05 water and energy

84
KIBERT CHAPTERS 9 & 10 SBLT101 FALL 2016

Upload: jill-watkins-leed-ap-bdc

Post on 26-Jan-2017

33 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 05 Water and Energy

KIBERT CHAPTERS 9 & 10 SBLT101 FALL 2016

Page 2: 05 Water and Energy
Page 3: 05 Water and Energy

Water Resource Depletion/Distribution

Page 4: 05 Water and Energy

Hydrologic Cycle Terminology (p.331)Hydrologic Cycle

Potable Water

Groundwater

Surface Water

Stormwater

Rainwater

Page 5: 05 Water and Energy

Hydrologic Cycle Terminology (p.331)Rainwater Harvesting

Reclaimed Water

Blackwater

Graywater

Xeriscaping

Living Machine

Page 6: 05 Water and Energy

Green Building Water Strategy1. Minimize the consumption of potable water.

2. Minimize wastewater generation.

3. Maximize rainwater infiltration into the ground.

Page 7: 05 Water and Energy

Benefits of Water EfficiencyEnergy savings – more money can be saved by reducing the energy needed to move, process, and treat water than the actual value of the saved water

Reduced wastewater production – reducing overall water consumption also reduces wasterwater generation, plus, wastewater costs can be significantly higher than the cost of potable water

Lower infrastructure costs

Environmental benefits – reduced need for natural resource

Page 8: 05 Water and Energy

Steps to Developing a Water Strategy1. Select the appropriate water sources for each consumption purpose.

2. For each purpose, employ technologies that minimize water consumption.

3. Evaluate the potential for a dual wasterwater system.

4. Analyze potential for innovated wastewater strategies.

5. Apply life cycle costing

6. Design landscaping to use minimal water.

7. Design parking, paving, roads, and landscaping to maximize the infiltration of stormwater

8. Incorporate green roofs.

Page 9: 05 Water and Energy

Plumbing Fixtures & ControlsToilets and Urinals

Showers

Faucets

Drinking Fountains

Electronic Controls

Page 10: 05 Water and Energy

Nonpotable Water SourcesRainwater Harvesting

Graywater Systems

Reclaimed Water

Page 11: 05 Water and Energy

Wastewater StrategiesConstructed Wetlands

Living Machines

Page 12: 05 Water and Energy

Stormwater Strategies (p. 355)Vegetated roofs

Bioswales

Infiltration basins

Pervious paving

Page 13: 05 Water and Energy

Landscape StrategiesProper planning and design

Soil analysis

Appropriate plant selection

Practical turfgrass areas

Efficient irrigation

Use of mulches

Appropriate maintenance

Page 14: 05 Water and Energy

Landscape StrategiesCharacteristics of the natural landscape:

Regional identity – sense of place

Intricacy and detail – biodiversity

Elements of change – seasonal

Page 15: 05 Water and Energy

11 POINTS, 3 PREREQUISITES

Page 16: 05 Water and Energy

Prereq: Outdoor Water Use ReductionINTENT

To reduce outdoor water consumption.

Page 17: 05 Water and Energy

Prereq: Outdoor Water Use ReductionREQUIREMENTS

Reduce outdoor water use through one of the following options

Option 1: No Irrigation Required.◦ Show that landscape plants do not require a permanent irrigation system beyond a 2-year

establishment period.

Option 2: Reduced Irrigation.◦ Reduce the project’s landscape water requirement by at least 30% from the baseline for the site’s peak

watering month.

Page 18: 05 Water and Energy

Prereq: Indoor Water Use ReductionINTENT

To reduce indoor water consumption.

Page 19: 05 Water and Energy

Prereq: Indoor Water Use ReductionREQUIREMENTS

Reduce overall water consumption by 20% from baseline for the fixtures and fittings in Table 1.

Page 20: 05 Water and Energy

Prereq: Indoor Water Use ReductionREQUIREMENTS

Reduce overall water consumption by appliances and equipment by meeting requirements in Table 2.

Page 21: 05 Water and Energy

Prereq: Indoor Water Use ReductionREQUIREMENTS

Reduce overall water consumption by processes by meeting requirements in Table 3.

