Page 1: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

1

FINANCING OF INFRASTRUCTURE FINANCING OF INFRASTRUCTURE PROJECTS byPROJECTS by

IFCI LimitedIFCI Limited

Page 2: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

2

INFRASTRUCTURE PROJECTS

•Power ProjectsPower Projects•Thermal-Coal, Naphtha, Gas•Hydro- Run of River, Dam•Non-Conventional-Wind, Co-generation, Solar

•Telecom ProjectsTelecom Projects•Basic Telecom Services•Cellular Services•Paging Services

•Ports-Container Terminal, Dry & Bulk TerminalPorts-Container Terminal, Dry & Bulk Terminal•Roads, Bridges & BypassRoads, Bridges & Bypass•RailwaysRailways•Sewerage & Water SupplySewerage & Water Supply

Page 3: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

3

• Rupee Loans• Foreign Currency Loans• Underwriting Commitments• Guarantees

Foreign Loans Deferred Payments

TYPES OF FINANCIAL ASSISTANCE

Page 4: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

4

WHY PRIVATE SECTOR PARTICIPATION?

Most Favourite for Infrastructure1. Funds – Private Investment & Foreign

Investment2. Viability – Investors and lenders make long term

commitment3. Efficiency – Balance of Construction &

Operation costs.4. Transfer of advanced technology5. Good management6. Speed of Construction7. Standards & Performance of facility

Page 5: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

5

MODELS OF PRIVATE SECTOR PARTICIPATION (PSP)

BT- Build-Transfer: Simple Construction contract

BOT- Build-Operate-Transfer

BOOT- Build-Own-Operate-Transfer

BTO- Build-Transfer-Operate

BOO- Build-Own-Operate

Page 6: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

6

TYPICAL BOT STRUCTURE

Off taker

Investors

EPC ContractorLenders

Principal

O & M Contractor

Raw Material Supplier

Promoter / SPV

Supply contract

Concession Agreement Off take

agreement

Turnkey

Contract

O & M Contract

Shareholder agreement

Lenders agreement

Page 7: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

7

STRUCTURE IN POWER PROJECT

SPV

Principal/Govt.

Suppliers

Lenders Investor Contractor

Operator

User/SEB

Dev. agreement

Supply Contract

LoanAgreement

ShareholderAgreement

EPCContract

O&MContract

PPA

Page 8: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

8

STRUCTURE IN ROAD PROJECT

SPV

Principal/Govt.

Operator

User

Concession agreement

LoanAgreement

ShareholderAgreement

EPCContract

O&MContract

Toll

Lenders

Investors Contractor

Page 9: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

9

CONTRACTUAL ARRANGEMENT ASSOCIATED WITH BOT

AppraisalDesign

Construction

Commissioning

Time

Cum

mulative C

ashflow

Traditional Construction

Turnkey

Produit-en-main

Build – Operate - TransferO & M cotracts

Decommissioning

Project Cashflow

+

_

Page 10: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

10

ROLE OF GOVERNMENTRegulator•Reduce Political Risk

•Reduce Bidding Risk

•Reduce Financing Risk – Land, Infrastructure

•Reduce Demand Risk – Market

•Transfer from Promoter to Principal

Page 11: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

11

SUITABILITY OF BOT CONTRACTS

BOOT / BOT – Tunnels, Bridges, Roads, Rail Infrastructure, Power Generation & Distribution, Water & Sewerage System & Telecommunication

Franchising – Rail Operating Services\

BOO – Water & Sewerage System, Clinical Waste, Hospital Equipment & Prison (Custodial Services).

Leasing/Contracting Out – Hospital Building, School Building, Prison Building & Airport.

Page 12: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

12

RISKS IN INFRASTRUCTURE PROJECTS

Global Risk

•Political: Country and Concession

•Legal: Host country and Agreement

•Commercial: Market, Reservoir and Currency

•Environmental: Sensitivity, Impact and Ecological

Page 13: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

13

RISKS IN INFRASTRUCTURE PROJECTS

Elemental Risk

•Construction: Physical, Construction, design and Technology

•Operation: Maintenance, Training, Operation

•Finance: Interest, Payback, Loan and Equity

•Revenue: Demand, Toll and Development

Page 14: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

14

INFRASTRUCTURE PROJECTS : RISKS

Risk FactorsSupply / Traffic / ReserveMarketForeign ExchangeOperating: TechnicalOperating: CostOperating: ManagementEnvironmentalInfrastructureForce MajeureCompletionEngineeringPoliticalFundingSyndicationLegal

Royalties, TaxProj. Loan, Capital Exp., InterestProj. Loan, InterestOverheads.

