1 permanent international association of navigation congresses - pianc july 15, 2008 ris - rivers...
TRANSCRIPT
1
Permanent International Association of Navigation Congresses - PIANC
July 15, 2008
RIS - RIVERS INFORMATION SYSTEMOur “Invisible” Transportation Network
Richard C. LockwoodRichard C. LockwoodChief, Operations DivisionChief, Operations Division
U.S. Army Corps of Engineers, Pittsburgh DistrictU.S. Army Corps of Engineers, Pittsburgh District
RIVERS INFORMATION SERVICE
RIS GOALS
•RIS will be an electronic system that will pull data from various existing sources both Government and commercial and process and display that information in customizable user friendly formats
•Modify or replace existing USACE systems to achieve a single system that will inform and be informed by the systems already in use by our navigation partners.
• Use existing layered GIS based technology, Electronic Navigation Charting and data summarizing to provide all partners with the specific information they need to staff, operate and use the Inland Navigation system.
• Eliminate duplication of data entry and ensure seamless transfer between USACE systems and Navigation and Government partners.
3
• Generate confidence both within and outside USACE that RIS is a valuable tool that will improve operational reliability of the system while reducing data entry requirements and costs.
• RIS will use existing technology, Electronic Navigation Charting and data summarizing to provide all partners with the specific information they need to staff, operate and use the Inland Navigation system.
• RIS will eliminate duplication of data entry and ensure seamless transfer between USACE systems and Navigation and Government partners.
• RIS will generate confidence both within and outside the Government that the Inland Waterways System is an efficient, safe and reliable transportation system.
4
CONSTRAINTS
• RIS must protect sensitive and proprietary information of the commercial Navigation partners.
• RIS must fit seamlessly into the bigger CRIS service and use existing standards for data coding and classification
• RIS must be capable of informing and being informed by USCG’s AIS (Automated Identification System) and other existing commercial systems for tow tracking and scheduling
• RIS must be capable of informing and being informed by other USACE systems (Asset Management, OMBIL, CWMS, etc) and other Partner systems (NWS, USGS, IRS, Customs, etc.)
• Navigation data (current, wind speed, lock condition, gauge readings, dam operating data, etc.) provided via or by RIS must not expose USACE to any liability concerning the use of that data.
5
CURRENT DATA COLLECTION
• Lock Operators receive hard copy information from deckhand on the tow and then manually enter the data into OMNI or LPMS. (2 systems)
• OMNI/LPMS require 123 Different Items to be entered
• Result is some “simplification” – Barge tonnage information is not accurate.– Not every jumbo barge has 1500 tons
• Facilities are not getting credit for the tonnage they pass each year.Lower tonnage means lower funds
• The Corps have teams of personnel reconciling the OMNI data with the Monthly Commodity Reports submitted to the IRS & Department of Commerce by Industry.
• The data is inaccurate and unreliable.
6
Lockage Work Area
Times and Stall
Information
7
Lockage Work Area
Barge Information
8
Weather Work Area
Entered every three
hours
9
Readings Work Area
Gage information
entered every hour or after a
dam gate move
10
Readings Work Area
Individual dam gate levels are recorded
11
RIS
TOWING VESSELS
USACE ASSET MANAGEMENT
LOCKLOCAL DATA
SYSTEM DATA
TOWING COMPANIES
TERMINAL OPERATORS
PORT AUTHORITIES
SHIPPERS
USCG AIS
OMBILNATNL WEATHER SER
USGS
RECREATIONAL BOATERS
CWMS
IRS
DHS
RIVER INFORMATION SERVICE
CUSTOMS
DOE
12
STRATEGY
• LEVERAGE WORK OF PIANC WG 125 TO CREATE A NEW INFORMATION SYSTEM– USE EXISTING INFORMATION– CUSTOMIZABLE DATA DISPLAY FOR ALL USERS– UTILIZE MARINE INFORMATION OVERLAYS– ELIMINATE MULTIPLE DISPLAYS
• REPLACE OMNI/LPMS WITH LOMA (LOCK OPERATION MANAGEMENT)– NO MANUAL DATA INPUT– AUTOMATIC CAPTURE OF REAL TIME DATA AT LOCK– ELIMINATE REDUNDANT AND CONFLICTING SYSTEMS
13
Hydrographic Overlay
The latest data provides a clear view of the channel and river bottom contours.
14
AIS Overlay
15
RADARSAT Overlay
16
Lock Queue Overlay
17
Connected
SMART LOCK OVERLAY
18
Environmental Data Overlay
19
Real Time Current Velocity (RTCV) Overlay
20
• FIRST MEETING OF US NATIONAL RIS TEAM 15 JULY 2009
• ENDSTATE, GOALS AND INITIATIVES DEFINED• MARK STEVENS VP @ INGRAM BARGE HAS
PILOTHOUSE PROTOTYPE• JIM McCARVILLE / PORT OF PITTSBURGH
COMMISSION AND CMU STUDENT PRACTICUMS– SMARTLOCK– RIVER NET– WIRELESS WATERWAYS
CURRENT INITIATIVES
21
22
Questions?