Overview• Stage 1 - Concept (Current Works)
– Design Elements– General Specifications– Construction Timeframe Update
• Masterplan– Design Elements Summary
• Proposed Sportsfield User Policy• Questions
Byron Regional Sport and Cultural Complex
3
Stage 1 - Concept (Current Works)
• Design Elements– Multi Purpose Facility – (2500 - 2700m2)
• 2 Basketball Courts [International Size]
– Athletics Track– 3 Football Fields (Soccer) (100m x 68m) [FIFA/FNC Std]
– 2 Cricket Ovals (able to be used for AFL)
– 1 Rugby Field (100m x 68m) [ARL/NRL/ International Std]
– 2 General Purpose Fields (50m x 80m)
– 1 Hockey Field (91.4m x 55m [International Size])
– 2 External Netball Courts
Byron Regional Sport and Cultural Complex
4
Stage 1 - Concept (Current Works)• Design Elements (cont)
– 146 Space Sealed Car Park • (plus 6 Bus/Coach spaces)
– 158 Space Car Park• (plus 9 Bus/Coach Spaces)
– Amenity Block includes Canteens between Rugby and Hockey Fields
– Toilet Block between Netball Courts & General Purpose Field– Canteen Facility incorporated into Multi Purpose Facility – Storage Facilities/Site Workshop– Water Reuse Irrigation System from West Byron STP
Byron Regional Sport and Cultural Complex
5
Stage 1 - Concept (Current Works)
• General Specifications– Field sizes to at least Regional Standard– Access
• Roundabout to RTA standard (can be upgraded in future if required)
• Emergency access to be constructed to north through WBSTP Site
– 2 Bioretention Basins have been constructed– Site soils have been treated and reused onsite– Field Lighting
• 100 Lux - Football Fields• 200 Lux - Athletics Field
Byron Regional Sport and Cultural Complex
6
Stage 1 - Concept (Current Works)
• General Specifications– Ewingsdale Cycleway
Byron Regional Sport and Cultural Complex
7
Stage 1 - Concept (Current Works)
• Construction Timeframe– Earthworks
• Completed
– Turf• Complete Feb 2011
– Irrigation• Complete Feb 2011
– Perimeter Fencing• Complete Jan 2011
– Lighting• Complete March 2011
Byron Regional Sport and Cultural Complex
8
Stage 1 - Concept (Current Works)
• Construction Timeframe– Turf maintenance (approx 9.5 ha)
• Complete June 2011
– Amenities/Sheds• Complete Feb 2010
– Roundabout• Complete December 2010
– Car park• Complete Feb 2011
– Landscaping• Complete Feb-May 2011
Byron Regional Sport and Cultural Complex
9
Stage 1 - Concept (Current Works)
• Construction Timeframe– Multi Purpose Facility
• Concept Plans Completed – June 2010• DA Approved – August 2010• D & C Contract (Close Tender) – 7 December 2010• Award of Contracts
– MPF – December 2010
– MPF Project Management – December 2010
• Construction commences - Feb/March 2011• Footings to be laid - by June 2011• MPF Completion - December 2011
Byron Regional Sport and Cultural Complex
10
plan
11
12
13
Master Plan Summary• Design Elements
– Field Lighting to Aust Std and REF requirements• Typical 100 - 200 lux
– Criterium Cycle Path – 1000m
– Skate Park– Playground Area– Additional Parking
• 41 spaces plus overflow on General Purpose Field• Seal remaining 158 unsealed car park and bus area
– Visitor Information Centre– Additional Outdoor Netball Court
Byron Regional Sport and Cultural Complex
14
15
Proposed Sportsfield User Policy• Shire Wide Approach
– Review Current and Future Maintenance– Audit Current Payments – e.g. Electricity– Usage – Sporting Groups, Schools – Classification System– Procedure Development i.e. Wet Weather– Undertake Consultation– Associated Policy Development
• Naming of Public Places and Community Facilities Policy• BSC Sponsorship Policy
– Will inform management of BRSCC
Byron Regional Sport and Cultural Complex
16
Questions??
Byron Regional Sport and Cultural Complex
17
18