Cash Costs, RoyaltiesOutput/Qty., PrincipalCapital Exp., InterestCash Costs, Capital Exp.

Cash CostsCash Costs, Increase in Wkg. CapitalCash Costs, OverheadsOutput/Qty., Cash Costs

Output/Qty.Output/Qty., Price, Increase in Wkg. Cap.Price, Interest, Principal

Areas of impact

Page 15: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

15

INFRASTRUCTURE PROJECTS – RISK TRADE OFF

Supply / Traffic / ReserveFuel Supply Agreement; Traffic/Reserve Reports of Consultants.

Market PPA / Sales Contract

Foreign exchange Government Support; PPA/ Sales Contract;FX Hedging/ Swaps

Operating Technology:SPV / JVA; Maintenance Guarantee; O & M Agreement

Operating CostSPV / JVA; PPA / Sales Contract; Fuel Supply Agreement.

Page 16: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

16

INFRASTRUCTURE PROJECTS – RISK TRADE OFF

Operating ManagementSPV / JVA; O & M Agreement.

EnvironmentalO & M Agreement; Environmental Warranty; Insurance; Environmental Report.

Infrastructure Concession; Government Support.

Force MajeureLDs;Insurance.

Page 17: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

17

INFRASTRUCTURE PROJECTS – RISK TRADE OFF

CompletionConcession; Implementation Agreement; Completion Support; Turnkey Contract; Performance Guarantee; LDs; Engineering Report of Independent Engineer

EngineeringTurnkey Contract; Engineering Report of Independent Engineer

PoliticalConcession; Comfort Letter from Govt.; Implementation Agreement; SPV / JVA; LDs; legal opinion

Page 18: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

18

INFRASTRUCTURE PROJECTS – RISK TRADE OFF

ParticipationImplementation Agreement; SPV / JVA; Completion Support; PPA / Sales Contract.

SyndicationLoan Agreement; Inter - Creditor Agreement

LegalConcession; Implementation Agreement; Comfort Letter of Govt.; Loan Agreement; Inter – Creditor Agreement; Mortgages / Charges; Legal Opinion.

Page 19: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

19

POWERPOWER

Page 20: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

20

HYDRO POWER PROJECT - ROR

Page 21: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

21

HYDRO POWER PROJECT – DAM

Page 22: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

22

HYDRO POWER PROJECT – DAM

Page 23: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

23

HYDRO POWER PROJECT – MICRO

Page 24: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

24

POWER GRID

Page 25: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

25

HYDRO PROJECT-MAJOR RISKS

•Hydrology

North India –Snow Fed- Capacity Utilization-50-60 %

Central & South India-Monsoon- Capacity Utilization-20-30%

• Project Completion

Force Majeure

Geological Uncertainties

•Rehabilitation & Resettlement

•Environmental

Page 26: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

26

THERMAL PROJECT - COAL

Page 27: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

27

THERMAL PROJECT - COAL

Page 28: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

28

THERMAL PROJECT - COAL

Page 29: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

29

COAL BASED PROJECT- MAJOR RISKS

•Location from Coal Mine

•Coal Transportation Arrangement

•Ash Content in Coal

•Availability of Water

•Environmental-Disposal of Fly Ash

•Off take Arrangement-Transmission Line

Page 30: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

30

GAS BASED PROJECT-MAJOR RISKS

• Location from Gas wells

•Availability of Gas

•Availability of Water

•Technology

•Gas Pricing Policy in India

Page 31: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

31

DG BASED PROJECT- MAJOR RISKS

•High Variable Cost of Power

•High Maintenance Cost

•Transportation Risk of Fuel

Page 32: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

32

WIND ENERGY BASED PROJECT- MAJOR RISKS

•Availability of Wind Energy Potential- Capacity Utilization-25-30% ( Tamil Nadu and Karnataka)

•Financial Policies- 80% Depreciation in the first year of operation

•O & M contract

•Technology- 1 MW , Height of Tower-80 M

Page 33: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

33

• Debt Equity ratio : 70 : 30 Core promoters’ contribution : 15 - 20%(in

large projects) Preference to existing power companies

with Good Track Record Satisfactory track record of participants

Promoters

EPC contractors

O&M contractors

LENDING NORMS: POWER PROJECTS

Page 34: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

34

LENDING NORMS: Contd…

Statutory clearances and approvals to be obtained from CEA (if applicable) Environment agencies Signing of power purchase agreements Fuel allocation

POWER EVACUATION ARRANGEMENTS

Page 35: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

35

• Security mechanism & credit enhancement Creation of English mortgage

Pledge of shares aggregating to minimum 51% of

equity

Assignment of licenses, rights and titles to project

documents etc.