Page 22: 05 Water and Energy

Prereq: Indoor Water Use ReductionADDITIONAL GUIDANCE

1. Select compliance path:• Path 1: Projects where all fixtures meet EPA WaterSense standards. Submit product information.

• Path 2: Projects where fixtures do not meet WaterSense standards. Show use-based calculations to demonstrate 20% reduction total for all fixtures.

2. Specify WaterSense labeled products: tank toilets, urinals, showerheads, private restroom faucets and aerators.

3. Specify high-efficiency fixtures and appliances. Things to keep in mind:• Some fixtures do not need to meet the 20% reduction: food service-related equipment, fixtures

regulated by health codes, janitor sinks, laboratory sinks

Page 23: 05 Water and Energy

Prereq: Indoor Water Use ReductionADDITIONAL GUIDANCE• Differences between public and private restrooms: Fixtures in residences, hotel rooms, and private

hospital rooms are private. All others are public.

• Commercial projects containing residential-type dishwashers, washing machines, etc. should comply with residential water standards for these fixtures.

4. Design process water systems, including equipment cooling systems, to limit or eliminate potable water use and to capture and reuse excess generated heat.

Page 24: 05 Water and Energy

Prereq: Indoor Water Use ReductionDOCUMENTATION AND CALCULATIONS

1. Project occupancy. Count occupants consistently across all LEED credits.

2. Gender ratio. Default gender mix is half male and half female. Assumptions that differ from the default must be supported by a narrative and supporting data.

3. Days of operation. Default is 365.

4. Fixture types, flush or flow rate, product information, % of occupants using each fixture.

5. Occupant types: employees and staff (FTE), and visitors.

Page 25: 05 Water and Energy

Prereq: Indoor Water Use ReductionDOCUMENTATION AND CALCULATIONS

Page 26: 05 Water and Energy

Prereq: Building-Level Water MeteringINTENT

To support water management and identify opportunities for additional water savings by tracking water consumption.

Page 27: 05 Water and Energy

Prereq: Building-Level Water MeteringREQUIREMENTS

Install permanent water meters that measure total potable water use for the building and site. Meter data must be summarized monthly and annually. Can be manual or automated.

Commit to sharing with USGBC the whole-project water data for a five-year period beginning on the date the project is LEED certified.

Page 28: 05 Water and Energy

Credit: Outdoor Water Use ReductionINTENT

To reduce outdoor water consumption.

Page 29: 05 Water and Energy

Credit: Outdoor Water Use ReductionREQUIREMENTS (1-2 pts.)

Reduce outdoor water use through one of the following options

Option 1: No Irrigation Required.◦ Show that landscape plants do not require a permanent irrigation system beyond a 2-year

establishment period.

Option 2: Reduced Irrigation.◦ Reduce the project’s landscape water requirement by at least 50% from the baseline for the site’s peak

watering month.

50% reduction = 1 point

100% reduction = 2 points

Page 30: 05 Water and Energy

Credit: Indoor Water Use ReductionINTENT

To reduce indoor water consumption.

Page 31: 05 Water and Energy

Credit: Indoor Water Use ReductionREQUIREMENTS

Reduce overall water consumption by at least 25% from baseline for the fixtures and fittings in Table 1.

Page 32: 05 Water and Energy

Credit: Indoor Water Use ReductionADDITIONAL GUIDANCE

1. Consider alternate water sources: reclaimed water, graywater, rainwater, stormwater, used process water, etc.

2. Untreated water sources from streams, rivers, well water, etc. are ineligible.

3. Choose uses that need the least treatment first, such as irrigation and toilet flushing.

Page 33: 05 Water and Energy

Credit: Cooling Tower Water UseINTENT

To conserve water used for cooling tower makeup while controlling microbes, corrosion, and scale in the condenser water system.

Page 34: 05 Water and Energy

Credit: Cooling Tower Water UseBEHIND THE INTENT

Refrigeration systems remove heat, usually from air, to cool the interior of buildings.

This heat is expelled into either the atmosphere or another medium.

