1. 2 welcome 3 table of contents welcome salient features sustainability achievements financial...

49
1

Upload: drew-ryden

Post on 14-Dec-2015

228 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

1

Page 2: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

2

WELCOME

Page 3: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

3

Table of contents

Welcome

Salient features

Sustainability achievements

Financial review

Strategy

› Short-term challenges and progress

› Medium to long-term strategy

Operational review

› Products, services and clients

› Competitors and value proposition

› Geographical footprint and key contracts

Risk management

Segmental review

Order book and outlook

Capex

Conclusion

Page 4: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

4

SALIENT FEATURES

Page 5: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

5

Salient features – 28 February 2013

Revenue up 31.3% to R2.3bn (2012:R1.8bn)

EBITDA up 103% to R269.3m (2012:R132.6m)

Headline earnings up 220% to R77m (2012:R24m)

HEPS up 231% to 20.5 cents (2012:6.2 cents)

PAT up 382% to R87.7m (2012:R18.2m)

EPS up 400% to 23.5 cents (2012:4.7 cents)

Order book up 43.7% to R2.5bn (2012:R1.8bn)

Operating cash decreased by R60m to R33.6m

Page 6: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

6

Salient features continued

Gross margin 16.1%

Operating margin 6.5%

Established on-the-ground presence in Ghana and Tanzania

Esorfranki Pipelines secured project in Swaziland

Invested R194m in property, plant & equipment

Invested R68m in property developments

ISO 18001 safety accreditation achieved

Page 7: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

7

Sustainability achievements

We have maintained a successful return to profitability for three successive periods

Gross margin 16.1%

Operating margin 6.5%

Our order book has been strengthened to R2.5bn

Established on-the-ground presence in Ghana and Tanzania

Esorfranki Pipelines secured project in Swaziland

Invested R194m in property, plant & equipment

ISO 9001 Quality accreditation maintained in all divisions

ISO 18001 accreditation has been obtained in all divisions

ISO 14001 accreditation was obtained in all divisions post year-end

Our LTIFR of 0.59 is significantly better than the industry norm of 1.33

Regrettably one fatality at the beginning of this calendar year

Page 8: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

8

FINANCIAL REVIEW 28 February 2013

Page 9: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

9

Statement of Financial Position: salient features as at 28 February 2013

2012R’000

2013R’000

Assets

Non-current assets 1 151 181 1 237 461

Current assets 665 288 1 006 320

Total assets 1 816 469 2 243 781

Equities and liabilities

Share capital and reserves 937 432 1 053 262

Non-current liabilities 316 658 540 326

Current liabilities 562 379 650 193

Total equity and liabilities 1 816 469 2 243 781

Net asset value per share (cents) 241.5 280.0

Page 10: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

10

Statement of Financial Position: salient features (1 March 2012 – 28 February 2013)

Total assets

Cash & cash equivalents Trade and other receivables No impairment of intangibles

R33.6mR826.7m

PPE Investment in construction equipment Sale of Pinetown property

R193.9mR25m

Cash reserves

Operational cash-flow consumed Acquisition PPE Dividends paid Secured borrowings Debt/(debt+equity) ratio

(R32.9m)(R193.9m)

Nil(R448m)

42.5%

Equity

Profit after tax FCTR Dividend paid

R87.7mR3.9m

Nil

Page 11: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

11

Statement of Income: salient features

2012R’000 %

2013R’000

Revenue 1 771 692 31.3 2 325 958

EBITDA 132 656 103 269 265

Profit/(loss) after tax 18 216 382 87 710

Headline earnings/(loss) 24 046 220 77 027

HEPS 6.2 231 20.5

Page 12: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

12

STRATEGY

Page 13: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

13

Material issues

MATERIAL ISSUE

Growth considering the external environment

CHALLENGE

Intensifying competition and margin contraction

RESPONSE & PROGRESS

Expansion in the African market

Targeting higher margin private sector projects such as low cost housing

Taking equity share in developments

Page 14: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

14

Material issues

MATERIAL ISSUE

B-BBEE scorecard

CHALLENGE

To continually strengthen Esorfranki’s B-BBEE position and comply with Construction Charter requirements essential for securing government and parastatal contracts

