04/02/2004 - FH
Plans for 2005
PH-DT1-GS
![Page 2: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/2.jpg)
04/02/2004 - FH
Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans
Technicians: Andrea d’Auria, Patrick Carrie, Daniel Fromm, Steven Pavis, Albin Wasem, Sylvain de Boissieu Frederic Merlet
FSU: Aygun Aydin, Vincent Darras, Leon Muller, Herminio Rama, A. Sari.
Protvino Team: Andre Kiver, Vladimir Kosenko, Anatoli Kapitchinkov, and since 2 days: Alexander Provotorov, Irina Smotrova
On Behalf of
![Page 3: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/3.jpg)
Overview
• Achievements / short flashback on 2004• Update Resource Situation• Overview Construction Schedule• Detailed Plans for 2005• Installation Schedule (as shown in Nov. 04) • Forecast on Expenses for 2005• Next Steering Meeting
![Page 4: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/4.jpg)
Flashback 2004
• Mixer Module is nearly finished; 3 months delay bco Pressure Regulator; finished end of April.
• Pump Racks construction is ongoing (60-70% completed); finished by June (up to schedule).
• ATLAS Distribution; altogether 30 Racks, construction is ongoing (60-70% completed) (up to ATLAS Schedule)
• TPC debugging finished; installation at point 5 is ongoing (see Stefan’s talk)
![Page 5: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/5.jpg)
Summary 2004
• 2004 was a year with important progress for the construction of the gas systems.
• Work flow has considerably increased compared to previous years. (Component cleaning and analysis processes have improved a lot.)
• Internal Organization– FSU unit defined and installed. Major changes for work
organization and for the team leader.– Protvino Team increased from 1 to 3 persons.– Quality control has become systematic and the results are
encouraging.
New cleaning facility Bldg. Xxx is operational since one month.
![Page 6: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/6.jpg)
Developmental areas
• QC of modules after construction and cabling. Plan: use MTF database for Workflow (QC) and later for maintenance.
• Difficulties to handle the huge workflow in the lab. (number of components, number of racks in parallel,…) (We will be still at the critical load for the next 12 months.)
• Calibration of flow cells was too slow, but going fine now. Though, debugging and tuning is still taking a lot of time.
![Page 7: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/7.jpg)
Present Resource Situation
1. Construction and Installation Manpower
• PROTVINO team 5 people • FSU 5 people
2. Lab Space:– Labs in Bldg’s 155 and 167 are
operational
– New Lab in Bldg. 216 will be ready end of March.
Pipe worker Cabler
4 1
4 1(Since yesterday)
The department has given high priority and SMI group has worked very fast
![Page 8: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/8.jpg)
Work Plan Overview
Construction
2006 20072005
Installation
Commissioning
Main serial construction should end autumn 2006
ALICETPC
Pilot commissioningmulti channel
system
Main commissioning
phase
Installation block for block
![Page 9: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/9.jpg)
Objectives 2005
• Finnish Mixer Module: by April
• Finnish Pump – Mechanics by April/Mai– Chassis and Cabling around June
• Humidifier Module– New module 2 racks to built.– Chassis and Controls covered by Xavier.
• Exhaust Module start by April • ATLAS ID Flushing systems (finish <
November)
Rack Construction (1)
![Page 10: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/10.jpg)
Objectives 2005
• Distribution:– ATLAS (Muon) finish all racks < May.
Including calibrated flowcells
– ATLAS TRT Distribution (deliver Racks < July)
– Build ALICE and LHCb during second half of 2005.
Rack Construction (2)
Target: Finish all distribution racks by the end of 2005
![Page 11: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/11.jpg)
Objectives 2005
• We would like to make a number of control chassis, i.e. Pump, Exhaust, Humidifier, Purifier, CC-Module. (to be produced outside)
• The Hardware Modules made in 2005 need to be cabled: Distribution, Pump, Exhaust, Humidifier.
• The Distribution read-out:– Large scale test of ELMB’s, Webmass (new interface to
CAN bus)
• The cabling layouts for the experimental sites have to be made and communicated to the experiments.
Electrical Control Chassis and Cabling
… and this starts toady, see talk of Steven
![Page 12: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/12.jpg)
Overview Construction Schedule
Distribution
Mixer (series)
Purifier (series)
SG-Circulation, Exhaust (series)
Pump (series)
Humidifier Module
Pre-Distribution (series)
Membrane Sep. (series)
Special Units:
TRT Distribution (ATLAS)
RICH Modules (LHCb)
ID Flushing (ATLAS)
2006 20072005
New
Advanced
…still to come
Delayed
![Page 13: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/13.jpg)
Installation Phase (1) (Managed by Mar Capeans)
• A new phase with new difficulties:– Safety requirements (work permits, equipment,
etc.)– Need more tools and equipment that stay on-site. – Rationalize work organisation bco. distance to the
sites; – Need a 2nd car for the Section.
• Propose: cost sharing 700 CHF/y/experiment.
Note: currently we can effort to work only on one site at a time.
![Page 14: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/14.jpg)
Installation Phase (2)
Installation should be organized by Zones:– ALICE TPC is pilot installation– Generally UX caverns come first, rack connections of
multi channel systems are handled by piping contracts of the experiments. (example CMS)
– SG and US areas: should be installed as complete areas where possible
• Plan: Start with ALICE TPC then may be CMS SG
– Apart from some exceptions commissioning of closed loop systems will be done in 2007.
– Flushing of Open circuits can be possible before.
![Page 15: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/15.jpg)
Proposal Installation Planning (1)
Area / Sub-Detector
InstallationSG Building
MuonsTRT
USA15UX
Muons BarrelMuons EndcapTRT
System Commissioning InstallationTRT MilestoneMuons Commissioning
20072004 20062005 ATLAS:•UX racks in time in 2005•Main Commiss. in 2007
Area / Sub-DetectorInstallation
SG BuildingUSC55UX Cavern
Closed Loop Commissioning
2004 2005 2006 2007
CMS :•UX racks are done•Do SG in 2005
Closed LoopCommissioning
As shown in November 2004
![Page 16: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/16.jpg)
Proposal Installation Planning (2)
Area / Sub-Detector
InstallationTPCSG BuildingPlugUX CavernSystem Commissioning
Single Pass SystemsTRD, TOF
20072004 20062005 ALICE:•TPC in commis. early 2005•Single Pass Syst.’s Mid. 2006•TRD, TOF in 2007
Area / Sub-DetectorInstallationSG BuildingUXAUXCSystem Commissioning
Muon, OTRICH
2004 2005 2006 2007
LHCb:•Muon and OT Distribution early 2006•RICH’s pending
TRDAs shown in November 2004
![Page 17: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/17.jpg)
Installation Schedule
• The schedule is not rock solid, adjustments and corrections to optimize the work flow will be necessary.
• Arbitration must be done in the Steering Meeting
![Page 18: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/18.jpg)
Steering Meeting / 6 months
Providing:• Full status report on the project• Cost review• Schedule review • Status of production rate.
• Next Meeting:Date to be scheduled ( June 2005 ? )
![Page 19: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea](https://reader036.vdocument.in/reader036/viewer/2022072015/56649edb5503460f94beac39/html5/thumbnails/19.jpg)
Forecast for Expenses in 2005
ATLAS[kCHF]
CMS [kCHF]
ALICE [kCHF]
LHCb [kCHF]
Materials 273 161 172 (+TRD) 266
Manpower 20 100 180 160
Total 293 261 352 426
Period: March 2005 to Dec. 2005