER INTERIOR SLABS:

A. Unless otherwise indicated on the Drawings, place a 6-inch minimum layer of granular drainage fill.

B. Compact this fill material to 95 percent of maximum density at optimum moisture content.

3.09 DRAINAGE FILL UNDER EXTERIOR SLABS:

A. Provide 4-inch minimum layer of granular drainage fill sub-base for exterior concrete slabs.

B. Compact with mechanical platform tamper or as approved by DNR Construction Inspector.

3.10 PLACING BACKFILL ADJACENT TO WALLS AND FOOTINGS:

A. Deposit fill on each side of piers, walls and freestanding structures simultaneously to approximately the same elevation.

1. Protect below grade waterproofing, dampproofing and insulation with a single thickness of 1/2" fiberboard, 1/8" asphalt impregnated board or other approved means.

2. Place fill in workable condition, free of clods, frost, or debris, in 6" lifts and thoroughly compact each lift with mechanical tamper.

B. Do not operate heavy equipment for spreading and compacting backfill closer to any wall than a distance equal to the height of the backfill above the top of the footings.

1. Backfill adjacent to walls shall be compacted to the same density as the adjacent fill with a small vibratory or hand tamping compactor.

3.11 PREPARATION OF EARTH SUBGRADE FOR CONCRETE:

A. When excavating for footings or bottom mat slabs to be cast on native soil, excavate to final grade in a manner as to not disturb the existing soil.

1. If the soil is disturbed, compact it to the satisfaction of the DNR Construction Inspector.

2. If the soil is not capable of compaction to the satisfaction of the DNR Construction Inspector, remove the disturbed material, and replace it with thoroughly compact structural backfill material.

B. Do not place concrete on surfaces that are muddy, frozen or contain frost.

Page 38: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-7

C. If during the course of construction, bottom surfaces become saturated with water or muddy, remove the undesirable material and replace with compacted structural backfill as indicated above.

3.12 PLACING PIPE IN FILL:

A. When it is necessary to place pipe culverts, drain piping, or other appurtenances in general or structural backfill, bring the fill up to at least one foot above the top of the pipe or appurtenances.

1. Do not leave areas of backfill depressed to allow for trenches.

2. After the compacted fill is complete, excavate for the pipe or appurtenances.

3. Backfill materials and compaction shall conform to the fill in which it is placed.

3.13 TRIMMING AND CLEAN UP:

A. Conduct final trimming and cleaning up shall as follows:

1. Smooth out all irregularities, fill all washouts, make slopes uniform, slightly rounded at top and bottom, and compact the entire area of the fill to the required lines, grades and cross sections, within 1/10 foot above or below the established grade.

2. Where additional material is required, provide similar fill as the one used, and obtain such material from source approved by the Architect/DNR Construction Inspector.

3. When work is completed, remove and dispose of surplus material including stumps, trees and brush, and leave premises in a condition acceptable to the DNR Construction Inspector.

3.14 FINISH GRADING:

A. After completion of rough grading, scarify areas to receive topsoil to finish grade shown.

B. Deposit topsoil to a minimum depth of 6". In areas with existing topsoil, no additional topsoil is required.

C. Grade topsoil to eliminate water pockets or irregularities.

D. Eliminate soil lumps and round abrupt changes in slope.

E. Spread excess earth on site as directed by DNR Construction Inspector.

Page 39: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 EARTHWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02200-8

3.15 SITE RESTORATION:

A. All disturbed areas within the boundaries of this project not specifically receiving a finished surface are to be seeded in accordance with Section 02930.

B. Prepare all surfaces to receive seeding per "Standard Specifications" 2001 I.D.O.T., Section 2601.04.

END OF SECTION 02200

Page 40: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-1

SECTION 02230 HORIZONTAL DIRECTIONAL DRILLING (HDD)

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Installation of pressure and gravity piping using the horizontal directional drilling (HDD) method.

1.02 RELATED SECTIONS

A. Section 02220 -Trenching, Backfilling and Compacting

B. Section 02730 -Sanitary Sewer Systems

C. Section 02660 – Water Distribution System

D. Section 02990 -Restoration and Cleanup

1.03 FIELD MEASUREMENTS

A. Verify that survey bench mark, control point, and intended elevations for the Work are as shown on drawings.

1.04 COORDINATION

A. Verify work associated with lower elevation utilities is complete before placing higher elevation utilities.

1.05 SCOPE

A. The Contractor shall furnish all labor, materials, tools, and equipment as necessary to drill horizontally and install the specified pipe in the locations as shown on the Drawings and described herein.

1.06 UTILITIES

A. Before work is started, Contractor shall locate utilities and other subsurface structures which may be affected by or interfere with the proposed construction.

1.07 SUBMITTALS

A. Shop Drawings are required for the following:

1 Instructions for installation of piping by applicable supplier.

2 Graph plotting in plan and profile of pilot drilling hole.

PART 2 - PRODUCTS

2.01 BACKFILL MATERIALS

A. General: Backfill material shall be that material excavated from the trench, providing that the material does not contain any unacceptable material and can be effectively compacted by mechanical or pneumatic compaction equipment to the specified density.

B. Acceptable Backfill Materials:

1. Provide soil materials free from organic matter and deleterious substances, containing no rocks or lumps over 6 inches in greatest dimension, frozen materials, rubbish, or unsuitable materials.

2.02 MATERIALS

Page 41: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-2

A. Excavation, fill, pipe and fittings, and concrete materials shall be as specified in Related Work Sections.

2.03 PIPE MATERIALS

A. Refer to Specifications Section 02730 – Sanitary Sewer Systems.

B. Refer to Specifications Section 02660 – Water Distribution System.

2.04 APPURTENANCES

A. Repair couplings (pressure applications):

1. Mechanical fittings meeting requirements of pressure application; bolted couplings, Smith-Blair 441LR, or approved equal.

a. Sleeve: Ductile iron ASTM A536.

b. Gaskets: Grade 30 compounded rubber of new materials.

c. Follower flanges: Ductile iron ASTM A536.

d. Bolts and Nuts: 304 stainless steel.

e. Coating: Shop coat enamel.

2. Sleeve fittings meeting pressure requirements of PVC pipe and designed to slide completely over pipe ends.

B. Flexible Couplings (non-pressure applications):

1. Flexible couplings designed to connect spigot ends of similar or dissimilar pipe and provide positive seal against infiltration and exfiltration; Fernco Flexible Coupling or equal.

a. Flexible elastomeric body conforming to applicable requirements of ASTM C443, C425, C564 and D1869; series 304 stainless steel bands and housings.

b. Furnish with shear rings designed to provide extra strength and rigidity to construction; series 304 stainless steel bolts, nuts and housing.

2. Sleeve fitting meeting pressure requirements of PVC pipe and designed to slide completely over pipe ends.

C. Service Saddles for directional drilled sewer:

1. Saddle tee or wye in compliance with ASTM F1336 with gasketed branch and rubber seal to main.

2. Mounting clamps series 304 stainless steel; adjustable compression type; 2 per saddle.

PART 3 - EXECUTION

3.01 GENERAL

A. The pipe shall be installed in the location to the line and grade designated on the Drawings by horizontal directional drilling.

B. All materials delivered to the project for work on the project shall be neatly piled. Excavated material which is not removed from the immediate site of the work shall be kept trimmed up so as to cause as little inconvenience to the owners of neighboring property and to the public, as

Page 42: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-3

possible.

C. Excavated material, including but not limited to, pipe, pavement, concrete, and concrete rubble, and masonry units, which is unsuitable for backfill and all excavated material which has not been used for backfill shall, upon completion of the project, be removed from the site of the work by the Contractor at his own cost and expense.

D. The drill staging area shall be kept neat and orderly and disturb as little area as possible. The pipe staging area shall be set up on the opposite side of the crossing, disturbing as little area as needed to accommodate workers, equipment, and to string, join and inspect the pipe.

3.02 PRESSURE PIPE

A. Assemble and install pipe as specified herein, as shown on Standard Drawings and in accordance with the manufacturer's recommendations and guidelines.

B. Protect pipe and joints during handling against impact, shocks, freefall and gouging.

C. Make joints with equipment and methods recommended by pipe manufacturer.

1 Clean joint contact surfaces immediately prior to jointing; use lubricants, primers, cement or adhesives as recommended by pipe manufacturer.

2 Protect solvent weld joints from damage during cement cure; do not disturb pipe joint until fully cured; maintain joint at required temperature until fully cured.

D. Examine pipe for defects and specification compliance prior to installation; damaged or unsound pipe or pipes with defective joints will be rejected.

E. Remove debris from piping.

F. Prior to beginning each directional bore:

1 Inspect and calibrate steering control system and drill head field locator.

2 Verify that that there is adequate time, equipment, and materials necessary to complete the bore.

3 Review field staking of path and construction plans; provide additional staking of directional bore path at no additional cost to the Owner.

4 Verify location of all utilities; contact the Engineer before proceeding if directional bore path is in conflict with existing utilities or if specified separation distances will not be maintained.

5 Determine drilling fluid mixture to be used based on subsurface soil conditions; additional soil testing will be performed at no additional cost to the Owner.

G. Directional boring and installation of pipe:

1. Select ground entry and exit locations and angles needed to accommodate the installation of the pipe at the horizontal alignment, vertical profile, and to depths shown on the plans; do not exceed the allowable pipe bending limits established by the manufacturer; excavate bore pit as needed.

2. Locate and install pressure relief pits as needed to relieve excessive drilling fluid pressure.

3. Complete boring of pilot hole to alignment and depth necessary to assure that final location of pipe is in general compliance with plans; utilizing the drill head field locator collect and record horizontal alignment and depth of bury at 100 foot intervals.

Page 43: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-4

4. Backream the pilot hole to a diameter between 125% (minimum) and 150% (maximum) of the maximum outside diameter of the pipe material to be installed; 'slugging' of pilot hole is prohibited; exercise care not to 'hump' ground surface or surface of roads, drives, or sidewalks.

5. Before installing pipe, verify all measurements at site; make necessary field measurements to accurately determine piping make-up length.

6. Pull assembled pipe and tracer wire into borehole during last pass by reamer; continuously monitor pullback forces during pullback; limit pull forces so as to prevent damage to pipe; pushing of pipe into borehole to aid with insertion is prohibited; Provide adequate support of pipe during installation; do not allow twisting or binding of pipe in excess of manufacturer's recommendations

7. Connect directionally bored pipe with pipe or appurtenance installed by conventional trench excavation.

8. Clean up and dispose of cuttings and excess drilling fluids in a manner consistent with local, State and Federal requirements.

9. Back-fill excavated bore pit as appropriate. ,

10. Repair damage to ground surface or surface of roads, drives, or sidewalks along path of bore at no additional cost to Owner; remove mounded soils and or surfacing and repair as specified.

11. Length of bore will be equal to pipe length installed between points of connection to appurtenances or to piping installed by other methods, including not more than 20 feet of open trench excavation per bore,

3.03 GRAVITY PIPE

A. Assemble and install pipe as specified herein, as shown on Standard Drawings and in accordance with the manufacturer's recommendations and guidelines.

B. Protect pipe and joints during handling against impact, shocks, freefall and gouging.

C. Make joints with equipment and methods recommended by pipe manufacturer.

1 Clean joint contact surfaces immediately prior to jointing; use lubricants, primers, cement or adhesives as recommended by pipe manufacturer.

2 Protect solvent weld joints from damage during cement cure; do not disturb pipe joint until fully cured; maintain joint at required temperature until fully cured.

D. Examine pipe for defects and specification compliance prior to installation; damaged or unsound pipe or pipes with defective joints will be rejected.

E. Remove debris from piping.

F. Prior to beginning each directional bore:

1. Inspect and calibrate steering control system and drill head field locator.

2. Verify that that there is adequate time, equipment, and materials necessary to complete the bore.

3. Review field staking of path and construction plans; provide additional staking of directional bore path at no additional cost to the Owner.

a. Update staking to reflect elevation of pilot hole that is needed to accomplish the

Page 44: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-5

installation of piping at the flow line elevation shown on the plans.

4. Verify location of all utilities; contact the Engineer before proceeding if directional bore path is in conflict with existing utilities or if specified separation distances will not be maintained.

5. Determine drilling fluid mixture to be used based on subsurface soil conditions; additional soil testing will be performed at no additional cost to the Owner.

G. Directional boring and installation of pipe:

1. Select ground entry and exit locations and angles needed to accommodate the installation of the pipe at the horizontal alignment and vertical alignment shown on the plans; do not exceed the allowable pipe bending limits established by the manufacturer; excavate bore pit as needed.

2. Locate and install pressure relief pits as needed to relieve excessive drilling fluid pressure.

3. Complete boring of pilot hole to alignments and depth necessary to assure that final location of pipe is within allowable tolerance of compliance with plans; utilizing the drill head field locator and other methods, collect and record horizontal alignment and vertical alignment at 50 foot intervals.

4. Allowable tolerance of horizontal and vertical alignment deviation from piping system design as shown on .the plans:

a. Horizontal alignment of pilot hole shall be within +/-2 inches at 50 foot intervals.

b. Vertical alignment of pilot hole shall be within +/-0.1 feet at 50 foot intervals.

c. Retract and repeat directional drilling attempts, until horizontal and vertical alignments are within allowable tolerances, or install gravity sewer piping in accordance with Specification Section 02730.

5. Back-ream the pilot hole to a diameter between 125% (minimum) and 150% (maximum) of the maximum outside diameter of the pipe material to be installed; 'slugging' of pilot hole is prohibited; exercise care not to 'hump' ground surface or surface of roads, drives, or sidewalks.

6. Before installing pipe, verify all measurements at site; make necessary field measurements to accurately determine piping make-up length.

7. Pull assembled pipe into borehole during last pass by reamer; continuously monitor pullback forces during pullback; limit pull forces so as to prevent damage to pipe; pushing of pipe into borehole to aid with insertion is prohibited; provide adequate support of pipe during installation; do not allow twisting or binding of pipe in excess of manufacturer's recommendations.

8. Connect directionally bored pipe with pipe or appurtenance installed by conventional trench excavation.

9. Provide sufficient length of pipe to extend past termination point to allow connection to other pipe sections.

10. Allow minimum of 24 hours for stabilization after installing pipe before making connections to pipe.

11. Mark location and depth of bore with spray paint on paved surfaces, and wooden stakes on non-paved surfaces at each end bores and at 25-foot intervals along bore.

Page 45: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-6

12. Backfill excavated bore pit as appropriate.

13. Clean up and dispose of cuttings and excess drilling fluids in a manner consistent with local, State and Federal requirements.

14. Repair damage to ground surface or surface of roads, drives, or sidewalks along path of bore at no additional cost to Owner; remove mounded soils and or surfacing and repair as specified.

15. Length of bore will be equal to pipe length installed measured from point of connection to piping or manholes, for each size of pipe and type of pipe material along centerline of pipe with no deductions for manholes.

3.04 SERVICE CONNECTIONS

A. Conform to details shown on Drawings.

B. Install saddle wyes; use standard saddle tee and riser in lieu of saddle wye where invert of sewer is 10' or more below ground surface; see Standard Drawing.

C. Place stopper in end of service pipe:

1 Provide weather tight joint on stopper to match that on pipe spigot; block plug to undisturbed earth with 2" x 4" strut.

2 Mark location of sewer service connection with magnetic tape; connect to end of service.

D. Install as recommended by manufacturer.

E. Backfill excavated area after recording exact location of service connection.

3.05 CONNECTIONS BETWEEN DISSIMILAR PIPE

A. Provide and install suitable couplings for joining dissimilar materials.

B. Install compacted granular bedding and backfill on stable trench for 12 inches either side of repair coupling.

3.06 PROTECTION OF WATER SUPPLIES

A. There shall be no physical connection between a public or private potable water supply system and a sewer, or appurtenances thereto, which would permit the passage of any wastewater of polluted water into the potable water supply.

B. Wells: Sewers constructed of standard sewer materials shall not be laid within 75 feet of a public well or 50 feet of a private well. Sewers constructed of water main materials may be laid within 75 feet of a public well and within 50 feet of a private well, but not closer than 25 feet to either.

1. Where above separation is not met, notify Engineer immediately; Engineer will authorize relocation of sewer as required.

C. Horizontal separation of gravity sewers from water mains:

1. Gravity sewer should be separated from water mains by a horizontal distance of at least 10 feet unless:

a. The top of sewer main is at least 18 inches below the bottom of water main and,

b. The sewer is placed in a separate trench or in the same trench on a bench of undisturbed earth at a minimum horizontal separation of 3 feet from water main.

2. Where required clearances between sewer and water main cannot be maintained: Use ductile iron pipe as specified for pressure pipe; pressure test and leakage test pipe as

Page 46: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 HORIZONTAL DIRECTIONAL DRILLING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02230-7

specified herein.

D. Separation of sewer and water main crossovers:

1 Where new sewer crosses over water main or service where top .of sewer is within 18" of bottom of water main or service; provide 20' length of ductile iron pipe for sewer centered on the water main.

2 Support water and sewer pipes and backfill with low permeability soil.

E. Force mains shall be separated at least 4 feet horizontally from water main.

1. Where specified horizontal distance cannot be maintained; notify Engineer immediately; Engineer will authorize relocation of force main or water main as required.

F. Provide all necessary shut-down, repair and relocation of water mains, sanitary sewer or force main where conflicts occur; furnish labor, equipment, pipe and fittings; repair and relocation will be paid for as Extra Work; when broken due to carelessness of Contractor, repair is incidental to construction.

3.07 FIELD TESTS

A. Perform testing in compliance with requirements of Specifications Sections 02730 – Sanitary Sewer Systems and 15042 – Cleaning and Pressure Testing of Pipelines.

END OF SECTION 02230

Page 47: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-1

SECTION 02316 TRENCHING, BACKFILLING & COMPACTING

PART 1 - GENERAL 1.01 SECTION INCLUDES

A. Pipe bedding requirements.

B. Trench excavation and backfill.

C. Backfill for manholes, appurtenances and structures.

D. Erosion control and dewatering.

E. Sheeting, shoring and bracing.

F. Cleanup. 1.02 GENERAL REQUIREMENTS

A. Schedule Work to keep roadways, sidewalks, and utilities in usable condition; avoid property owner inconvenience insofar as practicable.

