04/02/2004 - FH Plans for 2005 PH-DT1-GS

Upload: whitney-butler

Post on 02-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

04/02/2004 - FH

Plans for 2005

PH-DT1-GS

Page 2: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

04/02/2004 - FH

Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans

Technicians: Andrea d’Auria, Patrick Carrie, Daniel Fromm, Steven Pavis, Albin Wasem, Sylvain de Boissieu Frederic Merlet

FSU: Aygun Aydin, Vincent Darras, Leon Muller, Herminio Rama, A. Sari.

Protvino Team: Andre Kiver, Vladimir Kosenko, Anatoli Kapitchinkov, and since 2 days: Alexander Provotorov, Irina Smotrova

On Behalf of

Page 3: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Overview

• Achievements / short flashback on 2004• Update Resource Situation• Overview Construction Schedule• Detailed Plans for 2005• Installation Schedule (as shown in Nov. 04) • Forecast on Expenses for 2005• Next Steering Meeting

Page 4: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Flashback 2004

• Mixer Module is nearly finished; 3 months delay bco Pressure Regulator; finished end of April.

• Pump Racks construction is ongoing (60-70% completed); finished by June (up to schedule).

• ATLAS Distribution; altogether 30 Racks, construction is ongoing (60-70% completed) (up to ATLAS Schedule)

• TPC debugging finished; installation at point 5 is ongoing (see Stefan’s talk)

Page 5: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Summary 2004

• 2004 was a year with important progress for the construction of the gas systems.

• Work flow has considerably increased compared to previous years. (Component cleaning and analysis processes have improved a lot.)

• Internal Organization– FSU unit defined and installed. Major changes for work

organization and for the team leader.– Protvino Team increased from 1 to 3 persons.– Quality control has become systematic and the results are

encouraging.

New cleaning facility Bldg. Xxx is operational since one month.

Page 6: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Developmental areas

• QC of modules after construction and cabling. Plan: use MTF database for Workflow (QC) and later for maintenance.

• Difficulties to handle the huge workflow in the lab. (number of components, number of racks in parallel,…) (We will be still at the critical load for the next 12 months.)

• Calibration of flow cells was too slow, but going fine now. Though, debugging and tuning is still taking a lot of time.

Page 7: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Present Resource Situation

1. Construction and Installation Manpower

• PROTVINO team 5 people • FSU 5 people

2. Lab Space:– Labs in Bldg’s 155 and 167 are

operational

– New Lab in Bldg. 216 will be ready end of March.

Pipe worker Cabler

4 1

4 1(Since yesterday)

The department has given high priority and SMI group has worked very fast

Page 8: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Work Plan Overview

Construction

2006 20072005

Installation

Commissioning

Main serial construction should end autumn 2006

ALICETPC

Pilot commissioningmulti channel

system

Main commissioning

phase

Installation block for block

Page 9: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Objectives 2005

• Finnish Mixer Module: by April

• Finnish Pump – Mechanics by April/Mai– Chassis and Cabling around June

• Humidifier Module– New module 2 racks to built.– Chassis and Controls covered by Xavier.

• Exhaust Module start by April • ATLAS ID Flushing systems (finish <

November)

Rack Construction (1)

Page 10: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Objectives 2005

• Distribution:– ATLAS (Muon) finish all racks < May.

Including calibrated flowcells

– ATLAS TRT Distribution (deliver Racks < July)

– Build ALICE and LHCb during second half of 2005.

Rack Construction (2)

Target: Finish all distribution racks by the end of 2005

Page 11: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Objectives 2005

• We would like to make a number of control chassis, i.e. Pump, Exhaust, Humidifier, Purifier, CC-Module. (to be produced outside)

• The Hardware Modules made in 2005 need to be cabled: Distribution, Pump, Exhaust, Humidifier.

• The Distribution read-out:– Large scale test of ELMB’s, Webmass (new interface to

CAN bus)

• The cabling layouts for the experimental sites have to be made and communicated to the experiments.

Electrical Control Chassis and Cabling

… and this starts toady, see talk of Steven

Page 12: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Overview Construction Schedule

Distribution

Mixer (series)

Purifier (series)

SG-Circulation, Exhaust (series)

Pump (series)

Humidifier Module

Pre-Distribution (series)

Membrane Sep. (series)

Special Units:

TRT Distribution (ATLAS)

RICH Modules (LHCb)

ID Flushing (ATLAS)

2006 20072005

New

Advanced

…still to come

Delayed

Page 13: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Installation Phase (1) (Managed by Mar Capeans)

• A new phase with new difficulties:– Safety requirements (work permits, equipment,

etc.)– Need more tools and equipment that stay on-site. – Rationalize work organisation bco. distance to the

sites; – Need a 2nd car for the Section.

• Propose: cost sharing 700 CHF/y/experiment.

Note: currently we can effort to work only on one site at a time.

Page 14: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Installation Phase (2)

Installation should be organized by Zones:– ALICE TPC is pilot installation– Generally UX caverns come first, rack connections of

multi channel systems are handled by piping contracts of the experiments. (example CMS)

– SG and US areas: should be installed as complete areas where possible

• Plan: Start with ALICE TPC then may be CMS SG

– Apart from some exceptions commissioning of closed loop systems will be done in 2007.

– Flushing of Open circuits can be possible before.

Page 15: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Proposal Installation Planning (1)

Area / Sub-Detector

InstallationSG Building

MuonsTRT

USA15UX

Muons BarrelMuons EndcapTRT

System Commissioning InstallationTRT MilestoneMuons Commissioning

20072004 20062005 ATLAS:•UX racks in time in 2005•Main Commiss. in 2007

Area / Sub-DetectorInstallation

SG BuildingUSC55UX Cavern

Closed Loop Commissioning

2004 2005 2006 2007

CMS :•UX racks are done•Do SG in 2005

Closed LoopCommissioning

As shown in November 2004

Page 16: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Proposal Installation Planning (2)

Area / Sub-Detector

InstallationTPCSG BuildingPlugUX CavernSystem Commissioning

Single Pass SystemsTRD, TOF

20072004 20062005 ALICE:•TPC in commis. early 2005•Single Pass Syst.’s Mid. 2006•TRD, TOF in 2007

Area / Sub-DetectorInstallationSG BuildingUXAUXCSystem Commissioning

Muon, OTRICH

2004 2005 2006 2007

LHCb:•Muon and OT Distribution early 2006•RICH’s pending

TRDAs shown in November 2004

Page 17: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Installation Schedule

• The schedule is not rock solid, adjustments and corrections to optimize the work flow will be necessary.

• Arbitration must be done in the Steering Meeting

Page 18: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Steering Meeting / 6 months

Providing:• Full status report on the project• Cost review• Schedule review • Status of production rate.

• Next Meeting:Date to be scheduled ( June 2005 ? )

Page 19: 04/02/2004 - FH Plans for 2005 PH-DT1-GS. 04/02/2004 - FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea

Forecast for Expenses in 2005

ATLAS[kCHF]

CMS [kCHF]

ALICE [kCHF]

LHCb [kCHF]

Materials 273 161 172 (+TRD) 266

Manpower 20 100 180 160

Total 293 261 352 426

Period: March 2005 to Dec. 2005