RESPONSE AND PROGRESS

Ownership - in negotiations with potential BEE investor with expected finalisationin June 2013

Management - examination of board structure with intention of appointing black female non-exec by end H1 2014

Maximise procurement, business development and CSI spends

Page 15: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

15

Material issues

MATERIAL ISSUE

Liquidity - financial management during times of growth

CHALLENGE

Balancing the group’s growth (double construction sector) with liquidity to service investments in housing and development

RESPONSE & PROGRESS

Sufficient liquidity and capital to meet business objectives through additionalbanking facilities

Provision of company and institutional guarantees to free up cash retentions

Page 16: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

16

Material issues

MATERIAL ISSUE

Project execution - on time, within budget and to required quality

CHALLENGE

Ability to start projects efficiently and manage limited senior resources and volatile labour while ensuring quality and safety

RESPONSE & PROGRESS

Efficient risk-controlled delivery of quality projects

Limits of authority depending on size and profile of contracts

Project team monitors risk, execution, cost and payment from appointment on monthly basis

SHEQ compliance continuously monitored within the frameworks ofISO 9001, 14001 & 18001

Page 17: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

17

Material issues

MATERIAL ISSUE

Skills shortage

CHALLENGE

Scarce resources undermine delivery and expansion

RESPONSE & PROGRESS

Creation of attractive employment proposition, a people-centred culture,skills development programme and succession planning

Employees are offered bursaries as well as skills training

LDC employees are trained in a wider range of skills than is required forthe contract for their further empowerment

In-house accredited training centre based at Germiston workshop

Page 18: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

18

Material issues

MATERIAL ISSUE

SHEQ – impact of safety, health, environment and quality on operations

CHALLENGE

Potential threat to employees, natural resources, client’s and group’s reputationthrough non-compliance

RESPONSE & PROGRESS

ISO 9001, ISO 14001¹ and ISO 18001 accredited

Superior safety record (LTIFR<1.00)² compared to industry average of 1.33

Safety management system implemented in Africa

Rejuvenated fuel-efficient fleet and fuel-efficiency plan

SHEQ training, regular internal & external audits

Strategies for reducing, re-using and recycling resources

1 Post year-end ISO 14001 Environmental accreditation achieved2 Actual February 2013 rolling monthly average LTIFR of 0.59

Page 19: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

19

Material issues

MATERIAL ISSUE

Past collusive and anti-competitive practices within the industry

CHALLENGE

To settle all outstanding Competition Commission issues

PROGRESS

The CC investigation into alleged anti-competitive behaviour in the piling and drilling markets was referred to the Tribunal following a failed settlement offer. Negotiations have been reopened post year-end and the board is convinced that the estimated penalty provision previously allowed in the financial statements will suffice

During the recent fast track settlement process offered to the construction industry Esorfranki Limited filed one marker relating to a prescribed offence and will accept an imposed fine of R115 850

Esorfranki was further mistakenly implicated in one other instance relating to Shearwater prior to acquisition which has now fallen away

Any further developments will be communicated to all stakeholders as they occur

Page 20: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

20

Medium to long-term strategy

Continue harnessing synergy within the group

Expand product offering and grow market share

Geographical diversity in Civils and Pipelines

Environmental accreditation ISO 14001 obtained post year-end

Securing long-term contracts to create future visibility and to underpin sustainability

Focus on sustainable growth nodes within government infrastructure programmeswhen they occur

Supply chain management will take cognisance of environmental impactand carbon emissions will be measured and managed

Addressing Construction Charter requirements to improve B-BBEE scoring by31 December 2013

