7/30/2019 04-Gis Sc Project Status Report
1/36
Status***
Project Name/DescriptionProject
NumberProject
Importance
June
July
August
September
Project
Start Date
Preliminary
End Date
Adjusted
End Date
Projected
Status**
A Phase 6 -OR-Trans/Pooled Fund
Project
- Design and construct Web based checkin and out- Check out system
GIS19
Medium
G G G G 06/30/04 06/30/05 12/31/08 G
A Phase 7 - OR-Trans FY 2007
- Statewide data partnership- Wasco County Pilot project- Develop/Coordinator QA/QC of data
with Road Authorities- Continue Pooled Fund participation- Develop Routing data on State
highways
GIS19
(TO #15)
Medium
G G G G 05/01/07 06/30/08 G
Project Status
August 2008
GIS Monthly Project Status Rep
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 1
-
7/30/2019 04-Gis Sc Project Status Report
2/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
August
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
A Environmental Data Management
System
(formerly SR-SAM)
GIS31
(TO #4,
TO #12)
Medium
G G G G Ongoing Ongoing Ongoing G
H TOC GIS Interface
Phase 2
- Implementation of viewing tool- Provide GIS expertise to the project
GIS42
High
05/01/06 05/01/07 On Hold-
6/1/2007
H Traffic Mobility Management System
Phase 2
Develop data models and business
processes based on recommendationsand findings from Phase 1.
Create/capture and catalogue data (or
secure access to data) that will be usedand maintained for managing traffic
mobility. Develop applications that assist in
managing traffic and freight mobility. Prototype applications, data and
GIS39
High
03/01/06 On Hold-
6/1/2007
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 2
-
7/30/2019 04-Gis Sc Project Status Report
3/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
August
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
A STIP TransGIS Scoping Tool
Phase 1 & 2
GIS47
Hig
h
Y Y Y Y 5/10/2007 11/15/2007 11/30/2007
12/31/0703/15/08
4/1/08
6/15/08
9/01/08
Y
H SPIS Pilot for OR-Trans - Proof of
Concepts
GIS44
High
07/13/06 12/31/06 On-Hold
H Alternate Fuels Corridor - I5 Potential
Sites Research
- GIS map and database of all availablesites associated with the I-5 corridor.
GIS50
MissionCritical 01/10/08 02/29/08 2/25/2008
H Alternate Fuels Corridor - I5 Potential
Sites Research- PHASE 2
- GIS map and database of all availablesites associated with the I-5 corridor.
GIS50-2
A TPOD (Transportation Planning Online
Database)
- Use GIS interface to view scannedplanning studies
GIS52
High
G G G G 05/01/08 6/1/2008
07/15/08
9/31/08
G
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 3
-
7/30/2019 04-Gis Sc Project Status Report
4/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
August
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
A ODOT Solar Highway
- Identify ODOT R/W that Solarequipment can be tied into PGEtransmission lines
GIS54
Mission
Critical
Y Y Y Y 03/10/08 05/01/08 6/1/2008
7/31/08
Y
H RWDMS II - GIS Component
- Enhance GIS connection to R/W
FileNet System.
GIS55
M
ission
C
ritical G G G G 03/10/08 05/01/08 G
Q ArcGIS ODOT GUI Update
- Update existing template to improveefficiency and standardization.
GIS56
Medium
06/01/08
A Traffic Counting Application Features
Enhancement
- Contractor will enhance applicationused by field traffic counting staff
TO #23 Y Y Y Y 1/3/07 3/10/2008
06/01/08
9/1/08
Y
H Interchange Diagramming in GIS GIS58
Medium
8/1/08 9/1/08
H Electric Vehicle Charging Stations Site
Data Collection Assistance
GIS59
Hig
h
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 4
-
7/30/2019 04-Gis Sc Project Status Report
5/36
Status***
Project Name/DescriptionProject
Number
P
roject
Importance
June
July
A
ugust
Sep
tember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
Pr
ojected
S
tatus**
Project Status
A GIS Data In Progress
Projects categorized as:OEM or Sum
Assign sub-numbers (Sum)
GIS21
High
G G G G Ongoing Ongoing Ongoing G
A GIS Data Completed GIS21
High
C C C C Completed Completed Completed C
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 5
-
7/30/2019 04-Gis Sc Project Status Report
6/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
A
ugust
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
A GIS Infrastructure Support (cont.)
Training
GIS11-01
H
igh
G G G G Ongoing Ongoing Ongoing G
A GIS Infrastructure Support (cont.)
Demonstrations
(6 month drop-off cycle)Target:OTCDoug Tindall, Hwy Div ManagerAdditional PBLT groupsArea ManagersProject Manager
GIS11-02
High
G G G G Ongoing Ongoing Ongoing G
A GIS Infrastructure Support (cont.)
Customer Support
GIS11-03
High
G G G G Ongoing Ongoing Ongoing G
A GIS Infrastructure Support (cont.)
Metadata
GIS11-04
High
Y Y Y Y Ongoing Ongoing Ongoing Y
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 6
-
7/30/2019 04-Gis Sc Project Status Report
7/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
A
ugust
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
A GIS Infrastructure Support (cont.)
Standards
GIS11-05-01
High G G G G Ongoing Ongoing Ongoing G
A GIS Infrastructure Support (cont.)
SoftwareEvaluation/Purchase/Implementation
(E) - Evaluation
(P) - Purchase(I) - Implementation
GIS11-06
High
G G G G Ongoing Ongoing Ongoing G
GIS Infrastructure Support (cont.)
Process Guidelines
GIS11-08
High
A GIS Infrastructure Support
SDE ImplementationSpatial ReferencePopulate Database
GIS11-09
High
G G G G 6/1/2006 8/15/2006 G
GIS Infrastructure (cont.)
Hardware
GIS11-14 G G G G G
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 7
-
7/30/2019 04-Gis Sc Project Status Report
8/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
A
ugust
Se
ptember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
Status**
Project Status
GIS Infrastructure (cont.)
Planning
GIS11-15 G G G G G
GIS Infrastructure Support
OBDP Migration
GIS11-17 G G G G G
A OEM & Small Projects (cont.)
Scenic Byways GIS Implementation
GIS23-02
MissionCritical
Y Y Y Y 5/1/06
Active12/1/07
7/31/2006 11/15/2006
5/15/07
5/1/08
6/15/08
9/01/08
10/1/08
Y
A OEM & Small Projects (cont.)Access Management GIS
Implementation
GIS23-03
MissionCritical
Y Y Y Y1/29/2007
3/1/08
6/30/2007 6/30/076/30/08
9/01/08
Y
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 8
-
7/30/2019 04-Gis Sc Project Status Report
9/36
S
tatus***
Project Name/DescriptionProject
NumberProject
Im
portance
June
July
A
ugust
September
Project
Start Date
Preliminary
End Date
Adjusted
End Date
P
rojected
S
tatus**
Project Status
A OEM & Small Projects (Cont)
Traffic Counting Field Data Collection
GIS23-04
(TO#10)
G G G G 1/11/2006 3/15/2006 12/31/2006
06/1/2006
07/15/06
08/01/07
G
H OEM & Small Projects (cont.)
