HW # 4 Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ

Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock.

Assume the current time is 1:00 p.m. The times required to unload each truck and the times that the goods they contain are due in the plant are given in the table below:

Determine the schedules that result for each of the rules: (1) FCFS ; (2) SPT ; (3) EDD ; and (4) CR. In each case compute the mean flow time, average tardiness, and number of tardy jobs.

Truck# Unloading time

Time Material Is Due

1 20 mins 1:25 p.m.

2 14 mins 1:45 p.m.

3 35 mins 1:50 p.m.

4 10 mins 1:30 p.m.

Page 3: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

3

HW # 4

FCFS

Mean flow time = 202/4 = 50.5Avg. Tardiness = 68/4 = 17Number of Tardy trucks = 2

Truck#

ti Fi di Ti

1 20 20 25 0

2 14 34 45 0

3 35 69 50 19

4 10 79 30 49

Total 202 68

Page 4: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

4

HW # 4

SPT

F’=157/4=39.25Avg. Ti=48/4=12# of Tardy Trucks = 2

Truck# ti Fi di Ti

4 10 10 30 0

2 14 24 45 0

1 20 44 25 19

3 35 79 50 29

Total 157 48

Page 5: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

5

HW # 4

EDD

F’=43.25T’=7.25# of Tardy job = 1

Truck# ti Fi di Ti

1 20 20 25 0

4 10 30 30 0

2 14 44 45 0

3 35 79 50 29

Total 173 29

Page 6: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

6

HW # 4

CR : Current Time = 1:00pm

Truck# ti di CR

1 20 25 25/20 =1.25*

2 14 45 45/14 =3.21

3 35 50 50/35 =1.43

4 10 30 30/10 =3

Pick!

Page 7: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

7

HW # 4

CR : Current Time = 1:00pm+20min = 1:20pm

Truck# ti di di-CurTime

CR

2 14 45 25 25/14 =1.79

3 35 50 30 30/35 =0.86*

4 10 30 10 10/10 =1

Pick!

Page 8: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

8

HW # 4

Current Time = 1:20pm+35min = 1:55pm

Late Jobs use “SPT” order, pick #4, then #2

Truck# ti di di-CurTime CR

2 14 45 -10

4 10 30 -25 Pick!

Truck# ti Fi di Ti

1 20 20 25 0 F’=54.75

3 35 55 50 5 T’=18.50

4 10 65 30 35 #of Tardy Jobs=3

2 14 79 45 34

Page 9: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

9

HW # 5 p.414 Five jobs must be scheduled for batch processing on a

mainframe computer system. The processing times and the promised times for each of the jobs are listed here.

job 1 2 3 4 5

processing time 40 min 2.5 hr 20 min 4 hr 1.5 hr

promised time 11:00 A.M. 2:00 P.M. 2:00 P.M. 1:00 P.M. 4:00 P.M.

Assume that the current time is 10:00 A.M.

(a) If the jobs are scheduled according to SPT, find the tardiness of each job and the mean tardiness of all jobs.

(b) Repeat the calculation in part (a) for EDD scheduling.

Page 10: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

10

HW # 5

SPT : Current Time 10:00 AM

3 – 1 – 5 – 2 – 4

Job ti Fi di Ti

3 20 10:20 240 0

1 40 11:00 60 0

5 1:30 12:00 360 0

2 2:30 15:00 240 60

4 4:00 19:00 180 360 T’=84 mins

420

Page 11: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

11

HW # 5 EDD : 1 – 4 – 3 – 2 – 5

(Tie uses ‘SPT’ ), otherwise : 1 – 4 – 2 – 3 – 5 ; T’=136

Job ti Fi di Ti

1 40 10:40 60 0

4 4:00 14:40 180 100

3 20 15:00 240 60

2 2:30 17:30 240 210

5 1:30 19:00 360 180 T’=110550

Page 12: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

12

HW # 6Consider the information given in Problem 4. Determine the

sequence that the truck should be unload in order to minimize (a) Mean flow time. (b) Maximum lateness. (c) Number of tardy jobs.

Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock.

Assume the current time is 1:00 p.m. The times required to unload each truck and the times that the goods they contain are due in the plant are given in the table below:

Truck# Unloading time

Time Material Is Due

1 20 mins 1:25 p.m.

2 14 mins 1:45 p.m.

3 35 mins 1:50 p.m.

4 10 mins 1:30 p.m.

Page 13: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

13

HW # 6 From #4

(a) SPT minimizes F’ : 4 – 2 – 1 – 3

(b) EDD minimizes maximum lateness

: 1 – 4 – 2 – 3

(c) By Moore’s Algorithm

: 1 – 4 – 2 – 3

Page 14: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

14

HW # 7 On May 1, a lazy MBA student suddenly realizes that he

has done nothing on seven different homework assignments and projects that are due in various courses. He estimates the time required to complete each project (in days) and also notes their due dates:

Project 1 2 3 4 5 6 7

Time (days) 4 8 10 4 3 7 14 Due date 4/20 5/17 5/28 5/28 5/12 5/7 5/15

Because projects 1, 3, and 5 are from the same class, he decides to do those in the sequence that they are due. Furthermore, project 7 requires results from projects 2 and 3, so project 7 must be done after 2 and 3 are completed. Determine the sequence in which he should do the projects in order to minimize the maximum lateness.