Focus on concession and development projects

Focus on private sector clients to balance dependency on government contracts

Page 21: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

21

OPERATIONAL REVIEW 28 February 2013

Page 22: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

22

Products & Services

Geotechnical Pipelines Civils

Piling

Lateral support

Marine structures

Pipejacking

Thrust boring

Bridgejacking

Diaphragm walls

Ground improvement

Dynamic compaction

Ground remediation

Soils investigation

Geotechnical design

Gas and petrochemical steel pipelines

Water and wastewater pipelines

Sewer pipelines

Pump stations

Pipeline refurbishments

Cement mortar lining

Valve chambers

Associated concrete structures

Associated infrastructure

Pressure testing

Road construction

Bridge construction

Township infrastructure

Mining infrastructure

Water reticulation

Water towers

Reservoirs

Sewer reticulation

Bulk earthworks

Building

Housing

Development

Page 23: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

23

Clients

Geotechnical Pipelines Civils

Civil contractors

Building contractors

Listed & private contractors

Government at:

› Central

› Provincial

› Municipal levels

Property development companies

Parastatals:

› Eskom

› Transnet

› Rand Water

› Umgeni Water

› Portnet, etc

Mining sector including most major mining houses

Government at:› Central› Provincial› Municipal levels

Parastatals:› Transnet› Rand Water› Umgeni Water› Portnet› TCTA & DWAF

Mining sector Private clients

› RBM› Foscor› Mondi

Cross-border

› FIPAG Mocambique

› Botswana Government

› Zimbabwe

› Swaziland

Eskom

Sanral

Anglo Coal

Xstrata

RAL

Gauteng Province

Government

› Central

› Provincial

› Municipal levels

Private developers

Bakwena Concessions

Debswana

Page 24: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

24

Competitors

Geotechnical Pipelines Civils

Steffanutti Stocks in-house geotechnical division

Aveng in-house geotechnical division

Dura (Solentache Bachy is a large global contractor)

Wepex

Gauteng Piling

Terrastrata

Geomechanics

Keller (largest global geotechnical contractor)

WK Pipelines

WBHO

Aveng

Group 5

Steffanutti Stocks

Cerimele Construction

Murray & Dixen

Concor

Ikon

Murray & Roberts

Aveng

WBHO

Group 5

Steffanutti Stocks

Basil Read

Raubex

Erbacon

Protech-Khutheli

Diesel Power

Haw & Inglis

Page 25: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

25

Value proposition

Geotechnical Pipelines Civils

Geotechnical market leader in South Africa

Good reputation and well known brand in SSA

Design alternatives constantly investigated

Geographical diversity entrenched and expanded

Depth of management know-how

Well-established business processes over 65 years

Plant capacity retooled and modernised

ISO 9001, ISO14001 andISO 18001 accredited

Niche leader in welded pipelines

Supply and install all aspects of cross-country pipelines

Supply and install pipelines in a myriad of materials

Experienced and talented management team

Excellent track record with blue-chip clients

Extended work footprint to Swaziland

ISO 9001, ISO14001 andISO 18001 accredited

Diversified range of construction services

Plant capacity and capability expanded

Excellent workshop facilities

Strong relationships with clients and consulting engineers

Experienced and talented management team

Increased longer-term projects in order book

ISO 9001, ISO14001 andISO 18001 accredited

Page 26: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

26

Geographical footprint

AFRICA

GHANA

DRC

ANGOLA

NAMIBIA

BOTSWANA

ZIMBABWE

SWAZILAND

MAURITIUS

MADAGASCAR

MOZAMBIQUEZAMBIA

MALAWI

TANZANIA

KENYAUGANDA

SEYCHELLES

Page 27: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

27

Geotechnical - key contracts

Country and contact Description

Angola:Kinaxixi MXD complex

Phase I - 1 150 soil nails, 4 200m² of gunite, 310 micropiles and over 370 soldier piles. Phase II comprised the installation of up to five rows of Titan anchors, 7 500m² of gunite arches and approximately 90 jet grout columnsDuration: 15 months - in progressPhase III - diaphragm wall, anchors and piling - under negotiation (R42.5m)

Ghana:ADA Groynes

Phase 1: Construction of the temporary staging jetties for the construction of 7 No permanent groynesPhase 2: Increased scope to 11 No. jetties, and under negotiation. Anticipated commencement January 2014 (R150.0m)