Asset Management Safety Rating Pilot
GIS23-09
MissionCritical
6/9/2006 10/1/2006 5/1/2007
A Transportation Model Development
High
G G G G Ongoing Ongoing Ongoing G
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 9
-
7/30/2019 04-Gis Sc Project Status Report
10/36
St
atus***
Project Name/DescriptionProject
Number
P
roject
Imp
ortance
June
July
August
Sep
tember
Project
Start Date
Preliminary
End Date
Adjusted
End Date
Projected
Status**
Project Status
* Requires Attention
C=Complete Requires Corrective Action
H=On Hold Project complete or not started
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 10
-
7/30/2019 04-Gis Sc Project Status Report
11/36
Comments
3/8/07: The first web page for the check in/out site has been created. Info
gathered from JAD session was used to design interface and some of the
functionality. At this point the web page is a mark up of information and thefunction of loading the data will be worked out after the overall design has been
finished. 4/3/07: Pooled fund project meeting on 3/24/07 in Nashville TN. NE, TN,
IO, WA and OR were all in attendance. California has joined the pooled fund.
7/9/07: ODOT has secured $30K per year for the next two years for the pooled
fund. 10/31/07: ODOT has recommended agreement points to Walla Walla County
on the Oregon boarder. Walla Walla has returned a revised set. Discrepancies
were noted between line work ODOT used to establish points and line work the
county used. Those are being looked into now. 2/19/08: The FME Workbench for
the pilot is complete. Data has been translated from source data and back using
the Workbench. 4/21/08: Pooled Fund (GISDC) annual mtg was on May 13-14 in
Olympia Wa.. Partners from all participating states were their to discuss findings,
goals, direction about the check in/out application. 8/25/08 WA_Trans Policy
Advisory
Commitee mtg on 9/4. This will address technical issues that will guidethe tools and design for the load/extract/change detection software.
2/19/08: U of O is working on the QAQC phase of data validation. A snap shot
dataset will be created as part of this process for interim needs and agreementpoints will be established for coordination with the local Road Authorities for thelong term integration goal. 3/6/08: U of O is compiling statistics of issues for eachroad authority (RA) and will begin work on the QAQC using the GeoMedia platformper ODOTs request. Will meet withOEM and GeoSolve to discuss incorporating data requirements for ODOT's
certified mileage reporting in OR-Trans process via local RA data. 4/21/08: UofOhas had personnel changes and lost their project manager so they have recruitedfor a new project manager. A few weeks worth of work was lost with the transitionbut UofO has committed to trying to meet the previous deadlines. OR-Trans hasreceived a 2008/09 grant for $50k from USGS for continued work on QAQC and
distribution of OR-Trans to the National Map effort.7-2008 Work is nearly complete
developing a routing network, specification gathering for GIS routing software is
underway with completion scheduled for Aug. 1. 8/25/08 OEM
contract w/ counties at DOJ for review. OEM placed a hold on data
distribution to OR-Trans until new contract is signed. Crash data for
Wasco Pilot has been extracted and geocoded to OR-Trans data.
Mid Sept. mtg is planned to demonstrate data to Wasco Co. Marion/LinnCo. pilot to resolve agreement points was scheduled for August but has
been pushed back because of loss of resources (Loren Mueller). Chad N
has taken over some tasks that Loren had but he also has GIS technical
support functions for ODOT that take his time.
ort
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 11
-
7/30/2019 04-Gis Sc Project Status Report
12/36
Comments
11/5/07: Currently meeting with Tech Center Environmental managers, Geo-Environmental unit managers, maintenance environmental project managers todevelop 2008 work plan goals. 2008 Work Plan will be submitted to EDMS Steeringthis winter. Prototype RES/RAZ products will be presented to RES/RAZ sub-committee for feedback early 2008. 1/9/08: Completed 2007 customer outreachand scheduled Steering Committee for February 2008. RES/RAZ revisedprototypes currently in development. Archaeological field application recentlycompleted. Biology and Mitigation field applications in revision at Mason Bruce &Girard through Spring 2008. EDMS web application development resumes at Alsea
Geospatial Spring-Summer 2008. 4/17/08: EDMS Steering Committee metFebruary 20. Archaeological GPS application development was completed inMarch. SRSAM mapping committee met April 14. RES/RAZ map rewrite in processthrough June 2008. 7/14/08: RES/RAZ map rewrite process through July 2008.
Resource grade GPS training underway in Regions through mid-August. 9/8/08:
GPS trainings completed. RES/RAZ map rewrite
in progress, currently converting thematic Line Charts previously
3/8/07: Prototype delivered, waiting for final requirements.
09/14/06: Placed on Hold by Motor Carrier Staff. 10/31/06: Project completed.Motor Carrier does not need any additional work at this time.3/8/07: Dennis, Pete Randall, Erik Havig, OBDP Staff and Ron Winterrowd met todiscuss future developer needs. Additional discussions will occur over the next fewmonths. Invited Randall Thomas to May Steering Committee to discuss needs forproject. 1/4/08: Randall Thomas reports that final database testing is
underway. GIS portion of this project remains on hold.
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 12
-
7/30/2019 04-Gis Sc Project Status Report
13/36
Comments
11/28/06: Approved at GIS Steering Committee. 2/21/2007: First requirements
meeting scheduled for March. 5/10/07: Met with customers, and received more
direction from Cathy Nelson. 7/9/07: Project outline developed. Sample 'mxd'
created. Waiting for customer team to be identified. 9/13/07:Application in
refinement. Requirements defined at meetings with TLT, PBLT, STIP Coord. andSystem Managers. Data received and decoded. Workshop scheduled for Sept 12-
using ILink system. Training software acquired. 11/8/07: Training complete in
Region 1,2,3,4,5. Customer generated reviews being addressed and data updates
to be implemented before deployment. 1/3/08: Tested revised tools and database
management. Preparing web accessible instructional resources. Base softwareinstalls are complete. Tools are being distributed to customers. 2/20/08:
Distribution of tools continues. 3/20/08: Distribution of tools continues. Most delay
due to FSU resourcing for software installation. 4/4/08: Distribution continues. FSU
Software installs slow. 4/15/08: Distribution continues.
Software installs nearly complete. 5/09/08: Completing distribution
and preparing survey for user feedback. 7/09/08: Distribution continues.
25 customer installs remain.
6/17/08: Contact business (Safety Management System staff) for future direction of
this project. 7/16/2008 This project is linked to TAD db project RFW # 16117
that has not started as if this date.
