1 a member of the team focus group integrated management systems industry view 2 michael thompson...
TRANSCRIPT
1
A Member of the Team Focus Group
Integrated Management SystemsIndustry View 2
Michael Thompson BSc (Eng), FFICE, MCIWEM
Roe Thompson Limited
2
RTL
What is Integrated Management?
The intents of Integrated Management are– to improve delivery of the specified product to the
customer– to improve communication to the man at the sharp end– to remove duplication of paperwork arising from
operating separate management systems which actually have a lot in common.
We cannot ignore the close affiliation of these intents with those of the Partnering approach.
3
RTL
What is Integrated Management?
These intents can be achieved in a Project through the Partnering or Team approach by setting up, to all intents and purposes, a Single Organisation which can draw from the several organisations involved
Better control of the Project and the finished product can be attained
Some of the annual performance targets, suggested by Sir John Egan in “Rethinking Construction” (July 1998), can be approached
We will get ever closer to the concepts of “Best Practice”
4
RTL
“Rethinking Construction”
Indicator Improvement each year
Capital costAll costs excluding land and finance.
Reduce by 10%
Construction timeTime from client approval to practical completion.
Reduce by 10%
PredictabilityNumber of projects completed on time and within budget.
Increase by 20%
DefectsReduction in number of defects on handover.
Reduce by 20%
AccidentsReduction in the number of reportable accidents.
Reduce by 20%
ProductivityIncrease in value added per head.
Increase by 10%
Turnover and profitsTurnover and profits of construction firms.
Increase by10%
ANNUAL PERFORMANCE TARGETS
5
RTL
What is Best Practice?
There is no single definition for Best Practice. One definition:
– It is the achievement of all the goals laid down by a Project Team (including the Client) for the final product, by consideration of the best techniques of procurement, contract strategy, quality assurance and good supply management.
6
RTL
Can we do things better?
When we look back, could we have done better with our projects?
Even with the Partnering / Team approach could we have done better?
Should we not strive for 100% in “Excellent”?
Would not then Best Practice be achieved?
7
RTL
Case History: Pennington WwTW
Four organisations, working together without walls between them:– Client:- Southern Water– Project Manager:-
Montgomery Watson– Designer:- McDowells– Contractor:- Birse
Construction
8
RTL
The Challenge
Build a brand new sewage treatment works from outline design on a “green field” site within 21 months and within budget
Undertake the earthworks during the worst period of the year!.
9
RTL
A Quick Start
The Project started on 24 July 1995 The Team Building Workshop took place on 31
July 1995 and a Charter agreed and signed The Value Management Workshop commenced
on 2 August 1995 A firm outline design was in place within 10
days.
10
RTL
Alliance Charter
The Charter
Mission Statement“Our project objectives are to deliver the scheme to the desired quality and levels of service at the lowest life-cycle cost and highest value, on time and with no surprises to the satisfaction of all Partnering Team Organisations”
11
RTL
The Pennington Organisation
Sou th ern W ater Mon tg om ery W atson McDowells B irse Con stru ction
Prin cip als ' G rou p
Civil Desig nMcDowells
M&E Desig nMcDowells
G eotech n icalMcDowells
P rocess Desig nMcDowells
S tru ctu res Desig nMcDowells
Ad m in istration Assistan t
Desig n Man ag erMcDowells
S ite Ag en tB irse Con stru ction
M&E P roject Man ag erB irse W ater
P roject Su rveyorB irse Con stru ction
Safety Man ag erB irse Con stru ction
Q A Man ag erB irse Con stru ction
P lan n in g En g in eerB irse Con stru ction
Con stru ction Man ag erB irse Con stru ction
Area Man ag er O p eration sSou th ern W ater
NRA LiaisonSou th ern W ater
P lan n in gAd am s Hen d ry
Lan d Issu esMon k Rawlin g
C lien t Man ag erSou th ern W ater
Valu e Man ag erMon tg om ery W atson
P lan n in g Su p ervisorMon tg om ery W atson
Q u ality Man ag erMon tg om ery W atson
Project Man ag erMon tg om ery W atson
In vestm en t Man ag erSou th ern W ater
Independent of the Pennington Team was a firm of Quantity Surveyors auditing expenditure, using the Contractor’s cost files.
Independent of the Pennington Team was a firm of Quantity Surveyors auditing expenditure, using the Contractor’s cost files.