B. Do not trespass on private property. Maintain construction operations on existing right-of-way

or easements provided by IDNR. C. CONTRACTOR shall provide name(s) and telephone number of person(s) who have access to

equipment and are authorized to make emergency repairs to CONTRACTOR's Work, such as to correct trench cave-ins, moving excavated material, and correct other problems during weekends and off-work hours, so access can be maintained for fire fighting equipment, and to maintain barricades for public safety.

D. Disposal area(s):

1. Remove brush, rubbish, spoil, excess excavated material, and material not suitable for backfill to off-site location of CONTRACTOR's choice.

2. Remove waste material promptly as it is generated by construction operations. Do not permit to accumulate. See also "Cleanup," this Section.

1.03 ACCESS TO STREETS AND HIGHWAYS

A. Maintain suitable means of access for users.

B. Suitable access shall mean a roadway of sufficient width, free from ruts, potholes, and mudholes, and capable of carrying a passenger car without damage to car.

C. When access must be denied due to construction, provide suitable access within 24 hours after

responsible construction is completed. D. Whenever construction is stopped due to inclement weather, weekends, holidays, or other

reasons, suitable access shall be provided for users.

Page 48: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-2

1.04 EXISTING UTILITIES

A. Obtain from utility companies locations of buried utilities in the project areas. B. Repair, at no additional cost to IDNR, existing fences, culverts, and drain tile disturbed by

construction. C. CONTRACTOR fully responsible for liaison with utility companies and for repairing, at no

expense to IDNR, utilities damaged by CONTRACTOR. D. In event of break in existing watermain, gas main, sewer, or electric or communication cable,

immediately notify responsible official of organization operating utility affected. PART 2 - PRODUCTS 2.01 PIPE ENVELOPE

A. Applies to full trench width from bottom of trench to 1 foot above top of pipe. B. Depth of fine granular material for bedding shall be not less than 1/4 of the pipe diameter below

the bottom of the pipe, but in no case shall bedding be less than 4 inches. Bedding shall support the bottom quadrant of the pipe.

C. Bedding and initial backfill materials shall be crushed stone meeting IDOT Gradation Number

32. 2.02 REMAINING BACKFILL

A. Applies to backfill above 1 foot above top of pipe. B. As soon as the condition of the pipe will permit, the entire width of the trench shall be backfilled.

Earthen materials or aggregate shall be placed longitudinally along the pipe. Elevation of the haunching material on each side of the pipe shall be the same. Special care shall be taken to completely fill the space under the pipe haunches. Materials shall be placed in maximum 6-inch layers, loose measurement and compacted by ramming or tamping.

C. Where subgrade conditions warrant extra precautions for the bedding of rigid pipe, IDNR

Construction Inspector may order the construction of a concrete cradle to support the rigid pipe. Cradle shall be constructed as directed by the IDNR Construction Inspector. Extra payment for concrete cradle may be made in accordance with the Contract Documents if not shown on the Drawings.

D. Granular backfill material shall be crushed stone meeting IDOT Gradation Number 32. E. Trenches shall be backfilled in accordance with the following methods, in accordance with the

details on the Drawings: 1. METHOD 1 - This method applies to pipes under grassed yards and open spaces and

unimproved areas. In this method, the trench shall be backfilled with excavated

Page 49: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-3

materials in a manner that will not dislodge or damage the pipe or cause bridging action in the trench. The material shall be deposited in uniform layers not exceeding 12-inches thick, loose measure. Each layer shall be compacted by ramming or tamping or, if directed by the IDNR Construction Inspector, inundated or deposited with water. Pipes in these areas will generally not require water jetting unless the IDNR Construction Inspector determines that early settlement is required. If jetting is used, it shall be considered incidental to piping installation and no additional compensation will be allowed. Top 4 inches shall be topsoil. Any rocks or clods greater than 2 inches in diameter shall be removed from the topsoil as it is spread. Top of the trench shall be left neatly rounded to allow for settlement.

2. METHOD 2 – This method applies to roadways or parking areas that do not have

permanent surfaces (gravel). In this case, the trench from top of granular bedding to 8 inches below ground surface shall be backfilled with excavated earthen materials in a manner that will not dislodge or damage pipe or cause bridging action in trench. The material shall be deposited in uniform layers not exceeding 12 inches in thickness, loose measure. Each layer shall be compacted by ramming or tamping. Eight (8) inches of aggregate shall be applied so that the finished surface of the aggregate is at the proposed surface elevation or matches the existing surface elevation.

3. METHOD 3 - This method applies to all pipes buried beneath existing utilities or

structures. In this case, the trench from the top of the granular pipe bedding to at least 6 inches above the existing utility or structure shall be backfilled with granular backfill. The granular material shall be deposited in uniform layers not exceeding 6 inches thick, loose measure, and each layer shall be compacted by ramming or tamping. Trench from 6 inches above the existing utility or structure to the surface shall then be backfilled in accordance with another applicable method; I, II, IV, V, VI, or VII.

4. METHOD 4 - This method applies to any area where the existing or new surface is

Portland cement concrete or bituminous concrete (asphalt). In this case, the trench from the top of the granular pipe bedding to the bottom of the existing or new surface shall be backfilled with granular backfill. Granular material shall be deposited in uniform layers not exceeding 6-inches thick, loose measure, and each layer shall be compacted by ramming or tamping.

5. METHOD 5 - This method applies to all pipes within earthen dikes. From the top of the

pipe bedding to 6 inches below the new finish grade, the trench shall be backfilled with earthen materials (similar to those used in the dike construction) in 8-inch layers. Fill top 6 inches of trench with topsoil or roadway aggregate, to match the existing dike surface.

F. Water Jetting Backfill:

1. Where water jetting is called for, all trench backfill shall be compacted by jetting and water soaking in the manner described below.

2. Trench compaction shall be started at the point of lowest elevation of the trench and work up along the trench.

3. Jetting and water soaking shall not begin until the trench has been backfilled to within 6 inches of the finished surface.

4. Holes through which water is injected into the backfill shall be centered over the trench

Page 50: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-4

backfill and at longitudinal intervals of not more than 6 feet. 5. Additional holes shall be provided if deemed necessary by the IDNR Construction

Inspector to secure adequate settlement. 6. All holes shall be jetted and shall be carried to a point 1 foot above the top of the pipe. 7. Drilling the holes by means of augers or other mechanical means will not be permitted. 8. Care shall be taken in jetting so to prevent direct contact with, or other disturbances of

the pipe. 9. No more than 100 linear feet of completed sewer lines shall remain un-jetted at any one

time. 10. Water shall be injected at a pressure and rate just sufficient to sink the holes at a

moderate rate. 11. After a hole has been jetted to the required depth, the water shall continue to be injected

until it begins to overflow the surface. 12. CONTRACTOR shall, at his own expense, bore test holes at such locations as the IDNR

Construction Inspector may designate in order to determine the effectiveness of the water soaking.

13. Soil auger shall be used for boring test holes. 14. As soon as the jetting and water soaking has been completed, all holes shall be filled

with soil and compacted. 15. Surface depressions resulting from backfill subsidence caused by jetting and water

soaking shall be filled and re-compacted by tamping or rolling to the satisfaction of the IDNR Construction Inspector.

16. Water shall be furnished at the IDNR's expense. 17. CONTRACTOR shall use water only at those times designated by the IDNR. 18. CONTRACTOR shall conform to municipal ordinances, rules, or regulations concerning

its use. 19. Water jetting backfill shall be incidental to pipe line installations.

G. Where there is a deficiency of suitable backfill material due to a rejection of part or all of the

excavated material as unsatisfactory for backfill purposes, CONTRACTOR shall furnish satisfactory backfill material wasted from trench excavation in other locations or from other sources furnished by the CONTRACTOR. Backfill furnished and disposal of unsatisfactory material under these circumstances shall be incidental to piping installation.

H. Material for earthen backfill may be job-excavated material, free from debris, stones larger than 2

inches, organic matter, and frozen material.

I. Backfilling shall proceed so that not more than 100 feet intervals between the end of the backfilled section and the end of the laid pipe. No backfill material shall be placed until the IDNR Construction Inspector has examined the grade of the pipe.

J. Where the trenches have been sheeted or braced, care must be taken in removing the same to

keep the backfilling well above the lower ends of the sheeting or bracing so as to prevent caving of the sides of the trench down onto the pipe and displacing them or damaging structures along the sides of the trench.

K. Tamping shall be done with a hand held tamper or vibratory plate of 6 inches or less in width.

No other type of compaction equipment will be allowed. Care shall be used to place and tamp this backfill as not to disturb the joints, alignment, or grade of the pipe. Backfilling shall be carried on simultaneously on both sides of the pipe.

Page 51: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-5

L. Where the trench excavation is within the public right-of-way, or within 5 feet of a roadway,

sidewalk, driveway, or wherever indicated on the Drawings, the trench backfill shall be tamped continuously to the surface with a mechanical tamper of a type approved by the IDNR Construction Inspector. All material shall be compacted to 95 percent of the Standard Proctor Density as determined by ASTM D1557. No layer of material being compacted shall exceed 1 foot in depth. IDNR Construction Inspector reserves the right to perform density tests after tamping is complete on any layer.

M. Where un-compacted backfill is indicated on the Drawings, the backfill material from top of the

granular backfill to the surface may be simply pushed into the trench and run over with the backfilling equipment.

2.03 BACKFILL FOR MANHOLES, APPURTENANCES, AND STRUCTURES

A. Backfill material as required for adjacent trench. 2.04 SURFACE RESTORATION

A. Anywhere the excavation is in other than the traveled way of streets or alleys, the surface shall be leveled and raked to the original ground and seeded in accord with Section 02930.

2.05 SIDEWALK AND PAVEMENT MATERIALS

A. Concrete pavement, and all types of concrete base pavement, may be cut only where, in the manner and to the extent specified herein, or authorized by the IDNR Construction Inspector. Cuts shall be no larger than necessary to provide adequate working space for proper installation of pipe and pipeline appurtenances. Use concrete saw for the cutting of concrete pavements along each side of trenches and at structures. All cuts shall be a minimum of 2 inches deep or 1/4 the depth of the pavement, whichever is greater.

B. Concrete pavements over trenches excavated for pipelines shall be removed to a width not less

than 24 inches wider than the width of the trench at pavement subgrade. Trench width at pavement subgrade shall not exceed the minimum dimension that will allow good and safe construction except that no under cutting will be permitted. A shoulder not less than 12 inches in width, at any point, shall be left between the cut edge of the pavement and top edge of the trench. Pavement cuts shall be made to and between straight lines that, unless otherwise required, shall be parallel to the centerline of the trench.

C. Where the line of the trench parallels the length of concrete walks and the trench location is all or

partially under the walk, then the entire walk shall be removed and replaced. If necessary to remove concrete curbs, gutters, or walks, they shall be replaced to the existing joints.

D. Concrete streets and drives: Refer to Section 02520. Asphalt streets and drives: Refer to Section

02751.

PART 3 - EXECUTION 3.01 TRENCH CONSTRUCTION

Page 52: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-6

A. Widths:

1. Trenches shall be excavated to limiting trench widths and pipe clearances to provide adequate working space and clearances for proper pipe installation, jointing, and embedment operation.

2. For the protection of the pipe from external loads, limits to the maximum width of the lower portion of the trench below an elevation 6 inches above the top of the installed pipe shall apply.

3. Such limiting minimum and maximum trench widths together with the minimum permissible clearance between the installed pipe and either trench wall shall be as follows:

Minimum and Maximum Trench Widths *

Pipe Size, Inches

Minimum Width, Inches

Minimum Sidewall Clearance, Inches

Maximum Width, Inches

4 20 5 30 6 20 5 30 8 20 5 30 10 23 5 30 12 26 6 30

*Measured 6 inches above top of pipe. **Applies to cover depths to 18 feet.

B. Tunneling and Boring: All excavation shall be done in open trenches except where tunneling or boring is shown on the Drawings or where written consent is given by the IDNR Construction Inspector to tunnel or bore.

C. Open Trench in Advance of Work: Not more than 100 feet of trench shall be opened up in

advance of the completed sewer or conduit work. D. Barricading Work:

1. CONTRACTOR shall provide and maintain the fences, walks, and bridges that are necessary for the public safety and convenience.

2. CONTRACTOR shall place sufficient lights on or near the work and keep them burning from sunset to sunrise to ensure the safety of the public.

3. CONTRACTOR shall keep watchmen on the work whenever the IDNR Construction Inspector deems it necessary.

4. Material delivered to the job shall be placed with minimal interference to traffic.

E. Bell holes shall be carefully excavated at proper intervals so that the bells support no part of the load. No more shall be excavated than necessary to ensure the making of good joints.

F. Sheeting and Bracing:

1. In limiting trench widths, proper trench wall protection shall be used in accordance with OSHA Standards.

2. If proper trench wall protection is not used, OSHA specified wall slopes shall be required for each type of soil.

3. If wall protection is used, the sides of the trench shall be properly secured and supported

Page 53: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-7

by bracing and sheet piling according to approved sheeting methods. 4. Sheeting shall not extend below the top of the pipe. 5. Bracing, sheeting, and shoring will not be considered an extra. 6. CONTRACTOR shall sling, shore up, and secure in place all present sewers, water lines,

conduits, and structures of a similar nature that are encountered in or near the trenches. 7. CONTRACTOR at his expense shall restore any such structure or conduit damaged by

the excavation to its original condition. G. No explosives are to be used.

H. Dewatering:

1. CONTRACTOR shall provide and maintain proper and adequate dewatering equipment for the removal and disposal of all surface and ground water entering trench excavation, and shall keep the trench excavation dry until the structure or conduit to be built therein is completed to the extent that no damage will result from hydrostatic pressure, flotation, or any other effect of such water.

2. No ground or surface water shall be discharged into the sanitary sewer system. 3. No reinforcement steel shall be placed in water, and no water shall be permitted to rise

over such steel before the concrete has been deposited. 4. Surface water shall be diverted or otherwise prevented from entering trenches to the

greatest extent practicable without causing damage to adjacent property. 5. All excavation for trenches which extend down to or below the static ground water

elevations shall be dewatered by lowering and maintaining the ground water surface so as not to interfere with the making of good workmanlike joints.

6. Dewatering shall be done by means of well points or by other acceptable means until the pipe laying has been completed, and backfilling has been completed to a stage where danger from flotation is eliminated.

7. CONTRACTOR will be held responsible for the condition of any sewer, drain, or other conduit or pipeline that may be used for drainage purposes, and all such pipes or conduits shall be clean and free from sediment before acceptance thereof by the IDNR Construction Inspector.

I. Whenever work is to proceed over private property or other than the traveled way of streets or

alleys, the topsoil shall be removed to a depth as directed by the IDNR Construction Inspector up to a maximum of 1 foot. Such topsoil shall be stockpiled separately until backfilling operations are completed and then spread in a uniform layer, a minimum of 6 inches thick, over the area disturbed by the work.

3.02 OTHER REQUIREMENTS

A. Trenches not requiring select backfill: Pile excavated material, suitable for backfill, in an orderly manner a sufficient distance back from edge of excavation to avoid slides or cave-ins; 2 foot minimum clear distance.

B. Trenches requiring granular backfill: Place unsuitable excavated material directly on trucks and

haul away. No spoil banks permitted.

C. If granular material suitable for trench backfill is encountered in trenches requiring trench backfill, pile in an orderly manner a sufficient distance back from edge of excavation to avoid

Page 54: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-8

slides or cave-ins, 2 foot minimum clear distance.

D. Excavate existing utilities sufficiently in advance of pipe laying to determine crossing arrangement. No payment will be allowed for down time due to utility relocation.

E. Use caution when placing and compacting backfill to avoid placing construction loads on pipe

that may damage or displace newly laid pipe.

F. Support, brace or remove utility poles either adjacent to or in trench excavation at no cost to IDNR.

G. Utility mains shown on Drawings, in conflict with new facilities: Perform relocation or make

arrangements with utility to perform Work at no additional cost to IDNR.

H. Utility mains not shown on Drawings, in conflict with trench excavation or new facilities:

1. Notify IDNR and Utility Company immediately. 2. Authorized relocation performed by CONTRACTOR or performed by others at

CONTRACTOR's expense paid for under provisions of Article 11 of General Conditions.

3.03 SHEETING, SHORING, AND BRACING

A. Construct sheeting, shoring, and bracing where shown on Drawings and where required to hold

walls of excavation to protect existing utilities, trees, structures, and other similar features and to provide protection of employees.

B. Design of sheeting, shoring, and bracing shall be responsibility of CONTRACTOR and shall

comply with OSHA requirements.

C. When movable trench shield is used below centerline of pipe, it shall never be lifted prior to any forward movement to avoid the caving in of the bottom sides of the trench walls.

3.04 DEWATERING

A. Execute Work in the dry.

B. Provide equipment for handling water encountered.

C. Do not lay pipe or pour concrete on excessively wet soil.

D. Prevent surface water from flowing into excavation; promptly remove any water accumulated.

E. Divert stream flow and/or sewage away from areas of construction.

F. Do not discharge water pumped from excavations to existing sanitary sewers.

G. Methods used shall not cause settlement or damage to adjacent property. 3.05 SIDEWALK AND PAVEMENT REMOVAL

Page 55: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-9

A. Where large portions of existing streets are removed, measure and record exact dimensions and

elevations before pavement removal. Streets and curbs shall be rebuilt to same widths and elevations as existed prior to construction.

B. Remove pavement, sidewalk, or curb and gutter to minimum of 1 foot from trench. No

undercutting will be permitted. C. Saw cut vertically; remove on straight lines approximately parallel or perpendicular to centerline

of pavement. D. Concrete and bituminous concrete and bituminous oil & chip pavements:

1. Cut with concrete saw; minimum vertical cut 1-1/2- inch, as needed to give clean break. 2. Break out remainder of slab.