2/25/08: Project Complete. 4/15/08: Customer utilizing data and tools. Training set
for map production tool. 6/5/08: Project database and security developed for
customer use during research phase. Data use restrictions prompted this
action. Customer continues research and mapping. Field work and site
decisions planned for completion by customer, end of June 2008.
3/20/08: Waiting for allocation of resources. 4/4/08: First meeting scheduled to gain
access to database and determine location of scanned documents. 4/15/08: Data
and scanned documents located. Database schema in review as is document
storage/access location. 5/09/08: No Change. Resources are scarce. 06/19/08:
Database in revision to achieve functionality and meet GIS standards.
Redundancy and organization of documents in review to prepare for action by
temporary staff and to insure proper posting and updates. Temp staff begins
work to add and update documents, update database, revise organization and
document naming. GIS staff designs interface for database entries and link
management.
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 13
-
7/30/2019 04-Gis Sc Project Status Report
14/36
Comments
3/20/08: Experiencing problems obtaining data from PGE (Portland General
Electric). 4/4/08: No data from PGE. 04/15/08: Data received. Site maps in
progress. 5/09/08: Data analysis and mapping in progress. 06/18/08: Dataprocessing has increased due to data limitations. Additional map productionrequired from GIS staff to provide detail for analysis.
3/20/08: Feasibility testing complete.
3/20/08: Waiting for allocation of resources. 4/4/08: Short discussions have begun.4/15/08: Project scope and purpose to be reviewed. Possible split as two projects.5/09/08: Project split confirmed. This project addresses desktop toolset.Navigation and data access toolbars in development. Data migration to SDE/SQLin process. Team reviewing modules developed by business partners and otheragencies. 7/09/08: Resources unavailable.
1/3/08 - Project approved. 2/25/08 - Data provided to consultant. 3/7/08 - Projectdue to be delivered week of 3/10/08. Software delivered, working on softwareversion issue. 4/18/08: Software out of iCARE. Working with contractor to fine tune
bugs with program. 6/25/08: Tech's have program installed on their laptops and aretesting program. 7/14/08: Sending issue log to contractor on 7-14-08. 9/1/08:
Waiting on contractor to complete changes.
6/25/08: Waiting for resources.
Resource will be available 8/1
9/4/08: Lynn Bailey has received ArcGIS 2 training and with the assistance of
Sarah Abbott, Region 1 GIS support technician is doing the project
themselves with a minor amount (four hours) of support from Ryan Johnson.
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 14
-
7/30/2019 04-Gis Sc Project Status Report
15/36
Comments
ODOT Areas
ATR's 2007
Flow Map State
AADT
Expressways
Nonstate Functional Class
State Functional Class
Freight Routes
Highway ClassificationHighway ones, fives, tens, tenths, hundredths
Lane Width and Type
Left and Right Turns
Maintenance Units
Mileposts
National Network (state on nonstate)
NHS (state on nonstate)
Nmber of LFanes
Posted Speeds
Rest AreasRoutes x-ref (state on nonstate)
Signals
Viewpoints
Weigh Stations
Ambulance Service Areas (for internal use only)
Bridges 2008
ODOT FacilitiesState Airport Runways
LIDAR Imagery Index
Access Management Permits (CHAMPS) (8/08)
Acess Management Permits (U Permit) (8/08)
Cattle Guards and Passes (8/08)
Engineering Stations (8/08)
Highway Intersections (8/08)
Highway Network Update (8/08)
Medians (8/08)
Public Use Airports (8/08)
Public Use Runways (8/08)
RLIS Update (8/08)
Shoulder Width and Type (8/08)
Surface Width and Type (8/08)
SPIS 2005-2007 (8/08)
Culverts Under 6 feet (8/08)
Culverts 6 to 20 feet (8/08)
Contracts (8/08)
Scenic Byways (8/08)
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 15
-
7/30/2019 04-Gis Sc Project Status Report
16/36
Comments
TRAINING RECEIVED:
GPS and ArcPAD (GIS Unit) (8/08)
ArcGIS II - BM, MH (7/08)
Data Editing and Manipulation - JS, MH (7/08)
Advanced Project Management - CB (8/08)Making Projects Work - CB (7/08)Fast Start in Project Management - CB (6/08)GIS in Action Conference (RJ, BM, CC, LM, MH) (5/08)Advanced Project Management - P.S. (4/08)
TRAINING DELIVERED:
R.J. gave training to 3 GeoHydro staff about taking GIS data into the field (06/08)
EDMS through MG&J contract, Region enviro. staff using GPS for field data
collection (7/08 thru 8/08)
GIS web pages / tools - Geo/Hydro GIS Database Comm (03/08).
STIP Scoping GIS tool - GIS Steering Committee (3/20/08)
STIP Scoping GIS tool - Area Manager Team qrtly mtg (04/24/08)
GIS Right-of-Way Parcel Access - D.Tindall / L.Young (4/2008)
CUSTOMER SUPPORT HOURS:
62 (03/08)34 (04/08)59 (05/08)
77 (06/08)
33 (07/08)
26 (08/08)
METADATA:
01/08: No Resources02/08: No Resources03/08: No Resources
04/08: off_hwy_local_2008, signed_rtes, mileposts cemeteries, its_2007,agg_odot
05/08: No resources 06/08: No resources
07/08: Cattle Guards, Cemetery, highway fives, ones, hundredths,
intersects, ITS
08/08: Aggregate Sites, Medians, Shoulders, Scenic Byways, Solar Power,
Wind Power
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 16
-
7/30/2019 04-Gis Sc Project Status Report
17/36
Comments
In Progress:
OpenLM for ArcGIS (license mgmt software) (E:GIS unit testing)"Where have all the license gone"
(ArcScript utility for checking current license use) (E: ICARe in progress)Intergraph GeoMedia Professional 6.01 (E; GIS unit testing)Intergraph GeoMedia Transportatoin Manager 6.01 (E; GIS unit testing)
Intergraph GeoMedia Fusion 6.01 (E; GIS unit testing)ArcGIS 9.2 - build 480 (E; ICARe complete; GIS unit testing)ArcGIS 9.2 - build 480 SDK (E; ICARe testing)
Complete:
LogLicenseUse (ArcScript utility that provides additional ESRI license serverlogging; Implementation)
ArcPad 7.1.1 (ICARe complete)ArcPad Application Builder 7.1.1 (ICARe complete)FME 2008 (ICARe complete)
7/13/06: Spatial Reference: Review Spatial Reference set-ups and decisions withBusiness Partners and other agencies. Review extents vs. precision to determinewith regards to ODOT needs / GIS Unit needs / Engineering needs.Recommendation forthcoming. Populate Database: Test files have been loadedand various interactions. 9/14/06: Spatial Reference settings in place. Image
loading techniques in review and being documented.11/01/06: Data identified andcopied to SQL/SDE environment. 1/03/07:Additional server storage acquired.3/8/07: Image migration in process. 1/9/08: Image migration complete but have notbeen able to create pyramids; progress halted since 8/2007; waiting on support.4/2/08: It has been decided that since some imagery is the same as that provided
by the portal that there is no longer a need to host this imagery ourselves. 6/18/08:
GIS Unit has requested creation of two new databases through I.S. DBA staff .'ODOT' will host standard data tables, replacing shapefiles posted to 'NAS' server.'PROJECTS' will contain project based file groupings. 9/2/08: The databases
have been created and are in use.