Durban:Mt. Edgecombe Interchange

Piling:Closing out post-tender negotiations with main contractor (R40.0m)

Mozambique:Steval Tank FoundationsSouthern Sun, Maputo

Beira / Maputo - Piling (R16.0m)Piling (R3.2m)

Kenya:Garden City Mall

Piling:Awaiting official order (R15.0m)

Johannesburg:Sasol Offices

Lateral Support:Awarded and on site (R16.0m)

Cape Town:Tenesol Solar Farm

Piling:Awarded and on site (R16.0m)

Namibia:FNB Development, Windhoek

Lateral Support:Awarded and on site (R10.0m)

Page 28: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

28

Pipelines - key contracts

Country and contact Description

Eastern Cape, Xonxa Dam Pipeline

Installation of 23km of 600mm diameter steel pipeline near QueenstownDuration: 12 months - in progress

Swaziland, Mhlume Canal - Siphon 4

Installation of 1.5km of 1 900mm steel pipe between two existing canals in the Mhlume areaDuration: 8 Months - site establishment has commenced

KZN, Lower Thukela Pipeline Installation of 29km of 900mm steel pipeline between command reservoir, (Tugela river), and the Mvoti WTW. Stanger areaDuration 18 months - in progress

KZN, Umlaas Road,Bulk Water Main

Installation of 13km of 1 100mm pipe, from Richmond off take to Umlaas RoadDuration: 21 months - in progress

KZN, Ethekwini Water & Sanitation

Provision of Water and Sanitation to Informal Settlements in EthekwiniDuration: 23 months - in progress

KZN, Hazelmere Raw Water Pipeline

Installation of 2.4km of 800mm pipeline from Hazelmere Dam to Hazelmere Water Treatment WorksDuration: 6 months - in progress

KZN, Kwahlokohloko Bulk Water Supply

Construction of 5,8km of 900mm Steel Pipeline for the Bulk Water Supply to KwahlokohlokoDuration: 8 months - in progress

KZN, Woodmead, Main Water Supply

Supply and install 9 km of 500mm Pipeline to the Thulele / Woodmead Developments and the Avon Peaking Power PlantDuration: 12 months - nearing completion- however, new R22.5m V.O. issued

Page 29: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

29

Civils - key contracts

Country and contact Description

North West, BakwenaN4 Toll Road. Phases 2, 3 & 4

Construction of a second 21km eastbound carriageway along a section of the N4Duration: 30 months - in progress and due for completion Dec 2013

Mpumalanga, Kusile Power Station

Underground service ducts to completed terraces and general services pipelinesDuration: 36 months - in progress

Mpumalanga, Kusile Power Station

Construction of bulk earthworks to terracesDuration: 18 months - in progress

Gauteng, Diepsloot EastHousing & Infrastructure

Construction of 8 000 residential houses and associated civils infrastructurePhase 1: Construction of 2 pedestrian bridgesDuration: 10 months - in progress

Northern Cape, Kathu Construction of infrastructure and housing for Bestwood developmentDuration 15 months - in progress

Gauteng, RosslynOrchards Development

Developer for the infrastructure and construction for 1400 entry level housing unitsDuration: 3-7 years – in progress

Page 30: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

30

RISK MANAGEMENT

Page 31: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

31

Matrix of major risks

Material risks Mitigation

Dependency on government infrastructure spend

Product and market diversification, strategic B-BBEE rating and geographical diversity

Working capitalmanagement

Weekly cash flow forecast, working capital facilities, tougher on debt collection and KPAs of divisional managers

BEE Promotion from within, careful management of transformation process at board level. BEE ownership deal under negotiation and board restructure

Material shortagesmaterial delivery delays

Proper planning, qualifying bids, site contracts and manuals and KPAs of divisional managers

Credit risk and cost reporting Monthly review at EXCO meeting, monthly review of contract financials. Credit policy with varying limits for approving client credit limits

Bribery and corruption Obtain court interdicts, exposure of corruption through whistle-blowing and enforce Code of Ethics and Conduct. Social & Ethics Committee established. Zero tolerance

