Page 1: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

1

Introduction to Legal and Contractual Aspects of CDM

Projects

University of Twente 21 March 2006

Robert O’SullivanClimate Focus

Page 2: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

2

Content

• Nature of Emissions Rights• Project Structuring• Basic legal documentation• Emission Reduction Purchase

Agreement• Scenario• Conclusions

Page 3: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

3

Nature of Emission Rights

Page 4: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

4

Sources of emission rights

• International treaties• Regional, national and state legislation or

codes• Contracts • Common law and equity

Page 5: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

5

A taxonomy of what is traded• Units defined by the Kyoto Protocol:

– Assigned Amount Units (AAUs)– Certified Emission Reductions (CERs, tCERs, lCERs)– Emission Reduction Units (ERUs)– Removal Units (RMUs)

• Units defined by EU and national legislation:– EU Allowances– UK Allowances and Credits– Australian Abatement Certificates and Sequestration Rights– US SOx and NOx Allowances– Other

• Units defined by contracts:– Verified Emission Reductions (VERs)

Page 6: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

6

What are they?• Treatment and characteristics of units is more

important than whether or not they are ‘property’– Represent a right to be used as a compliance unit,

and emit one tonne of GHG in this context? – Transferable?– Ownership and possession by entities?– Clearly defined?– Irrevocable/indefeasible once issued?– Protection of 3rd party interests such as charges?

(restricted transfer on this basis?)– Treatment as financial services?– What conditions are imposed on any of the above?

Page 7: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

7

Contractual Rights• Emission Reductions

– ‘any right, interest, credit, entitlement, benefit or allowance to emit (present or future) arising from or in connection with any GHG Reduction by the Project and includes any right that may be created under any regulatory or legal regime as a result of the GHG Reductions whatsoever’

• Verified ERs– ERs which have been verified and certified by an

independent auditor, but have not been formally issued

• So what are ERs and VERs?– Not as secure as other emission units– Still of value

Page 8: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

Creation of VERs and CERs

Creation of GHG Reductions Creation of GHG Reductions (measured in tonnes of CO2e)(measured in tonnes of CO2e)

Verification by DOEVerification by DOE

VERsVERs

Approval of Methodologies , Approval of Methodologies , approval of the project, approval of the project,

registrationregistration

CERsCERsCarbon Carbon ContractContract $$$$

Issuance by EB

Verification (by DOE)Verification (by DOE)

Page 9: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

9

So what is used in contracts?• Depends on what the project produces• Early World Bank CDM and JI contracts were

for VERs• Most CDM and JI contracts are for CERs and

ERUs• VER contracts tend to be restricted to the

voluntary market

Page 10: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

10

Project Structuring

Page 11: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

11

Project Structuring

• Initially the CDM anticipated direct investments into projects

• Today the most common form of a carbon contract is forward contract in the form of an Emission Reductions Purchase Agreement (ERPA)– An ERPA is a long term off-take agreement

• An increasing number of developers are also choosing to sell on the spot market

• Equity investments are being seen

Page 12: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

12

Equityinvestor

Bank

Technology Supplier

CER BuyerElectricity purchaserGovernment

€? CERs?

CERs€

Tech€

Local $€

eConstruction

O&MAccess

Affected peopleetc

CDM Project Structures

Approval

Parent Company

Page 13: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

13

Project Structuring Issues• Who owns the project, who generates the

CERs?– Establish initial CER ownership.

• Do other parties have an interest in the CERs?

• Who do I want as project partner?– Buyer: who to buy from– Seller: work through an intermediary, partner,

parent vs. directly with buyer?

• Who are the other Project Participants, and how are they involved?

Page 14: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

14

2 Case Studies:

• Landfill Projects generating ERs through capture of methane [and electricity generation]

• Generally public projects or public private partnerships

• Contractually flexible as different rights and obligations get easily separated [waste, land, landfill gas, CERs..]

• Example for necessary due diligence?