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 17
-
7/30/2019 04-Gis Sc Project Status Report
18/36
Comments
8/31/08: Regions 3 and 5 NAS servers are full. The Salem server has more
storage space and is reaching capacity. Region 5 now has a fiber connection
so data sccess shold be much faster. We are investigating if perhaps the new
connection is fast enough in combination with SDE to scale down the Region
5 NAS. Options for Region 3 are still being explore.
1/03/07: No resources at this time. 3/8/07: Sponsor ready to initialize TransGIS
implementation. All data work is complete with a March meeting planned. 5/10/07:
Met with customers for initial requirements. On hold for GIS - resources. Anothermeeting with the customers will be scheduled to refine the requirements and
schedule the work. 9/13/07: Metadata in development. New production method
scoped for distributed through TransGIS portal. 11/8/07: Still on hold pending
resources. 12/4/07: Completed new GIS layer Scenic Byway layer
for presentation to the OTC. Waiting for OTC approval of two new
byways. Also waiting on metadata from customer. 03/20/08: Needsto be published on TransGIS and customer has not completed
metadata. 4/4/08: Meeting scheduled to discuss TransGIS display
requirements. 4/15/08: Project review team meeting scheduled. Data update in
progress. 5/09/08: Web Page display requirements determined and in
development. 7/09/08:ArcGIS mxd Draft prepared and implemented through
TransGIS. Waiting for customer review.
01/03/07: No change in status. 3/8/07: New extract provided to GIS Unit. 'Mapping'
of this data very difficult due to missing data. Resources need to be found to
provide consultation to Access Management for data cleaning. Also, extracts needto be reconsidered. 5/10/2007: Met with customers in April and they have
requested a demonstration of TransGIS (remotely) for the District Access
Coordinators to assist in determining additional project requirements. A schedulewill be set and a GIS/IS resource will be providing that demonstration. 11/8/07:
Meeting was held in Region 2 Tech. Center. Resources have delayed any
additional meetings. PM will speak with business and determine if enough
requirements have been identified to begin development of site.1/03/2007 - PM is
meeting to get an update on required data availability status with GIS dataadministrator and is scheduling a final requirements meeting in January with the
Project team. 03/20/08: PM has scheduled April meeting to determine if customer
will accept current data availability to meet project requirements. Need to set newend date. 04/15/08: Update meeting occurred. Scope reviewed; data layers in
review and application
needs solidified. New end date set. 05/09/08: No Change. 6/17/08: Surveyed field
permit
specialist for top 10 data layers most useful in their work. 7/16/2008 received 10
top layers,
proto type is developed and will be sent to business for approval. 9/3/08:
Application\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 18
-
7/30/2019 04-Gis Sc Project Status Report
19/36
Comments
3/13/06: Customers have received frequent training refresher courses. Data entry
has been validated. Insufficient resources to address 'instant-update' to main
database. Other report capability not distributed until resources available. 9/14/06:
Continued GIS and data support delivered by GIS Unit. Data is received by GIS
Unit as needed.11/01/06: Counting season complete. Data being received by GIS
Unit as it becomes available. 01/03/07: Data received and in review. 2007 Hose
Counts Sheets being prepared. Work with consultants continues. 3/8/07: 2007
count year application and data provided to field staff. Refresher training provided.
TSM staff trained to support field staff. GIS will assist in copying datasets during
collection season. GIS unit will append data to main database once approved byTSM staff.
7/13/06: GIS Team is awaiting data and value or rating system. 9/14/06: GIS Unit
working with sponsor to convey data and GIS standards, identify various resources,
review ongoing tests and define data responsibili ty. 2/21/07: This project on-hold
awaiting direction from business sponsor. 3/8/07: No business resources at this
time. 5/2/07: No business resources at this time. Contacted business (Safety
Management System staff) for future direction on this project. 7/16/2008 This
project has been on hold - Requested response from business to find out if
they still had interest in moving forward with this project. They have several
other related initatives in the queue at this time.
8/25/08: Deschutes County model: being updated in VISUM. Incorporating
Prineville into model. Finalizing base year. Deschutes County HERS-ST:
Process beginning to tie the VISUM model to HERS-ST (Highway Economic
Requirements System-State Version). Brookings model: being updated in
VISUM. Work progressing. Woodburn model: being updated in VISUM. Work
progressing. SWIM2: The statewide model team is working to meet a
November 1 deadline for beta version that will be used for analysis. The
project is in the middle of the final tasks needed to meet this date. Several
minor calibration tasks are being completed. Changes to file structure anddata storage on the SDC cluster are being tested. A few changes are needed
to the model GUI. During the testing phase several errors were identified and
are being corrected. OHAS: the pilot test locations have been identified-
Grants Pass, Eugene, and Gresham. The pilot will test the survey instrument
questions, recruitment methods random phone call, mailings, phone lists,
etc) , non-reponse issues, sampling, etc. The information gleaned from the
pilot will affect the design of the actual survey scheduled for ODOT
Region 2 this fall. GreenSTEP passed a major milestone August 14th
when i was peer reviewed. The consensus ws the model is robust and well
designed. Significant amount of work must be done on the input side, but
the bulk of the model is complete. The model overview was also
presented to the Oregon Global Warming Commission August 19, 2008
and received favorably. GreenSTEP is getting more and more attention
across agencies. The potential of this tool to be expanded and connected
across agencies and other analytical tools is increasing. The may become
more relevant to ODOT GIS efforts in the future.
\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office 19
-
7/30/2019 04-Gis Sc Project Status Report
20/36
Comments
OEM = Operations & Essential Maint.
*Small Projects
A*=Application
20
-
7/30/2019 04-Gis Sc Project Status Report
21/36
COMPLETED PROJECTS
Project #Project
Start
Date
End
Date
Adjusted
End Date
GIS09 GIS Software Evaluation Process
- Develop GIS software evaluation
guidelines (complete)
- Develop test plan template
(complete)
- Develop template for cost analysis
(Life cycle costs)
3/01/01
3/1/02
9/30/02
1/23/03
5/22/037/24/03
DGIS04 ITS Traffic Counting Equipment
(Closed on 3/01/01)
10/1/00 3/1/01
DGIS05 TransGIS (Version 2.0)
- Develop plan for next phase
- Intermodal (Freight)- Pavement
- Congestion
- Bridge
- Traffic Counting
9/1/01
DGIS06 Highway Layer for ArcView
- Conversion program from MGE to ArcInfo.Allows users to dynamically segment, review
and display their own highway data.