E. Sidewalks: Saw cut and remove to nearest joint beyond minimum distance of 1 foot from edge

of trench. F. Dispose of waste material.

3.06 RESTORATION OF SURFACES

A. Restoration of surfaces shall include the removal of the existing surface, and disposal of surplus material, and the construction of new surfaces. Surface restored shall be equal to or better than the surface removed. Surfaces not removed during excavation but damaged by the CONTRACTOR's equipment or operation shall also be removed and replaced or repaired to original condition.

B. CONTRACTOR shall furnish and maintain at all times during construction warning signs,

barricades, lights or other warning devices required by applicable federal, state and local authorities.

C. Wherever conduits are constructed under traveled roadways, driveways, sidewalks, curbs and

gutters, or other traveled surfaces, a temporary surface shall be placed over the top of the trench as soon as possible after compaction has been satisfactorily completed:

1. Temporary surface shall consist of 12 inches of coarse aggregate, materials as specified

for trench backfill (crushed limestone or washed gravel). 2. Top of the temporary surface shall be smooth and meet the grade of the adjacent

undisturbed surface. 3. Temporary surface shall be maintained at the CONTRACTOR's expense until final

restoration of the surface is performed as specified. 4. No permanent restoration of surfaces shall be initiated until authorized by the IDNR

Construction Inspector. 5. Temporary surfacing shall be required over the entire width of the trench, but any width

in excess of the specified trench width shown on the Drawings shall not be used in computing payment quantities.

D. CONTRACTOR shall restore (unless otherwise specified or directed by the IDNR Construction

Page 56: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/02009 TRENCHING, BACKFILLING & COMPACTING E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02316-10

Inspector) all removed or damaged permanent type pavements, sidewalks, driveways, curbs, gutters, fences, poles and other property and surface structures removed or disturbed during or as a result of construction operations to a condition which is equal to or better than the appearance, quality and condition that existed before the work began. Restoration shall be made as soon as possible after compaction of the backfill has been completed.

3.07 CLEANUP

A. CONTRACTOR shall clean up as the Work proceeds. Premises shall be kept free of accumulations of waste materials and earth, rubbish and other debris resulting from the work. If in the judgment of the IDNR Construction Inspector, the CONTRACTOR fails to keep the site clean as described herein above, the IDNR Construction Inspector will recommend to the IDNR withholding all progress payment until the site has been cleaned up to the IDNR Construction Inspector's satisfaction.

B. All debris and waste materials and salvaged materials unless required by the Specifications to be

reused or delivered to the IDNR, shall become the property of the CONTRACTOR and shall be removed by the CONTRACTOR from the construction site.

C. Any dirt, mud, or other debris tracked onto the adjacent streets by any of the CONTRACTOR's

or supplier's vehicles shall be immediately cleared from the surface. Where truck crossings occur over sidewalks, they shall be kept free from all spilled earth and grading materials and shall at all times be maintained in a passable condition for foot traffic.

D. Generally, the transportation of materials to and from the job site shall be over regular streets.

When the CONTRACTOR's operations or that of its shippers, haulers, or subcontractors are such that dirt, mud, or debris are spilled or otherwise deposited on streets, driveways, or sidewalks, CONTRACTOR shall clean up any large chunks before the close of every day's operation or before it is broken up or becomes impacted on the surface. In case of dispute or CONTRACTOR's failure to perform the cleanup work, the IDNR may clean the streets and walks, remove the rubbish, etc. and will charge the cost to the CONTRACTOR by withholding monies due to cover all charged work.

E. At completion of the Project, CONTRACTOR will remove all waste materials, rubbish and

debris from and about the premises as well as all tools, scaffolding and surplus materials, and will leave the site clean and ready for occupancy by the IDNR. CONTRACTOR will restore to their original condition those portions of the site disturbed or damaged by the CONTRACTOR's operations.

F. Open burning of debris will not be permitted unless specifically authorized in writing by the

IDNR, and then only following state, municipal or other local codes, ordinances, rules or regulations.

3.08 WATER POLLUTION CONTROL (SOIL EROSION)

A. CONTRACTOR shall conform to Sections 2602.01 through 2602.03, IDOT Standard Specifications, for all required temporary erosion control measures.

END OF SECTION 02316

Page 57: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-1

SECTION 02530 SEWERAGE SYSTEMS

PART 1 - GENERAL 1.01 SECTION INCLUDES

A. Piping materials used for wastewater service: Polyvinyl chloride sewer pipe; Polyvinyl chloride (PVC) pressure pipe; Ductile-iron forcemain pipe; Air release valves.

B. Pipe installation, including connections to existing system, connections between pipes of

dissimilar materials, new sewer or forcemain paralleling watermain or crossing watermain, repair of damaged watermains and services, sanitary and storm sewers, and sanitary service connections, and testing.

1.02 RELATED SECTIONS

A. Section 01300 - Submittals. B. Section 02316 - Trenching, Backfilling, and Compacting. C Section 02605 - Manholes. D Division 3 - Concrete.

1.03 SUBMITTALS

A. Include data on manufacturer's catalog data for pipe, pipe joints, gaskets, frames, lids, and gratings.

B. Submit certificates from manufacturer evidencing compliance with standards listed herein for

pipe, pipe joints, frames, lids, and gratings. C. Certification by nationally recognized, independent organization that components, materials, and

treatment chemicals in contact with potable water conform to ANSI/NSF Standard 60 or 61, as applicable.

PART 2 - PRODUCTS 2.01 POLYVINYL CHLORIDE (PVC) GRAVITY SEWER PIPE

A. Conform to sizes 4 to 15-inch diameter, ASTM D3034, SDR 26. B. Material: PVC. Minimum Cell Classification 12454B as defined in ASTM D1784. C. Joints: Flexible, elastomeric type: ASTM D3212. Gasket materials: ASTM F477. D. Fittings: Gasketed sewer fittings meeting requirements of applicable pipe and joint

specifications.

Page 58: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-2

E. Pipe design and installation shall result in installed pipe having deflection of less than 5 percent. 2.02 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

A. Material and class: ASTM D2241, 200 psi, SDR 21. B. Joints shall be integral bell with elastomeric gaskets. C. Fittings shall be cast or ductile-iron furnished by pipe manufacturer and rated for 200 psi. D. Restrained joints:

1. Fittings: Series 2500 bell restraints, EBAA Iron Sales, Inc., or equal. 2. Straight PVC pipe: Series 1600 restraint harness, EBAA Iron Sales, Inc., or equal.

2.03 POLYETHYLENE (PE) FORCEMAIN

A. The pipe and fittings shall be made using Extra High Molecular Weight (EHMW) high-density polyethylene with a standard thermoplastic material designation code of PE3408 and conforming to ASTM D3035. Pressure rating Class 160, DR 11.

B. Joints shall be fusion welded per the Manufacturer’s recommendations.

C. Polyethylene pipe and fittings may be joined together or to other materials through the use of electrofusion fittings, flange adapters with back-up rings, mechanical couplings designed for connecting polyethylene pipe and fittings to itself or another material, or MJ adapters. Consult the Manufacturer of the joining device for proper installation procedures.

2.04 AIR/VACUUM RELEASE VALVES

The Air / VacuumValves shall be single body double orifice to permit large quantities of air to escape or enter thru the larger diameter air and vacuum orifice when filling or draining a pipeline. When the pipeline is filled and under pressure the large air & vacuum orifice shall stay closed, but the smaller diameter air release orifice shall remain operative and open to allow small pockets of air accumulating, to escape automatically and independently of the large orifice. The large air & vacuum orifice shall shut-off when the free acting center guided plug is raised, into the orifice, by the lifting force of the concave bottom float. The large orifice shut-off shall be without spilling. The float shall be heavily constructed stainless steel; hermetically sealed; and having a concave bottom impact area to provide immediate resistance to flow and instant upwards movement to shut off the large orifice without spilling. The Buna-N seat must be fastened to the valve cover, without distortion for drop tight shut-off. Valve exterior to be painted Phenolic Primer Red Oxide for high resistance to corrosion.

Page 59: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-3

All materials of construction shall be certified in writing to conform to A.S.T.M. specifications as follows: Body, cover Cast iron ASTM A126 Gr.B Concave Float Stainless Steel ASTM A240 T304 Float Stem Stainless Steel ASTM A581 T303 Needle & Seat Buna-N Plug Brass Leverage Frame Cast Iron

A. Function: Allow entrained air to escape through an air release orifice without spillage or spurt.

B. Working pressure: 0-50 psi. C. Connection sizes: 1. Inlet: 2-inch NPT. 2. Outlet: 2-inch NPT. D. Orifice size: 7/32-inch. F. Accessories:

1. Furnish back-flushing attachments and valves. 2. Install isolation valve between forcemain and air valve.

G. Manufacturer: APCO Series 4445 SARV; or equal.

Page 60: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-4

2.05 TRACER WIRE A. Tracer wire: #12 THHN or TWHN copper wire. B. Splice kits: 3M - Scotchcast No. 3832, or equal. C. Ground rods: 1. Provide uniform covering of electrolytic copper metallically bonded to steel rod. 2. Minimum diameter: 3/8". 3. Minimum length: 60". 4. Blackburn Catalog #3755 or equal.

D. Ground rod clamp: corrosion-resistant copper alloy ground rod clamp; Blackburn Catalog

#G3 or equal. PART 3 - EXECUTION 3.01 PIPE INSTALLATION

A. Store, handle, join, lay, and otherwise install pipe in conformance to pipe manufacturer's recommendations.

B. Before installation, verify all measurements at site; make necessary field measurements to

accurately determine sewer make-up lengths or closures. C. Use proper pipe unloading and handling procedures to prevent damage to pipe and coating. D. Carefully protect joint material from injury while handling and storing pipe; support pipe to keep

weight off joint material; use no pipe with joints deformed, gouged, or otherwise impaired. E. Keep pipe clean of dirt and foreign matter; clean bell and spigot surfaces of pipe with gasket-type

joints and paint with lubricant recommended by manufacturer prior to jointing pipe; conform to manufacturer's recommendations.

F. Touch-up abraded pipe coatings. G. Joints shall be kept clean and installed in accordance with manufacturer's recommendations. H. Gravity sewers:

1. Commence at lowest point in line; lay spigot ends pointing in direction of flow. 2. Lower pipe carefully into trench; lay true to line and grade. 3. Provide smooth, uniform invert; spigots shall bear against bell shoulders.

4. Check each length of pipe for defects and hairline cracks at ends prior to lowering into trench. No defective pipe shall be used.

5. Line and grade: a. Set laser system as required from benchmarks and reference points. b. Check grade of each pipe; check line of every other length of pipe.

6. Stepping on pipe before backfilling not allowed.

Page 61: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-5

7. PVC pipe installation shall result in installed pipe having deflection of less than 5 percent.

8. Install 2" wide detectable warning tape in trench directly over plastic sewer pipe for full length of pipe and buried 1' to 2' below ground surface.

I. Forcemain in trench:

1. Minimum cover: 5 feet, 6 inches. 2. Lay to line and grade if shown/or indicated on the Drawings. 3. Use suitable fittings where grade or alignment requires offsets greater than the

deflections recommended by pipe manufacturer. 4. Clean and inspect each section of pipe prior to lowering into trench. 5. Provide restrained joints where piping changes direction using a manufactured fitting. 6. Refer to Section 02316 for backfill requirements.

7. Install 2" wide detectable warning tape in trench directly over plastic sewer pipe for full length of pipe and buried 1' to 2' below ground surface.

J. Directional Boring: 1. Expose or pothole all pipes and utilities which are to be crossed; provide minimum

9" clearance except for water mains provide clearance as specified hereinafter. 2. Change alignment gradually; do not exceed manufacturer's recommendation for

minimum allowable radius; inject flowable fill or grout in bore holes to be abandoned; inject flowable fill or grout at same time tool string is removed to avoid collapse of cover material.

3. Provide minimum 5.5' earth cover over top of pipe. 4. Cut exposed spline 1/2" from coupling wall to reduce soil drag; bevel couplings on

leading edge to minimize soil friction. 5. Install tracer wire with pipe as specified hereinbefore. 6. Clean out pipe upon completion of work. 7. Contractor responsible for correct vertical and horizontal alignment; pipe installed

with incorrect vertical and/or horizontal alignment will be replaced by Contractor with proper installation at no additional cost to Owner.

a. Horizontal alignment between structures as shown on plans may be altered upon authorization of Engineer.

8. Water for directional boring shall be provided by Contractor from off-site. All costs of delivering water to the site shall be borne by the Contractor.

3.02 CONNECTIONS TO EXISTING SYSTEM

A. Connections to existing manhole: 1. Cut hole in existing manhole at required elevation. 2. Remove dirt and debris. 3. For sanitary sewers, install flexible watertight connection device in accordance with

manufacturer’s recommendations. 4. Insert new sewer pipe flush with inside of manhole. 5. Reconstruct manhole bottom to suit new connection. B. Connections to existing sewer: Use manufactured coupling.

Page 62: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-6

C. Plug existing sewers where indicated; fill pipe with concrete for minimum length of 2 feet. D. Connect no storm drains to sanitary sewer. E. Connect no sanitary service drains to storm sewer.

3.03 CONNECTION BETWEEN PIPES OF DISSIMILAR MATERIALS

A. Connection between dissimilar gravity pipe materials 12 inches and smaller in diameter: Install manufactured flexible coupling in accordance with ASTM C425.

B. Connection between dissimilar gravity pipe materials larger than 12 inches in diameter:

1. Construct 6-inch thick concrete collar around joint; Extend collar 12 inches each way from joint.

2. Reinforce with welded wire fabric. C. Connection between 2 different types of pressure pipes: 1. Use suitable manufactured connection. 2. Design pressures same as for pipe. 3. Install in accordance with manufacturer's recommendations. 3.04 CONCRETE ENCASEMENT

A. Pour concrete beneath and around pipe after pipe jointing is complete. B. Encase with 8 inch minimum thickness as measured at outside of pipe barrel or full width of

trench bottom. C. Use 2 temporary pipe supports under barrel per pipe length; 1 near bell and 1 near spigot end. D. Provide adequate ties and braces to prevent displacement or flotation during encasement.

3.05 NEW SEWER OR FORCEMAIN PARALLELING WATERMAIN A. Where watermain paralleling new sewer or forcemain is less than 10 feet horizontally from sewer

or forcemain, notify IDNR Construction Inspector. B. Obtain authorization from IDNR to relocate sewer or forcemain to obtain 10 feet of horizontal

separation if possible. C. If impossible to relocate sewer, bottom of watermain shall be at least 18 inches above top of

sewer, and in separate trench or on undisturbed shelf to one side of sewer with at least 3 feet of horizontal separation.

D. If impossible to maintain required clearance, sewer shall be constructed of ductile-iron pipe

conforming to AWWA C151. 1. Horizontal separation of at least 2 feet must be provided. 2. Pressure test at 30 psi for 1 hour to assure water-tightness before backfilling. 3. Maximum allowable leakage shall be 0.1 gal/hr per 1,000 feet per inch diameter.

Page 63: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-7

3.06 NEW SEWER OR FORCEMAIN CROSSING WATERMAIN A. Notify IDNR if: 1. New sewer crosses over watermain. 2. Sewer crosses under watermain and vertical clearance is less than 18 inches. 3. New forcemain crosses over or under watermain and vertical clearance is less than 18

inches. B. If sewer crosses under watermain, relocate watermain to provide minimum 18 inches vertical

clearance, for minimum of 10 feet each side of sewer. Locate center of standard length of watermain pipe over sewer.

C. If relocation of watermain to obtain required clearance is not practical or if sewer crosses over

watermain, construct sewer with one full length, 20 feet minimum, of ductile-iron pipe conforming to AWWA C151; center both sewer and watermain pipe lengths at crossing.

D. If forcemain crosses over or under watermain and vertical clearance is less than 18 inches obtain

authorization from IDNR to relocate forcemain to provide at least 18 inches vertical clearance. 3.07 REPAIR OF DAMAGED WATERMAINS AND SERVICES

A. CONTRACTOR shall repair breaks in existing lines caused by construction operations. B. Watermains:

1. Replace with pipe equal in type and quality to that damaged. 2. Repair sleeves shall be mechanical joint split sleeve.

C. Water services: 1. Pipe: Copper, ASTM B88 Type K. Replace entire section of pipe. 2. Provide corporation stops, curb stops, and service boxes complete with lid and plug as

required. 3. If lead piping is encountered, contact IDNR and record location. Damaged lead piping

shall not be repaired. Replace with Type K copper where specified above. 4. Where curb box lids are located in new pavement, install flush with new pavement and

provide plastic pipe sleeve in pavement. 3.08 REPAIR OF DAMAGED SANITARY AND STORM SEWERS

A. CONTRACTOR shall repair or replace breaks in existing sewers caused by construction operations. Provide temporary connections if required.

B. If pipe is damaged by construction operations such that it requires replacement, the following

material shall be used:

Page 64: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-8

1. Pipe: Ductile-iron; AWWA C151.

Pipe Size, inches Minimum Pressure Class

8 to 12 350 14 to 20 250 24 to 64 200

2. Connections:

a. Flexible coupling in accordance with ASTM C425 for pipes 12 inches and smaller.

b. Concrete collar minimum of 12 inches either side of joint and 6 inches thick for pipes larger than 12 inches.

C. Ductile iron replacement pipe shall extend minimum of 2 feet beyond both sides of new sewer

trench. D. Provide positive slope to match existing sewer.

3.09 TESTS

A. Gravity sewers, sanitary: 1. Conduct infiltration test on sewers located entirely below ground water table and

conduct exfiltration test on sewers located partially or entirely above ground water table. Tests shall be conducted before connection of any sanitary services.

2. Manhole exfiltration test: Plug pipes and fill sanitary sewer manhole with water to depth used in testing line or 6 feet minimum; allow water to stand minimum of 2 hours and refill to original elevation; after minimum of 30 minutes, record difference in elevation and convert to gallons per hour lost.