Page 15: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

15

HW # 7 1 53

2 7

4 6

last. #4 JOBS },,min{

}{min)}({min{4,6,7} VJOBS

FJ

LATENESS MAXIMUM MINIMIZE To

Vj

7

1ii

2314506502750

dFFg

50

iiVjii

Page 16: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

16

PROJ# 1 2 3 4 5 6 7

Time 4 8 10 4 3 7 14

Due Date -11 16 27 27 11 6 14

4}-7-3-2-{....5 far, so last JOB#5 3 6}-11,14-min{14

{5,6} V 148-22J4}-7-3-2-{.... far, so

last JOB#2 6 6}-11,22-16,22-min{22 {2,5,6} V 2210-32J4}-7-3-{... far, so

Last #3 JOB 5 6}-32 27,-32 16,-min{32 {2,3,6} V 3214-46J

Last. #7 JOB 3214}-6,46-min{46 {6,7} V 464-50J

HW # 7

Page 17: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

17

4-7-3-2-5-6-1

Last JOB#6 5 6}-11 (-11),-min{11{1,6} V 113-14J

PROJ# ti Fi di Fi-di

1 4 4 -11 15

6 7 11 6 5

5 3 14 11 3

2 8 22 16 6

3 10 32 27 5

7 14 46 14 32

4 4 50 27 23

HW # 7

Page 18: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

18

8-7-3-5-6-4-1-2 1select {1,2}V8-7-3-5-6-4 4select {2,4}V8-7-3-5-6 6select {4,6}V8-7-3-5 5select {4,5,6}V8-7-3 3select {3,4,5}V8-7 7select {3,5,7}V8 8select {3,5,8}V

41362

m/c 1 JOBS 8

7

6

5

4

3

2

1

587

HW # 8

Page 19: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

19

HW # 9

(a) To minimize mean flow time SPT: 6-4-2-1-3-5

(b) To minimize “Number of Tardy Jobs”

Moore’s Algorithm

Page 20: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

20

Job ti Delivery ti di

1 1:12 15 1:27 3:30

2 :40 15 55 2:00

3 2:12 15 2:27 3:00

4 :30 15 45 5:00

5 3:06 15 3:21 4:00

6 :25 15 40 6:00

HW # 9

Page 21: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

21

HW # 9 (b) Moore’s Algorithm starting from EDD

Job ti’ Fi’ di Li

2 55 55 2:00 -1:05

3 2:27 3:22 3:00 22

1 1:27 4:49 3:30 1:19

5 3:21 8:10 4:00 4:10*

4 45 8:55 5:00 3:55

6 40 9:35 6:00 3:35

Delete Job # 3

Page 22: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

22

Job ti’ Fi’ di

2 55 55 2:00

1 1:27 2:22 3:30

5 3:21 5:43 4:00

4 45 5:00

6 40 6:00

Job ti’ Fi’ di

2 55 55 2:00

1 1:27 2:22 3:30

4 45 3:07 5:00

6 40 3:47 6:00

HW # 9

(b) Moore’s Algorithm

Delete Job # 5

Page 23: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

23

2-1-4-6-3*-5* (by SPT for tardy jobs)

or 2-1-4-6-5*-3*

# of Tardy Jobs = 2

(c) To minimize maximum lateness

EDD: 2-3-1-5-4-6

Max Li=4:10

HW # 9

(b) Moore’s Algorithm

Page 24: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

24

HW # 10

Seven jobs are to be processed through a single machine. The processing times and due dates are given here.

Project 1 2 3 4 5 6 7

Processing time 3 6 8 4 2 1 7

Due date 4 8 12 15 11 25 21

Determine the sequence of the jobs in order to minimize:

(a) Mean flow time.

(b) Number of tardy jobs.

(c) Maximum lateness & compute the maximum lateness.

(d) What is the makespan for any sequence?

Page 25: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

25

HW # 10

(a) SPT minimize F’

6 – 5 – 1 – 4 – 2 – 7 – 3

(b) To minimize Number of Tardy Jobs

Use Moore’s Algorithm

first EDD: 1 – 2 – 5 – 3 – 4 – 7 – 6

Page 26: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

26

Job ti Fi di Li

1 3 3 4 -1

2 6 9 8 1

5 2 11 11 0

3 8 19 12 7

4 4 23 15 8

7 7 30 21 9*

6 1 31 25 6

Delete Job # 2

HW # 10 (b) By Moore’s Algorithm

Page 27: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

27

Job ti Fi di

1 3 3 4

5 2 5 11

3 8 13 12

4 4 15

7 7 21

6 1 25

Delete Job # 3

HW # 10 (b) By Moore’s Algorithm

Page 28: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

28

∴ 1 – 5 – 4 – 7 – 6 – 2* - 3* ( tardy jobs by SPT)

or 1 – 5 – 4 – 7 – 6 – 3* - 2* Number Of Tardy Jobs = 2

Job ti Fi di

1 3 3 4

5 2 5 11

4 4 9 15

7 7 16 21

6 1 17 25

HW # 10 (b) By Moore’s Algorithm

Page 29: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

29

(C) EDD minimize Maximum lateness

1 – 2 – 5 – 3 – 4 – 7 – 6

maximum lateness = 9

(d)

31 same the is sequence any for

tmakespann

1ii

HW # 10

Page 30: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

30

#37• To minimize maximum lateness subject to the

precedence constraints. Lawler’s Algorithm

Job# ti Di

1 4 5

2 10 10

3 2 7

4 1 9

5 8 22

6 3 25

7 2 18

8 6 20

1→ 2→ 5→ 6

4→ 7→ 8

3

Page 31: 1 By: Prof. Y. Peter Chiu Scheduling ~ HOMEWORK SOLUTION ~

31

By Chiu’s algorithm

V1={3,6,8} max Di → 6

V2={3,5,8} max Di → 5

V3={2,3,8} → 8

V4={2,3,7} → 7

V5={2,3,4} → 2

V6={1,3,4} → 4

V7={1,3} → 3

Last → 1

The Optimal sequence is 1-3-4-2-7-8-5-6