Page 1: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

1

Implementation of an EHS Review/Approval Procedure for New Equipment and Processes

David E. Downs, CIH, CSP

President

EHS Management Partners, Inc.

Page 2: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 2

Context for the Development of an Equipment Review Process

• Context– Division of Rapidly Growing Medical Device

Manufacturer • 2000 employees; growing to 3000 over 2 years

• Operations - assembly, extrusion, metal finishing

• 7-8 facilities in local area

• One EHS Manager, one EHS staff, one Admin

Page 3: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 3

Context for the Development of an Equipment Review Process

• Internal Design and Construction of Manufacturing Equipment– Unique and innovative product line– Rapid growth in both depth and breath– 5-10 new manufacturing devices released each

week

Page 4: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 4

Context for the Development of an Equipment Review Process

• Initially began as a process for equipment documentation and conformance under ISO 9000 program

• Facilities requirements - power, water, space

• Sign-off by EHS Manager added as an “after-thought”

Page 5: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 5

Initial Implementation

• No structure to assessment

• Based on ability of EHS staff to recognize and resolve significant issues

• Lack of internal consistency

• No documentation of results

• Timing Issues– Responsiveness– Push-back on Findings

Page 6: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 6

Review Process Development

• Consultant initially asked to “help out” with volume

• Liability Issues

• Challenges– Reasonable Comprehensiveness– Consistency– Responsiveness/Efficiency– Documentation– Business Integration

Page 7: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 7

Equipment Review Process Design

• Developed a Format for Process Review– Addressed Full Range of EHS issues– Set up as a word processing form– Completed blank form in field– Entered data, printed results, sent

documentation as follow-up

• Improvement, but not efficient

Page 8: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 8

Equipment Review Process Design

• Modified to a MS Access database

• Data entry at the time of review on portable computer

• Print Equipment Review Document on site with portable printer

• Document now incorporated into Equipment Documentation Package

Page 9: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 9

Equipment Review DatabaseEquipment Data

Page 10: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 10

Equipment Review DatabaseHazardous Chemicals

Page 11: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 11

Equipment Review DatabaseHazard Assessment Criteria

Page 12: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 12

Equipment Review DatabasePhysical Hazards

Page 13: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 13

Equipment Review DatabaseErgonomic Assessment

Page 14: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 14

Equipment Review DatabasePPE Hazard Assessment

Page 15: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 15

Equipment Review DatabaseEvaluation Results

• Possible Review Outcomes– Released with no restrictions– Released with recommendations for

improvement– Released on condition of correction of specified

items– Not Released

Page 16: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 16

Equipment Review DatabaseReview Results

Conditions Corrected Follow-up Checkbox

Page 17: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 17

Equipment Review Report

Page 18: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 18

Corrective Action Follow-up

Requirements

CorrectiveAction

Page 19: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 19

Process Results

• More comprehensive

• More consistent

• More efficient

• Better documented

• Better follow-up on required changes

• Integrated into process/equipment documentation

Page 20: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 20

Additional Process Results

• Education of Engineers and Designers

• Involvement earlier in the development process

• Establishment of de facto standards

• Equipment Improvement over time

• Increased visibility and credibility of EHS function

• Now completely executed in-house

Page 21: 1 Implementation of an EHS Review/Approval Procedure for New Equipment and Processes David E. Downs, CIH, CSP President EHS Management Partners, Inc

Copyright - EHS Management Partners, Inc. - 1999 21

Conclusions

• Being involved in the process of new equipment/process development is a critical EHS function

• Find a way to be an effective part of the process, not an addendum