1 cdbi inspection insights for 2008 kelly clayton senior reactor inspector engineering branch 1...

11
1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

Upload: lawrence-rice

Post on 05-Jan-2016

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

1

CDBI Inspection Insights for 2008

Kelly ClaytonSenior Reactor Inspector Engineering Branch 1 Region IV

Page 2: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

2

Preview

Clarity on “Margin” concept, other issues with this inspection

Selection of items and Types of Margin

Use of Operator Actions and Plant-Ref. Simulator

Use of Operating Experience

Plant Modification Impacts

PIR impacts

Summary

Page 3: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

3

Clarity on “Margin” concept

Example: A pump purchased with 5000 gpm capacity to met an initial design requirement of 4000 gpm would have a 1000 gpm margin. However, after plant changes, the actual requirement may be 4200 gpm. IST results show a decrease in pump performance to 4100 gpm leaving a negative margin. Inspectors seeing arguments that there is still a 200 gpm margin from original design.

Page 4: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

4

Other “issues” with this inspection

• Licensee representatives not always effective at ensuring proper personnel are available to address inspector issues.

• Numerous occasions in locating/identifying design basis for systems and components. Sometimes weeks from time of initial requests without results.

Page 5: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

5

Selection of items

Follow IP 71111.21, which specifies to:“Select 20-30 risk-significant and low design margin samples in the following categories: components, operator actions and operating experience.

Usually pick approximately 20/5/5 for final selections (components/OA/OE).

Page 6: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

6

Types of Margin

Analytical margin Operations margin Maintenance margin Complexity margin

Page 7: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

7

Use of Operator Actions and Plant-Ref. Simulator

Screen risk-significant Operator manual actions

Operations Engineer on the CDBI team will develop the “high-risk” scenarios (with licensee training staff) to run on one or two crews (selected randomly) to verify manual actions selected are achievable.

Use HRA worksheets

Verify other actions thru plant walk-downs using plant procedures

Operator work-arounds

Page 8: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

8

Use of Operating Experience

• Includes items selected and generic issues

• Evaluate how licensee dispositions the OE

• Acquire objective evidence that OE issue is resolved (beyond a written evaluation)

Page 9: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

9

Plant Modification Impacts

Verify that design bases, licensing bases, and performance capability of components have not been degraded through modifications (IP 71111.17, section 02.02.a)

Verify proper considerations for screening of 50.59 issues and various conclusions are correct.

Verify post-mod test operability

Page 10: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

10

PIR impacts

Review significant corrective action documents for the last four years, including degraded/deficient conditions

Review adequacy of technical evaluation, corrective actions, operability determinations

Follow IP 71152 for additional guidance

Page 11: 1 CDBI Inspection Insights for 2008 Kelly Clayton Senior Reactor Inspector Engineering Branch 1 Region IV

11

Summary

To have a successful CDB Inspection:

1. Review the IP and plan accordingly

2. Have a strong design margin program

3. Have a strong Corrective Action program

4. Review OE and implement as necessary