Page 15: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

Ownership of Emission Reductions Project Example: Landfill Project I

MunicipalityMunicipality

Carbon ContractCarbon Contract Power Purchase A.Power Purchase A.

Owns the landOwns the land

Operates the landfillOperates the landfill

Collects the wasteCollects the waste

Sells the Electricity Sells the Electricity

Page 16: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

Ownership of Emission Reductions: Project Example: Landfill Project II

Shareholder Shareholder AgreementAgreement

Power Power Purchase Purchase

AgreementAgreement

Grid Connection Grid Connection AgreementAgreement

Carbon Carbon ContractContract

Power Generation Power Generation LicenseLicense

Environmental Environmental LicenseLicense

Use of Land Use of Land AgreementAgreement

Landfill Gas Landfill Gas Transfer AgreementTransfer Agreement

Loan AgreementLoan Agreement

Construction Construction AgreementAgreement

Operations- and Operations- and Management Management AgreementAgreement

Landfill Concession Landfill Concession AgreementAgreement

Special Purpose Special Purpose CompanyCompany

Page 17: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

17

Basic Legal Documentation for

Carbon Projects

Page 18: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

18

Letter of Endorsement / No-Objection• Not required under Kyoto, but can be useful• Between Seller/Buyer and Host Country• Expression of Support / Non Objection• Evidence that the Host Country has been

informed and endorses the project • No binding endorsement which does not

create a right to any future approval

Page 19: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

19

Letter of Approval

• Required under Kyoto• Between the Host Country and the Project

Developer• But also: between the Buyer and an Annex I

country• Should be unconditional• Not clear whether the approval can be

withdrawn• Not clear how the Letter of Approval would

be treated in a dispute (double intl’/ natl’ nature, may grandfather rights)

Page 20: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

20

Letter of Intent / Exclusivity Agreement

• Between Seller and Buyer• Early legal document• Secures exclusivity• Cost recovery in case the project sponsor

unilaterally decides not to move forward with the negotiations

• Helps the project sponsor to obtain financing• Gives comfort to the Buyer to start spending

money on due diligence and contract drafting and negotiation

• May include some basic or key terms regarding the transaction that will appear in the ERPA

Page 21: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

21

CER Transfer Contracts

• Assignments– To equity holders– As part of a technology supply agreement

• Spot contracts– Standardized sale of CERs after issuance– Not project specific

• Forward contracts– Emission Reduction Purchase Agreements– Project specific

Page 22: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

22

Emission Reductions Purchase

Agreement

Page 23: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

23

ERPA: Purpose

• Record agreement

• Identify responsibilities

• Establish rights

• Manage Risk

Requires understanding of CDM rules, so tend to

be complex and difficult for unspecialized

lawyers

Page 24: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

24

“CERSPA” initiative

• Sponsored by Inter-American Investment Corporation

• Objective to produce a balanced CER Sale and Purchase Agreement template and explanatory Guidance Document– Open source, freely available – Contain more detailed information, plus

translations into a number of languages (Spanish, Portuguese, Chinese)

– Will be online soon at www.cerspa.org

Page 25: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

25

ERPA: Key Terms

• Conditions of effectiveness (conditions precedent)• Price

– Upfront payments?

• Volume and delivery• Listing as Project Participant and Communication

with EB• Damages/default• Monitoring and Verification• Governing Law, Costs, Force Majeure

Page 26: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

26

ERPA: Conditions of effectiveness• Cross effectiveness of other contracts

– Financial closure– Power purchase agreement

• Project Commissioning• Legal opinions • LoA, validation, registration

• Useful for buyer to be able to drop a non-performing project without default proceedings

• Useful for a seller to avoid liability if the project is not registered

Page 27: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

27

Price: Fixed Price

“The Buyer agrees to pay the Seller €X for each CER delivered to the registry account of the Buyer before 1st March, 2013”

Page 28: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

28

Price: Simple Indexed Price

“The Buyer agrees to pay the Seller X% of the Market Price of [an EU Allowance] [CER Spot Market Price] for each CER delivered into the registry account of the Buyer before 1st March 2013”

