Page 1: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

1

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Update of Interim Safety Improvement Planning

Presentation to Board of Airport Commissioners

November 16, 2009

Michael D. Feldman Deputy Executive DirectorFacilities Management Group

Page 2: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

2

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

LAWA’s Airfield Safety Goals

• Overall: Continue to be proactive in enhancing safety on the airfield while maintaining efficient movement of aircraft

• Interim: Reduce risk levels as much as possible while maintaining airfield operational efficiency pending ultimate North Airfield configuration decisions

• Long-Term Improvements: Eliminate and/or substantially reduce levels of risk while maintaining airfield operational efficiency

Page 3: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

3

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Background of IRSIP Study

• North Airfield Technical Studies – Independent Airfield Safety Assessments

• 2007 North Airfield Safety Risk Assessment Report

• Independent North Airfield Safety Study (NASA, Academic Panel) - ongoing

• BOAC Direction to LAWA to Identify Further Safety Enhancements During Interim Period

• IRSIP Study

• Status Update Presentation to BOAC on April 6, 2009

Page 4: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

4

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Airfield Safety Improvements Implemented

• South Airfield Improvement Project - completed

• Enhanced Marking and Lighting System – completed

• Runway Status Light System – pilot program completed

• ASDE-X system installation – completed

• Pilot and Controller Awareness Program – on-going

Page 5: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

5

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Safety/Risk Terminology

• Hazard: condition that is necessary to lead to an incident or accident.

• Likelihood: Probable frequency of hazard occurrence (i.e. once per week/month/year/10 years/100 years).

• Severity: A measure of the end result (i.e. increased pilot and FAA workload, extreme pilot measures to avoid collision, loss of life and property).

• Risk: a predicted result of an event and the probability of the event occurring.

Page 6: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

6

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

FAA Engineering Recommendations

• FAA places priority on runway separation and proper airfield geometry

• Pending resolution of the final airfield geometry, the FAA prefers the following:

“. . .. The preference is for aircraft to cross in the last third of the runway whenever possible, since within the middle third of the runway the arriving/ departing aircraft is usually on the ground and traveling at a high rate of speed.”1/

1/ FAA Engineering Brief No. 75: Incorporation of Runway Incursion Prevention into Taxiway and Apron Design, November 19, 2007.

Page 7: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

7

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Existing North Airfield System

Page 8: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

8

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Current Configuration – Risk Matrix

Severity No Safety Effect

Minor Major Hazardous Catastrophic

Likelihood 5 4 3 2 1

Frequent – AMore than once

per week

Probable – BOnce every

month

Remote – COnce every

year

Extremely Remote – D

Once every 10-100 years

Extremely Improbable – ELess than once

every 100 years

LAX 005

LAX 008

LAX 009

LAX 001

LAX 002

LAX 007

LAX 006

Source: LAX-WCG, Inc. Safety Risk Management Panel, May 2007

* Unacceptable with Single Point and Common Cause Failures

High Risk

Medium Risk

Low Risk

LAX 003

LAX 004

LAX 010

*

Page 9: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

9

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Safety Risk Assessment Panel

• FAA Subject Matter Experts

• Air Traffic Control

• Runway Safety

• LAWA Subject Matter Experts

• Airfield Operations

• Planning

• Safety Risk Assessment Expert

• Panel Focus

• Review Hazards LAX001 and LAX002 to confirm that the hazards still exist based on current operations and the implementation of short-term enhancements

• Review the Preferred Alternative and determine if it would reduce the severity and/or likelihood of the hazards occurring

• Evaluate the potential of the Preferred Alternative causing additional hazards and/or worsening other existing hazards

Page 10: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

10

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

IRSIP – Taxiway Relocations

Page 11: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

11

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Interim Improvements (IRSIP) – Initial Safety Panel Findings Risk Matrix

Severity No Safety Effect

Minor Major Hazardous Catastrophic

Likelihood 5 4 3 2 1

Frequent – AMore than once

per week

Probable – BOnce every

month

Remote – COnce every

year

Extremely Remote – D

Once every 10-100 years

Extremely Improbable – ELess than once

every 100 years

LAX 005

LAX 008

LAX 009

LAX 001

LAX 002

LAX 007

LAX 001

LAX 006

Source: LAX Safety Risk Management Panel, September 2009

* Unacceptable with Single Point and Common Cause Failures

High Risk

Medium Risk

Low Risk

LAX 003

LAX 004

LAX 010

LAX 002 *

Page 12: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

12

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Runway Status Light Locations

Page 13: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

13

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Next Steps

• December Board Meeting: Staff will request authority to initiate IRSIP design and environmental review

• Provide results of this work to NORSAC Committee and the Academic Panel.