3. Maximum allowable exfiltration or infiltration: 200 gallons per mile per inch diameter of sewer per 24-hour day in any test section, including manholes.

4. Visible leakage at joints, or leakage in excess of that specified, shall be repaired at CONTRACTOR's expense.

5. Furnish and install all plugs, measuring devices, and other equipment. 6. Maximum length of test section: 1,000 feet. 7. Low pressure air testing may be used instead of in- or exfiltration tests at

CONTRACTOR's option. Low pressure air test shall be in general accordance with ASTM C828 for vitrified clay pipe, ASTM C924 for reinforced concrete pipe, and ASTM F1417 for plastic pipe.

B. Gravity sewers, alignment test:

1. Check alignment by lamping, laser, or other approved survey method. 2. Sewers 15 inch and larger, maximum misalignment:

a. Vertical: 0.20 feet. b. Horizontal: 0.50 feet.

3. Sewers smaller than 15 inch: Lamp shall be visible through section of pipe lamped. 4. Misaligned, displaced, or otherwise defective sewer shall be repaired or replaced at

CONTRACTOR's expense.

Page 65: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SEWERAGE SYSTEMS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02530-9

C. Pressure mains: 1. Furnish and install all materials and equipment necessary. 2. Flush out line before test to remove air; insert taps if necessary to blow off air trapped in

line. 3. Pressure test for 2 hours at 75 psi at lowest point in line under test; maximum pressure

variation during test: 5 psi. 4. Leakage test: Perform concurrently with pressure test. Maintain 75 psi pressure for 2

hours; measure water supplied to maintain test pressure within 5 psi of test pressure by pumping from drum or by similar means. Compute maximum allowable leakage by formula:

___ L = SD √P 133,200

L = Maximum allowable leakage in gallons per hour S = Length of pipe test in feet D = Nominal pipe diameter in inches P = Average test pressure, psig

5. Locate and repair or replace all defective pipe or fittings until leakage is within the

specified allowance. D. Flexible sewers, deflection test: Installed pipe deflection shall be tested by CONTRACTOR with

rigid ball or 9-arm mandrel or other approved "Go-No Go" device. Sewer shall be tested no sooner than 30 days after backfilling. Pipe with deflection exceeding 5 percent shall be removed and replaced at no cost to IDNR.

END OF SECTION 02530

Page 66: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MANHOLES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02605-1

SECTION 02605 MANHOLES

PART 1 - GENERAL 1.01 WORK INCLUDES

A. Provide precast concrete manholes and flat tops for utility access.

1.02 REFERENCES

A. American Society for Testing and Materials (ASTM):

1. ASTM C76 - Reinforced Concrete Culvert, Storm Drain and Sewer Pipe. 2. ASTM C478 - Precast Reinforced Concrete Manhole Sections. 3. ASTM A48 - Gray Iron Castings. 4. ASTM A615 - Deformed and Plain Billet-Steel Bars for Reinforcing. 5. ASTM A185 - Welded Steel Wire Fabric for Concrete Reinforcement.

1.03 QUALITY ASSURANCE

A. Manufacturer furnishing manholes shall certify that the manholes and components proposed

meet or exceed the ASTM specifications referenced in Section 2.01, MATERIALS. 1.04 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Deliver, store and handle precast units, components and assemblies in a manner to prevent damage. Keep all components and assemblies under adequate cover until incorporated into the work.

B. All damaged, broken, or otherwise defective materials will be rejected.

PART 2 - PRODUCTS 2.01 MATERIALS

A. Manholes shall be either integrally cast bottom precast ring using concrete specified below or precast base and barrel sections. Precast units shall be in accordance with ASTM C478 or ASTM C76, Class IV. Precast units shall have an inside diameter as shown on the Drawings.

B. Concrete masonry units, ASTM C139, may be used for manhole barrel sections, if called for

on the Drawings or authorized by the INDR Construction Inspector on an individual basis. C. Concrete masonry unit manholes shall be built with mortared joints on a flat base component. D. Base component shall be a monolithic unit, minimum thickness of 8-inches, unless otherwise

shown on the Drawings. Base shall be set in compacted granular bedding not less than 6-inches thick, extending to the limits of excavation.

E. Provide joints using O-ring rubber gasket (ASTM C433) sealed on the inside and outside

with mortar. No bituminous materials shall be used in the manhole construction. Where

Page 67: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MANHOLES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02605-2

shown on the Drawings or for manhole joints subject to a constant hydrostatic pressure, CONTRACTOR shall install an external rubber seal with metal bands around the joints in the barrel section.

F. Cones shall be eccentric. G. Precast flat tops, of varying sizes and thickness, are required for some manholes.

CONTRACTOR to install varying sizes of access frames and lids or castings in flat tops, as shown on the Drawings.

H. Circular cast iron frames and lids:

1. Conform to the requirements of gray iron castings, ASTM A48. 2. Circular manhole frames and covers shall be heavy duty weighing a minimum of 265

lbs. 3. Closed lids shall have a concealed pickhole and shall be self-sealing with rubber

gasketed lids. 4. Castings shall be set in full mortar beds. 5. Neenah R-1670-A, Neenah R-1772; or equal.

I. Manhole steps:

1. Set into the manhole walls at the time when the manholes are cast. 2. Set at 16-inch centers. 3. Embedment 5 inches. 4. Width 10 inches 5. Materials. Step shall consist of a 3/8-inch steel reinforcing rod, encapsulated in

polypropylene plastic. 6. Free of sharp edges, have non-slip surface, and end lugs to prevent feet from slipping

off.

J. Concrete: Supply 3,500-psi concrete in accord with the pertinent provisions of Section 03300 of these Specifications. 1. For concrete in manholes, comply with ASTM C150, Type III. 2. For concrete in cradle and encasement: Contractor's option.

K. Wire fabric reinforcement shall consist of wire conforming to ASTM A185.

L. Bar reinforcement shall conform to ASTM A615, intermediate grade.

M. Mortar: Comply with ASTM C270, Type M.

N. Except as detailed on the Drawings, manholes greater than 5 feet in depth shall have eccentric precast cone sections, and manholes 5 feet in depth or less shall have vertical sidewalls and flat slab tops.

O. Precast reinforced concrete box sections shall conform to ASTM C850.

PART 3 - EXECUTION 3.01 COORDINATION

Page 68: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MANHOLES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02605-3

A. Schedule work and notify all contractors in ample time so that provisions for their work can be made without delaying the project.

3.02 INSTALLATION

A. Excavation: In order to permit the joints to be mortared properly and also to permit proper compaction of the backfill material, the excavation shall be made to a diameter of at least 2 feet greater than the outside diameter of the structure.

B. Sub-base Preparation: Adequate foundation for all manhole structures shall be obtained by

removal and replacement of unsuitable material with well-graded granular material, by tightening with coarse ballast rock, or by such other means as provided for foundation preparation of the connected piping.

C. Base Installation (Precast-Base):

1. Well-graded granular bedding course conforming to the requirements for aggregate for trench backfill, not less than 6 inches in thickness and extending to the limits of the excavation, shall be firmly tamped and made smooth and level to assure uniform contact and support of the precast element.

2. Precast base section shall be carefully placed on the prepared bedding so as to be fully and uniformly supported in true alignment and making sure that all entering pipes can be inserted on proper grade.

D. Precast Units With Integral Base:

1. Precast units may be constructed with a precast base section or a monolithic base structure as specified.

2. Precast sections shall be placed and aligned to provide vertical sides and vertical alignment of the ladder rungs.

3. Completed units shall be rigid, true to dimensions and shall be watertight. 4. All lift holes on precast elements shall be completely filled with mortar. 5. All joints between precast elements on manholes shall be made with an O-ring rubber

or neoprene gasket.

E. Inlet and Outlet Pipes: 1. Piping connections to manholes shall be made with molded PVC or rubber gaskets. 2. Connection method shall guarantee a watertight seal.

F. Placing Castings:

1. Castings placed on concrete or masonry surface shall be set in full mortar beds. 2. Mortar shall be mixed in proportion of one part cement to three parts sand, by

volume, based on dry materials. 3. Castings shall be set accurately to the finished elevation so that no subsequent

adjustment will be necessary. G. Manhole Inverts:

1. Construct manhole flow channels of concrete, mortar or drain line pipe, which shall be of semicircular section conforming to the inside diameter changes in size or grade gradually, and changes in direction shall be by true curves.

Page 69: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 MANHOLES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02605-4

2. Provide such channels for all connecting pipes to each manhole and benching as shown on the Drawings.

H. Jointing and Plastering: Completely fill inside and outside of barrel’s rubber gasket joints

with mortar and leave smooth and free from surplus mortar on the inside of the manhole.

I Frames and Covers: 1. Unless otherwise shown on the Drawings, set frames and covers in full mortar bed. 2. In paved areas, top of the cover will be flush with the finished pavement. 3. In unpaved areas, top of the cover will be 2 inches higher than finished grade.

J. Backfill:

1. Space between the sides of the excavation and the outer surfaces of the manhole shall be backfilled with aggregate for trench backfill if the manhole is in a pavement or if the nearest point of the excavation for the manhole falls within 2 feet of a structure.

2. Use backfill and compaction procedures as specified for the adjoining pipe. 3.03 CLEANING

A. All newly constructed manholes shall be cleaned of any accumulation of silt, debris or foreign matter of any kind and shall be free of such accumulations at the time of final inspection.

END OF SECTION 02605

Page 70: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 LAWNS AND GRASSES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02930-1

SECTION 02930 LAWNS AND GRASSES

PART 1 – GENERAL 1.01 SUMMARY

A. Work includes seedbed preparation and application of seed mixtures and fertilizer to: 1. All areas so designated on the Drawings. 2. All areas within the boundaries of this Project having been disturbed by the

construction efforts on this Project, and not receiving finished surfacing. 3. Areas as determined by the IDNR Construction Inspector.

1.02 RELATED SECTIONS A. Drawings and General Provisions of the Contract, including the General Covenants and

Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not necessarily limited to, the following: 1. Section 02316 - Trenching, Backfilling & Compacting.

1.03 REFERENCES

A. Standards of materials and construction shall conform to the Standard Specifications for Highway and Bridge Construction, latest Series of the Iowa Department of Transportation.

1.04 QUALITY ASSURANCE

A. Perform all Work in this Section in accordance with the requirements of the IDOT Standard Specifications Section 2601.

1.05 PROJECT/SITE CONDITIONS

A. Environmental Requirement: 1. Seeding shall be performed only during normal application periods, optimum

temperature, moisture and climatic condition to promote germination and plant growth.

2. Normal application periods are between March 1 and May 31 and between August 10 and September 30.

B. Existing Conditions:

1. Survey job conditions prior to commencing work. 2. Bring any discrepancies between existing work and the Drawings and Specifications

to the attention of the IDNR Construction Inspector. 3. Connections to existing facilities shall be made in accordance with the obvious intent

of Drawings and Specifications. 4. Claims for extra payments as a result of failure to examine existing conditions at the

site will not be allowed. PART 2 - PRODUCTS

Page 71: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 LAWNS AND GRASSES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02930-2

2.01 MATERIALS

A. Topsoil used for seedbed shall be friable clay loam surface soil found in a depth of not more than 12 inches. Satisfactory topsoil is reasonably free of subsoil, clay lumps, stones, and other objects over 2 inches in diameter, and without weeds, roots, and other objectionable material.

B. Seeds shall be "red-tag" quality or better supplied from the latest available crop, free of

noxious weed seed and supplied in the following varieties and percentages of weight. C. Provide mixture of types and quantities as specified herein for seeding of areas designated by

the IDNR Construction Inspector as indicated on the Drawings, and as specified herein. 1. Class "A" Mixture: For areas to remain in semi-natural state where mowing is

required only as a temporary control measure:

Fescue, Kentucky 31 25 lbs. per acre Switchgrass (Blackwell) 8 lbs. per acre Alfalfa (Northern Grown) 5 lbs. per acre Birdfoot Trefoil (Empire) 4 lbs. per acre Alsike Clover 4 lbs. per acre

2. Class "B" Mixture: For same situation as where Class "A" mixture is used but where a lighter mix is preferable:

Fescue, Kentucky 31 20 lbs. per acre Switchgrass (Blackwell) 3 lbs. per acre Alfalfa (Northern Grown) 4 lbs. per acre Birdfoot Trefoil (Empire) 4 lbs. per acre Alsike Clover 4 lbs. per acre

3. Class "C" Mixture: For area designated as fine seeded, lawns or other mowed grass areas (See Paragraph 3.04.D. rate):

Bluegrass, Kentucky 70 % Ryegrass, Perennial, Fineleaf 10 % Fescue Creeping Red 20 %

4. Class "D" Mixture: For all areas, unless otherwise specified, where a prairie grass in natural state is required:

Perennial Ryegrass, Fineleaf 30 lbs. per acre Switchgrass (Blackwell) 5 lbs. per acre Sideoats Grama 5 lbs. per acre Little Bluestem 5 lbs. per acre Sand Reedgrass 5 lbs. per acre

D. Seed will be delivered on site in separate packaging for each individual type of seed within

each mixture and mixed in the presence of the IDNR Construction Inspector if required.

Page 72: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 LAWNS AND GRASSES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02930-3

E. Commercial mixture in the quantities as specified will be acceptable at the discretion of the IDNR Construction Inspector if these quantities are verifiable.

2.02 FERTILIZER

A. Comply with IDOT Standard Specification 2601. Nutrient mixture shall be 15-15-15. 2.03 FUNGICIDE

A. All seeds for permanent seeding shall be treated with a non-mercurial fungicide (75 percent concentration or equivalent) at the rate of 5-1/2 ounces per 100 pounds of seed.

2.04 ACCESSORIES

A. Mulching material: Oat or wheat straw, reasonably free from weeds or foreign matter detrimental to plant life.

B. Excelsior blanket: Uniform open weave jute matting.

1. Excelsior blanket shall consist of a machine-produced mat of curled wood excelsior of 6-inches or longer fiber length, with consistent thickness and the fiber evenly distributed over the entire area of the blanket.

2. Top of each blanket shall be covered with a photodegradable extruded plastic mesh. 3. Blanket shall be smolder resistant without use of chemical additives.

PART 3 - EXECUTION 3.01 EXAMINATION

A. Examine the areas and conditions under which work of this section will be performed.

B. Correct conditions detrimental to timely and proper completion of the work.

C. Do not proceed until unsatisfactory conditions are corrected. 3.02 SEEDBED PREPARATION

A. Area to be seeded shall be raked or graded to fill washes or gullies.

B. Pick up and dispose of all debris, including stones, boulders, logs, stumps, or other foreign material that will interfere with the seeding operation.

3.03 FERTILIZER APPLICATION

A. Spread fertilizer over the area at the rate of 650 pounds per acre (actual nutrient).

B. Unless otherwise indicated, spread all fertilizer with a mechanical spreader that will secure a uniform rate of application.

C. Spread fertilizer after the preliminary preparation of seedbed and prior to the sowing of any

seeds.

Page 73: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 LAWNS AND GRASSES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02930-4

D. Disk the fertilizer and roll the area prior to seeding.

E. On area inaccessible to field machinery, spread fertilizer after preparation of the seedbed and

thoroughly rake into the soil.

F. Application of fertilizer in combination with seeding by hydraulic seeder as specified in IDOT Section 2601.04H will be acceptable at the discretion of the IDNR Construction Inspector.

3.04 SEED APPLICATION

A. Preparation: Mix all seeds specified for this project thoroughly at the project site prior to placing in spreading equipment.

B. On all areas accessible to field machinery, all grass seeds may be sown with a gravity,

cyclone or hydraulic seeder as specified herein. On areas inaccessible to field machinery, the use of hand-cyclone seeder will be permitted.

C. Apply Class "C" Mixture in all disturbed areas unless otherwise directed by the IDNR.

D. Apply Class “C” seed mixture at a rate of 4 pounds per 1,000 square feet during fair and calm

weather. One half of the seed mixture shall be sown in one direction and the remainder at right angles to the first sowing.

3.05 MULCHING

A. Apply mulch at the rate of 2,000 pounds per acre. 3.06 SEED PROTECTION ON SLOPES

A. Cover seeded slopes with excelsior blanket. Roll matting down over slopes without stretching or pulling.

B. Lay matting smoothly on soil surfaces, burying top end of each section in narrow 6-inch

trench. Leave 12-inch overlap from top roll over bottom roll. Leave 4-inch overlap over adjacent section.

C. Staple outside edges and overlaps at 36-inch intervals.

D. Lightly dress slopes with topsoil to ensure close contact between matting and soil. E. In ditches, unroll matting in direction of flow. Overlap end of strips 6 inches with upstream

section on top.

3.07 SEED APPLICATION IN MAINTAINED LAWNS

A. For maintained lawns to be seeded as part of this project, apply fertilizer prior to preparation of the seedbed.

Page 74: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 LAWNS AND GRASSES E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 02930-5

B. A rotary tiller will be required for preparation of the seedbed. The seedbed after tilling will be raked firm, smooth and free of clods, rocks and other debris.

C. Roll the seedbed both before and after the application of seeds. Apply seeds over damp soil

by broadcast seeding.

D. Roll, seed, and fertilize by hand or with hand operated equipment areas inaccessible to field equipment.

3.08 SPRING OVERSEEDING

A. Seedbed preparation will not be required provided the over-seeding is applied when the ground is free from frost action after March 1 and before April 1 or as directed by the IDNR Construction Inspector.

END OF SECTION 02930

Page 75: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-1

SECTION 03100 CONCRETE FORMWORK

PART 1 - GENERAL 1.01 SUMMARY

A. Work includes all labor, materials, and equipment required to construct, shore, and remove all forms to accommodate all cast-in-place concrete work, as shown on the Drawings and as specified in other Sections of these Specifications.

B. Related Sections: Drawings and General Provisions of the Contract, including the General

Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not necessarily limited to, the following:

1. Section 03200 - Concrete Reinforcement. 2. Section 03300 - Cast-In-Place Concrete.

1.02 REFERENCES

A. Safety: All formwork and methods of construction shall conform to the requirements of the state of Iowa Bureau of Labor and all OSHA Standards.