GoI / state govt. Guarantee

Escrow & Trust and Retention Account

LENDING NORMS: Contd…

Page 36: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

36

30% of total equity to be brought upfront by promoters. The balance 70% should be backed by acceptable credit support

Completion support

Prudential norms Exposure to the industry

Exposure to the company

Exposure to the group

LENDING NORMS: Contd..

Page 37: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

37

WORKING CAPITAL ESTIMATION

Covered under PPA

•Fuel Inventory : 2 Months

•Secondary Fuel Inventory : 2 Months

•O & M expenses : 1 Month

•Receivables : 2 Months

Page 38: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

38

PROCUREMENT PROCESSMoU Route

•Fixed Tariff •Interest Payment •Depreciation/ Debt Repayment•O & M Expenses (Coal -2.5 %, Gas-2.5 % ,DG-4 %)•16 % return on Equity•Tax

Fixed Charges payable at 68.5 % PLF Incentive on return on Equity @ 0.7 % for 1% increase in PLF

•Variable Tariff•Fuel cost at specified heat rate ( Coal-2500 Kcal/ Unit, Gas-2900 Kcal/unit combined-2000Kcal/unit)

Page 39: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

39

PROCUREMENT PROCESS: Contd…

Competitive Bidding

•Fixed Tariff- Lowest- Criteria for selection

•Variable Tariff- Based on Heat Rate

Page 40: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

40

MAJOR CONCERNS/ISSUES IN POWER SECTOR

• STATE ELECTRICITY BOARDS (SEB)- CREDIT WORTHINESS

- UNBUNDLING OF SEBs

- HIGH T&D LOSSESTechnical Commercial Total

Andhra Pradesh 23% 13% 36%

Madhya Pradesh 25% 22% 47%

(Based on latest study by ICRA and CRISIL)

- UNMETERED SUPPLY

- LOW COLLECTION EFFICIENCY

- LOW EFFICIENCY OF SEB’s POWER PLANTS

(SEBs - 62%(approx.), Central Sector - 72%)

Page 41: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

41

ISSUES IN POWER SECTOR (Contd..)LOW AGRICULTURE/DOMESTIC TARIFF.SEBs REQUIRE GOVT. SUPPORT FOR MEETING DEFECIT

LIMITED ESCROWABLE CAPACITY OF SEBs

DELAY IN OBTAINING GOVT. CLEARANCES LEADING TO TIME & COST OVERRUNS.

REVISION OF PPAs BY SEBs EVEN AFTER FINANCIAL CLOSURE

Page 42: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

42

ISSUES IN POWER SECTOR (Contd.)

• RATIONALISATION OF STAMP DUTY RATES PREFERABLY BY FIXING A CAP AS IS DONE IN STATES LIKE GUJARAT, MAHARASHTRA & MP ETC. TO ENABLE THE IPPs TO CREATE ENGLISH MORTGAGE

• STANDARDISATION OF TENDERING PROCEDURE FOR COMPETITIVELY BID PROJECTS

• EXPOSURE LIMITS FOR FIs

• ABSENCE OF ACTIVE SECONDARY DEBT MARKET FOR SECURITISATION OF ASSETS

Page 43: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

43

ISSUES IN POWER SECTOR (contd..)

•BOTTLENCKS IN AVAILABILITY / TRANSPORTION OF FUEL

•ENVIRONMENTAL ISSUES - EFFECTS OF FLY ASH, THERMAL DISCHARGE AND EFFLUENTS ON FLORA, FAUNA ETC.

- RESETTLEMENT AND REHABILITATION OF AFFECTED PERSONS ESPECIALLY FOR HYDRO PROJECTS

Page 44: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

44

ISSUES REGARDING POWER TARIFF

• LOW AGRICULTURE / DOMESTIC TARIFF

• HIGH COMMERCIAL AND INDUSTRIAL TARIFF

• AGRICULTURE / DOMESTIC TARIFF BEING SUBSIDISED BY HIGH INDUSTRIAL TARIFF

• HIGH INDUSTRIAL TARIFF LEADS TO HIGHER COST OF PRODUCTION IN POWER INTENSIVE INDUSTRY

Page 45: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

45

POWER TARIFF ISSUES (Contd..)

• POWER INTENSIVE INDUSTRY PRODUCTS WOULD BE LESS COMPETITIVE IN GLOBAL SCENARIO.

