19 Jul 2022 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on: http://b-e-r.user.jacobs-university.de/index.php/ publications Gert Brunekreeft Jacobs University Bremen [email protected] November 22, 2013 CRNI annual conference, Brussels http:// www.germany.info/ Vertretung/usa

Upload: lucy-skerritt

Post on 15-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

18 Apr 20231

Network Unbundling and the Cost of Misaligned Coordination:Lessons from Electricity and Railways

paper to appear soon on:http://b-e-r.user.jacobs-university.de/index.php/publications

Gert Brunekreeft

Jacobs University Bremen

[email protected]

November 22, 2013CRNI annual conference, Brussels

http://www.germany.info/Vertretung/usa

Page 2: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

Unbundling and Electricity

GB 18 Apr 2023 2

EU: First directive 1996/92/EC

► Unbundling: accounting separationNon discriminatory network accessPrevention of cross-subsidiesTransparency

 

EU: Second directive 2003/54/EC:

► Legal, functional and managerial unbundlingLegal unbundlingManagerial unbundlingPersonnel splitIndependent decision rights for network maintenance. Firewalls

EU: Third Directive 2009/72/EG

► Option out of three:

1.Ownership unbundling

2.Deep-ISO

3.Independent Transmission Operator (ITO) (“third way”)

Page 3: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

Unbundling and Railways

Background:– 4th Railway Package 2013

EU-Commission, 2013, “The fourth railway package – completing the single European railway area to foster European competiveness and growth”, 31.01.2013, Brussels.

– Impact Assessment 2013EU-Commission, 2013, Impact Assessment, Brussels, 30.1.2013 SWD(2013) 12 final

Subgoal: “optimizing the governance of infrastructure management”

– Two “challenges”: •“Equal access challenge” •“Efficient management challenge”:

– Ensure better coordination/alignment between the infrastructure managers and rail operators

► Balancing between competition and coordination!GB 18 Apr 2023 3

Page 4: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

UK railways – McNulty-report

McNulty report 2011 for the UK-government on the UK railway system– UK railway system is a separation (unbundled) model

Two main conclusions:

► the UK railway system is significantly less efficient than comparable peers

• 40% inefficient!

► the main cause of the inefficiency is far-reaching fragmentation of the system

• leading to misaligned incentives GB 18 Apr 2023 4

Page 5: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

McNulty-report (cont’d)

“Barriers to efficiency” in more detail:– Fragmentation of structure and interfaces

– Ineffective and misaligned incentives

– Fares structures do not send efficient pricing signals

– The industry’s legal and contractual framework is complex

One of the main recommendations:“Closer alignment of route-level infrastructure management with Train

Operating Companies (TOCs), at one or other of the following levels:

– minimum – cost and revenue sharing, and joint targets; or

– intermediate – joint ventures or alliances; or

– maximum – full vertical integration through a concession of infrastructure management and train operations combined.”

GB 18 Apr 2023 5

Page 6: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

Cost of coordination: 3 sources

1. regulation versus unbundling dilemma– The combination of strict regulation and strict unbundling can quickly lead to

inefficient outcomes; see next slide

2. difficulties with optimal network charging– Distributional effects

– Legal constraints

– Informational constraints

– Unbundling itself: does the network charge reach the end-user?

3. strategic behavior resulting in misaligned incentives– Asymmetric information and incentive compatibility are real challenges

– Classical: sunk investment and long life duration, which is different for infrastructure and users

GB 18 Apr 2023 6

Page 7: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

regulation versus unbundling dilemma

GB 18 Apr 2023 7

► Two numerical examples

Source: Brunekreeft, 2013, BEWP-DP 15, p. 11

► Either loosen regulation (revenue- and cost-sharing models) or loosen unbundling.

Page 8: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

Conclusions

In the unbundling debate, we need to weigh the benefits against the cost more carefully

We need to balance better between competition and coordination

Policy recommendation:– Either loosen regulation (revenue- and cost-sharing models) or

loosen unbundling– Find other innovative governance structures that strike a better

balance

GB 18 Apr 2023 8

Page 9: 1-May-15 1 Network Unbundling and the Cost of Misaligned Coordination: Lessons from Electricity and Railways paper to appear soon on:

18 Apr 20239

Thank you!

Gert Brunekreeft

Jacobs University Bremen

[email protected]