B. ACI Code 347.

1.03 SUBMITTALS

A. Provide concrete mix formula to IDNR Construction Inspector. B. Within 30 calendar days after award of the contract, submit manufacturer's data and

installation instruction for proprietary materials including form coatings, ties and accessories, and manufacturer's form system if used.

C. When requested by the IDNR Construction Inspector for the purpose of explaining details or

structural integrity, the CONTRACTOR shall submit those drawings requested prior to construction of the project.

1.04 QUALITY ASSURANCE

A. Design of formwork is the responsibility of the CONTRACTOR. B. Standards: Comply with all applicable provisions of ACI 347.

PART 2 - PRODUCTS 2.01 MATERIALS

A. Form Materials:

1. Construct formwork for exposed concrete surfaces with smooth-faced undamaged plywood, un-dented metal, or other panel-type materials acceptable to the IDNR

Page 76: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-2

Construction Inspector, to provide continuous, straight, plumb, smooth cast surface, furnish in largest practical sizes to minimize number of joints.

2. Provide form material with sufficient thickness to withstand pressure of newly-placed concrete without reflection or bowing.

B. Form Ties:

1. Provide factory-fabricated, adjustable length removable or snap-off metal form ties,

designed to prevent form deflection and to prevent spalling concrete surfaces upon removal.

2. Provide ties so that portion remaining within concrete after removal of exterior parts is at least 1-1/2 inch from the outer concrete surface. Form ties shall not leave a hole larger than 1-inch diameter in the concrete surface.

C. Form Coating: Provide commercial formulated form-coating compounds that will not bond

with, stain, nor adversely affect concrete surfaces requiring bond or adhesion, nor impede the wetting of surfaces to be cured with water or curing compounds.

2.02 DESIGN OF FORMWORK

A. Design, erect, support, brace, and maintain formwork so that it will safely support vertical and lateral loads that might be applied, until such loads can be supported by the concrete structure.

B. Carry vertical and lateral loads to ground by formwork system and in-place construction that

has attained adequate strength for that purpose. C. Construct formwork so that concrete members and structures are of correct size, shape,

alignment, elevation, and position. D. Design forms and falsework to include assumed values of live load, dead load, weight of

moving equipment operated on formwork, concrete mix, height of concrete drop, vibrator frequency, ambient temperature, foundation pressures, stresses, lateral stability, and other factors pertinent to safety of structure during construction.

E. Provide shore and struts with positive means of adjustment capable of taking up formwork

settlement during concrete placing operations, using wedges or jacks or a combination thereof.

F. Provide trussed supports when adequate foundations for shores and struts cannot be secured. G. Support form facing materials by structural members spaced sufficiently close to prevent

objectionable deflection. H. Fit forms placed in successive units for continuous surfaces to accurate alignment, free from

irregularities, and within allowable tolerances. I. Provide camber in formwork as required for anticipated deflections due to weight and

pressures of fresh concrete and construction loads.

Page 77: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-3

J. Provide formwork sufficiently tight to prevent leakage of cement paste during concrete placement. Solidly butt joints and provide backup material at joints as required to prevent leakage and fins.

K. Earth Forms:

1. Side forms of footings may be omitted and concrete placed directly against excavation only when requested by the CONTRACTOR and accepted by the IDNR Construction Inspector.

2. When omission of forms is accepted, provide additional concrete 1-inch on each side of the minimum design profiles and dimensions shown.

PART 3 - EXECUTION 3.01 EXAMINATION

A. Examine the substrate and conditions under which work of this section is to be performed, and correct unsatisfactory conditions that would prevent proper and timely completion of the work.

B. Do not proceed until unsatisfactory conditions have been corrected.

3.02 ERECTION

A. General:

1. Construct forms complying with ACI 347, to the exact sizes, shapes, lines, and dimensions shown, and as required to obtain accurate alignment, location, grades, level, and plumb work in finish structures.

2. Provide for openings, offsets, sinkages, keyways, recesses, moldings, reglets, chamfers, blocking, screeds, bulkheads, anchorages, inserts, and other features required.

3. Use selected materials to obtain required finishes. 4. Forms for openings and construction which accommodates installation by other

trades whose materials and products must be fabricated before the opportunity exists to verify the measurements of adjacent construction which effects such installations, shall be accurately sized and located as dimensioned on the Drawings.

5. In the event that deviation from the Drawing dimensions results in problems in the field, CONTRACTOR shall be responsible for resolution of the conditions as approved by the IDNR Construction Inspector, without additional expense to the IDNR.

B. Fabrication:

1. Fabricate forms for easy removal without hammering or prying against concrete

surfaces. 2. Provide crush plates or wrecking plates where stripping may damage cast concrete

surfaces. 3. Provide top forms for inclined surfaces where the slope is too steep to place concrete

with bottom forms only.

Page 78: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-4

4. Kerf wood inserts for forming keyways, reglets, recesses, and the like, to prevent swelling and assure ease of removal.

5. Provide temporary openings where interior area of formwork is inaccessible for cleanout, for inspection before concrete placement, and for placement of concrete.

6. Brace temporary closures and set tightly to temporary openings on forms in as inconspicuous locations as possible, consistent with design requirements.

. Form intersecting planes to provide true, clean-cut corners.

C. Falsework:

1. Erect falsework and support, brace and maintain it to safely support vertical, lateral, and asymmetrical loads applied until such loads can be supported by in-place construction.

2. Construct falsework so that adjustments can be made for take-up and settlement. 3. Provide wedges, jacks, or camber strips to facilitate vertical adjustments. 4. Carefully inspect falsework and formwork during and after concrete placement

operations to determine abnormal deflection or signs of failure; make necessary adjustments to produce work of required dimensions.

D. Forms for Exposed Concrete:

1. Drill forms to suit ties used and to prevent leakage of concrete mortar around tie

holes. 2. Do not splinter forms by driving ties through improperly prepared holes. 3. Provide sharp, clean corners at intersecting planes, without visible edges or offsets. 4. Back joints with extra studs or girts to maintain true, square intersections. 5. Use extra studs, walers, and bracing to prevent objectionable bowing of forms

between studs and to avoid bowed appearance in concrete. 6. Do not use narrow strips of form material that will produce bow. 7. Assemble forms so they may be readily removed without damage to exposed

concrete surfaces.

E. Corner Treatment:

1. Unless shown otherwise, form chamfers with 3/4 inch by 3/4 inch strips, accurately formed and surfaced to produce uniformly straight lines and tight edge joints on exposed concrete.

2. Extend terminal edges to required limit and miter chamfer strips at changes in direction.

F. Control Joints: Locate as directed by IDNR Construction Inspector or as indicated on the

Drawings. G. Provisions for Other Trades:

1. Provide openings in concrete formwork to accommodate work of other trades. 2. Verify size and location of openings, recesses and chases with the trade requiring

such items. 3. Accurately place and securely support items to be built into forms.

Page 79: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-5

H. Cleaning and Tightening:

1. Thoroughly clean forms and adjacent surfaces to receive concrete. 2. Remove chips, wood, sawdust, dirt, and other debris just before concrete is placed. 3. Retighten forms immediately after concrete placement as required to eliminate mortar

leaks. 3.03 INSTALLATION

A. Embedded Items: 1. Set and build into the work anchorage devices and other embedded items required for

other work that is attached to, or supported by, cast-in-place concrete. 2. Use setting drawings, diagrams, instructions and directions provided by suppliers of

the items to be attached thereto. 3. Set edge forms or bulkheads and intermediate screed strips for slabs to obtain

required elevations and contours in the finished slab surface. 4. Provide and secure units to support types of screeds required.

B. Comply with ACI 347 for shoring construction, and as herein specified. Submit a shore

removal and re-shoring schedule and drawings for the IDNR Construction Inspector review before proceeding with this work.

C. Do not proceed until schedule and drawings have been reviewed.

3.04 APPLICATION

A. Coat form contact surfaces with form coating compound before reinforcement is placed. Do not allow excess form coating material to accumulate in the forms or to come in contact with surfaces that will be bonded to fresh concrete. Apply in compliance with manufacturer's instructions.

3.05 FIELD QUALITY CONTROL

A. Concrete shall not be placed in forms until inspected by IDNR Construction Inspector and permission is given to start placing concrete.

3.06 CLEANING

A. Formwork not supporting concrete, such as sides of beams, walls, columns, and similar parts of the work, may be removed after cumulatively curing at not less than 50 degrees F for 24 hours after placing concrete, provided concrete is sufficiently hard to not be damaged by form removal operation, and provided that curing and protection operations are maintained.

B. Formwork supporting weight of concrete, such as beam soffits, joists, slabs, and other

structural elements may not be removed in less than 14 days, and not until concrete has attained design minimum 28-day compressive strength. Determine potential compressive strength of in-place concrete by testing field-cured specimens representative of the concrete location or members, as specified in other sections.

Page 80: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE FORMWORK E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03100-6

C. Form-facing material may be removed four days after placement, only if shores and other vertical supports have been arranged to permit removal of form-facing material without loosening or disturbing shores and supports.

D. Clean and repair surfaces of forms to be reused in the work. Split, frayed, delaminated or

otherwise damaged form-facing material will not be acceptable. Apply new form-coating compound material to concrete contact surfaces as specified for new formwork. When forms are reused for successive concrete placement, thoroughly clean surfaces, remove fins and laitance, and tighten forms to close all joints. Align and secure joints to avoid offsets.

END OF SECTION 03100

Page 81: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE REINFORCEMENT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03200-1

SECTION 03200 CONCRETE REINFORCEMENT

PART 1 - GENERAL 1.01 SUMMARY

A. Section includes all reinforcing steel, steel mesh, and accessories and the installation of

these items for all concrete reinforcement for this project. B. Related Sections: Drawings and General Provisions of the Contract, including the

General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not necessarily limited to, the following:

1. Section 03100 - Concrete Formwork. 2. Section 03300 - Cast-In-Place Concrete.

1.02 REFERENCES

A. Comply with all applicable provisions of the following standards:

1. CRSI "Manual of Standard Practice." 2. ACI 315 "Details and Detailing of Concrete Reinforcement." 3. ACI 318 "Building Code Requirements for Reinforced Concrete."

1.03 SUBMITTALS

A. Submit complete shop drawings of all materials proposed to be furnished and installed under this section in accordance with ACI "Manual of Standard Practice for Detailing Concrete Structure," ACI 315. Show:

1. Bar schedule, stirrup spacing, diagrams of bent bars, and arrangements and

assemblies. 2. Review shop drawings requirements with IDNR Construction Inspector before

ordering shop drawings.

B. Mill Certificates: Submit steel producer's certificates of mill analysis, tensile and bend tests for reinforcing steel.

1.04 DELIVERY, STORAGE AND HANDLING

A. Deliver reinforcement to the job site bundled, tagged, and marked. Use metal tags indicating bar size, lengths, and other information corresponding to markings shown on placement diagrams.

B. Store reinforcement at the job site in a manner to prevent damage and accumulation of

dirt and excessive rust. PART 2 - PRODUCTS 2.01 MATERIALS

Page 82: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE REINFORCEMENT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03200-2

A. Reinforcing steel shall consist of deformed bars of the size called for on the Drawings.

Steel shall conform to ASTM A615 Grade 40. Deformation shall conform to ASTM A305. Mill certificates showing conformity with these requirements shall be furnished to the INDR Construction Inspector for each melt.

B. Wire reinforcement shall conform to ASTM A82. C. Welded wire fabric shall conform to ASTM A185. D. Tie Wire: No. 16 double annealed iron wire. E. Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening

reinforcement in place:

1. Use wire bar-type supports complying with CRSI recommendations, unless otherwise indicated. Do not use wood, brick and other such unacceptable materials.

2. For slabs on grade, use supports with sand plates or horizontal runners where base material will not support chair legs.

3. For exposed-to-view concrete surfaces, where legs of supports are in contact with forms, provide supports with either hot-dip galvanized or plastic protected legs.

PART 3 - EXECUTION 3.01 EXAMINATION

A. Examine the substrate, formwork, and the conditions under which concrete reinforcement is to be placed, and correct conditions that would prevent proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected.

3.02 INSTALLATION

A. Comply with the specified standards for details and methods of reinforcement placement and supports, and as herein specified.

B. Clean reinforcement to remove loose rust and mill scale, earth, and other materials that

reduce or destroy bond with concrete. C. Position, support, and secure reinforcement against displacement by formwork,

construction, or concrete placement operations. Locate and support reinforcing by metal chairs, runners, bolsters, spacers, and hangers, as required.

D. Place reinforcement to obtain the minimum coverages for concrete protection. Arrange,

space, and securely tie bars and bar supports together with 16-gauge wire to hold reinforcement accurately in position during concrete placement operations. Set wire ties so that twisted ends are directed away from exposed concrete surfaces.

Page 83: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CONCRETE REINFORCEMENT E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03200-3

E. Bars are to be tied at all intersections except where spacing is less than one foot in each direction, in which case alternate intersections are to be tied.

F. Install welded wire fabric in lengths as long as practicable. Lap adjoining pieces at least

one full mesh. G. Provide sufficient numbers of supports and of strengths to carry reinforcement. Do not

place reinforcing bars more than 2 inches beyond the last leg of any continuous bar support. Do not use supports as bases for runways for concrete conveying equipment and similar construction loads.

H. Splices: Provide standard reinforcement splices by lapping ends, placing bars in contact,

and tightly wrapped tie wire around bars. I. Galvanized or epoxy coated reinforcement: Weight of reinforcement will be calculated

from the theoretical weight of the nominal sizes and actual lengths of the various sizes of reinforcement shown on the plans. No adjustment in weight will be made for galvanizing or epoxy coating.

END OF SECTION 03200

Page 84: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-1

SECTION 03300 CAST-IN-PLACE CONCRETE

PART 1 - GENERAL 1.01 SUMMARY

A. Section includes all labor, materials, and equipment required to construct all walls, footings, piers and slabs, and all other work or items classified as cast-in-place concrete.

B. All concrete foundations and slabs as shown on the Drawings, as well as all other concrete

not specified elsewhere, are classified as cast-in-place concrete. 1.02 RELATED SECTIONS

A. Drawings and General Provisions of the Contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not necessarily limited to, the following:

1. Section 03100 - Concrete Formwork. 2. Section 03200 - Concrete Reinforcement.

1.03 REFERENCES

A. Codes and Standards: Comply with provisions of following codes, specifications and standards except where more stringent requirements are shown or specified.

1. Uniform Building Code, U.B.C., latest edition. 2. American Concrete Institute (ACI):

a. Manual of Concrete Practice. b. ACI 301 - Specifications for Structural Concrete for Buildings. c. ACI 304 - Recommended Practice for Measuring, Mixing, Transporting, and

Placing Concrete. d. ACI 305 - Hot Weather Concreting. e. ACI 306 - Cold Weather Concreting. f. ACI 308 - Standard Practice for Curing Concrete. g. ACI 318 - Building Code Requirements for Reinforced Concrete.

3. American Society for Testing of Materials (ASTM):

a. ASTM C33 - Standard specification for concrete aggregates. b. ASTM C31 - Making and curing compressive and flexural strength test

specimens in the field. c. ASTM C94 - Standard specification for ready-mixed concrete. d. ASTM C138 - Test for unit weight, yield and air content of concrete. e. ASTM C143 - Test for slump test of Portland cement concrete. f. ASTM C150 - Standard specification for Portland cement. g. ASTM C260 - Standard specification for air-entraining admixture for

concrete.

Page 85: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-2

h. ASTM C309 - Standard specification for liquid membrane-forming compounds for curing concrete.

i. ASTM C494 - Standard specification for chemical admixtures for concrete. j. ASTM D994 - Standard specification for pre-formed expansion joint filler

for concrete. k. ASTM D1850 - Standard specification for concrete joint sealer, cold

application type.

4. Concrete Reinforcing Steel Institute (CRSI), Manual of Standard Practice. 5. State of Iowa Building Code, latest edition.

1.04 SUBMITTALS

A. Product Data: Submit manufacturer's product data with application and installation instructions for proprietary materials and items, accessories, admixtures, patching compounds, water stops, joint systems, curing compounds, dry-shake finish materials, and others as required by IDNR Construction Inspector.

B. Samples: Submit samples of materials specified as requested by IDNR Construction Inspector

including names, sources and descriptions.

C. Quality Control Submittals:

1. Design Data: Submit data on proposed design mixes when trial batch method is used. 2. Test Reports: Employ, when necessary, at CONTRACTOR's expense, a testing

laboratory acceptable to the IDNR Construction Inspector to perform material evaluation tests and submit reports.

3. Material Certificates: Provide materials certificates in lieu of materials laboratory test reports when permitted by IDNR Construction Inspector. Manufacturer and CONTRACTOR, certifying that each material item complies with or exceeds specified requirements, shall sign material certificates.

1.05 QUALITY ASSURANCE

A. During the progress of installation of the work of this section, provide at least one worker who shall be thoroughly familiar with the specified requirements, completely trained and experienced in the necessary skills, and who shall be present at the site and shall direct all work performed under this section.

B. Use adequate numbers of skilled workers to ensure installation in strict accordance with the approved design.

1.06 DELIVERY, STORAGE, AND HANDLING

A Protection: Use all means necessary to protect the materials of this section before, during, and after installation and to protect the work and materials of all other trades.

B. Replacement: In the event of damage, immediately make all repairs and replacements

necessary to the approval of the IDNR Construction Inspector and at no additional cost to the IDNR.

Page 86: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-3

1.07 PROJECT/SITE CONDITIONS

A. Environmental Requirements: Weather conditions shall be observed. No work shall be attempted in frozen conditions without written approval from the IDNR Construction Inspector.

B. Existing Conditions: Review job conditions prior to commencing work. Bring any

discrepancies between existing work and the Drawings and Specifications to the attention of the IDNR Construction Inspector.

PART 2 - PRODUCTS 2.01 MATERIALS

A. Portland Cement: ANSI/ASTM C 150, Type I or Type III high early-strength cements, unless otherwise acceptable to IDNR Construction Inspector.