Page 29: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

29

Price: Simple Indexed Price with Floor and Ceiling

“The Buyer agrees to pay the Seller X% of the Market Price of an EU Allowance for each CER delivered into the registry account of the Buyer before 1st March 2013, except that irrespective of the Market Price of an EU Allowance the price paid for each CER shall never be greater than €X per CER and shall never be less than €X per CER”

Page 30: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

30

Price: Different Approaches in Practice

Market Price Simple Indexed PriceFixed Price Indexed Price with Floor & Ceiling

Page 31: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

31

Pricing: Factors that Affect the Starting Price• Bargaining• Demand• EUA price

– weather• EU policy developments• Timing of payments and delivery• Delivery “guarantees”/ remedies for under delivery• Who pays share of proceeds for EB admin expenses

($0.10/0.20 per CER) and other taxes• Risks

– Regulatory (baseline, additionality, registration) – Project (underlying project risks inc. technology, financing etc) – Host country (LoA) – Counter party (capitalization, experience)– Reputation (resettlement?)

Page 32: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

32

Upfront payments

• Generally only given if required to complete financing

• Security questions:– What kind? (L/C, parent guarantee, amortized

equity)

– How to get it? - Lenders probably won’t share it.

• Discount of CER price

Page 33: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

33

Volume and Delivery• When• Where (to an from)• How

– primary transfer (Art. 6/12)– secondary transfer (Art.17)– Communication rights with the EB

• How much– CDM: share of proceeds for adaptation (2%)

• Seniority (these issues won’t necessarily appear

together in the same clause)

Page 34: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

34

Fixed Annual Volume

“Before the 1st February each year the Seller agrees to deliver the first X CERs generated by the Project in the previous Year into the registry account nominated by the Buyer”

Page 35: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

35

Fixed total amount with “Acceleration”

• Combined with seniority and fixed total delivery obligations

“Before the 1st February each year the Seller agrees to deliver 100% of the CERs generated by the Project in the previous Year into the registry account nominated by the Buyer until a total of X CERs have been delivered”

Page 36: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

36

Percent: Total and Annual

“Before the 1st March 2008 the Seller agrees to deliver X% of the CERs generated by the Project before 1st January 2008 into the registry account of the Buyer”

“Before the 1st February each year the Seller agrees to deliver % X of the CERs generated by the Project in the previous Year into the registry account nominated by the Buyer”

Page 37: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

37

Volume and Delivery: Fixed vs. %

Default Amount

Fixed

Fixed with acceleration

% with Default Amount

Default Amount

Default Amount

Green may or may not be default depending on seniority

Page 38: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

38

Project Participants and Communication with EB• “Project Participant” is someone authorized to

participate in a CDM project pursuant to a LoA. • Listed in A.3 of the PDD• PPs have a number of rights re. a project including:

– Right to tell the EB where to send CERs when they are issued

• To be realized, PP must be named as communication focal point in modalities of communication

– Right to receive CERs when first issued by the EB– Right to receive notification and respond to any request

for review• “Party Involved” is an Annex I or non-Annex I party to

KP that has issued a LoA. They have a number of rights:– To be listed as a PP– To request a review at registration and issuance

Page 39: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

39

Project Participants and Communication with EB

• Issues that arise from this:– Who is listed as a PP?

• Most buyers want to be listed, so that they can get CERs directly from EB without going through art. 17 transfer.

– Who has communication rights with EB?• Most buyers want this as security that they will

receive their CERs• May be problematic for Seller if there are multiple

buyers• Joint communication is possible

– Make sure buyer is removed from being a PP after they have all their CERs

Page 40: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

40

Remedies: Delivery Default“If the Seller fails to deliver the Default Amounts the Buyer may;

Require the Seller to provide replacement CERs to the Buyer

Recover damages from the Seller

Require the Seller deliver additional CERs in the following Year in an amount equal to the difference between the amount delivered and the Default Amount

Terminate the Agreement and recover from the Seller any outstanding Advance Payment and other outstanding costs plus interest of X%.”