• POWER INTENSIVE MANUFACTURING SECTOR WOULD ALSO REQUIRE SUBSIDY FROM GOVT. FOR COMPETITIVENESS.

• SEBs REQUIRE SUBSIDY FROM GOVT. TO MEET CASH FLOW DEFECIT (Rs.34000 CRORES IN THE YEAR 1999-2000)

Page 46: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

46

REFORMS & RESTRUCTURING OF SEBS

RESTRUCTURING OF SEBs- UNBUNDLING/CORPORATISATION OF OF SEBs IN TO GENERATION, TRANSMISSION & DISTRIBUTION COMPANIES.- PRIVATISATION OF DISTRIBUTION ZONES/COMPANIES• SETTING UP OF STATE ELECTRICITY REGULATORY COMMISSION (SERC)- OPERATIONALISATION OF SERC - ISSUING OF TARIFF ORDERS• REFORMS TO IMPROVE OPERATIONAL/FINANCIAL PARAMETERS OF SEBs- IMPROVING THE T&D INFRASTRUCTURE AND 100% METERING.

Page 47: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

47

REFORMS OF SEBS (contd..)

- ESTIMATION OF T&D LOSSES AND REALISTIC TIME FRAME FOR REDUCTION OF LOSSES - IMPROVING BILLING & COLLECTION EFFICIENCY- ENERGY AUDIT• MAJOR MILESTONES PROPOSED FOR REFORMS

- 100% METERING

- T&D LOSS REDUCTION

- T&D SYSTEM AUGMENTATION

- ENERGY AUDIT

- IMPROVEMENT IN COLLECTION EFFICIENCY

- COMPUTERISATION OF BILLING

Page 48: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

48

REFORMS (contd..)

-IMPROVEMENT IN PLF & AVAILABILITY OF SEB PLANT

- RATIONALISATION OF TARIFF BY REDUCING CROSS SUBSIDY.

Page 49: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

49

P O R T S

Page 50: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

50

MAJOR CONCERNS

• Mortgaging of jetty area in favour of lenders as security for financial assistance.

Limitation for fixing tariffs by the sponsors at major ports.

Requirement of explicit provision under major ports trust act for private sector participation.

Environmental issues: affect on estuaries and coastal zone flora, fauna, etc.

Labour is extremely unionized in ports and oppose modernization

Page 51: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

51

MAJOR CONCERNS: Contd…

Insufficient back-up land for bulk cargo storage /container yards at ports.

• Lack of road and railway linkage between ports and hinterland.

Page 52: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

52

REFORMS contd..

• National Port AuthorityEnsuring a well defined process with

clear objective and firm political commitment for and towards port reforms.

Ensuring sound, stable and pro-active regulatory framework with appropriate regulatory procedures.

Page 53: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

53

REFORMS contd..

• Privatisation New capacity addition should come entirely

through the private sector. Encourage private sector participation in new

terminals at existing ports including cargo handling services.

Encourage private sector participation in Port Services, like Labour, Pilotage, Towage etc.

Encourage private participation in minor port / green field projects.

Page 54: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

54

REFORMS contd..

Excess Port Labour and Labour reforms Initiate labour reforms and improve labour

relations Compensate port labour suitably while going

ahead with the privatisation process Need to buyout existing labour keeping pace

with improvements in cargo handling technology

Page 55: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

55

REFORMS contd..

• Connectivity Development of infrastructure linkages to the

hinterland, like Railway and Road network for smooth and faster movement of cargo.

• Bankable concessions for port projects Ensuring adequate security for loans by

allowing mortgaging of the "Marine works" and other assets like land acquired in Lender's favour.

Page 56: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

56

ROADS & BRIDGES

Page 57: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

57

ISSUES• Land acquisition and resettlement: normally lead to

delay in project completion and higher contingency provisions.

• Leakage in toll collection.• Resistance by users to pay tolls• Alternative routes increase uncertainty in toll

collections• Absence of security by way of mortgage to lenders.• Environmental issues: felling of roadside trees,

increase in noise pollution, drainage of the area .

Page 58: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

58

PROCUREMENT PROCESS•Small Projects- Bridges, By pass-Tolls are fixed- Minimum Concession period criteria for selection.

•Large Projects- (4 laning)

•Tolls are fixed and concession period are fixed- minimum upfront grant criteria for selection.

•Annuity Based Projects-Concession period fixed , min. annuity payable biannually criteria for selection.

Page 59: 1 FINANCING OF INFRASTRUCTURE PROJECTS by IFCI Limited

59

THANK YOU