1 july ssue building connections

2
1 Construction on the Pikangikum Power Line continues into July with PowerTel and their subcontractors. This month the first steel poles will be assembled and placed to allow stringing to proceed. Previous activities of material delivery, structure framing, pole setting and anchor installation continue in July with the start of stringing activities. A new parking expansion was constructed at Taxi Bay for residents of Pikangikum First Nation. This allows room for gravel trucks to haul for the construction of the substation road. The crews remain busy with structure framing and assembly. The structures are assembled by attaching the steel arms, grounding wires and insulators. After each structure is assembled, a setting crew digs an excavation and installs each structure using a crane or radial boom vehicle. July and August will see a lot of activity stringing conductors and shield wire. The stringing activity involves pulling out special designed ropes which are then used to pull out the conductor wires and shield wires. Equipment on the ground each end of the stringing activity keeps tension on the ropes and conductor so that neither will touch the ground during the work. J ULY 2018 I SSUE Previous Milestones 25kV line installation is complete All required line equipment has been purchased July 2018 Pole installation and framing Begin stringing activities Substation construction continues August 2018 Line foundation complete September 2018 Final site inspection and restoration October 2018 Substation construction complete November 2018 Line construction complete December 2018 Line energization High-Level Project Schedule BUILDING CONNECTIONS PIKANGIKUM POWER LINE PROJECT Crews are working to frame and string the 115 kV line along the wood poles. One of the first steel poles to be assembled and placed to allow stringing to proceed. Should you have any concerns or questions related to construction activities, please contact us. For Project information, please visit our website: www.pikangikumpowerlineproject.com July Project Update Community Members working on the Power Line Project.

Upload: others

Post on 15-Apr-2022

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 JULY SSUE BUILDING CONNECTIONS

1

Construction on the Pikangikum Power

Line continues into July with PowerTel and their

subcontractors. This

month the first steel

poles will be

assembled and

placed to allow

stringing to

proceed. Previous

activities of material

delivery, structure

framing, pole setting

and anchor

installation continue

in July with the start

of stringing

activities. A new

parking expansion

was constructed at

Taxi Bay for

residents of

Pikangikum First

Nation. This allows

room for gravel trucks to haul for the

construction of the substation road.

The crews remain busy with structure

framing and assembly. The structures are

assembled by attaching the steel arms,

grounding wires and insulators. After each

structure is assembled, a setting crew digs an

excavation and installs each structure using a

crane or radial boom vehicle. July and August

will see a lot of activity stringing conductors

and shield wire. The stringing activity involves

pulling out special designed ropes which are

then used to pull out the conductor wires and

shield wires. Equipment on the ground each

end of the stringing activity keeps tension on

the ropes and conductor so that neither will

touch the ground during the work.

JULY 2018 ISSUE

Previous Milestones

25kV line installation is

complete

All required line

equipment has been

purchased

July 2018

Pole installation and

framing

Begin stringing

activities

Substation

construction continues

August 2018

Line foundation

complete

September 2018

Final site inspection

and restoration

October 2018

Substation

construction complete

November 2018

Line construction

complete

December 2018

Line energization

High-Level

Project Schedule

BUILDING CONNECTIONS

P I K A N G I K U M P O W E R L I N E P R O J E C T

Crews are working to frame and string the 115 kV

line along the wood poles.

One of the first steel poles to

be assembled and placed to

allow stringing to proceed.

Should you have any concerns or questions related to construction activities, please contact us.

F o r P r o j e c t i n f o r m a t i o n , p l e a s e v i s i t o u r w e b s i t e : w w w . p i k a n g i k u m p o w e r l i n e p r o j e c t . c o m

July Project Update

Community Members working on the Power Line

Project.

Page 2: 1 JULY SSUE BUILDING CONNECTIONS

PowerTel invites all interested

Candidates to forward their

resumes to:

Ashley Lawrence E: [email protected]

P: 1 (705) 866-2825 Ext. 1007

P I K A N G I K U M P O W E R L I N E P R O J E C T

Your Community Contact

Email General Project Inquiries To: [email protected]

P: (807) 728-3287 Jonah Strang

E: [email protected]

2

JULY 2018 ISSUE

Learn more about the

Wataynikaneyap Power Training Program, contact:

Marlon Gasparotto OSLP Training Coordinator

P: (807) 474-3300

E: [email protected]

CONTACT US

Interested in the Project? Explore our Website & Facebook Page for more information!

https://www.pikangikumpowerlineproject.com/

Pikangikum Power Line Project

Work areas have environmental monitors to observe all wildlife in the area and follow protection measures where required.

P IKANGIKUM W ILDLIFE

ARTWORK FROM EENCHOKAY BIRCHSTICK SCHOOL

How will the power line help your community and the environment?

Artist: Ardelle - Artist: Ashlyn Artist: Neebin

“When the power sometimes goes out at

night, we have to use candles. It will be a lot

safer .”

The PowerTel Environmental Team is pleased to have several

community members working together to conduct wildlife monitoring near

the construction area. This month bird sweeps were conducted with the help

of the environmental trainees. One pair of nesting sandpipers was identified

within the construction area and an appropriate mitigation buffer was

implemented to not interfere with the nesting period.

Caribou calving and migration was also closely monitored this spring

and a total of 13 caribou were spotted. Construction activity is reduced in

sensitive areas to limit disturbance in certain locations and at times

throughout the project.

PowerTel hosted the first session for ECO Canada’s Environmental

Monitoring Certification course, known as BEAHR Training. The training is a

community-based, culturally relevant, short-term course developed for

anyone with a desire to work in the environmental field. Students

conducted classroom studies and field trips outlining foundation skills,

introduction to the environmental sector (hydrology, ecology, soils science),

and technical skills (GPS, ARC GIS and mapping).

Left: Preparing for Conductor Stringing

Right: Shawna Cheena, PowerTel Site Administration