Page 41: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

41

Remedies: Payment default“In the event of a Payment Default interest payable to the Seller shall accrue to the Buyer at a fixed rate of X% per annum

If the Buyer has not remedied a Payment Default within the cure period, the Seller may recover damages from the Buyer

If the Buyer has not remedied a Payment Default within the cure period, the Seller may recover CERs already delivered to the Buyer but not paid for

If the Buyer has not remedied a Payment Default within the cure period, the Seller may terminate the agreement”

Page 42: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

42

Remedies: Intentional Breach• Normally have strict damages remedies for

defaults that are the result of intentional misconduct or gross negligence

Page 43: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

43

Remedies and Pricing

Market Price Simple Indexed PriceFixed Price Indexed Price with Floor & Ceiling

Default Default

Page 44: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

44

Force Majeure

• “Events beyond the control of a party”• Absolves an affected party from liability re.

obligations affected by a FM event (e.g. delivery, payment)

• Issue of what is included/excluded– EB decisions?– Biological processes?– Wind/water availability?

Page 45: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

45

Elements of Risk in Carbon DealsKey Issues:

– Market/Price Risk– Project Risk

• Finance, Approvals, Construction, Production• Has an impact on:

– Existence of Project– Therefore existence and production of CERs

• Needs management for the long term– Kyoto Protocol Risk

• Host Country Approval, Compliance, Eligibility, Transfer• Has an impact on:

– Existence and compliance of CERs/ERUs– Price

• Needs management for the long term

Page 46: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

46

Risk Allocation

• Principle: Assign risk to the party best able to bear it

• Investors/creditors/seller assume most project risks

• Buyer or Seller take Kyoto Protocol related risks

• Market risk is often shared

Page 47: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

47

• Market/Price risk:– Selling/purchasing CERs of different seniority– Flexible pricing– Option contracts (put or call)

• Kyoto risk: – Host country agreement or letter of approval– Using approved methodologies– Entering into an ERPA after project registration– Securing the right to communicate with the EB– Obtaining Host Country and Annex I country approval

(+authorization)

Risk Mitigation Tools

Page 48: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

48

• Project and delivery risk– Ensure management and operational capacity of the

counterpart – Secure stable financing of the project– Ensure resource availability– Ensure legal compliance – Using conservative CER projections– Sell from a pool – Ensure the senior right to the CERs (buyer)– Establish reporting obligations (buyer)

• Seller payment/receipt of CER risks– Credit check– Alternative registries/delivery = issuance– Escrow agent (see CERSPA guidance document)

Risk Mitigation Tools

Page 49: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

49

Scenario

• Just agree on basic terms that will be carried over to the ERPA

• No need for “legal” drafting

Page 50: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

50

Conclusions

Page 51: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

51

Lessons Learned

• The Carbon Prices do not have a big impact on IRRs of Energy Projects

• High transaction costs, but they are coming down• Not all countries welcome CDM/JI investments• Rulings and interpretations of the international regulator

often not predicable and ambiguous• We are running out of time

BUT:

Page 52: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

52

Lessons Learned

• Additional Income Stream – An ERPA secures an additional income stream for the project

• Additional Environmental Benefits – An ERPA monetizes the global environmental value of a project

• Additional Knowledge Generation – Developing an ERPA provides a learning experience to all parties

• Additional Due Diligence – An ERPA may lead to additional scrutiny and risks assessments of the project

• Forming Additional Partnerships – An ERPA broadens the stakeholder basis and the support for a project

Page 53: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

53

Summary

• Risk profiling of a project is key• Removal of risks comes at a price• Interests of the Parties need to be clear• Individually negotiated contracts are more

complicated but more stable than standardized agreements

• Harmonizing ERPA with lending agreements increases the robustness of both agreements

• Timing is key

Page 54: 1 Introduction to Legal and Contractual Aspects of CDM Projects University of Twente 21 March 2006 Robert O’Sullivan Climate Focus

54

Questions?

Robert O’SullivanClimate Focus