• On-going collaboration with the FAA regarding additional Runway Status Light Installations and IRSIP

• Finalize Safety Risk Management Panel Report

Page 14: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

14

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

Discussions/Questions

Page 15: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

15

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX001 – Taxiway Y• What is going on: Simultaneous use of Runway 24R for

Arrivals and Runway 24L for Non-Heavy Departures

• What may occur: The departing Non-Heavy aircraft is cleared for departure and begins its takeoff roll and the arrival on Runway 24L, instructed to hold on Taxiway Y, approaches to hold line at the same time.

• What is the hazard: The aircraft that landed on Runway 24R inadvertently crosses past the hold line on Taxiway Y and crosses Runway 24L at the same time a Non-Heavy begins its departure roll down Runway 24L.

• What may be the outcome if the hazard occurs: Either or both pilots conduct a severe maneuver to avoid a potential collision, which would be classified by the FAA as a “severe operational error.”

Page 16: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

16

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX001 – Taxiway Y

Page 17: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

17

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX001 – Taxiway Z• What is going on: Simultaneous use of Runway 24R for Arrivals and

Runway 24L for Non-Heavy Departures

• What may occur: The departing Non-Heavy aircraft is cleared for departure and begins its takeoff roll and the arrival on Runway 24L, instructed to hold on Taxiway Z, approaches to hold line at the same time.

• What is the hazard: The aircraft that landed on Runway 24R inadvertently crosses past the hold line on Taxiway Z and crosses Runway 24L at the same time a Non-Heavy begins its departure roll down Runway 24L.

• What may be the outcome if the hazard occurs: Either or both pilots conduct a severe maneuver to avoid a potential collision, which would be classified by the FAA as a “severe operational error.”

Page 18: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

18

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX001 – Taxiway Z

Page 19: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

19

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX002 – Taxiway Y• What is going on: Simultaneous use of Runway 24R for

Arrivals and Runway 24L for Heavy Departures

• What may occur: The departing Heavy aircraft is cleared for departure and begins its takeoff roll and the arrival on Runway 24L, instructed to hold on Taxiway Y, approaches to hold line at the same time.

• What is the hazard: The aircraft that landed on Runway 24R inadvertently crosses past the hold line on Taxiway Y and crosses Runway 24L at the same time a Heavy begins its departure roll down Runway 24L.

• What may be the outcome if the hazard occurs: Either or both pilots conduct a severe maneuver to avoid a potential collision, which would be classified by the FAA as a “severe operational error.”

Page 20: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

20

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX002 – Taxiway Y

Page 21: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

21

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX002 – Taxiway Z• What is going on: Simultaneous use of Runway 24R for

Arrivals and Runway 24L for Heavy Departures

• What may occur: The departing Heavy aircraft is cleared for departure and begins its takeoff roll and the arrival on Runway 24L, instructed to hold on Taxiway Z, approaches to hold line at the same time.

• What is the hazard: The aircraft that landed on Runway 24R inadvertently crosses past the hold line on Taxiway Z and crosses Runway 24L at the same time a Heavy begins its departure roll down Runway 24L.

• What may be the outcome if the hazard occurs: Either or both pilots conduct a severe maneuver to avoid a potential collision, which would be classified by the FAA as a “severe operational error.”

Page 22: 1 Los Angeles World Airports | LAX Interim Runway Safety Improvement Project Update of Interim Safety Improvement Planning Presentation to Board of Airport

22

Los Angeles World Airports | LAX Interim Runway Safety Improvement Project

North Airfield Hazards

• Hazard LAX002 – Taxiway Z