Competition Build on reputation through strong brand, be competitive in terms of price and quality, include alternative bids and in-house design

Underperforming contracts Immediate identification and response, follow up with possible disciplinary action, ensure accountability, appoint the right people to the right jobs, minimise non-conforming reports & compliance reviews against policies and procedures

Page 32: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

32

Management

Meetings Tender committees Site visits Risk management officer and internal audit Monthly cost and resource meetings Authority levels

Board, Risk, EXCO, Divisional & Site Finalisation meetings Regular and varied Continuous programme of checking and assessment Attended by CEO and CFO in all divisions Regularly updated and adhered to

Contracts

Basic conditions of tender Pricing Project management software Costs Scope Margins Tendering process Quality ISO 9001 Safety ISO 18001 Environmental ISO 14001

FIDIC, NEC, GCC, client specific Overhead, mark-up, risk Integrated with financials Production, programme, current prices Resource planning & management (people and plant) Contract specific Tender finalisations, limits of authority, policies and

procedures

Risk management

Page 33: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

33

SEGMENTAL REVIEW

Page 34: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

34

Segmental review - Geotechnical

Geotechnical2012

R’0002013

R’000

Segment review 734 092 787 857

PBIT 50 253 76 105

Segment assets 722 746 734 464

Number of employees 1 191 1 169

Revenue growth 4% 7.3%

Operating margins 7% 10%

Order book 321 205 327 624

Pending awards 150 500 144 515

Prospects 468 210 860 000

Non-government 67% 84%

Government 33% 16%

Page 35: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

35

Segmental review - Pipelines

Pipelines2012

R’0002013

R’000

Segment review 227 821 323 552

PBIT 2 234 30 583

Segment assets 84 007 191 552

Number of employees 373 763

Revenue growth 35% 42%

Operating margins 1% 9%

Order book 220 073 518 822

Pending awards 260 867 32 000

Prospects 3 115 000 1 630 000

Non-government - -

Government 100% 100%

Page 36: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

36

Segmental review - Civils

Civils2012

R’0002013

R’000

Segment review 824 051 1 214 549

PBIT 25 377 76 525

Segment assets 583 537 963 994

Number of employees 1 820 2 701

Revenue growth 59% 47%

Operating margins 3% 6%

Order book 1 215 762 1 269 039

Pending awards 1 613 000 3 235 000

Prospects 3 788 500 2 940 000

Non-government 23% 45%

Government 77% 55%

Page 37: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

37

ORDER BOOK AND OUTLOOK

Page 38: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

38

Order book as at 28 February 2013

Business unitOrder book(R millions)

Secured revenueFY 2014

(R millions)

Secured revenueFY 2015+

(R millions)

Geotechnical 327 624 327 624 0

Civils 1 269 039 890 039 379 000

Pipelines 518 822 441 776 77 046

Developments 410 900 54 892 356 008

Total 2 526 385 1 714 331 812 054

Page 39: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

39

Geotechnical outlook as at 28 Feb 2013

Awarded Pending and key

Johannesburg R68m R190m

Cape Town (including Ghana) R129m R283m

Angola R11m R232m

Durban R78m R183m

East Coast (Mozambique, Tanzania, Mauritius) R41m R117m

Total R940m R327m R1 005m

Page 40: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

40

Pipelines outlook as at 28 Feb 2013

Description Value

Current contracts BG3 near Vaal Mooihoek 4 Bluff military base Umlaas Road Thulele/ Woodmead Hazelmere Stanger Xonxa Dam Kwahlokohloko Warden

R519m

Pending and potential awards Kwahlokohloko Reservoir R32m

Key contracts Western Aqueduct Northern Aqueduct

R1 630m

Total R2 181m

Page 41: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

41

Civils outlook as at 28 Feb 2013

Current contracts rolled over from last year as at 28 Feb 2013 (2014FY only)

Description Value

Roads RAL current road Contract Bakwena N4 (Mooinooi)

R149m (16.8%)

Kusile Package 26 Terraces contract Package 25 General Services Pipeline Additional Terraces Contract Crushing Contract

R315m (35.4%)