9/1/00 2/28/02
DGIS07 SMMS Web Based Access
- (DGIS 10 is complete)
2/15/01 5/15/02
DGIS09 Automated Collision Diagram- Phase 1
- Study options
6/30/01
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
22/36
COMPLETED PROJECTS
DGIS09 Automated Collision Diagram
- Phase 2
- Development/Testing
5/30/02 9/01/02
01/01/03
DGIS09 Automated Collision Diagram- Phase 3
- Implementation
3/1/03 4/01/035/22/03
DGIS10 SMMS Metadata migration to SQL Server 2/15/01 6/1/01
DGIS11 DMV Project 8/1/01 10/1/01
DGIS15 Access Control Demonstration- Incorporate resources
- Changes to CHAMPS database and
hyperlink to GIS tools
- Database development for ROW research
10/31/02 2/28/03
GIS01 Base Layer Development 3/24/98 9/22/98
GIS05 Aggregate Sites
Phase 1
Intranet database application
5/29/00 5/30/01
GIS05 Aggregate Sites
Phase 2
Intranet GIS application
1/31/01 5/30/01
GIS05 Aggregate Sites
Phase 3Desktop GIS application
12/31/00 5/30/01
GIS07 Non-State Hwy Functional Classification
System Attribution
6/1/00 12/1/01
GIS13 State Highway 1:24,000 road alignments 6/30/01 7/31/01
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
23/36
COMPLETED PROJECTS
GIS14 GIS Base Layers Phase 2- Select 6 new base layers1-Pavement Conditions 19992-ITS3-Bridge4-Intermodal (FIMS)5-Crash6-Non State Highway Functional Class7-Federal Urban Trans Boundary
Cust.: All GIS users
1/24/01 3/1/3102
GIS15 Non-State Hwy Functional Classification and
National Highway System to SQL
1/9/01 5/31/02
GIS16 Wasco County Pilot ProjectPhase 16 target areas
5/01/2001 6/30/01
GIS16 Wasco County Pilot Project
Phase 2All roads GIS coverage
7/23/01 9/30/01
GIS17 Upgrade of GIS related softwarePhase 1 - testing
10/25/01 3/31/02
GIS17 Upgrade of GIS related softwarePhase 2 - implementation
1/1/02 3/31/02
GIS18 Road Authority Database 7/1/01 10/1/01
GIS20 Oregon Statewide Burial Site & Cemetery
Base Layer(Phase 1) (Cultural framework)- Develop GIS layer for cemeteries from
ODOT map bases.(Approx. 500)
4/30/02 12/30/02
GIS20 Oregon Statewide Burial Site & CemeteryBase Layer(Phase 2) (Cultural framework)
4/30/02
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
24/36
COMPLETED PROJECTS
GIS21 GIS Layers Complete
Projects categorized as:OEM or Sm
Assign sub-numbers
(Quarterly drop-off cycle)
(Mar-Jun-Sept-Dec)
GIS23 OEM & Small Projects(OEM)
- Other projects completed by the GIS
Project Team
(Quarterly drop-off cycle)
(Mar-Jun-Sept-Dec)
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
25/36
COMPLETED PROJECTS
GIS24 Tsunami Inundation Mapping Analysis 3/5/2003 4/4/03
GIS26 On-Line Contractor Emergency RegistrySystem- Build GIS interface to IS Web developedsite
12/15/02 4/01/035/1/03
ArcView Lat/Long coordinates 08/01/00 9/15/00
Arc View Display of DGN Files 09/01/00 09/15/00
ArcView Location Reference System (LRS)Highway Milepoint Readout
08/01/00 09/15/00
GPS Standards 05/01/00 05/01/00
Rail Network 08/01/00 03/15/00
Rail Crossing 03/15/00 05/31/00
Federal benchmark layer (NGS) (Complete) 07/15/00
Desktop GIS - STIP/SIP (DGIS03a) 06/16/00 10/15/00
Joint Estimation Model Data Development(Medford)
05/15/00 09/30/00
ODOT Injection Wells Inventory (Phase 1)
(Complete)
6/22/00 09/01/00
Statewide Model Application Project(Willamette Valley)
6/1/00 12/1/00
Non-MPO Travel Model Data Support(Lebanon)
3/1/00 11/30/00
Generation 2 Statewide Model 7/1/99 12/31/01
Urban Transportation Model Development- Coos Bay/North Bend
6/1/01 12/1/01
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
26/36
COMPLETED PROJECTS
Urban Transportation Model Development
- Woodburn
9/1/01 6/1/02
Urban Transportation Model Development- Roseburg
3/13/02 5/30/02
Urban Transportation Model Development- Wilsonville
5/1/02
Urban Transportation Model Development
- Newberg
6/1/02 12/31/02
Urban Transportation Model Development- Redmond
12/31/02
Urban Transportation Model Development- Brookings
7/1/02 7/1/03
Urban Transportation Model Development- Central Oregon
5/1/03 7/1/03
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
27/36
COMPLETED PROJECTS
Comments
Outside contracts reviewed. Software evaluated. Project Plan created. ARC IMS Web software received 9/25/00.
Installed and sent through NPE. Approval received to purchase software. Placed on hold for lack of resources.Returned to active status 1/22/02. Draft of GIS Software Evaluation Guidelines presented to Steering Committee
3/28/02. Dennis will make revisions and bring to 1/23/03 committee meeting. Using purchase of SDE (spatial dataengine) GIS server software to develop and test process. (Will not work with OTS software). Used proposed ArcSDEacquisition to demonstrate revised Life Cycle template which is currently being revised based on Steering Committee
feedback. Complete
TDD and ITS Unit developing project plan. Gave demo to ITS Unit and fieldtechnicians. Wait ing for data needs assessment from ITS Unit. Roll-out
database using Internet GIS viewing tool as pilot. Updating and cleaning data
for pilot. Delivered prototype to customer for testing. Java script rewritten. Roll-out to additional users, distribute toITS. The application has been delivered.
Met with Pavement, STIP coordinators, Intermodal (Freight), Congestion, Traffic Safety, Bridge and TransportationSystems Monitoring. Re-scheduling to meet with Motor Carrier. Developing decision list to priorit ize actions.