12
RTL
Value Management
The Team underwent an intensive VM workshop phase within the first three weeks of scheme commencement
This developed an optimum outline design
The Client’s Operations personnel signed up to the Team’s outline design on completion of the VM workshop
13
RTL
V M Cost Comparisons
VMAlternatives
Base10
Scenario
1aScenario
2aScenario
3aScenario
4aScenario
5Scenario
6aAsbaselinebutadjustedfor 10yearsadequacy
1200l/s,60gm/hd/d,4 PSTs,FBDA, 4FSTs, 6%sludgethickening
1200l/s,60gm/hd/d,rect PSTs,surfaceaeration, 3FSTs, 25%sludgedewatering
1200l/s,60gm/hd/d,Jetta, 3PSTs,surfaceaeration, 3FSTs, 25%sludgedewatering
1200l/s,60gm/hd/d,aerationditch, 3FSTs, 6%sludgethick, 25%sludgedewatering
1600 l/s,60gm/hd/d,Jetta, 3PSTs,FBDA, 3FSTs, 6%sludgethickening
1200 l/s,60gm/hd/d,Jetta, 4PSTs,surfaceaeration,3FSTs, 6%sludgedewatering
CAPEX 12,000,000 12,193,000 11,815,000 11,825,000 11,900,000 11,880,000 11,675,000
OPEX 60 yrs 11,795,760 11,795,760 17,743,020 19,463,280 14,118,019 11,916,720 18,600,000
NPV @ 7.5% 13,873,003 14,028,360 14,830,530 15,158,622 14,224,543 13,798,911 14,933,084
Difference 0 +155,357 +957,527 +1,285,619 +351,540 -74,092 +1,060,081
VMAlternatives
Base10
Scenario
1aScenario
2aScenario
3aScenario
4aScenario
5Scenario
6aAsbaselinebutadjustedfor 10yearsadequacy
1200l/s,60gm/hd/d,4 PSTs,FBDA, 4FSTs, 6%sludgethickening
1200l/s,60gm/hd/d,rect PSTs,surfaceaeration, 3FSTs, 25%sludgedewatering
1200l/s,60gm/hd/d,Jetta, 3PSTs,surfaceaeration, 3FSTs, 25%sludgedewatering
1200l/s,60gm/hd/d,aerationditch, 3FSTs, 6%sludgethick, 25%sludgedewatering
1600 l/s,60gm/hd/d,Jetta, 3PSTs,FBDA, 3FSTs, 6%sludgethickening
1200 l/s,60gm/hd/d,Jetta, 4PSTs,surfaceaeration,3FSTs, 6%sludgedewatering
CAPEX 12,000,000 12,193,000 11,815,000 11,825,000 11,900,000 11,880,000 11,675,000
OPEX 60 yrs 11,795,760 11,795,760 17,743,020 19,463,280 14,118,019 11,916,720 18,600,000
NPV @ 7.5% 13,873,003 14,028,360 14,830,530 15,158,622 14,224,543 13,798,911 14,933,084
Difference 0 +155,357 +957,527 +1,285,619 +351,540 -74,092 +1,060,081
Preferred option - Scenario 5
14
RTL
The Programme Advantage
Typical comparison: Partnering (Integrated
Management) - 21 months D&C - 26 months Conventional - 30 months
Savings in time Savings in cost
Task Name
Design & Construction
Start
Outline Design
Tendering & Appointment
Detail Design
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
21/07
03/08
JF A J J A S NDJ F A J JA SONDJ F A J J S NDJ FM MJ J S ND J FM MJ J S1995 1996 1997 1998 1999Task Name
Design & Construction
Start
Outline Design
Tendering & Appointment
Detail Design
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
21/07
03/08
JF A J J A S NDJ F A J JA SONDJ F A J J S NDJ FM MJ J S ND J FM MJ J S1995 1996 1997 1998 1999
Task Name
Conventional
Start
Outline Design
Detail Design
Tendering & Appointment
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
21/07
23/11
J F A J J A S NDJ F A J J A SONDJ F A J J S NDJ FM MJ J S ND J FM MJ J S1995 1996 1997 1998 1999Task Name
Conventional
Start
Outline Design
Detail Design
Tendering & Appointment
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
21/07
23/11
J F A J J A S NDJ F A J J A SONDJ F A J J S NDJ FM MJ J S ND J FM MJ J S1995 1996 1997 1998 1999
Design and Construct
Design and Construct
ConventionalConventional
Task Name
Partnering
Start
Outline Design
Detail Design
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
24/07
05/03
DJ FM MJ J SOND JFM MJ J S ND JFM MJ JA SOND J FM J J A SOND JF A J JA S1995 1996 1997 1998 1999Task Name
Partnering
Start
Outline Design
Detail Design
Earthworks
Civil Works
M&E Works
Completion Tests
Handover Tests
Defects Liability
End DLP
24/07
05/03
DJ FM MJ J SOND JFM MJ J S ND JFM MJ JA SOND J FM J J A SOND JF A J JA S1995 1996 1997 1998 1999
PartneringPartnering
15
RTL
The foundation of the Integrated Management System, the Control Plan (Project Management Plan) addressed all aspects of the Scheme
It linked to the Plans of all four parties in the Partnership
The Pennington Contol Plan
S ou th ern W ater S ervicesP ro jec t C on tro l P lan
(In te rn a l P roced u res )
M cD ow ellsP ro jec t Q u a lity P lan
(IS O 9 0 0 1 )
B irse C on s tru c tionS ite Q u a lity P lan
(IS O 9 0 0 2 )
M on tg om ery W atsonW ork P lan(IS O 9 0 0 1 )
P E N N IN G TO N W wTw S C H E M EP ro jec t M an ag em en t C on tro l P lan
(P ro jec t M an ag er)
16
RTL
Principal Issues Addressed The Partnership and its
“Arrangement” Contracts Quality Systems and
Procedures Safety (incl. CDM) Environment Programme Variation orders Reporting
Design Procurement Manufacture Construction Installation Commissioning Performance Testing H&S File (inc. O&M) Successes & Lessons
Learnt
17
RTL
The Filing System
A Single Filing System for all to use.
No letters between partners, but confirmation memos
Other files between Contractor and Sub-contractors also accessible
Everything auditable.
18
RTL
Some Pennington Successes
Rapid establishment of the design with confidence through Value Management processes
Effective Risk Management relating to Planning Permission and Discharge Consent
Design and construction taking place concurrently
Rapid appointment of sub-contractors
Self supervision of construction works (TQM approach)
Joint planning with Operations the testing and commissioning of the Plant
Fast resolution of earthworks problems
19
RTL
Pennington - Conclusion
Completed and commissioned 2 weeks early
Completed £700,000 within budget
Self-supervised - quality excellent!
Good Health & Safety record
Environmental constraints observed
But in retrospect, we are sure that we could have done
better!
20
RTL
Where to next?
Hundreds of Project Teams are being formed annually, adopting the Partnering Approach with Integrated Management
Many of these are producing successful projects But remarkably the approach is still very new for a
good many in the construction industry More and more need to understand the benefits that
can be achieved through the approach, particularly at a senior level.