Mine work at Anglo Coal Various mines R66m (7.4%)

Building Bestwood Housing Development R101m (11.4%)

General Pipejacking Bestwood Infrastructure Thabazimbi Infrastructure

R259m (29%)

Total R890m

Page 42: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

42

Civils outlook as at 28 Feb 2013

Pending awards and targeted key contracts

Description Value

Civils N4 next phase Additional crushing at Kusile Temba WWTP Greenside Terrace Munitoria Mafube Remedial Works Kusile Housing (details unknown) PRASA Stations Schools Moz housing and infrastructure (4-5 yrs) Bestwood (4-5 yrs) Platinum Park Rustenburg BRT Solar Energy Diepsloot East Development

Building

Pipejacking

Developments

General

R6 175m

Page 43: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

43

General outlook 2014FY and beyond

Gautrain private development spinoff

Sandton Rosebank Hatfield Park Station surrounds

and Braamfontein

Sasol Head Office I have no doubt that significant

development will occur around Park Station and into the Braamfontein surrounds once this leg is operationalas evidenced elsewhere

Resource arena Mozambique Gasfields Iron ore and manganese Coal Platinum

There is still significant work to be done to benefit from South Africa’s own huge resource base as well as that of our neighbours

General Private & Commercial Developments

African new markets Presidential infrastructure initiative Integrated Housing Developments

Indication that this is starting to pick up Ghana, Kenya, Uganda and Zambia As per State of the Nation address High priority for government

Page 44: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

44

General outlook 2014FY and beyond

Energy Sector Medupi & Kusile Power Stations Nuclear Power Station 3rd Coal fired Power Station Transmission Lines Solar and Wind initiatives

Some housing still to happen Has been in the press extensively lately Rumours Geotechnical foundation solutions Geotechnical and Civils

Sanral andother roads

15 000km non-toll roads +R10bn in 2014 budget Coal haul-road upgrades R20bn GFIP phase 2

Sanral are obviously in a state of flux after the e-tolling debacle but will ultimately be supported by central government

This is due to come out to tender again

Other parastatals Transnet Port authorities

PetroSA Coega

R330bn capex spend Drydocks, Digout and general harbour

upgrades Refined product line from Maputo Refinery, smelter or both

Page 45: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

45

CAPEX

Page 46: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

46

Capex

Segments (R’000) Financial years

2011 2012 2013

Geotechnical 11 793 51 100 42 815

Civils 17 964 205 317 132 406

Pipelines 6 104 620 17 083

Corporate 14 512 685 1 626

Total 50 373 257 722 193 930

Revenue 1 366 433 1 771 692 2 325 958

Page 47: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

47

Conclusion

Having successfully maintained a profitable position for three

successive periods, we are confident that the leaner, meaner,

happier, more focused persona of Esorfranki Limited will

continue to bode well for the future of all its stakeholders!

THANK YOU!

Page 48: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

48

Disclaimer

Forward-looking statements

This presentation contains forward-looking statements that, unless otherwise indicated, reflect the

company’s expectations as at 28 February 2013. Actual results may differ materially from the company’s

expectations if known and unknown risks or uncertainties affect its business or if estimates or

assumptions prove inaccurate. The company cannot guarantee that any forward-looking statement will

materialise and, accordingly, readers are cautioned not to place undue reliance on these forward-looking

statements. The company disclaims any intention and assumes no obligation to update or revise any

forward-looking statement even if new information becomes available as a result of future events or for

any other reason.

Page 49: 1. 2 WELCOME 3 Table of contents  Welcome  Salient features  Sustainability achievements  Financial review  Strategy ›Short-term challenges and

49

www.esor f rank i .co.za

Esorf rank i L imi ted | 30 Act iv ia Road Act iv ia Park Germis ton 1401

PO Box 6478 Dunswart 1508 South Af r ica

Bernie Krone | CEO

+ 27 83 259 5984

+27 11 776 8700

+27 11 822 1158

[email protected]

Wessel van Zyl | CFO

+ 27 82 498 3518

+27 11 776 8700

+27 11 822 1158

[email protected]