B. Normal Weight Aggregates: ANSI/ASTM C 33, and as herein specified.

1. Coarse aggregate for concrete shall consist of gravel or crushed stone particles, from

a source approved by IDOT, or combinations of these materials. The aggregate shall meet these requirements:

a. Abrasion loss: Percent of wear, determined in accordance with AASHTO

T96, Grading A or B, shall not exceed 35 for gravel and 50 for other crushed stone.

b. Durability: Coarse aggregate durability shall be a minimum of Class 1. CONTRACTOR, with the IDNR Construction Inspector’s authorization, and at no extra cost, may furnish aggregate of Class 2 or Class 3 durability to the IDNR.

c. Gradation: Coarse aggregate shall meet requirements of IDOT Section 4109, Gradation No. 3, 4, or 5.

d. Maximum size of coarse aggregate: Not more than 3/4-inch minimum clear spacing between reinforcing bars and not more than 1/5th of smallest dimension of slab or member for which concrete is being used. Maximum size of coarse aggregate for un-reinforced slabs shall be 1/3rd of slab thickness.

2. Fine aggregate for concrete shall consist of clean, hard, durable mineral aggregate

particles free from injurious amounts of silt, shale, coal, organic matter, or other deleterious material, and shall be from a source approved by IDOT. Aggregate shall be fine aggregate, meeting the requirements of IDOT Section 4109 for Gradation No. 1.

C. Water: Water for concrete shall be clean, potable and free from injurious amounts of foreign matter.

D. Water-Reducing Admixtures: ANSI/ASTM, C 494, Type A and contain not more than 1

percent chloride ions.

Page 87: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-4

E. Air-Entraining Admixture: ANSI/ASTM C 260, added to mixer in lieu of air-entrained

cement.

F. Liquid Membrane-Forming Curing Compound: Liquid type membrane-forming curing compound complying with ANSI/ASTM C 309, Type I, Class A unless other type acceptable to IDNR Construction Inspector.

1. Curing compound shall form a continuous unbroken membrane which shall adhere to

moist concrete and which will not disintegrate, check or peel from the surface, or show signs of such deterioration within 30 days after application under actual working conditions.

2. Compound shall be sufficiently transparent and free from color so there will be no permanent change in the color of the concrete.

3. Compound shall contain, however, a temporary dye of sufficient color to make the membrane clearly visible for a period of at least 4 hours after application.

2.02 EQUIPMENT

A. Batching, Mixing, and Delivery Equipment: Use transit-mixed concrete from approved batching and mixing plant. Batch, mix, and transport concrete to site is accordance with ANSI/ASTM 94.

B. When air temperature is between 85 and 90 degrees F, reduce mixing and delivery time from

1-1/2 hours to 75 minutes. When air temperature is above 90 degrees F, reduce mixing and delivery time to 60 minutes.

2.03 ACCESSORIES

A. Pre-formed Joint Filler: ASTM D994 and as herein specified. Pre-formed non-extruding resilient material, 1/2-inch wide and of the depth required to bring surface to within 1/2-inch of finished surface.

B. Joint Sealer: ASTM D-1850 Concrete Joint Sealer, cold-application type. C. Vapor Barrier: Under slabs on ground, 6-mil polyethylene film, when required by the

Drawings. D. Storage: Store all cement materials in weather-tight enclosure, clear of ground, and protected

from weather with suitable covering. E. Embedded Items: Verify and coordinate embedded items furnished by other trades. F. Keyways and/or Expansion Tubes: IDOT Section 4191 or as required by the Drawings.

G. Admixtures:

1. Use air-entraining admixture in exterior exposed concrete, unless otherwise indicated as determined by ANSI/ASTM C 138.

Page 88: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-5

2. Add air-entraining admixture at manufacturer's prescribed rate to result in concrete at point of placement having air content within following limits (for concrete structures and slabs exposed to freezing and thawing or subjected to hydraulic pressure):

Maximum Size Aggregate Amount of Air (percent)

1-1/2" or 2" 5 (+/-1)

3/4" or 1” 6 (+/-1)

3/8" or 1/2" 7-1/2 (+/-1)

2.04 MIXES

A. Prepare design mixes for each type and strength of concrete by either laboratory trial batch or field experience methods as specified in ACI 301. If trial batch method used, use an independent testing facility acceptable to IDNR Construction Inspector for preparing and reporting proposed mix designs. Testing facility shall not be the same as used for field quality control testing unless otherwise acceptable to IDNR Construction Inspector.

B. Design mixes to provide normal weight concrete with the following properties:

1. 4,000-psi 28-day compressive strength. 2. 624 lbs cement per cubic yard minimum. 3. W/C ratio, 0.488 maximum.

C. Consistency: Quantity of water required for the proper consistency of concrete shall be determined by the slump test in accordance with ANSI/ASTM C143. Slump allowances shall be as follows:

1. Vertical Wall Sections, Columns: Maximum slump, 4 inches, plus or minus 1-inch

tolerance. 2. Footings, Beams, Slabs: Maximum slump, 3 inches, plus or minus 1-inch tolerance.

PART 3 - EXECUTION 3.01 EXAMINATION

A. Coordinate the installation of joint materials and moisture barriers with placement of forms and reinforcing steel.

B. Before placing concrete, inspect and complete formwork installation, reinforcing steel, and

items to be embedded or cast-in. Notify other crafts to permit installation of their work; cooperate with other trades in setting such work. Moisten wood forms immediately before placing concrete where form coatings are not used.

3.02 PREPARATION

A. Drain and pump all water from excavations, forms, and any locations where concrete is to be placed. Bottom of excavations shall be undisturbed earth free of frost or debris, level and compacted.

Page 89: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-6

B. Do not place any concrete until the IDNR Construction Inspector has inspected and approved

forms and soil conditions, and until reinforcing, sleeves, and embedded items have been placed. Clean all dirt and debris from transporting equipment. Clean reinforcement of all foreign matter. Clean forms and oil or wet (except in freezing conditions) surfaces.

C. Compact, level, and dampen base fill material under slabs on grade. Prior to placing

concrete, install polyethylene vapor barrier under interior slabs. Do not puncture or otherwise damage vapor barrier or membrane waterproofing.

D. Transport concrete to prevent separation of materials in accordance with ACI practices. Do

not add water to concrete during transporting. Handle from mixer to point of placement with carts, buggies, or conveyors. Do not dump concrete from mixer or from transporting equipment with a free fall of more than three feet. Deposit concrete as nearly to its final position as possible.

E. Clean transporting equipment at frequent intervals during placement. Do not use partially

hardened or contaminated concrete. 3.03 PLACEMENT OF CONCRETE

A. Place concrete in accordance with ACI 304 "Recommended practice for measuring, mixing, transporting and placing concrete" and as herein specified.

B. Deposit concrete continuously or in layers of such thickness that no concrete will be placed

on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as herein specified. Deposit concrete as nearly as practicable to its final location to avoid segregation.

C. Work concrete into corners and around reinforcement. Machine vibrate sufficiently to insure

thorough compaction and complete embedment of reinforcing. Stop placement at point of no shear, or where directed, and erect tight, plumb dams through forms.

D. Place concrete between construction joints in one continuous operation. Locate construction

joints in slabs under partitions. Brush on neat cement when pouring against hardened concrete.

E. Placing Concrete in Forms:

1. Deposit concrete in forms in horizontal layers not deeper than 24 inches and in a manner to avoid inclined construction joints.

2. Where placement consists of several layers, place each layer while preceding layer is still plastic to avoid cold joints.

3. Consolidate placed concrete by mechanical vibrating equipment supplemented by hand-spading, rodding or tamping. Use equipment and procedures for consolidation of concrete in accordance with ACI recommended practices.

4. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations not farther than visible effectiveness of machine.

5. Place vibrators to rapidly penetrate placed layer and at least 6-inches into preceding layer.

Page 90: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-7

6. Do not insert vibrators into lower layers of concrete that have begun to set. 7. At each insertion, limit duration of vibration to time necessary to consolidate

concrete and complete embedment of reinforcement and other embedded items without causing segregation of mix.

E. Placing Concrete Slabs:

1. Deposit and consolidate concrete slabs in a continuous operation, within limits of construction joints, until the placing of a panel or section is completed.

2. Consolidate concrete during placing operations so that concrete is thoroughly worked around reinforcement and other embedded items and into corners.

3. Bring slab surfaces to correct level with straight edge and strike off. Use bull floats or darbies to smooth surface, free of humps or hollows. Do not disturb slab surfaces prior to beginning finishing operations.

4. Maintain reinforcing in proper position during concrete placement operations.

F. Cold Weather Placing:

1. Protect concrete work from physical damage or reduced strength which could be caused by frost, freezing actions, or low temperatures, in compliance with ACI 306, "Cold Weather Concreting," and as herein specified.

2. When air temperature has fallen to or is expected to fall below 40 degrees F, uniformly heat water and aggregates before mixing to obtain a concrete mixture temperature of not less than 40 degrees F and not more than 80 degrees F at point of placement, and maintain minimum temperature over the entire work for no less than 72 hours.

a. Do not use frozen materials or materials containing ice or snow. Do not place

concrete on frozen subgrade or on subgrade containing frozen materials. b. Do not use calcium chloride, salt and other materials containing antifreeze

agents or chemical accelerators unless otherwise accepted in mix designs. G. Hot Weather Placing:

1. When hot weather conditions exist that would seriously impair quality and strength of concrete, place concrete in compliance with ACI 305, "Hot Weather Concreting," and as herein specified.

2. Cool ingredients before mixing to maintain concrete temperature at time of placement below 90 degrees F. Mixing water may be chilled, or chopped ice may be used to control temperature provided water equivalent of ice is calculated in total amount of mixing water.

3. Cover reinforcing steel with water-soaked burlap if it becomes too hot, so that steel temperature will not exceed the ambient air temperature immediately before embedment in concrete.

4. Wet forms thoroughly before placing concrete. 5. Use water-reducing retarding admixture (Type A) when required by high

temperatures, low humidity, or other adverse placing conditions.

H. Construction Joints: CONTRACTOR to submit placement and type of construction joints to IDNR Construction Inspector for review prior to placement of any concrete on the project.

Page 91: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-8

I. Expansion Joints:

1. Install expansion joint filler where interior slabs abut exterior walls, interior bearing walls and columns, at perimeter of concrete equipment pads, and other necessary locations as determined by the IDNR.

2. Omit expansion joint filler and install 15 pound felt, centered below doors, to break bond at exterior doors with concrete platforms, unless otherwise shown on the Drawings.

J. Control Joints:

1. Cut control joints in all exposed concrete slabs on grade, as directed by the Inspector. 2. Locate in a uniform pattern throughout parking areas. 3. Verify location and cut to depth of 1/6th of slab thickness with minimum of 3/4-inch

depth. 4. Cut with carborundum saw, approximately 6 to 24 hours after placing concrete and

when a minimum amount of raveling occurs in concrete. 5. On exterior walks, score with 1/4-inch by 1-inch deep control joints. Use straight

edge guide when scoring joints. Where required depth of control joint cannot be made by scoring, cut joints with carborundum saw.

3.04 CONCRETE FINISHING

A. Finish on Formed Surfaces:

1. All finished or formed surfaces shall conform accurately to the shape, alignment, grades and sections as shown on the Drawings.

2. Surfaces shall be free from fins, bulges, ridges, offsets, honeycombing or roughness, and shall present a finished, continuous, hard surface. All sharp angles, where required, shall be rounded or beveled.

3. Rough Form Finish:

a. Provide as-cast rough form finish to formed concrete surfaces that are to be concealed in the finish work or by any other construction.

b. Standard rough form finish shall be the concrete surface having the texture imparted by the form facing material used, with tie holes and defective areas repaired and patched, and all fins and other projections exceeding 1/4-inch in height rubbed down or chipped off.

4. Smooth Form Finish:

a. Provide as-cast smooth form finish for formed concrete surfaces that are to

be exposed to view, or that are to be covered with a coating material other than cement plaster applied directly to the concrete.

b. Produce smooth form finish by selecting form material to impart a smooth, hard, uniform texture and arranging them orderly and symmetrically with a minimum of seams.

c. Repair and patch defective areas with all fins and other projections completely removed and smoothed.

Page 92: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-9

B. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces occurring adjacent to formed surfaces, strike off smooth and finish with a smooth troweled finish.

C. Slab and Floor Finish:

1. For all floor and flat roof surfaces and all exterior concrete floor, sidewalk and flat slab surfaces, CONTRACTOR shall be particularly careful to provide an adequate slope to the drains or to suitable points of disposal.

2. Direction of slope and the amount of crowning generally are shown on the Drawings. Otherwise they shall be as prescribed by the IDNR Construction Inspector. Dry topping will not be allowed on any of the finishes.

3. Scratch Finish:

a. Apply scratch finish to monolithic slab surfaces that are to receive concrete floor topping or mortar setting beds for tile and other bonded applied cementitious-finish flooring material.

b. After placing slabs, plane the surface to a tolerance not exceeding 1/4- inch in 24 inches when tested with a straight edge.

c. Slope surfaces uniformly to drains where required. d. After leveling, roughen the surface before the final set by using stiff broom

brush or rake.

4. Float Finish:

a. Apply float finish to monolithic slab surfaces that are to receive trowel finish and other finishes hereinafter specified, and to slab surfaces which are to be covered with insulation, and as otherwise shown on the Drawings or in the schedules.

b. After placing concrete slabs, do not work the surface further until ready for floating.

c. Begin floating when the surface water has disappeared and when the concrete has stiffened sufficiently to permit operation of a power-driven float, hand float, or both.

d. Consolidate the surface with power-driven floats, or by hand floating if area is small or inaccessible to power units.

e. Check and level the surface plane to a tolerance not exceeding 1/4-inch in 10 feet when tested with a 10 foot straight edge placed on the surface at not less than 2 different angles.

f. Cut down high spots and fill low spots. g. Uniformly slope surfaces to drains where required. h. Immediately after leveling, re-float the surface to a uniform, smooth,

granular texture. 5. Trowel Finish:

a. Apply trowel finish to monolithic slab surfaces that are to be exposed to

view, unless otherwise shown, and to slab surfaces that are to be covered with resilient flooring, carpeting, paint, or other thin-film finish coating system.

Page 93: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-10

b. After floating, begin the first trowel finish operation using a power-driven trowel. Begin final troweling when the surface produces a ringing sound as the trowel is moved over the surface.

c. Consolidate the concrete surface by the final hand troweling operation, free from trowel marks, uniform in texture and appearance, and with a surface plane tolerance not exceeding 1/8-inch in 10 feet when tested with a 10 foot straight edge.

d. Grind smooth those surface defects that would telegraph through applied floor covering system.

6. Coordinate the required finish with the IDNR Construction Inspector prior to the

application. 3.05 CONCRETE CURING

A. Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

B. Start initial curing as soon as free water has disappeared from concrete surface after placing

and finishing. Weather permitting, keep continuously moist for not less than 7 days. C. Begin final curing procedures immediately following initial curing and before concrete has

dried. Continue final curing for at least 7 days in accordance with ACI 308, "Standard Practice for Curing Concrete." Avoid rapid drying at end of final curing period.

D. Curing Method:

1. Perform curing of concrete by moist curing, by moisture-retaining cover curing, by curing compound, and by combinations thereof as herein specified.

2. Provide moisture curing by the following methods:

a. Keep concrete surface continuously wet by covering with water. b. Continuous water-fog spray. c. Covering concrete surface with specified absorbent cover, thoroughly

saturating cover with water and keeping continuously wet. d. Place absorbent cover to provide coverage of concrete surfaces and edges,

with 4-inch lap over adjacent absorbent cover.

3. Provide moisture-cover curing as follows:

a. Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width with sides and ends lapped at least 3 inches and sealed by waterproof tape or adhesive.

b. Immediately repair any holes and tears during curing period using cover material and waterproof tape.

4. Provide curing compounds for slabs as follows:

a. Apply specified curing and sealing compound to concrete slabs as soon as final finishing operations are complete (within 2 hours).

Page 94: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-11

b. Apply uniformly in continuous operation by power-spray or roller in accordance with manufacturer's directions.

c. Re-coat areas subjected to heavy rainfall within 3 hours after initial application.

d. Maintain continuity of coating and repair damage during curing period.

5. Do not use membrane curing compounds on surfaces which are to be covered with coating material applied directly to concrete, liquid floor hardener, waterproofing, dampproofing, membrane roofing, flooring, painting, and other coatings and finish materials, unless otherwise acceptable to the coating manufacturer.

3.06 MISCELLANEOUS CONCRETE ITEMS

A. Filling-In:

1. Fill-in holes and openings left in concrete structures for passage of work by other trades, unless otherwise shown or directed, after work of other trades is in place.

2. Mix, place, and cure concrete as herein specified to blend with in-place construction. 3. Provide other miscellaneous concrete filling shown or required to complete work.

B. Equipment Bases and Foundations:

1. Provide machine and equipment bases and foundations as shown on the Drawings or required for the machine and equipment actually furnished.

2. Set anchor bolts for machines and equipment to template, at correct elevations, complying with certified diagrams or templates of the manufacturer furnishing the machines and equipment.

3. Provide isolation joints surrounding bases where indicated or required. 3.07 FIELD QUALITY CONTROL - TEST OF MATERIALS AND INSTALLED WORK

A. Materials and installed work may require testing and re-testing, as directed by IDNR Construction Inspector, at any time during progress of work.

B. Allow free access to material stockpiles and facilities. C. Tests, not specifically indicated to be done at IDNR's expense, including re-testing of rejected

materials and installed work, shall be done at CONTRACTOR's expense.

D. Slump Tests:

1. Take 1 slump test for each 10 cubic yards, or as directed by IDNR Construction Inspector, of concrete placed at 1 operation, in accordance with ASTM C 143.

2. Keep job record of test results and location. E. Control Tests:

1. During placement of concrete, take 3 standard 6-inch diameter test cylinders in accordance with ACI318-63 and ASTM C31 for each type of concrete used.

