04 chap016 aquino chase

Upload: smartorahul

Post on 08-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 04 chap016 Aquino Chase

    1/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    1

  • 8/7/2019 04 chap016 Aquino Chase

    2/28

    The McGraw-Hill Companies, Inc., 2004

    2

    McGraw-Hill/Irwin

    Chapter 16Materials

    RequirementsPlanning

  • 8/7/2019 04 chap016 Aquino Chase

    3/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    3

    Material Requirements Planning(MRP)

    MRP Logic and Product StructureTrees

    Time Fences

    MRP Example MRP II and Lot Sizing

    OBJECTIVES

  • 8/7/2019 04 chap016 Aquino Chase

    4/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    4

    Material Requirements

    Planning

    Materials requirements planning (MRP)is a means for determining the numberof parts, components, and materials

    needed to produce a product MRP provides time scheduling

    information specifying when each ofthe materials, parts, and components

    should be ordered or produced Dependent demand drives MRP

    MRP is a software system

  • 8/7/2019 04 chap016 Aquino Chase

    5/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    5

    Example of MRP Logic and

    Product Structure Tree

    (4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Product Structure Tree for Assembly A Lead Times

    A 1 day

    B 2 days

    C 1 day

    D 3 days

    E 4 days

    F 1 day

    Total Unit Demand

    Day 10 50 A

    Day 8 20 B (Spares)

    Day 6 15 D (Spares)

    Given theproduct structure tree for A and the lead time anddemandinformation below, provide a materials requirements

    plan that defines thenumberofunits ofeach component and

    when theywill beneeded

  • 8/7/2019 04 chap016 Aquino Chase

    6/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    6

    LT = 1 day

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    Order Placement 50

    First, thenumberofunits ofA are scheduled

    backwards to allowfor their lead time. So,in thematerials requirement plan below,we have to place

    anorderfor 50 units ofA on the 9th day toreceive

    themonday 10.

  • 8/7/2019 04 chap016 Aquino Chase

    7/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    7

    Next,weneed to start scheduling the components that makeup

    A. In the caseofcomponent B weneed 4 Bs foreach A.

    Sinceweneed 50 As, that means 200 Bs. And again,we back

    the scheduleup for thenecessary 2 days oflead time.

    D a y : 1 2 3 4 5 6 7 8 9 1 0

    A R e q u i re d 5 0

    O rd e r P la c e m e n t 5 0

    B R e q u i re d 2 0 2 0 0

    O rd e r P la c e m e n t 2 0 2 0 0

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    SparesLT = 2

    4x50=200

  • 8/7/2019 04 chap016 Aquino Chase

    8/28

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50LT=1 Order Placement 50

    B Required 20 200

    LT=2 Order Placement 20 200

    C Required 100

    LT=1 Order Placement 100

    D Required 55 400 300

    LT=3 Order Placement 55 400 300

    E Required 20 200

    LT=4 Order Placement 20 200

    F Required 200

    LT=1 Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    40 + 15 spares

    Part D: Day 6

    Finally,repeating the process for all components,we have the

    final materials requirements plan:

    The McGraw-Hill Companies, Inc., 2001

    8

  • 8/7/2019 04 chap016 Aquino Chase

    9/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    9

    Master Production Schedule (MPS)

    Time-phased plan specifying how

    manyand when the firm plans to build

    each end item

    Aggregate Plan

    (Product Groups)

    MPS

    (Specific End Items)

  • 8/7/2019 04 chap016 Aquino Chase

    10/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    10

    Types of Time Fences

    Frozen No schedule changes allowed within

    this window

    Moderately Firm

    Specific changes allowed withinproduct groups as long as parts areavailable

    Flexible

    Significant variation allowed as longas overall capacity requirementsremain at the same levels

  • 8/7/2019 04 chap016 Aquino Chase

    11/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    11

    Example of Time Fences

    8 15 26

    Weeks

    FrozenModerately

    Firm Flexible

    Firm Customer Orders

    Forecast and availablecapacity

    Capacity

    Exhibit 15.5

  • 8/7/2019 04 chap016 Aquino Chase

    12/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    12

    Material Requirements Planning System

    Based on a master production schedule, amaterial requirements planning system:

    Creates schedules identifying the specific

    parts and materials required to produce

    end items

    Determines exact unit numbers needed

    Determines the dates when orders for

    those materials should be released, basedon lead times

  • 8/7/2019 04 chap016 Aquino Chase

    13/28

    From Exhibit 15.6

    13

    The McGraw-Hill Companies, Inc., 2004

    Firm orders

    from known

    customers

    Forecasts

    of demand

    from random

    customers

    Aggregate

    product

    plan

    Bill of

    material

    file

    Engineering

    design

    changes

    Inventory

    record file

    Inventory

    transactions

    Master production

    Schedule (MPS)

    Primary reportsSecondary reports

    Planned order schedule for

    inventory and production

    control

    Exception reports

    Planning reports

    Reports for performance

    control

    Material

    planning

    (MRP

    computer

    program)

  • 8/7/2019 04 chap016 Aquino Chase

    14/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    14

    Bill of Materials (BOM) File

    A Complete Product Description

    Materials

    Parts

    Components Production sequence

    ModularBOM

    Subassemblies SuperBOM

    Fractional options

  • 8/7/2019 04 chap016 Aquino Chase

    15/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    15

    Inventory Records File

    Each inventory item carried as a

    separate file

    Status according to time buckets

    Pegging Identify each parent item that created

    demand

  • 8/7/2019 04 chap016 Aquino Chase

    16/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    16

    Primary MRP Reports

    Planned orders to be released at a futuretime Order release notices to execute the

    planned orders Changes in due dates of open orders

    due to rescheduling Cancellations or suspensions of open

    orders due to cancellation or suspensionof orders on the master production

    schedule Inventory status data

  • 8/7/2019 04 chap016 Aquino Chase

    17/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    17

    Secondary MRP Reports

    Planning reports, for example,forecasting inventoryrequirements over a period of time

    Performance reports used todetermine agreement betweenactual and programmed usageand costs

    Exception reports used to pointout serious discrepancies, suchas late or overdue orders

  • 8/7/2019 04 chap016 Aquino Chase

    18/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    18

    Additional MRP Scheduling Terminology

    Gross Requirements

    Scheduled receipts

    Projected available balance

    Net requirements

    Planned order receipt

    Planned order release

  • 8/7/2019 04 chap016 Aquino Chase

    19/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    19

    MRP Example

    A(2)B

    (1)

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3

    B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of X

    in week 10

  • 8/7/2019 04 chap016 Aquino Chase

    20/28

  • 8/7/2019 04 chap016 Aquino Chase

    21/28

  • 8/7/2019 04 chap016 Aquino Chase

    22/28

  • 8/7/2019 04 chap016 Aquino Chase

    23/28

  • 8/7/2019 04 chap016 Aquino Chase

    24/28

  • 8/7/2019 04 chap016 Aquino Chase

    25/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    25

    Closed Loop MRP

    Production Planning

    Master Production Scheduling

    Material Requirements Planning

    Capacity Requirements Planning

    Realistic?No

    Feedback

    Execute:

    Capacity Plans

    Material Plans

    Yes

    Feedback

  • 8/7/2019 04 chap016 Aquino Chase

    26/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    26

    Manufacturing Resource Planning

    (MRP II)

    Goal: Plan and monitor all resources of

    a manufacturing firm (closed loop):

    manufacturing marketing

    finance

    engineering

    Simulate the manufacturing system

  • 8/7/2019 04 chap016 Aquino Chase

    27/28

    McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.

    27

    Lot Sizing in MRP Programs

    Lot-for-lot (L4L)

    Economic order quantity (EOQ)

    Least total cost (LTC) Least unit cost (LUC)

    Which one to use?

    The one that is least costly!

  • 8/7/2019 04 chap016 Aquino Chase

    28/28

    The McGraw-Hill Companies, Inc., 2004

    28

    McGraw-Hill/Irwin

    End of Chapter 16