A cooling tower removes heat in part by evaporating water; as the water absorbs heat, it changes from a liquid to a vapor.

As the water evaporates, dissolved solids become more concentrated in the remaining water and eventually begin to deposit themselves on parts of the cooling tower, making them less efficient.

To prevent buildup of deposits, cooling towers remove a portion of the water through a process called blowdown. Makeup water is then added to replace evaporative losses and blowdown volume.

Page 35: 05 Water and Energy

Credit: Cooling Tower Water UseBEHIND THE INTENT

Cooling tower water efficiency is measured in the number of recirculation cycles before water must be removed by blowdown.

To significantly reduce makeup water inputs, optimize and increase the number of recirculation cycles by treating water to remove dissolved solids, rather than by relying only on blowdown and input of fresh makeup water.

Consider using A/C or steam condensate water or rainwater as makeup, instead of potable.

Page 36: 05 Water and Energy

Credit: Cooling Tower Water UseREQUIREMENTS

For cooling towers and evaporative condensers, conduct a one-time potable water analysis, measuring at least the five control parameters in Table 1.

Limit cooling tower cycles to avoid exceeding maximum values for any of the parameters.

Page 37: 05 Water and Energy

Credit: Cooling Tower Water UseREQUIREMENTS

Page 38: 05 Water and Energy

KIBERT CHAPTER 9

Page 39: 05 Water and Energy

Relationship Between Energy & WaterWEBBER ENERGY GROUP

Introduction

https://www.youtube.com/watch?v=Q9niPtOaPsw&list=PLNj4-L0QtXnTUy0R9c2QNsGWhNH0pV1fr&index=1

Energy & Water

https://www.youtube.com/watch?v=zHODtBhcLlU&list=PLNj4-L0QtXnTUy0R9c2QNsGWhNH0pV1fr&index=28

Page 40: 05 Water and Energy

Building Energy IssuesWEBBER ENERGY GROUP

Energy & the Built Environment:

https://www.youtube.com/watch?v=VYAI1hRGwxw&index=24&list=PLNj4-L0QtXnTUy0R9c2QNsGWhNH0pV1fr

Page 41: 05 Water and Energy

High-Perf. Building Energy Strategy1. Use building energy simulation tools throughout the design process

2. Optimize passive solar design of the building

3. Maximize the thermal performance of the building envelope

4. Minimize internal building loads

5. Maximize daylighting and integrate with a high-efficiency lighting system

6. Design a hyper-efficient HVAC system that minimized energy use

7. Select high-efficiency appliances and motors

8. Maximize use of renewable energy systems

9. Harvest and use waste energy

Page 42: 05 Water and Energy

Passive Design StrategyAUTODESK SUSTAINABILITY WORKSHOP

https://www.youtube.com/watch?v=sSyM9_BRH3Y&list=PLU-TfPimPH1T-1r79uoX0dM9ipHyzd0C1&index=3

Page 43: 05 Water and Energy

Passive Design Strategy1. SHAPE, ORIENTATION, AND MASSING 2. DAYLIGHTING

Page 44: 05 Water and Energy

Passive Design Strategy3. PASSIVE VENTILATION 4. PASSIVE COOLING

Page 45: 05 Water and Energy

Building Envelope(Climate zones p. 286)

Walls – thermal conductance/U-value

Windows – solar heat gain (SHGC) vs. visual transmittance (VT)

Roofs – solar reflectance index (SRI)

Page 46: 05 Water and Energy

Interior Load ReductionAUTODESK SUSTAINABILITY WORKSHOP

https://www.youtube.com/watch?v=iwDV6jg_6j0&list=PLU-TfPimPH1T-1r79uoX0dM9ipHyzd0C1&index=4

Page 47: 05 Water and Energy

Active Mechanical SystemsAUTODESK SUSTAINABILITY WORKSHOP

https://www.youtube.com/watch?v=Otm1oQDx71Y&index=1&list=PLU-TfPimPH1T-1r79uoX0dM9ipHyzd0C1

