07 verification of fault condition behaviour of synch 2-pole generator using flux 2d w-doorsamy uni...

Upload: andrei-ionel

Post on 14-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    1/31

    Flux Conference 2012

    Verification of fault condition behaviour of asynchronous 2-pole generator using Flux 2-Dfinite element analysis software

    W. Doorsamy

    University of the WitwatersrandDate : 18 October 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    2/31

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 20122

    Overview

    Introduction

    Background

    Methodology

    Experimental Setup

    Flux Model

    Fault Conditioning

    Measurement

    Results

    Conclusion

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    3/31

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 20123

    Introduction

    Increased load demands

    Alternative methods of energy generation/ sources as a solution

    Integrity of current generation systems have to be increased

    Need for simple, reliable and cost effective condition monitoring

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    4/31

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 20124

    Introduction

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    5/31

    Background

    Online and offline methods of conditioning monitoring

    Fault diagnosis accomplished through various methods:

    Chemical

    Mechanical

    Electrical

    5

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    6/31

    Background

    Diagnosis of incipient faults is essential prevention of extended

    downtime and even catastrophic failure

    Current methods utilise symptoms of damage/deterioration

    Unacceptable

    Previous work conducted on use of shaft signals for fault

    diagnosis

    6

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    7/31

    Methodology

    Consolidation of previous work conducted on fault diagnosis

    Identification of exact effects of faults on shaft and flux probe

    Simulation of fault conditions Experimental testing

    Validation

    Extend to use in multiple fault diagnosis

    7

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    8/31

    Experimental Setup

    Miniature Generator designed to mimic large turbo-generators

    Some Capabilities of Generator

    20 kVA, 2 Pole, 340 V (line)

    Cylindrical Rotor Core

    Insulated Bearings

    Open stator slots

    8

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    9/31

    Experimental Setup

    Mini-Gen designed with additional features

    Access to stator and rotor windings

    Outboard slip rings for static excitation

    Finished landings on shaft for use of specialised brushes

    Stator position relative to rotor may be manipulated

    Flux probes/search coils at various angular positions

    9

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    10/31

    Experimental Setup

    10

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    11/31

    Experimental

    Setup

    Three Phase

    Rectifier

    Mini-Gen

    Shaft Brushes

    Induction Motor(Prime Mover)

    11

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    12/31

    Flux Model

    Casing

    Stator

    Slots

    Air Gap

    Rotor Core

    Rotor Slots

    12

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    13/31

    Flux Model

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    13

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    14/31

    Fault Conditioning

    Incipient faults to analyse

    3 Rectifier

    Excitation winding short-circuit

    Static Eccentricity

    14

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    15/31

    Fault Conditioning Rectifier Fault

    15

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    16/31

    Fault Conditioning Rectifier Fault

    16

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    17/31

    Fault Conditioning Rotor Short

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    17

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    18/31

    Fault Conditioning Rotor Short

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    18

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    19/31

    Fault Conditioning Rotor Short

    19

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    20/31

    Fault Conditioning Eccentricity

    20

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    21/31

    Fault Conditioning Eccentricity

    21

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    22/31

    Measurement

    22

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    Probe

    Brushes

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    23/31

    Measurement

    23

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    Flux probe connector Shaft brush insert

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    24/31

    Results

    24

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    % Changetends toinfinity due to

    normalcondition 6th

    harmonic 0

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    25/31

    Results Rectifier Fault

    25

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    Flux Probe

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    26/31

    Results Rectifier Fault

    26

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    ConditionHarmonic

    (Hz)

    Simulation Measurement

    Percentage Change (%)

    No Load200 657.10 94.00

    250 43.99 38.24

    With Load200 95.04 140.11

    250 51.83 124.17

    Shaft Brushes

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    27/31

    Results Eccentricity

    Reasons for large harmonic change (Simulation)

    Simulation baseline (without fault) value at 300 Hz 0, therefore

    % change

    Real machine baseline (without fault) value has asymmetries

    (imperfections)

    Presence of noise

    Sensitivity of simulation i.e. no observation effects unlike with real

    setup

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    27

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    28/31

    Results Fault Diagnosis System

    28

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    29/31

    Conclusion

    Reasons for large harmonic change (expected)

    Simulation predict behaviour and optimise experiment

    Experimental results validate simulation predictions

    Algorithm -> viable

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    29

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    30/31

    Acknowledgements

    EIE - University of the Witwatersrand

    Professor W. A. Cronje

    National Research Foundation

    Cedrat

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 2012

    30

  • 7/30/2019 07 Verification of Fault Condition Behaviour of Synch 2-Pole Generator Using Flux 2D W-Doorsamy UNI Witwatersrand

    31/31

    Thank you

    Verification of fault condition behaviour of a synchronous 2-pole generator

    2012 Flux Conference - Rome, Italy, October 17-18, 201231