1 oecd - working party of senior budget officials public-private partnerships: affordability, value...
TRANSCRIPT
![Page 1: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/1.jpg)
1
OECD - Working Party of Senior Budget Officials
Public-Private Partnerships: Affordability, Value for Money and the PPP Process
Frédéric MARTYCNRS – GREDEG – University of Nice Sophia-Antipolis
OFCE – Innovation and Competition Department
Winterthur (Zürich) – 21-22 February 2008
![Page 2: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/2.jpg)
2
Public-Private Partnerships Affordability, Value for Money
and the PPP Process
The The EconomicsEconomics of PPPs : Affordability, Value for Money of PPPs : Affordability, Value for Money and and Risk SharingRisk Sharing
Why choosing the PPP route?Why choosing the PPP route?
Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
Session 2 – Thursday, February21
![Page 3: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/3.jpg)
3 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
What are the determinants of government commitment in PPPs ?
o Budgetary constraints and fiscal opportunism
o Economic efficiency in the whole life of the project
Experience shows the promises of cost savings are not always and significantly kept
o Transaction costs induced by the competitive process and the contractor monitoring
o The additional cost of private financing compared to sovereign debt must be taken into account
o The lack of competition for the market for some contracts or informational asymmetries induce rents for private contractor.
![Page 4: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/4.jpg)
4 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
Some figures on cost savings promised by PPPs
The UK exampleo Arthur Andersen and Entreprise LSE (2000) : 17%o On average, savings are assessed by the NAO as < 10%o for the MoD they range from 20 % (White fleet) to 4 - 5 % (DFTS / Skynet V)
Financial costsFinancial costs
o A public programme financed through guilt is 150bp cheapero Financial tools allow to limit to 80bp the additional costo For HM Treasury (2006), they just represent 5% of the overall cost of a project
![Page 5: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/5.jpg)
5 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
Transaction costsTransaction costs
o They can outweigh the potential savings of PPP (Williamson, 1976)
o If PPPs allows to reduce public procurement expenditures, what are the cost of cost savings ?
o Two types of transaction costs must be highlighted :
o Ex ante Ex ante (bidding and contracting costs)
o Ex post Ex post (monitoring costs)
![Page 6: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/6.jpg)
6 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o Ex ante costsEx ante costs
They can deter potential competitors from bidding and cancel the potential benefits of PPPs
Bidding costs represent 3 % of the project total expected cost : It is three time higher than the costs induced by conventional procurement schemes.
The public body is often bound to compensate the costs incurred by reserve bidders to make sure of a sufficient competitive pressure.
Advisory costs for the public partner amount to 3.7% on average but can reach 10 % for very complex project.
Because of such costs, HM Treasury considers that the minimum capital value for running a PFI is £20M.
![Page 7: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/7.jpg)
7 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
Ex post transaction costsEx post transaction costs
o For the USA, monitoring costsmonitoring costs are assessed between 3 and 25% of the capital value of PPP contracts.
o For the franchised UK railways, franchise management represents a third of the SRA operating budget.
o In PFI contracts, monitoring costs should be proportionate to the consequences of poor performance (HMT, 2004).
o Monitoring could be realised through value testing mechanisms (as benchmarking or market testing). Such provisions exist in 250 PFI contracts but potentially increase transaction costs.
![Page 8: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/8.jpg)
8 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o The critical dimension of the decision to commit into a PPP contract is the optimal risk management and not really cost savings.
o A proof by the Main Building Redevelopment contract of the MoD
o Public and private costs are both estimated at £ 746M
o The private solution was chosen because it protects government from cost and delays overruns
![Page 9: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/9.jpg)
9
746 M£
PSC distribution for the MBR (NAO, 2002)
Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
![Page 10: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/10.jpg)
10 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o Cost overruns are the main source of hidden costs in traditional procurement schemes.
o So even if private finance induces additional financing costs, choosing a PPP could be analysed as an insurance premium paid by the government against unexpected costs.
![Page 11: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/11.jpg)
11 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o The decision to enter in a long term contract despite higher expected costs could be analysed in terms of risk adversity.
o By choosing a PPP, Government values cost certainty in procurement.
![Page 12: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/12.jpg)
12 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o Two different levels must be considered (Blanc-Brude, 2007):
1. At the project level, a fixed price contract eliminates (or could eliminate) the risk of wasteful time or cost overruns.
2. At the portfolio level, contracting with a fixed price scheme and within a scheme in which government is bound to make payments all the contract long, eliminates the risk of sub-standard maintenance and congestion.
![Page 13: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/13.jpg)
13 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
o Two concluding remarks about risk transfer, affordability and value for money
1. The economics of PPP contract lies more on optimal risk allocation than maximal risk transfer
• A total Risk Transfer is an illusion : risk would be re-internalised by the Government
• The risk premium in the case of an excessive transfer would undermine the value for money
• The principle of PPP is to allocate the risk to the party, which is able to manage it at the lower cost.
![Page 14: 1 OECD - Working Party of Senior Budget Officials Public-Private Partnerships: Affordability, Value for Money and the PPP Process Frédéric MARTY CNRS –](https://reader036.vdocument.in/reader036/viewer/2022072015/56649ec55503460f94bcfaf0/html5/thumbnails/14.jpg)
14 Frédéric MARTY - Winterthur (Zürich) – 21-22 February 2008
2. A sub-optimal risk allocation could be induced if accounting strategies interfere with the government trade off between PPP and traditional procurement scheme.
• An opportunistic strategy could sacrifice the value for money to the contract’s consolidation within the accounts of the private partner.
• If government searches to get the project “off the books”, he could ignore both value for money and affordability considerations.