Page 48: 05 Water and Energy

Water HeatingSOLAR HOT WATER

Page 49: 05 Water and Energy

Electrical Power SystemsAUTODESK SUSTAINABILITY WORKSHOP

Lighting

https://www.youtube.com/watch?v=7tzBmMhdimc&list=PLU-TfPimPH1T-1r79uoX0dM9ipHyzd0C1&index=2

Intro to Energy Use

https://www.youtube.com/watch?v=4q8ugvNZyrM&list=PLU-TfPimPH1T-1r79uoX0dM9ipHyzd0C1&index=15

Page 50: 05 Water and Energy

Innovate!PACIFIC NORTHWEST LABS

https://www.youtube.com/watch?v=7EKhTNYLCTY

U.S. DEPARTMENT OF ENERGY

https://www.youtube.com/watch?v=rMXz455gt4o

Page 51: 05 Water and Energy

33 POINTS TOTAL, 4 PREREQUISITES

Page 52: 05 Water and Energy

Prereq: Fundamental CommissioningINTENT

To support the design, construction, and eventual operation of a project that meets the owner’s project requirements for energy, water, indoor environmental quality, and durability.

Page 53: 05 Water and Energy

Prereq: Fundamental CommissioningREQUIREMENTS

Complete commissioning requirements for mechanical, electrical, plumbing, and renewable energy systems and assemblies.

The building envelope, security system, fire alarm system, sprinklers and communication systems may also be included, but are not required.

Page 54: 05 Water and Energy

Prereq: Fundamental CommissioningREQUIREMENTS

Owner and design team develop the Owner’s Project Requirements (OPR) and the Basis of Design (BOD) documents.

The commissioning agent (CxA):• Reviews the OPR, BOD and project design

• Develops and implements the Cx plan

• Confirm incorporation of Cx req’ts. into the construction documents

• Develop construction checklists

• Develop functional testing procedures

• Verify testing execution

• Maintain an issues log throughout the Cxprocess

• Prepare final report

• Communicate directly with the owner

Page 55: 05 Water and Energy

Prereq: Fundamental CommissioningREQUIREMENTS

Page 56: 05 Water and Energy

Prereq: Minimum Energy PerformanceINTENT

To reduce the environmental and economic harms of excessive energy use by achieving a minimum level of energy efficiency for the building and its systems.

Page 57: 05 Water and Energy

Prereq: Minimum Energy PerformanceREQUIREMENTS

Option 1: Whole-building energy simulation◦ Demonstrate an improvement of 5% for new construction or 3% for major renovations in the building’s

performance rating compared with the baseline.

◦ Baseline = ASHRAE Standard 90.1-2010

◦ Meet this requirement before taking credit for renewable energy systems.

Use this option if:◦ The design team wants to continually review design decisions

◦ If the building or systems are complex

◦ If the project will use on-site renewable energy

Page 58: 05 Water and Energy

Prereq: Minimum Energy PerformanceREQUIREMENTS

Option 2: Prescriptive compliance with ASHRAE 50% Advanced Energy Design Guide• Meet ASHRAE Standard 90.1-2010 provisions

• Meet HVAC and water heating requirements in Chapter 4 of the ASHRAE 50% Advanced Energy Design Guide for Small to Medium Office Buildings (buildings smaller than 100,000 SF)

Use this option if:◦ If the building or systems are not complex

◦ If the building is under 100,000 SF (office/retail)

Page 59: 05 Water and Energy

Prereq: Minimum Energy PerformanceREQUIREMENTS

Option 3: Prescriptive compliance with Advanced Buildings Core Performance Guide• Meet ASHRAE Standard 90.1-2010 provisions

• Meet Sections 1-3 of the Core Performance Guide

Use this option if:◦ If the building is under 100,000 SF

◦ If the building is not a school, hospital, warehouse, or laboratory

Projects pursuing this Option cannot achieve points under EA Credit Optimize Energy Performance

Page 60: 05 Water and Energy

Prereq: Building-Level Energy MeteringINTENT

To support energy management and identify opportunities for additional energy savings by tracking building-level energy use.