2. Test 1 at 7 days and 1 at 28 days.

Page 95: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 CAST-IN-PLACE CONCRETE E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 03300-12

3. Take 1 set for every 20 cubic yards and any fraction with a minimum of 1 set of 3 cylinders for each day's pour.

4. Tag cylinders to show date and location of test cylinder. 5. Have compressive strength tests made by independent laboratory and results sent

directly to IDNR Construction Inspector. 6. Hold remaining cylinders in case of breakage. 7. Should retention at job site delay testing beyond 7 days, a 14 day test is acceptable. 8. Keep test cylinders shaded and damp until sent to laboratory.

3.08 REMEDIAL WORK

A. Reinforce or replace deficient work as directed by the IDNR Construction Inspector and at no additional cost to the IDNR.

B. Repair defective areas and fill form-tie holes and similar defects in accordance with ACI 301.

Where, in the opinion of the DNR Construction Inspector, surface defects such as honeycomb occur, repair the defective areas as directed by the IDNR Construction Inspector.

3.09 PROTECTION OF CONCRETE CONSTRUCTION

A. All surfaces shall be protected against injury. During the first 72 hours after placing the concrete, any wheeling, working or walking on the concrete shall not be permitted. All slabs subject to wear shall be covered with a layer of sand or other suitable material as soon as the concrete has set. Sisal-craft paper or other similar tough waterproof paper may also be used, provided all joints between adjacent strips of paper are carefully sealed. This does not alter the requirements for proper curing.

B. Do not place concrete slabs or top surfaces of walls during rain unless acceptable protective

shelter is provided; and during such weather, all concrete placed within the preceding 12 hours shall be protected with waterproof canvas or other suitable coverings. These shall be provided and kept ready at hand.

C. All concrete construction shall be protected from excessive loading. Installation of

mechanical and electrical equipment shall be accomplished by employing shores, bearing plates, frames, cranes and temporary beams.

END OF SECTION 03300

Page 96: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMERSIBLE SEWAGE PUMPS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 11315-1

SECTION 11315 SUBMERSIBLE SEWAGE PUMPS

PART 1 - GENERAL 1.01 WORK INCLUDES A. Construction of a new duplex submersible sanitary sewage pumping station at EB. Lyons

Interpretive Center, Dubuque.

B. Contractor shall furnish and install: One pumping station with duplex non-clog pumps in a fiberglass wetwell and valve

pit constructed within precast concrete components. C. Accessory items provided include: 1. Submersible pumps with all accessories. 2. Pump bases, connecting piping, supports, guide-rails, quick disconnects, equipment

hooks and other station accessories. 3. Level controls and cables. 4. Access covers for the wet wells and the valve pits. 5. Piping, valves, gauges, and supports. 6. Provide manufacturer's representative for start-up services. Instruct IDNR personnel

in the operation of the stations. 7. Electrical controls, panels and accessories for each station. 1.02 RELATED WORK A. Specified elsewhere: 1. Section 02605 - Manholes. 2. Section 16000 – Basic Electrical Materials and Methods. 1.03 TESTS A. Contractor shall arrange for all equipment manufacturers to provide factory-trained qualified

service technicians to oversee or inspect their complete equipment installation to assure that it is installed in accordance with their recommendations, make adjustments necessary to place the system in trouble-free operation, oversee initial start-up of the equipment and instruct the IDNR’s personnel in the correct care and operation of the equipment furnished. This shall not alleviate the Contractor’s responsibility for installing a complete working system. Manufacturer’s representative shall submit a report verifying the complete and proper installation of the pump controls prior to pump start-up.

1.04 SUBMITTALS A. Contractor shall furnish for review complete equipment Shop Drawings before installing any

equipment. Drawings shall be provided by the equipment manufacturer and shall show all dimensions and details for correct installation of all components of the pump stations and valve pits, with modifications for this project clearly marked. Shop drawing submittals must contain pump manufacturer's equipment details, system layout, control panel layouts, equipment installation and electric schematic drawings, as well as installation instructions for the pumps, including templates for proper orientation of the pumps, access covers, and other

Page 97: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMERSIBLE SEWAGE PUMPS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 11315-2

equipment within the station. B. Contractor must supply the IDNR with operating and maintenance literature from the pump

manufacturer. Standard Submittal Drawings, Operating & Maintenance Instruction Manuals and Parts Lists are required. Standard submittals will consist of at least the following items:

1. Pump outline drawings. 2. Control data. 3. Typical installation guides. 4. Technical manuals. 5. Parts lists. C. Contractor shall submit complete wiring diagrams, internal and external panel layouts,

construction details, component list, spare parts list, product data for each component, detailed description of operation, warranty information, installation instructions and operation and maintenance information. Wiring diagrams shall include wire sizes, terminal identification, field connections, and circuit identification. Programmable controllers are not allowed on this project.

1.05 WARRANTY A. Contractor shall guarantee that the equipment furnished shall be properly installed, and when

properly operated, shall perform the duty for which it is intended. Contractor shall guarantee all materials, workmanship, and completed installation and shall, at his own expense, furnish and replace any part or parts that may prove defective in material, equipment or workmanship within 2 years from the date of startup of the pumps. Pump warranty shall be in printed form and apply to all similar units.

1.06 QUALITY ASSURANCE A. Contractor shall furnish and install complete and working systems to perform the intended

purposes as required by the Drawings and these Specifications. Contractor shall be responsible for all details which may be necessary to properly install, adjust and place into operation the complete installation, and shall include the costs of all such details in the Bid.

B. Contractor is responsible to ascertain that the equipment comprising any system is installed

correctly, operates properly, and that the system functions as intended. C. For the purposes of standardization, all of the equipment for the systems shall be furnished by

a single manufacturer except as noted or otherwise authorized by the IDNR. Fabricated assemblies shall be shipped in the largest convenient sections permitted by carrier regulations, and adequately match marked for proper assembly.

PART 2 - PRODUCTS 2.01 GRINDER PUMP STATIONS

A. Furnish and install a grinder pump station consisting of two grinder pumps and motors, basin assembly, internal discharge piping, check valves, shut-off valves, quick-disconnect slide rail systems, lift chains, three level controls, stainless steel level control bracket, junction box,

Page 98: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMERSIBLE SEWAGE PUMPS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 11315-3

inlet fitting, and control panel.

B. Contractor shall furnish and install submersible wastewater pumps as shown in the Pump Performance Table.

PUMP PERFORMANCE TABLE

Description Location No. of

Units Total

Design Head (ft)

Voltage Phase Capacity at Design (gpm)

Motor 3 phase Explosion

proof Min. HP Max.

rpm Grinder Pump

EB Lyons 2 50 230 3 60 3.8 3330

C. Pumps: 1. Pumps shall be Flygt submersible Grinder pump model MP3068 216 impeller or

approved equal. This pump will deliver approx. 60 gpm @ 50 TDH, at 3330 rpm. An air filled 3.8hp, 290-volt, 3 phase explosion proof motor will drive the pump. FLS and 30’ of cable.

D. Accessories:

Two (2) flygt 2” discharge elbows Two (2) ¾” SS upper guide bar bracket Two (2) chain grip Three (3) floats Two (2) mini CAS for thermal and moisture monitoring (in panel) One (1) duplex control panel with VFD for phase conversion. The VFD and the

pumps will be from the same One (1) Fiberglass Basin, 5’X10’, ¾” SS guide rail, piping, Aluminum access hatch

w/vent connection & PVC 2” screened vent assembly, 304 SS nipples and fittings, Dual discharges 60” from top of wetwell, Anti-floatflange, CI inlet hub.

One (1) NEMA 4X Float operation with intrinsically safe relays, top mounted red lexan alarm light.

Anchor bolts, Junction box, valves, gauges, piping as shown in the drawings and incidental fittings for a complete operational lift station and valve pit.

a) Discharge Base Elbow. Discharge elbow designed to mount directly to the sump

floor shall be supplied for each pump. Design shall be such that the pump to discharge connection is made without the need for any nuts, bolts or gaskets. Base elbow shall also anchor and align the two, 2” guide rails.

b) Connecting Flange. A cast iron connecting flange/rail bracket shall be mounted on each pump discharge. It shall have a machined mating flange, which matches the base elbow discharge connection. Dealing of this discharge connection shall be

Page 99: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMERSIBLE SEWAGE PUMPS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 11315-4

accomplished by a simple linear downward motion of the pump culminating with the entire weight of the pumping unit supported entirely by the base elbow.

c) Lifting Chain/Cable. Each pumping unit shall be provided with a lifting chain or

cable, and be of sufficient length to extend from the pump to the top of the wet-well. Access frame shall provide a hook to attach the chain or cable when not in use. Lifting chain or cable shall be sized to the pump weight.

d) Float mounting bracket. Float-mounting bracket shall be provided with strain relief

that support and hold the level control cords. Continuous cords are to run from pump(s) and level controls to a control panel or junction box. No splices shall be made in the wiring. Bracket shall be fabricated from stainless steel or coated steel for corrosion resistance. Float bracket shall be attached to the access frame with 300 series stainless steel fasteners. Dielectric spacer should be installed when bolting to an aluminum access frame.

e) Pultruded Guide Rail. Dual rail guide design keeps the pump in proper alignment

with the stationary discharge piping. Rails shall be 2” galvanized steel pipe which bolt directly to the base elbow and to the access frame at the top of the wet-well by an upper guide rail bracket.

f) Level Controls: Pump on, off and alarm levels shall be controlled by three mercury

tube float switches. Switches shall be sealed in a corrosion-resistant polypropylene housing with a minimum of 18 gauge, 2-wire, SOW/A jacketed cable. Cable shall be of sufficient length to reach the junction box with no splices. Level controls shall be suspended from a stainless steel bracket so that adjustment or replacement may be done without the use of any tools. Level controls shall be UL/CSA listed.

g) Piping shall include one check valve, one plug valve, and all the necessary gaskets,

straight pipe, brackets, elbows, tees, and fittings. Where piping passes through a wall, a mechanical seal shall be used to make a watertight joint.

h) Controls for the pump shall be contained in a pad mounted aluminum or stainless

steel enclosure meeting NEMA 4X requirements with a hinged door and neoprene gasket. Enclosure shall be pad mounted large single door public works enclosure and manufactured by APX Technologies; or equivalent. Enclosure shall be natural aluminum, stainless steel, or painted white.

M. Provide duplex control panel. Enclosure shall have provisions for padlocking. Nameplate

shall be permanently affixed to the panel and include the model number, voltage, phase, hertz, ampere rating and horsepower rating. Warning label against electric shock shall be permanently affixed to the outer door. Provide the following components:

1. Main circuit breaker, breaker for each motor, and auxiliary 20A single pole breaker for convenience outlet.

2. IEC magnetic starter with a quick trip overload block for each pump. 3 Green run light for each pump. 4. H-O-A switch for each pump. 5. Alarm switch for on-off and test. 6. Vandal resistant outside flashing red alarm light. 7. An alternator relay to alternate pumps on each successive cycle.

Page 100: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 SUBMERSIBLE SEWAGE PUMPS E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 11315-5

8. Terminal strip for connecting pumps and controls. 9. Elapsed Time Meters: Displays hours and tenths, one required per pump. 10. Alarm bell with silence switch. 11. Condensation heater 12. Convenience outlet: Duplex receptacle mounted in box, GFCI protected. 13. Acknowledge alarm circuit, including alarm bell and exterior bell silence and

acknowledge button. 14. Lightning Arrester.

N. Incoming power shall be 230 volt, single phase, 60 Hz service.

2.02 Testing shall be required and include the following: a. Pumps shall be visually inspected to confirm Hp, voltage, phase and hertz

comply with the specifications. b. Motor shall be hi-potted per IEEE Standard 43 to test for moisture content

and/or insulation defects. c. Pump shall be allowed to run dry to check for proper rotation.

Page 101: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-1

SECTION 16000 ELECTRICAL

PART 1 - GENERAL

1.01 SUMMARY:

A. Section Includes: Providing all material, tools, equipment, and labor necessary to complete the following:

1. Provide complete and functioning electrical power transmission, services and systems as shown on the Drawings, as specified herein, and as required for a complete and proper installation of a campground electrical system including, but not limited to:

a. Electrical service, complete, of size, voltage and type indicated or required to point of connection with utility company's equipment; all conductors shall be copper.

b. Service entrance with metering equipment and feed switches or breakers.

c. Main distribution panels and distribution panels or boards as needed.

d. Complete feeder system, underground, from the main distribution panels to individual campsite power outlets and branch panels.

e. Complete branch circuit wiring for receptacles, junction boxes, area lighting, and similar uses.

f. Exterior lighting fixtures, lamps and poles, terminal and splice boxes, campsite power outlets, switches, receptacles, controls, and motors, motor starters, detectable tape, and similar items.

g. Hangers, anchors, sleeves, bushings, conduits, conduit risers and elbows, supports for fixtures, equipment mounting structures, transformer pads and other electrical materials and equipment in association therewith.

h. Trenching and backfilling for underground electrical installation not specified elsewhere.

i. Connections to distribution panels in Buildings or existing utility company equipment, as shown on the Drawings.

2. The omission of direct reference to an essential part, the necessity or use of which is reasonably implied shall not release the Contractor from providing the same.

3. Inspect the site as necessary to become familiar with all existing conditions affecting the performance of the work under this Contract. Extras will not be allowed for failure to do so.

B. Related Sections: Drawings and General Provisions of the contract, including the General Covenants and Provisions, Supplementary Covenants and Provisions and General Requirements as well as, but not necessarily limited to, the following:

Page 102: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-2

Section 02220 Trenching, Backfilling and Compacting

C. Certain material may be provided by others to be installed under this contract. Coordinate with DNR Construction Inspector, utility company and other slated to provide material to be installed as part of this contract.

1.02 REFERENCES:

A. Codes, Ordinances, and Standards: Comply with all applicable codes and regulations of the following:

1. National Electric Code, latest edition;

2. Local Utility Company Regulations;

3. Underwriter's Laboratories.

1.03 SYSTEM DESCRIPTION:

A. Power system shall be a 120/240 volt, 60 cycle, single phase 3-wire solid neutral, underground system.

1. Ground circuits at the transformer/main distribution panel with a No.6 AWG continuous copper grounding conductor type THW routed with the circuit conductors.

B. Verify the exact location of primary service, secondary service, and transformers at the job site.

C. Underground Service Entrance: Unless otherwise specified elsewhere conductors will be continuous direct burial cable, USE or UF neoprene jacket insulated and moisture resistant non-metallic outer covering.

1. Minimum burial depth 24 inches.

2. Furnish and install number and size of conductors shown or as required by N.E.C.

a. All conductors shall be copper.

1.04 SUBMITTALS:

A. Submit shop drawings, diagrams, and product information, material lists and manufacturer's specifications to Project Engineer before obtaining material, including but not necessarily limited to the following:

1. Panelboards, power outlets, and equipment.

2. Each specialized installation or system, including assembly or coordination Drawings.

C. Product Data, Submit:

1. Materials list of items proposed to be provided under this section;

Page 103: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-3

2. Manufacturers' specifications and other data needed to prove compliance with the specified requirements;

3. Manufacturers' recommended installation procedures which, when approved by the Project Engineer, will become the basis for accepting or rejecting actual installation procedures used on the work.

D. Manual: Upon completion of this portion of the work, and as a condition of its acceptance, deliver to the Project Engineer two copies of an operation and maintenance manual, which shall include:

1. Copy of the approved Record Documents for this portion of the work;

a. Shop drawings, diagrams, material lists, and product information.

b. As-built drawings showing any changes in construction, additions and/or deletions from the Project Engineer's Drawings.

2. Copies of all circuit directories;

3. Copies of all warranties and guarantees.

1.05 QUALITY ASSURANCE:

A. Qualification of Installers: For the actual fabrication, installation, and testing of the work in this section, use only thoroughly trained, licensed, experienced workers completely familiar with the items required and with the manufacturer recommended methods of installation.

1. In acceptance or rejection of installed work, no allowance will be made for lack of skill on part of workers.

B. Provide only new materials of grade and quality specified. Unless otherwise approved or specified, provide only materials, equipment, devices, fittings, etc., of U.S. manufacture.

C. Except as otherwise indicated, comply with the provisions of NEC and the standards by NEMA for electrical components.

1. Provide UL listed and labeled products where applicable.

1.06 DELIVERY, STORAGE, AND HANDLING:

A. Protection: Use all means necessary to protect the materials of this section before, during, and after installation and to protect the work and materials of all other trades.

B. Replacements: In the event of damage, immediately make all repairs and replacements necessary to the approval of the Project Engineer/DNR Construction Inspector and at no additional cost to the Owner.

1.07 SEQUENCING AND SCHEDULING:

Page 104: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-4

A. Coordination of Work: Plan all work so that it proceeds with a minimum of interference with the work of other trades.

1. Coordinate all openings, special frames and sleeves required in the building construction for electrical work with the construction work of others both within and outside of this Contract.

B. Cooperation with Other Trades: Coordinate the work to be performed in compliance with the requirements of other trades and afford other trades reasonable opportunity for the execution of their work.

1. Coordinate this work shall with the work of other trades at such time and in such a manner as not to delay or interfere with their work.

2. Examine the Contract Documents to determine the requirements of other similar trades.

1.08 WARRANTY:

A. Guarantee the entire installation, including every part and every specialized system, to the exception of lamps, from the standpoint of workmanship and material for one year after formal acceptance by the Project Engineer.

B. Correct any defects becoming apparent during the guarantee period at no cost to the Owner.

C. Do not construe this guarantee requirements as obligating the Contractor to make repair or replacements for equipment failure as a result of improper operation or maintenance by the Owner.

1.09 MAINTENANCE STOCKS:

A. Provide 5 percent excess over the required amount of spring-loaded nuts, washers, conduit clamps, and other specialized fasteners for mounting electrical equipment.

1. Store where directed by the DNR Construction Inspector.

B. Prior to the acceptance of the equipment with plug-in receptacles and ground fault interrupters, provide two GFI testers to be used by the DNR for testing and remain the property of the DNR thereafter.