Integrating data collection and storage for this and Region 2 Corridor Planning. Demo to Steering Committee 3/22/01.Met with Mgmt. System Managers to review data requests and formats. Continue to enhance and add features to theapplication (Shaded Relief, Print Functions, Save Settings, etc.). Work continues to enhance performance and
implement changes. Receiving data for all Hwy's: 2000 Pavement Friction, ITS Devices, partial Bridge data for Hwy162, ADT's and Speed data. Training complete, roll out from Mark Robinson on 9/28/01. Complete 10/22/01 will be
distributed to 60-70 additional users. In maintenance - to develop project plan for next phase.
Conversion program from MGE to ArcInfo. Created Measured Shapefile that can be used in ArcView 3.1. Common
alignments, equations and z mileages all displayed correctly. Minor problems uncovered, approx. 150 points did notplot. Documenting process, resolving problem areas. Testing by GISU is needed to determine if the file should bemade available to others throughout ODOT. Two measured shapefiles of the highway network were created in
January 2002 (1:24,000 network, production road network) with modified processes to improve accuracy. Testing byGISU continues. Complete 2/28/02
Loaded on test machine. Resources are needed. Software ready for testing, loading 10/2/01. Software DLL conflicts
halted implementation. No conflicts in new version of software. NPE submitted and software testing is underway.Metaweb and GeoConnect Admin Tools to be loaded when serial number is received from Intergraph. NPE for new
version complete. Loaded on test web. Bruce Westcott from Intergraph is working on problems withsoftware/hardware connections. Met with DBA and security on 5/3/02, web problem resolved. Testing under way with
Regions 1, 4 and 5. Change Mgmt. scheduled for May 28th, will then implement on production server. Complete
Software reviews complete, demo for Chuck complete, considering re-make of the Maryland model. City of Portland's
negative experience with the newest version of Intersection Magic and our crash data has discouraged its use. TrafficEngineers requested that we create our own package. The decision was made to design a new package using theMaryland system as a model. Complete
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
28/36
COMPLETED PROJECTS
Prototype in place and will make it similar to the in-house application (Visual Basic). Possible software to use for theactual drawing (Visio, MapObjects, MS Paint, etc.). 10/23/01 resources identified. Re-writing software. Working on
symbols to depict data. Should have prototype in May, first release in June and final release in September. Demo for
Traffic Managers meeting scheduled for June. Setting up two employees in Region 2 to test the application. DeliveredBeta version to R2 November 2nd. Testing and software revisions complete
Documentation nearly complete. Purchasing visio software. NPE review underway. Deploy 2 copies to each regionHQ traffic management staff. Visio software delivered, Documentation complete, demo to OTMS Steering Committee3/27/03. Distribution in process. Complete
Replace SMMS 3.1 with SMMS 3.2. Migrate from SMMS database to an SQL server. An SQL (test) server has been
built and the SMMS 3.2 SQL version is being tested. NPE in progress. Currently being placed on the SQL Server V7
(EXSQL7P2).Complete 6/12/01
Chuck met with DMV on July 18th to determine needs. Working on language breakdown. (I.e. Asian). Systemdelivered to DMV. In warranty mode. Complete 9/18/01 (80 hour project).
Resource materials have been acquired and sample sites chosen (The Dalles). Resources have been formatted intostandard/uniform projection. Project on hold, resources dedicated to GIS19. Project reactivated 11/10/02. Right-of-Way images acquired. Adobe Photoshop software on order to complete processing. Pilot covered State Highways in1 city. Pilot demo Complete .
Extended close date 11/30/00. Data Model approved, test data base has been created. Transferring data to newdatabase. Creating Standard and user documentation. Transferring data to production database (State highways,
County Boundaries, City limits, ATR sites). Finishing User documentation.
(1) Most of the application functions are complete. Adding enhancements and fixes as identified by the GeoHydrousers. GeoHydro forecasts completion by January 2002. Hired temp for data entry. Complete 7/13/01.
2.) Coordinating integration of the GIS portion. Application complete and in testing phase. Maintenance of aggregatesource location data needs to be worked out between GeoHydro and the GIS Unit. Complete 7/13/01.
3.) Script created to allow GeoHydro users to map data based on latitude and longitude values stored in the database
is waiting for review by Amy Landvoight and/or Mike Long. Scheduled review and acceptance June 7, 2001.Application is only for use by the GeoHydro personnel. Complete 7/13/01.
35,000 miles of road. 11/30/00 Attribution complete. Error checking in progress. Successfully developed and testedthe new MGE project and
access database. Complete 10/19/01.
Plus or Minus 40' of state highways. Complete August 2001.
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
29/36
COMPLETED PROJECTS
(Dependant on the completion of GIS 17) Add new layers to GIS SQL database 6 at a time. Database modeling anddata acquisition is under way. Layers changed to meet the needs of the Conditions Report and TransGIS version 2.Received 2001 Pavement Conditions data. Congestion data has been reviewed and released in TransGIS 2.1.
Congestion data is being viewed again. Re-visit corporate GIS base layers and bring back to Dec. 5th meeting.Project reassigned to GIS21. Descriptions and guidelines rewritten. Complete
Project Statement (002,026,028), Context of the System (140), Definition of the System/Subsystems (200/210), in draft
form awaiting approval. Began work on possible data model. Project Plan approved. Two prototype databasescreated on SQL server 7.0 for evaluation purposes on 8/31/01. Testing prototype SQL server database (HGIS15a)
using COTS (commercial off the shelf) software. Querying, reporting and updating capabilities are being tested usingGeoMedia Pro, Access and SQL Server utilities. Database model has been updated, preparing documentation (P Plus
Deliverables 170, 180 and 190). Testing and migration complete. Complete
Partner with other authorities to build a GIS network of all Oregon roads. First project co-operative with University ofOregon for completion of Wasco County. Contract review and data analysis took longer than anticipated, scope was
reduced. 6 target areas complete. Complete 6/26/01.
Phase 2 slightly delayed by other projects at the University; dedicated resources stretched thin resulting in attaching
attribution delays. Server crash caused some data loss. Other University obligations will end 10/5/01 at which timework will resume. Met with the University on 9/24/01 to resolve delays in phase 2 and discuss a potential phase 3
(additional counties). Complete 12/28/01 data sent to GPL and T-FIT for review.
Test existing GIS software and databases. NPE and testing completed on all products. Complete
Implementation plans are being developed. Migrate software and databases to SQL V7.0 adding capabilities andflexibility. Data structure modified and migrated to SQL 7. GeoMedia Pro is being used for production work.Complete
Database built and book published. Enhancements and updates are ongoing. Complete.
Met 9/24 to determine how to proceed with data compilation. Oregon Parks and Rec., ODOT Archeology and Mortuary
Board providing data. Fields confirmed at meeting. Verifying data entries. Completed GIS layer from ODOT map
base cemeteries.