Page 61: 05 Water and Energy

Prereq: Building-Level Energy MeteringREQUIREMENTS

Install building-level energy meters, or submeters whose data can be combined to show total energy consumption for all types (electricity, natural gas, steam, propane, etc.). Meter data must be summarized at least monthly.

Commit to sharing with USGBC the whole-project energy data for a five-year period beginning on the date the project is LEED certified.

Page 62: 05 Water and Energy

Prereq: Fundamental Refrigerant Mgt.INTENT

To reduce stratospheric ozone depletion.

Page 63: 05 Water and Energy

Prereq: Fundamental Refrigerant Mgt.REQUIREMENTS

Do not use chlorofluorocarbon (CFC)-based refrigerants in new heating, ventilating, air-conditioning, and refrigeration systems. When reusing existing HVAC&R equipment, complete a comprehensive CFC phase-out conversion before project completion. Phase-out plans extending beyond the project completion date will be considered on their merits.

Existing small equipment, like refrigerators and others that contain less than 225g of refrigerant, are exempt.

Page 64: 05 Water and Energy

Credit: Enhanced CommissioningINTENT

To further support the design, construction, and eventual operation of a project that meets the owner’s project requirements for energy, water, indoor environmental quality, and durability.

Page 65: 05 Water and Energy

Credit: Enhanced CommissioningREQUIREMENTS (2-6 pts.)

Option 1: Enhanced Systems Commissioning (3-4 pts.)◦ Path 1: Enhanced Commissioning (3 pts.)

◦ Complete commissioning requirements for mechanical, electrical, plumbing, and renewable energy systems and assemblies.

◦ (The building envelope, security system, fire alarm system, sprinklers and communication systems may also be included, but are not required.)

◦ The CxA must review contractor submittals during construction, verify system manual requirements and operator/occupant training requirements in the construction documents, and develop an ongoing commissioning plan.

◦ The CxA must review building operations 10 months after substantial completion.

OR◦ Path 2: Enhanced and Monitoring of Commissioning (4 pts.)

◦ Achieve Path 1.

◦ Develop monitoring-based procedures and measurements and update the systems manual as required.

Page 66: 05 Water and Energy

Credit: Enhanced CommissioningREQUIREMENTS (2-6 pts.)

AND/OR

Option 2: Envelope Commissioning (2 pts.)◦ Complete commissioning requirements for mechanical, electrical, plumbing, and renewable energy systems and assemblies.

◦ The CxA must review contractor submittals during construction, verify system manual requirements and operator/occupant training requirements in the construction documents, and develop an ongoing commissioning plan.

◦ The CxA must review building operations 10 months after substantial completion.

Envelope tests could include:◦ Air and water infiltration

◦ Thermal performance and air leakage

◦ Pressure

◦ Daylight glare control

Page 67: 05 Water and Energy

Credit: Enhanced CommissioningREQUIREMENTS (2-6 pts.)

Documentation for this credit can be the basis for documenting compliance for LEED O+M.

Page 68: 05 Water and Energy

Credit: Optimize Energy PerformanceINTENT

To achieve increasing levels of energy performance beyond the prerequisite standard to reduce environmental and economic harms associated with excessive energy use.

Page 69: 05 Water and Energy

Credit: Optimize Energy PerformanceREQUIREMENTS (1-18 pts.)

Establish an energy performance target no later than the schematic design phase. The target must be established as kBtu per square foot-year of source energy use.

Option 1: Whole-Building Energy Simulation (1-18 pts.)◦ Analyze efficiency measures during the design process, focusing on load reduction and HVAC-related

strategies, including passive measures.

◦ Renewable energy systems can be included.

◦ Points are awarded according to the following table:

Page 70: 05 Water and Energy
Page 71: 05 Water and Energy

Credit: Optimize Energy PerformanceREQUIREMENTS (1-18 pts.)

To be eligible for Option 2, projects must use Option 2 in the Minimum Energy Performance prerequisite.

Option 2: Prescriptive Compliance – ASHRAE 50% Advanced Energy Design Guide (1-6 pts.)◦ Building envelope, opaque: roofs, walls, floors, doors, continuous air barriers (1 pt.)

◦ Building envelope, glazing: vertical fenestration (1 pt.)

