Colorado River Canal Lining Projects Coachella & All-American Canals
Colorado River Canal Lining Projects Coachella & All-American Canals
January 2007
ASCE Construction DivisionWest Coast Mega Projects Conference
2
Colorado River BasinColorado River Basin
3
Canal Lining Projects LocationCanal Lining Projects Location
Coachella
Existing Lined
New CanalExisting Unlined
Map Key
El Centro
Lake Cahuilla
Chocolate Mountains
All American Canal
Coachella Canal
Salton Sea
4
Canal Lining ProjectsCanal Lining Projects
• Components of Colorado River Quantification Settlement Agreement
• Settles a water rights dispute and litigation dating to the 1960s
• Provides 93,700 ac-ft/yr of water
• SDCWA will receive 77,700 ac-ft annually
• SLR will receive 16,000 ac-ft annually
5
History of the All American Canal Lining ProjectHistory of the All American Canal Lining Project
• Congressional authorization of the Project was under PL 100-675, Title II signed into law by the President on November 17, 1988
• Concrete lining was from just downstream of Pilot Knob (~Station 1170+27) to Drop 4, a total of about 29 miles
• During preparation of the EIS/EIR the Project was modified to run from Station 1250+00 to Drop 3 due to:
– Major environmental issues between Drops 3 & 4 and costs to mitigate such
– Wanted to move the starting point away from Pilot Knob, (a sacred area of the Quechan Indians) to eliminate any potential environmental/cultural conflicts
• Approved the Record of Decision (ROD) on July 29, 1994
6
History of the All American Canal Lining ProjectHistory of the All American Canal Lining Project
• Completed and filed EIS/EIR in July 1994• Reclamation undertook a Re-examination and Analysis of 1994
FEIS/EIR and ROD which determined said documents remained current with the proposed action
• California State Legislature passes SB 1765 continuously appropriating $200 million for the two canal projects, with $126 million set aside for the Project. This bill was signed into law by the Governor on September 24, 1998
• California voters in 2003 approve Proposition 50; includes $20 million for the two canal projects; adds $9.65 million to Project for total of $135.65 million
• Quantification Settlement Agreement (QSA) and its related documents signed on October 10, 2003 with the Project a key component to reduce California’s water use to its 4.4 million acre-feet apportionment
7
History of the Coachella Canal Lining ProjectHistory of the Coachella Canal Lining Project
• Congressional authorization of the Project was under PL 100-675, Title II signed into law by the President on November 17, 1988
• Concrete lining from Siphon 7 to Siphon 32, a total of about 35 miles
• FEIS/FEIR was completed and filed on April 27, 2001• Record of Decision (ROD) signed on March 27, 2002• Amendment #1 to ROD signed on changing preferred
alternative to refined parallel canal• Key permit was the Corps of Engineers 404
nationwide permit received in June 2004
8
AACLP Project LocationAACLP Project Location
9
AACLP AlignmentAACLP Alignment
10
AACLP Project ElementsAACLP Project Elements
• Construct approximately 23 miles of lined canal adjacent to existing canal
• DWR funding up to $135.65 Million
• Current estimates indicate significant overrun of available funds
• Design is complete.
• Construction is expected to be completed in Spring 2009
11
All-American Canal Typical SectionAll-American Canal Typical Section
Proposed Lined Section 1.75H:1V side slope Reaches 1 & 2
2H:1V side slope Reach 3
Existing Unlined Section2H:1V side slope
50’
150’
130’ +/-
Spoils
24’ O&M Road
12
67,700 Acre-Feet per Year of Water Conserved from Lining the All-American Canal
67,700 Acre-Feet per Year of Water Conserved from Lining the All-American Canal
SDCWA 56,200 ac-ft
SLR11,500 ac- ft
13
How does lining 78% of the canal result in recovering 97% of seepage water?
How does lining 78% of the canal result in recovering 97% of seepage water?
Reach ac-ft Cumulative ac-ft
1 50,850 50,850
2 14,700 65,550
3 2,150 67,700
• The seepage recovery by reach is as follows:
14
Project ChallengesProject Challenges
Project team has and is working diligently on a fast-track basis to address a number of design, construction, scheduling, and cost issues to minimize costs (construction, environmental, and operations/maintenance) yet optimize the new canal facilities and the required environmental mitigation.