PART 2 - PRODUCTS

2.01 MANUFACTURERS:

A. Subject to compliance with requirements, manufacturer offering electrical material and components which may be incorporated in the work include, but are not limited to, the following:

1. Square D 2. General Electric

Page 105: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-5

3. ITE 4. Westinghouse 5. Hubbell 6. Bryant 7. Arrow-Hart

2.02 MATERIALS:

A. Provide only materials that are new, of the type and quality specified.

1. Where Underwriter's Laboratories, Inc. have established standards for such materials, provide only materials bearing the UL label.

B. Provide only copper conductors as part of permanent installation within this project, from connection with the power company's equipment to connection to fixtures, receptacles or other devices or appliance as specified herein.

1. The Project Engineer will not approve others for use anywhere within this project at any location.

2. Remove any wire or cable used on this project which does not meet this requirement and replace at no cost to the Owner.

C. Temporary Power:

1. In addition to providing temporary power, provide and pay the costs for installing permanent electrical meter or meters as required;

2. When permanent metering is in place and connected, the Owner will pay the costs for electrical power charged against the meter or meters.

2.03 COMPONENTS:

A. Distribution Panels:

1. Circuit breaker type with single main disconnect, solid neutral with voltage and main bus rating equal to or exceeding rating on panel schedule.

2. Boxes: Code gauge steel, galvanized, with surface cover.

3. Trim: Code gauge steel with grey enamel finish and door, complete with directory of circuits and key locked.

4. Branch circuit breakers: Plug-in or bolt-in, of rating and poles indicated, with thermal-magnetic tripping mechanism at each pole, with quick-make and quick-break action, toggle type operating mechanism.

a. Provide multiple pole breakers with a common trip.

b. Provide breakers with ground fault protection for outlets as required by Code, except for outlets requiring ground fault interruption as indicated on the

Page 106: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-6

Drawings for which separate and individual ground fault protection and reset features will be provided integral to the outlet.

5. Provide panels, for 200-Amp or less and 120/240 volt service, with amperage indicated, as manufactured by, but not limited to, one of the following:

a. Square D b. General Electric c. ITE d. Westinghouse

6. Provide main distribution panels: For 225-Amp, 400-Amp, or 600-Amp, and 120/240 volt service, as shown on the Drawings, provide main distribution panels with solid neutral and equipment ground bar installed, dead-front enclosed board assembly, NEMA type 3R rain-proof cabinet with concealed door hinge, gasketed door, 3-point vault-type locking mechanism with chrome finish padlock handle, with rust inhibiting primer and a finish coat of standard grey baked enamel, as manufactured by, but not limited to one of the following:

a. Square D b. General Electric c. Others as approved by the Project Engineer

7. U.L. approved and N.E.C. rated.

B. Wiring Devices:

1. Receptacles: Specification grade, duplex, 3-pole grounding type, amperage as shown, 125 V AC as manufactured by, but not limited to, one of the following:

a. Hubbell b. Bryant c. Leviton

C. Fittings, Boxes, Etc.:

1. All outlet boxes, junction boxes, and switch boxes shall be code gauge galvanized steel.

2. Boxes shall be square, rectangular, or octagonal of a suitable and ample size.

D. Raceways and Fittings:

1. Conduit shall be rigid galvanized steel conduit with compression or tap-on type fittings.

2. Conduit installed in concrete slab or underground shall be rigid galvanized coated with asphaltum paint.

3. All conduit and fittings shall be U.L. approved and N.E.C. rated.

4. No conduit smaller than 3/4" shall be used.

Page 107: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-7

5. Roadway conduit: Unless otherwise noted on the Drawings or elsewhere in the specifications, provide 2-1/2" diameter, schedule 80 PVC, Ul listed at 90 degrees, UV resistant electrical conduit for the installation of conductors beneath roadways.

6. Provide rigid galvanized steel electrical conduits, threaded at the top to accept rain-tight cap, for mounting of distribution of panels and equipment.

a. Rain-tight cap: galvanized steel, threaded fitting suitable for capping open end of rigid steel electrical conduit.

7. Corrugated flexible PVC Conduit: Where direct burial cable is not used provide unspliced, high tensile pvc corrugated flexible conduit to IPS dimensions, suitable for underground secondary distribution and under roadway application for protection of type TW, THW, RHW, or XHHW conductors used underground.

a. Provide IPS dimensions, schedule 430 PVC accessories including, but not necessarily limited to, couplings, adaptors, end bells and plugs, and PVC solvent cement suited for watertight joints.

b. Provide Corrugate flexible PVC conduit and accessories manufactured by Carlon, Cleveland, Oh., or approved equals.

E. Interior Conductors and Conductors Installed in Watertight Underground Conduits:

1. Wire and cable shall be 600 V insulated N.E.C. standard type TW, THW, RHW, or XHHW, and color coded.

2. All wiring shall be copper and No.12 AWG or larger, wires No.8 and larger shall be stranded.

F. Direct Burial Conductors:

1. Wire and Cable: 600 V insulated, NEC standard, type USE or UF, as shown on the Drawings

2. All wiring shall be copper and No.12 AWG or larger, wires No.8 and larger shall be stranded.

G. Grounding devices:

1. Grounding Electrodes: 5/8" diameter, minimum 10 feet long unless otherwise shown, "Copperweld" ground rods.

2. Electrode Conductor: Copper, no.6 AWG or larger, and type THW. Use clamp suitable for burial to fasten grounding conductor to rod.

H. Safety Switches:

1. Provide heavy duty, horsepower rated, quick-make and quick-break design, externally operated with provision for padlocking, fusible or non-fusible as shown on the Drawings.

Page 108: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-8

a. Equip with field or factory installed solid neutral assembly and service grounding kit.

2. Provide enclosure clearly marked for maximum voltage and horsepower rating, and:

a. Indoor: NEMA type 1.

b. Outdoor: NEMA type 3R, rain tight.

3. For dual rated switches, provide rating indicated on a metal plate riveted or otherwise permanently fastened to the enclosure.

4. Provide safety switches for 120/240 volt service, amperage as indicated as manufactured by, but not limited to one of the following:

a. Square D b. General Electric c. ITE d. Westinghouse

5. Safety switches shall be UL approved and NEC rated.

I. Campsite Power Outlets:

1. The following are the only approved receptacle to be provided for recreational vehicle use on campsites:

a. 5-20R GFI, 20 AMP duplex, 125 volts, in accordance with ANSI/NEMA WD 6-1989, for recreational vehicles.

b. R-32-U, 30 AMP duplex, 125 volts, in accordance with ANSI/NEMA WD 6-1989, for recreational vehicles.

c. 14-50R, 50 AMP duplex, 125/250 volts in accordance with ANSI/NEMA WD 6-1989, for recreational vehicles.

2. Provide individual recreational vehicle site service entrance equipment, as shown on the Drawings,Ul listed and labeled "Suitable for Recreational Vehicle Service Equipment", as manufactured by Midwest Electrical Products, Inc. P.O. Box 910, Mankato, Minnesota, Tel No. 507/625-4414, or approved equal.

3. Metallic R.V. Equipment: Unless otherwise noted on the Drawings, power outlets shall contain the circuit breaker and receptacles as specified herein.

a. Single unit Midwest Model No. U075CP6010, single unit Millbank Model No. U5200-XL-75 or approved equal for 50 Amp sites.

b. Double unit Midwest Model No. U075CB6010, double unit Millbank Model No. U5220-XL-75 or approved equal for 50 Amp sites.

Page 109: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-9

c. Provide NEMA 3R, light grey baked enamel, uni-post mounted power outlets, completely factory wired and assembled, with loop-feed lugs to accept specified wire size. Power outlet box to be 14-gauge galvanized steel. Post to be 12-Gauge galvanized steel.

d. Install stabilizer foot and post extension on pedestal as a footing base unless otherwise shown on the Drawings, or an alternate stabilization method is approved.

4. Nonmetallic R.V. Equipment: Injection Molded, thermoplastic enclosure with Corrosion resistant internal components, factory wired power receptacles in 20 and 30 AMP configuration, protected by a 30 AMP ground fault interrupter main breaker, a hinged cover to protect R.V. plugs. Midwest model No. U71 "Parkmate" or approved equal.

a. Terminal lugs will accept 1/0 copper cables.

b. The power center will be rated 100 AMP maximum, 120/240 volts, single phase, 3 wire with ground.

c. Power to be factory mounted on 12 gauge galvanized steel, grey baked on enamel, vented post for underground services, with loop-feed twin 2-300 MCM terminal per phase lugs.

d. Install stabilizer foot and post extension on pedestal as a footing base unless otherwise shown on the Drawings, or an alternate stabilization method is approved.

e. Provide a seven watt fluorescent light protected by an in-line fuse circuit protection and molded polycarbonate light cover.

f. Provide additional options as shown on the Drawings. Other options may include a light with manual switch or photo electric sensor, single service cable TV jack for type RG-59 coax cable, single service telephone jack type PH6596.

J. Detectable Warning Tape: 3-inch wide electronically detectable tape with markings: "Caution - Electrical Power Lines Below" provided by, but not necessarily limited to, one of the following:

1. Terra Tape D, Reef Industries, Inc., Houston, Texas

2. Dectatape, Allen Systems, Houston, Texas

3. Detectable Marking Tape III, Lineguard, Inc., Weaton, Illinois

K. GFCI Testers: Provide GFCI testers capable of indicating wiring errors and faulty GFI equipment.

1. Unitest GFI model No. 5708 manufactured by Beha Corporation, Clearwater, Fl. or approved equals.

Page 110: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-10

L. Mounting Channels and accessories: Provide 1-5/8" series, galvanized steel channels and accessories for mounting distribution panels, meters, and safety switches, including conduit clamps and spring-loaded nuts, provided by, but not necessarily limited to, one of the following:

1. Unistrut, GTE Products Corp., Wayne, MI.

2. Power-Strut, Elcen Metal Product Co., Franklin Park, IL.

M. Terminal and Splice Boxes: NEMA type 3R rain proof code approved cabinets, with removable door with stay-open position, provision for padlocking, concentric knockouts, and heavy zinc-coated finish, of sufficient voltages.

1. Include field or factory installed grounding kit.

2. Provide boxes for 120/240 service, Ul approved and NEC rated, of amperage indicated, as manufactured by, but not limited to, one of the following:

a. Square D b. Midwest Electric Products, Inc.

N. Provide other materials, not specifically described but required for a complete and proper installation, as selected by the Contractor subject to the approval of the Project Engineer.

PART 3 - EXECUTION

3.01 EXAMINATION:

A. Examine the areas and conditions under which the work of this section will be installed. Correct conditions detrimental to the proper and timely completion of the work. Do not proceed until unsatisfactory conditions have been corrected.

B. Verify location and configuration of existing facilities in relation to the work of this section before preparing bid.

C. Verify depths and location so all existing underground utilities

3.02 PREPARATION:

A. Coordination: Coordinate installation of electrical items with the schedules for other work, to prevent unnecessary delays in the total work.

B. Where electrical items are shown in conflict with locations of structural members and mechanical or other equipment, provide all required supports and wiring to clear the encroachment.

C. Accuracy of Data: The data indicated on the Drawings and in these Specifications are as exact as could be secured, but their absolute accuracy is not guaranteed.

Page 111: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-11

1. Exact locations, distances, levels, and other conditions will be governed by actual construction.

2. Use the Drawings and these Specifications for guidance, and secure the DNR Construction Inspector's approval of all changes in locations.

D. Measurements: Verify all measurements at the site.

1. No extra compensation will be made because of differences between locations shown on the Drawings and measurements at the site, except as provided In the General Covenants and Provisions.

E. Circuiting: The branch circuits have been designed for maximum economy consistent with sizes for voltage drop and other considerations.

1. Circuits and wire sizes shall be in accordance with the N.E.C. Install circuits as shown on the Drawings unless otherwise approved by The Project Engineer.

F. Electrical circuit drawings are diagrammatic in nature but are to be followed as closely as made possible by the actual construction and interface with the work of other trade in this or other contracts.

1. Where deviations are approved to comform with actual construction and the work of other trades, make such deviation without additional costs to the Owner, except as provided elsewhere in the Contract Documents.

G. Trenching and backfilling is required for installation of the work of this section. Perform all such trenching and backfilling in strict accordance with the provisions of Section 02200 of these Specifications.

3.03 INSTALLATION:

A. Conduits:

1. Where conduit is installed in concrete slabs, on the ground, underground, or exposed to the weather, make all joints liquidtight and gastight.

a. Bury all underground conduit to a depth of 2'0" below finished grade unless otherwise shown on the Drawings.

b. Install necessary sleeves, chases, bushings, and approved sealants where conduits pass through slabs, floors, walls and other structures.

c. Make necessary openings and spaces while keeping cutting and patching of work by other to an acceptable minimum.

2. Install bushing at conduit ends, to protect wires from abrasions, where conduit enters box or other fittings.

3. No conduit smaller than 3/4" shall be used for a branch circuit in this project.

Page 112: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-12

a. Unless otherwise specified, provide code-size conduit for number and size of wire required by Code.

4. Where conduit is exposed, run parallel to or at right angle with lines of the building.

a. Make bends free from dents and flattening with standard conduit elbows or conduit bent to not less than the same radius.

B. Roadway Crossing Electrical conduit:

1. Install specified conduit at location indicated on the Drawings by boring, jacking into place, or trenching, when permitted by the DNR Construction Inspector, into unpaved roadways.

2. Indentify roadway crossing location by placing two 2" P-K nails, one inch apart, six inches from each side of pavement.

a. In addition install a 12-inch long reinforcing rod or a 24-inch long treated wood stake at each end of conduit.

3. Plug and cap each end of conduit placed beneath roadway for future circuit installation.

a. Sand fill around each end to aid future location and installation.

4. Install conduit for primary circuits below the location of conduit for primary circuit where they are indicated on the Drawings to cross at the same location.

C. Installation of Conductors:

1. All conductors used for branch circuits will be minimum number 12 protected by 20 ampere circuit breakers.

a. Install larger wires where necessary to limit voltage drop or as required by NEC.

2. Conductors will be installed continuous from outlet to outlet and no splices shall be made except within outlet or junction boxes.

3. No underground splice will be permitted.

a. Conductors will run continuously from the main distribution panel to the terminal bar located in the first R.V. site service entrance equipment post on the circuit and continuously thereafter from terminal bar to terminal bar.

4. Balance the campsite loads between the two phase conductors by connecting the loads to alternate sides of each 120/240 volt, three wire circuit.

a. Follow NEC requirements to provide for coding convention to consistently identify conductors throughout the project.

3. No more than three circuits will be permitted in one raceway.

a. A common neutral may be used as permitted by the National Electric Code.

Page 113: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-13

4. Terminals and Splices: Stranded conductors shall be terminated with approved copper connecting lugs, accommodating the full diameter of the bare conductor.

a. Mains and feeders shall run their entire lengths in continuous sections without joints or splices.

5. Splices will be permitted only at outlet or junction boxes.

a. Splices shall be thoroughly cleaned, mechanically and electrically secured without solder, then soldered.

b. After soldering, wrap rubber and friction tape.

c. Vinyl plastic tape will be acceptable subject to the approval of local inspection authorities.

d. Scotch lock type S, M, L, and D connectors will be approved as equal to soldering.

D. Installation of main distribution panels:

1. Mount main distribution panels using specified conduit support posts and mounting channels, clamps and accessories as shown on the Drawings.

a. Install the rain-tight cap on top of support posts.

2. Unless otherwise specified, install copper studs and spade type bushings in utility company transformer, and install secondary connections between transformer and the main distribution panel.

a. Seek approval of utility company representative prior, during and after installation.

3. Install meter where indicated on The Drawings or as instructed by the utility company.

a. Installation subject to approval of utility company.

b. Provide utility company approved meter if so instructed by utility company.

4. Directories: Mount a typewritten directory behind glass or plastic on the inside of each panel door.

a. Show circuit numbers and circuit description for all outlets in each circuit.

5. Mounting Heights: To center of box above finished floor for the below-named items, shall be as follows, unless otherwise shown or indicated.

a. Flush toggle switches: 48".

b. Convenience outlets and similar: 12" - finished areas (unless noted otherwise).

c. Convenience outlets and power outlets: 48".

Page 114: 01000 GENERAL REQUIREMENTS

09-03-31-04 6/22/2009 ELECTRICAL E.B. LYONS INTERPRETIVE CENTER SANITARY SEWER FORCEMAIN 16000-14

d. Safety switches: 54" to operator.

e. Motor controllers: 54" or top even with safety switch.

f. Panelboards: 72" to top.

g. Other mounting heights are indicated on the Drawings by detail or by a plus dimension shown adjacent to the symbol.

E. Grounding System: Ground all equipment including panelboards, transformers, conduits systems, junction and splice boxes, RV site service equipment, motors and other apparatus, by conduit or conductor to grounding electrode as shown on the Drawings, using grounding clams suitable to direct burial.

1. Locate grounding electrode in area which will receive ground water regularly, and drive rod to depth of at least 8 feet.

2. Test to measure ground resistance, and provide not more than 5 ohms resistance, adding ground rods as required to achieve that level.

3.04 FIELD QUALITY CONTROL:

A. Testing: At the conclusion of the work, test each and every circuit to establish the proper operation of electric equipment and freedom from improper ground and to ascertain the insulation values which shall not be lower than those required by the National Electrical Code.

1. Test of equipment grounding conductors will show a resistance of no more than 25 ohms at any point on the circuit, except for grounding electrode which will show a resistance of no more than 5 ohms.

B. Carry out final test in the presence of the Project Engineer/DNR Construction Inspector.

C. Correct all work not meeting code requirements, and all circuits which fail testing, at no additional cost to the Owner.

3.05 CLEANING:

A. Exposed conduits, panel boards, fixtures, switches, hangers, and equipment exposed shall be thoroughly cleaned.

B. Fixture glass and shields shall be cleaned and washed.

C. Keep premises free from unnecessary accumulation of rubbish and debris resulting from the work of this section.

D. Dispose of all debris resulting from the work of this contract at no additional cost to the Owner.

END OF SECTION 16000