◦ Interior lighting, including daylighting and interior finishes: (1 pt.)

◦ Exterior lighting (1 pt.)

◦ Plug loads, including equipment and controls (1 pt.)

Page 72: 05 Water and Energy

Credit: Advanced Energy MeteringINTENT

To support energy management and identify opportunities for additional energy savings by tracking building-level and system-level energy use.

Page 73: 05 Water and Energy

Credit: Advanced Energy MeteringREQUIREMENTS (1 pt.)

Install meters for the following:◦ All whole building energy sources used by the building and

◦ Any individual energy end uses that represent 10% or more of the total annual consumption of the building◦ Examples include: interior lighting, space heating, cooling, fans, pumps, exterior lighting, water heating

◦ Meters must be permanently installed, record at intervals of one hour or less, and transmit data to a remote location

◦ Electricity meters must record both consumption and demand

◦ Store meter data for 36 months and be remotely accessible

◦ Capable of reporting hourly, daily, monthly, and annual energy use

Page 74: 05 Water and Energy

Credit: Demand ResponseINTENT

To increase participation in demand response technologies and programs that make energy generation and distribution systems more efficient, increase grid reliability, and reduce greenhouse gas emissions.

Page 75: 05 Water and Energy

Credit: Demand ResponseREQUIREMENTS (1-2 pts.)

Case 1: Demand Response Program Available (2 pts.)◦ Participate in an existing demand response program for a minimum of 1 year, with the intention of

multiyear renewal, for at least 10% of the estimated peak electricity demand.

◦ Include demand response in the scope of work for the CxA.

Case 2: Demand Response Program Not Available (1 pts.)◦ Provide infrastructure to take advantage of future demand response programs, including meters that

can accept external signals

◦ Develop a plan for shedding at least 10% of the estimated peak electricity demand.

◦ Contact local utilities to discuss participation in future demand response programs.

Page 76: 05 Water and Energy

Credit: Renewable Energy ProductionINTENT

To reduce the environmental and economic harms associated with fossil fuel energy by increasing self-supply of renewable energy.

Page 77: 05 Water and Energy

Credit: Renewable Energy ProductionREQUIREMENTS (1-3 pts.)

Use renewable energy systems to offset building energy costs.

Community solar systems are allowed if the project either owns or has a lease agreement for at least 10 years and if it’s located in the same utility service area.

Equivalent cost of usable energy produced by the renewable energy system

% renewable energy =

Total building annual energy cost

Page 78: 05 Water and Energy

Credit: Renewable Energy ProductionREQUIREMENTS (1-3 pts.)

Systems considered renewable are: photovoltaic, solar thermal, biofuel, wind, low-impact hydroelectricity, wave and tidal energy, geothermal energy.

Page 79: 05 Water and Energy

Credit: Enhanced Refrigerant Mgt.INTENT

To reduce ozone depletion and support early compliance with the Montreal Protocol while minimizing direct contributions to climate change.

Page 80: 05 Water and Energy

Credit: Enhanced Refrigerant Mgt.REQUIREMENTS (1 pt.)

Option 1: No refrigerants or low-impact refrigerants◦ Do not use refrigerants or use only refrigerants that have an ozone depletion potential (ODP) of zero

and a global warming potential (GWP) of less than 50.

Option 2: Calculation of refrigerant impact, based on the following table:

Page 81: 05 Water and Energy
Page 82: 05 Water and Energy

Credit: Green Power and Carbon OffsetsINTENT

To encourage the reduction of greenhouse gas emissions through the use of grid-source, renewable energy technologies and carbon mitigation projects.

Page 83: 05 Water and Energy

Credit: Green Power and Carbon OffsetsREQUIREMENTS (1-2 pts.)

Have a minimum 5-year contract to provide or offset at least 50% of the project’s energy use from green power, carbon offsets, or renewable energy certificates (RECs).

Green power and RECs must be Green-e Energy certified.

50% offset = 1 point

100% offset = 2 points

Page 84: 05 Water and Energy

HomeworkRead Kibert Chapters 11 and 13

Read LEED Chapters 9 and 10