Working with State Parks Div. who is adding Oregon Burial Guide cemeteries to our layer (additional 700 sites) and
BLM to build State Historical Preservation Office (SHPO). Complete
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
30/36
COMPLETED PROJECTS
ATR 2002 locations (ATR's) (OEM) 10/02ADT 2001 (Average Daily Traffic) (OEM) 10/02ODOT Areas Boundaries (OEM) 11/02
ASIS Aggregate Sites (OEM) 10/02Hwy Milepost Locations (OEM) 10/02
Schools Locations (All public schools) (OEM) 11/02Hwy Tenths for updated Hwy Network (OEM) 11/02US Corps of Engineers Navigable Waters (Complete 12/02) (OEM)Crash Segs 2001 (SIP) (Complete 12/02) (OEM)Crashes 5-yr composite by region (Complete 11/02) (OEM)Highways-lane widths (Complete 11/02) (OEM)
Highway-number of lanes (Complete 11/02) (OEM)Culverts 2002 (Complete 11/02) (OEM)
Truck Safety Corridors 2003Truck A/M Corridors 2003
Culverts 6-20 ft (12/03)Culverts less than 6 ft (12/03)Highway Mileposts 2002 (Complete 10/02) (OEM)Unincorporated Urban Communities 2002 (Complete 11/02) (OEM)ODOT Regions Boundaries (Complete 1/03) (OEM)
ODOT Districts Boundaries (Complete 1/03) (OEM)Highway Friction Values 2002 (Complete 2/03) (OEM)Highway Skid Factors 2002 (Complete 2/03) (OEM)Maintenance Crew Assignments (Complete 2/03) (OEM)
SPIS Sites (OEM) 4/03Tsunami ODOT Inundation Line (GIS21-04) (sm) 3/03
Complete:Access Mgmt ArcView (DGIS13-2) 11/01
Or State Hwy No. conversion (DGIS 13-17) 8/02A* CARS ArcExplorer (and CD for home users) (DGIS14-2) 2/03
A* Video Log-ArcExplorer Training (GIS23-05) 2/03D* Road Authority (GIS23-04)(Sm) 12/02D* City Annexation Data Modeling (GIS23-02)(Sm) (6/03)A* Software acquisition and distribution (Sm) (9/03)
A* Standard Data Display and Formatting (Sm) (10/03)A* Upgrade Crash Coder Desktop GIS tool and User Guide (OEM) (10/03)D* Bridge Location Project (11/03)D* 650 Map Project (11/03)A* Bridge Location to Web (11/03)
D* Ma in S eed-monitorin Loo s in Metro area for Traffic Condition
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
31/36
COMPLETED PROJECTS
Mapping project for statewide Tsunami exercise is complete. Maps show inundation line intersecting state highways,and lifeline routes. Being tested in statewide earthquake drill April 2nd and 3rd. Complete
Project development nearly complete. Mixture of techniques used to accomplish project. Internet use not yet
approved. Draft model presented to ODOT end-users 3/20 by the IS team (Diane Powers). Wait ing for XML templatesfrom IS Development Team. Network testing underway. Application and data complete and provided to customer. P+documentation in draft stage. Complete
Display Lat/Long coordinates and LRS in ArcView. The application is out for peer review. Ready to send through
product approval and Intranet roll-out. Going through NPE. (Complete)
Application complete. Ready to send through product approval and Intranet roll-out. (Complete)
Application complete. Ready to send through product approval and Intranet roll-out. Going through NPE. (Complete)
Document approved on April 20, 2000. Distribution is being planned
Revisions made, forwarded to State Forestry for review. Complete and delivered to State Service Center and GIS UserGroup.
User has accepted the ArcView Extension (application) software and installation instructions. Network testing of
extension is complete. Extension given to user.
Create National Geodetic Survey benchmark layer for Geometronics in ArcView & MGE software. (Complete)
Software purchase complete, documentation under development. Roll-out scheduled to start the week of August 28th.
Close after testing complete 10/10/00.
Quality check household activity locations from travel survey buffer points to create environmental design variables.
Building base layer of ODOT maintenance facilities (103) to satisfy Oregon's DEQ water permit requirements.(Complete)
Produce presentation of output from first generation statewide model. Completed 11/1/00. Project Lead was BrianGregor.
Base year employment & housing distributions and network characteristics. Completed 6/1/00. Project Lead was Sam
Ayash.
Road layer comprised of State Highways and nonhighways Functional Class network, attributed with functional class,number of lanes, posted speeds as available. Preliminary work should be completed by July 2001. Wil l be migrated to
statewide modeling software. Final review meeting scheduled in November 2001. GIS work for model is complete.
Wait ing for review from cities of the employment and household data. Recent vacancies in both City of Coos Bay andODOT Region 3 have slowed progress on this project. Employment and household data complete. Entering trafficcount data. Complete 12/31/01
Revised 10/12/00
-
7/30/2019 04-Gis Sc Project Status Report
32/36
COMPLETED PROJECTS
Transportation Analysis Zones (TAZ) defined. Count locations submitted to Region 2. Employer and householdgeocoding in progress. Region 2 will be hiring a consultant to perform field data collection. Employer and householdgeocoding complete. Region 2 has contracted with consultant to perform field data collection. TAZ and Network being
finalized. Analyzing traffic counts to network links. Incorporated city's housing and employment revisions. Complete
Scheduling with COG for update of existing model. Consultant compiling existing data. ODOT is collecting andreviewing traffic count data. Updating population and housing data for consultant. Complete 11/02
Reviewing consultant data. Complete
Providing preliminary TAZ, model road network, employment and housing data to City for review. Incorporating city
housing and employment revisions and forecast data. Need City of Dundee to validate employment, household andforecast data. Complete
Zone and network development in progress. Zones and network have been restructured. City has validated
employment and household data. Waiting for city to provide forecast data. Forecast data under development.Complete
Zone and network development in progress. Zones and network have been restructured. City has validated
employment and household data. Waiting for city to provide forecast data. Forecast data under development.Complete
Complete
Revised 10/12/00
ODOT Construction Plans andRi h f W M I d
GIS22
-
7/30/2019 04-Gis Sc Project Status Report
33/36
Right-of-Way Map Index
Drainage Facility Management- Develop system for inventorying,
evaluating and tracking condition ofpipes, culverts and storm waterfacilities
GIS29 11/1/03 3/4/04
Truck Route Permit Mapping and
Database
Phase 3- Outline processes formaintenance by data steward (MC)
GIS29 11/1/03 3/4/04
Region 1 Development Review
On Hold - Intranet application to create a spacial index (map) ofODOT C t ti j t d Ri ht f W fil d t t d i
-
7/30/2019 04-Gis Sc Project Status Report
34/36
ODOT Construction projects and Right-of-Way files data stored inITIS. Resources need to be assigned. Data from ITIS for Mapinformation has been obtained. Basic intranet application has beendeveloped in ArcIMS but does not include the Construction Projectsor Right-of-Way Maps, reports or additional queries. Projectapproved by Cathy Nelson. Project delayed due to other projectpriorities and lack of resources.