15
Design ChallengesDesign Challenges
• New parallel alignment to minimize canal excavation, rights-of-way, and dewatering
• Reach 1B is most difficult—a number of alternatives were considered. The embankment in-canal alignment was selected
• Project has and will continue to be impacted by increases in fuel, cement, and to a smaller extent steel prices
• Working together to ensure that all state funds required based on current schedule are available
16
Current StatusCurrent Status
• Design is complete and the project is preparing to begin construction
• Current schedule indicates construction completion in Spring 2009
17
Canal PhotosCanal Photos
18
19
20
CCLP Project Location
Existing Unlined
Map Key
Existing Lined
New Canal
Salton Sea
Coachella
El Centro
Lake Cahuilla
Chocolate Mountains
All American Canal
Coachella C
anal
21
CCLP AlignmentCCLP Alignment
22
CCLP Project ElementsCCLP Project Elements
• Construct approximately 35 miles of lined canal adjacent to existing canal
• Construction began October 2004
• Project expected to be completed April 2007
• DWR funding up to $83.65 Million
• Construction awarded for $71,198,900
• Current estimates for environmental and other areas indicate available funds will be exceeded
23
Coachella Canal typical sectionsCoachella Canal typical sections
Proposed Lined Section1.5H:1V side slope
Existing Unlined Section2H:1V side slope
16’
55’
40’ – 46’
Spoils
20’ O&M Road
24
26,000 Acre-Feet per Year of Water Conserved from Lining the Coachella Canal
26,000 Acre-Feet per Year of Water Conserved from Lining the Coachella Canal
SLR4,500 ac-ft
SDCWA21,500 ac-ft
25
Design/Construction ChallengesDesign/Construction Challenges
• With parallel canal, raised the invert of the canal 4 feet (from 2 feet below existing canal invert to 2 feet above existing canal invert)
• Developed a large mammal safety and water source strategy
• Performed ecological value assessment to meet environmental commitments in an economically sound manner
26
Current StatusCurrent Status
• Construction is slightly ahead of schedule• Construction is approximately 97% complete• Lining of the canal was completed in August 2006• Tie-ins to existing canal completed in November
2006• Water cutover occurred on December 4, 2006• Total excavation – 5.6 million cubic yards (approx.)• Structural concrete – 37,000 cubic yards (approx.)• Concrete lining – 1.3 million square yards (approx.)• Fencing and electrical work is in progress
27
Canal PhotosCanal Photos
28
29
30
31
32
33
SDCWA FundingSDCWA Funding
• Working together to ensure that all state funds required during the construction phase is available– Will ensure that all state funds are used prior to
the need for SDCWA funds for costs over $83.65 million for CCLP and $135.65 for AACLP
– This will reduce financing costs to SDCWA and the project
34
IID/DWR AACLP Funding Agreement
AACLP Project OrganizationAACLP Project Organization
All American Canal Coordinating Committee (Voting Members)• IID – Michael King • SDCWA – Kenneth Steele • Chairman – Joseph Summers
IID Executive Program ManagerKirk Dimmitt
Participants (Non-Voting)• Reclamation – Russ Reichelt• DWR – Chuck Keene• San Luis Rey – Clyde Romney• CVWD• PVID
Parsons Project ManagerUli Kappus
Environmental ActivitiesConstruction Management
Construction Manager – Tim Larson
DesignBookman-Edmonston
Project Manager – Wayne Dahl
Design CoordinationCoordinator – Rick Cox
• Montgomery Watson Harza• Various Consultants - Canal Design - Dewatering - Sedimentation - Soils - Flow Measurement/ Operations - Cost Estimating - Construction Techniques
• Geotechnics, Inc.• TESCO
Environmental Coordinator –
Michel Remington, IID
• AFM Affiliates Cultural Resources
• Dr. Paul Krausman
Large Mammal Surveys
• EcoSystems Restoration Associates Wetlands Enhancement• RECON • Parsons
35
AACLP OM&R Coordinating CommitteeAACLP OM&R Coordinating Committee
Non-Voting Member
Voting Members
Member Jointly Appointed
IID SLR
USBR
CVWD
IID prepares O&M plan for All-American Canal
SDCWA
36
CCLP Project OrganizationCCLP Project Organization
Coachella Canal Coordinating Committee (Voting Members)• CVWD – Patti Schwartz • SDCWA – Kenneth Steele • Chairman – Joseph Summers
CVWD Executive Program ManagerKirk Dimmitt
Participants (Non-Voting)• Reclamation – Russ Reichelt• DWR – Chuck Keene• San Luis Rey – Clyde Romney• IID – Paul Peschel• PVID
SDCWA/DWR Funding Agreement
CVWD Project EngineerDan Charlton
Design/Construction ManagementMontgomery Watson Harza – Bookman-Edmonston
• Project Engineer – Janet Atkinson• Construction Manager – John Dahl
Environmental Activities
• ASM Affiliates – Cultural Resources
• AMEC – Biological Manager, Construction Environmental Monitoring
Project Manager – Wayne DahlEnvironmental Coordinator – Monica Swartz, PhD
37
CCLP OM&R Coordinating CommitteeCCLP OM&R Coordinating Committee
Non-Voting Member
Voting Members
Member Jointly Appointed
SLR
USBR
CVWD
CVWD prepares O&M plan for Coachella Canal
SDCWA
38