1 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Project Procurement
David DaleProcurement Manager
NSLS-II ProjectProject Advisory Committee
November 20, 2007
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Procurement Staffing• Acquisition Strategy• Advance Procurement Planning• DOE Approval Requirements • Major Equipment Procurement Process• Ring Building Construction Schedule• Procurement Challenges• Summary
3 BROOKHAVEN SCIENCE ASSOCIATES
Procurement Staffing
COMPLIANCE/POLICY OFFICER
(Central Procurement)
PROCUREMENT MANAGERDavid E. Dale
PROCUREMENT CONSULTANT
Barry Miller
CONTRACT ADMINISTRATOR
Construction
David Paveglio
SR. CONTRACTS SPECIALIST
Major Equipment
George Woods
PRINCIPAL BUYEREquipment/Materials
Mike Canavan
PRINCIPAL BUYER Equipment/Materials
Frank Nemeth
4 BROOKHAVEN SCIENCE ASSOCIATES
Acquisition Strategy
• NSLS-II Acquisition Strategy Document • In accordance with DOE Directive M 413.3-1• DOE Approved Procurement System
• NSLS-II Project Team includes:• Dedicated Procurement Manager• Dedicated procurement staff• Procurement quality support
• Use of Full and Open Competition with Qualified Sources to the maximum extent possible
5 BROOKHAVEN SCIENCE ASSOCIATES
Procurement Strategy
Advance Procurement Planning
•Procurement Planning and Communication•Procurement forecast thru FY12 developed•Advance Procurement Planning (SNS model) Procurements over 100k or Risk Significant
•Procurement schedules include consideration for procurement methods and approval requirements
•Procurement schedule and status reports to track procurement activities (SNS model)
•Close Communication with Project and Technical Staff•Communication with Procurement Counterparts from other DOE Laboratories
6 BROOKHAVEN SCIENCE ASSOCIATES
DOE Approval Requirements
• DOE-BHSO• Advance Notice for sole source procurements >
$100K• Buy American Act waivers > $100K• Procurements > $5M
• DOE- CH Procurements > $10M-25M• DOE-HQ Procurements > $ 25M
7 BROOKHAVEN SCIENCE ASSOCIATES
Major Equipment Procurement
• Procurements Utilize Request for Proposal “Best Value” (RFP) Method• Specifications supported by Functional Requirements• Schedule and Contractor Performance - Integral Part of
Proposal Evaluation Criteria• Evaluation criteria developed through close coordination
with Control Account Managers• Procurements Publicly Announced on the FedBizOps
Website• Maximize competition• Develop New Sources
8 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 07 Major Procurements
• Description Amount Award
• A/E Ring Bldg $11M 9/05/07
• C/M Agent $956k 9/12/07
• A/E Chilled Water $996k 9/12/07
9 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 08 Major Procurements
• Description Amount RFP Award Comments
• Title III A/E Services 3.6M 5/08 9/08
• CM Construction 6.5M 5/08 9/08
• Site Preparation 1M 8/08 10/08
10 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 09 Major Procurements
• Description Amount RFP Award Comments
• Ring Building 191M 10/08 2/09 FY 07 Planning
• Chilled Water 15M 10/08 3/09 FY 08 Planning
• Vacuum Chambers 14M 1/09 6/09 FY 08 Planning
• Storage Ring Mag 18M 2/09 8/09 FY 08 Planning
11 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 10 Major Procurements
• Description Amount RFP Award Comments
• Linac 9.8M 10/09 10/10 FY 09 Planning
• SR Vacuum Pumps 7.9M 12/09 6/10 FY 09 Planning
• Compact Booster 17M 10/09 3/10 FY09 Planning
12 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 11 Major Procurements
• Description Amount RFP Award Comments
• SR Corrector PS 6M 3/10 10/10 FY 10 Planning
• SR Multiple PS 4.9M 3/10 10/10 FY 10 Planning
• Process Water 4.8M 9/10 2/11 FY 10 Planning
• SR RF Cryogenics 4.8M 6/10 10/10 FY 10 Planning
13 BROOKHAVEN SCIENCE ASSOCIATES
Fiscal Year 12 Major Procurements
• Description Amount RFP Award Comments
• Damping Wiggler 7M 9/11 2/12 FY11 Planning
• IV Undulator 7M 9/11 2/12 FY 11 Planning
• EPU 3.6M 11/11 2/12 FY 11 Planning
14 BROOKHAVEN SCIENCE ASSOCIATES
Conventional Construction Schedule
• 10/07 A/E Delivers Title I • 10/07 Draft Request for Proposal (RFP) developed• 11/07 Draft RFP to DOE BHSO • 12/07 DOE Procurement Validation Review• 1/08 Recommendations incorporated• 2/08 Draft RFP issued to industry• 4/08-5/08 Industry Feedback• 8/08-9/08 DOE reviews /approves RFP and proposed contract• 10/08 RFP Issued • 2/09 Contract Award
15 BROOKHAVEN SCIENCE ASSOCIATES
Procurement Challenges
FY 08• Establishing Advance Procurement Plans for FY 08
and 09• Site Clearing, Planned Award 10/08• Completion of A/E Design, Planned completion 8/08• General Construction Ring Building Planned RFP
10/08
16 BROOKHAVEN SCIENCE ASSOCIATES
Summary
• Acquisition Strategy has been developed• Procurement Integrated into the Project Team
with dedicated Procurement Management • Procurement Staff in place• Advance Procurement Planning Process • Procurement schedule includes consideration
of procurement methods and required approvals
• Procurement Plan for critical path conventional construction established