Phase 3 - On Hold - Motor Carrier is starting to maintain & updatedatabase. Route maps ready for State Printer. Completed 4separate MAP/GIS Layers, 1 in progress. Motor Carrier resourceshave not been available. Dennis will meet with Mike Bollinger todetermine direction.
Phase 3- On Hold- Motor Carrier is starting to maintain & update
database. Route maps ready for State Printer. Completed 4
separate MAP/GIS Layers, 1 in progress. Motor Carrier resourceshave not been available. Dennis will meet with Mike Bollinger to
determine direction.
-
7/30/2019 04-Gis Sc Project Status Report
35/36
TRAINING RECEIVED: SQL training 3/8/01
GeoMedia Intro Class 6/5/01
GIS in ActionGIS-T 2001
GeoMedia Pro 7/12/01-7/13/01-10/16/01-10/17/01-10/18/01
ArcIMS 6/28/01-6/29/01
TransGIS version 2 training
Advanced Access 10/23/01-10/24/01
SQL training 9/1/02
TransGIS version 2 training 1/02
GIS in Action, addressing conf. 08/02
XML Fundamentals fall/02
MicroStation V8 - GIS Unit 1/04Java - Chad N, Phil S 1/04
State Web dev Cert (HTML focus) fall/02
Sequal Server 2000 fall/02
ArcGIS 8 for Enviro Appl fall/02Map Objects Basics0online fall/02
MSTN V8 for Admin/User update 10/02
Java Scripting 11/02
Visual Basic-(Phil & Chad N)GIS Unit 12/02
HTML basics-Sue/GIS Unit 1/03
Excel XP - Sue/GIS Unit (1/03)
Cold Fusion - Lisa, Phil, Casey 4/03
ArcGIS - Casey, Phil, Lisa 4/03
Java Script - Lisa 4/03
Remote Control/Field Tach GIS course (8 GIS members) 5/03Requirements Mgmt - Sue 6/03
GIS in Action workshps and seminars-GIS Unit 5/04
MS access, advanced & Excel, advanced- Lisa L. 4/04
ArcGIS 9.0, I and II, (GISU), Kim Taylor (GeoEnviro), Charlotte
Gerkin (TSM), Chris Shearer and Diana Mann (RICS) 9/04
Java 1 Chad Nielsen (GISU)10/04
GPS Data Collection, Chad Nielsen, Casy Ragain (GISU),
Marcia Malstrom (IS), Jim Gavin (RICS), 9/04
GIS-T Lincoln Nebraska - Susan Mead (GIS), 04/05
TRAINING DELIVERED:
ArcView and ArcExplorer - Bridge Mgmt
ArcView - Darla Stoneman / Acces Mgmt
ArcExplorer - TSM
First Round - TransGIS users
GIS Tools-R1 6/02
ArcView-Darla Stoneman/Access Mgmt 6/02
TransGIS-initial users/R5 5/02
ArcExplorer - CAR 11/02
ONHP/ArcExplorer-Env at CCC and R3 10/02
GIS Tools R3 11/02
ArcExplorer-Access Mgmt (CHAMPS) 12/02
ArcExplorer - Motor Carrier 4/03
Resource Map Template production - Env. 4/03
Crash Viewer - Region 1- 5/03
ArcExplorer - 10 Approach Perm Spec 7/03
- -
ArcView - Region 1 staff 10/03
Crash Coding - CAR staff 10/03
GIS Brownbags 11/03
ArcView-General Support to Region 1 (Lisa) 6/04
15 users in queue
-
7/30/2019 04-Gis Sc Project Status Report
36/36
DEMONSTRATIONS:
ArcExplorer to GIS Steering Committee 3/22/01
ArcExplorer to OTMS Steering Committee 6/28/01Aggregate Demo
ESRI demo
Collision Diagram demo to Region Traffic Managers 6/02
OTMS - TransGIS & DMV demo 9/25/01
DMV demo to IS quarterly mgmt team 10/19/01
DMV & Trans GIS demo to GIS Steering Comm. 10/25/01
GIS Tools - ODOT Directors office 09-02
Rural Lands database project to GeoHydro 10/02
VBCrash to IT Exec Steering Comm and R2 10/02
TransGIS demo for Eugene Public Worls 11/02TransGIS demo for Eugene Public Worls 11/02
DMV App. & TransGIS - R2 Management 10/02
DMV App. & TransGIS - R2 Design Team 11/02
DMV App. & TransGIS - HR expanded staff 11/02
FC database demo-GIS Steering Comm 12/02
TransGIS demo for Traffic Recorder Techs 1/03
SR-SAM to GIS Steering Committee (1/03)
Functional Classification - TDS expanded staff 4/03GeoConnent/MetaWeb - GIS Steering Comm. 5/03
ArcGIS template - GIS Steering Comm. 5/03
TransGIS Web dev - TDS staff 6/03
ArcGIS 8.x template - TDS staff 6/03
TransGIS Web PP - Region1 Planners 6/03
TransGIS Web - OTMS SC - OTMS Exec SC - Trans. COI 6/03
TransGIS Web - GIS Steering Committee 7/03
TransGIS Web - TDS Expanded Staff 8/03
TransGIS PP - PBLT 8/03
TransGIS PP - Highway Division staff 12/03TransGIS - Chief of staff Lori Sundstrom 12/03
TransGIS - TPAU 12/03
TransGIS - Traffic Count Field Techs 1/04
Traffic Count GIS and Metro relationship 2/04
TransGIS - Planning Business Line Team 4/04
TransGIS - Parametrix 4/04
Network Software - GIS Steering Committee 5/04
GPS-ArcView Script for Data collect Team 7/04
TransGIS - OBDT 6/04
TransGIS - Region 1 Project Delivery 6/04Network Software - TPAU 6/04
TransGIS - Region 1 Traffic Mgmt 8/04
TransGIS - Region 1 Tech Center Managers 9/04
TransGIS - Region 4 Traffic Managers 9/04
TransGIS - DMV 10/04
TransGIS & Env TransGIS - OTMS Steering Comm 12/04
GIS File Storage System - GeoEnv Steering Comm 12/04
DMV App. & TransGIS - HR expanded staff 11/02
FC database demo-GIS Steering Comm 12/02
TransGIS demo for Traffic Recorder Techs 1/03
SR-SAM to GIS Steering Committee (1/03)
Functional Classification - TDS expanded staff 4/03
GeoConnent/MetaWeb - GIS Steering Comm. 5/03
ArcGIS template - GIS Steering Comm. 5/03
TransGIS Web dev - TDS staff 6/03
ArcGIS 8.x template - TDS staff 6/03
TransGIS Web PP - Region1 Planners 6/03
TransGIS Web - OTMS SC - OTMS Exec SC - Trans. COI 6/03