1 place holder for image center for sustainable landscapes pittsburgh, pa daniel zartman |...
TRANSCRIPT
1
PLACE HOLDER FOR IMAGE
Center for Sustainable Landscapes Pittsburgh, PA
Daniel Zartman | ConstructionAdvisor : Dr. Robert Leicht
Daniel Zartman | ConstructionAdvisor : Dr. Robert Leicht
Images courtesy of the Design Alliance Architects
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | ConstructionProject Background
2
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Presentation Outline:I. Project Background
I. General Information
II. Building Information
II. Analysis 1: Critical Industry Issue
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final Recommendations
VII.Acknowledgements
General Project Information: Owner: Phipps Conservatory Contractor: Turner Construction Location: Schenley Park,
Pittsburgh, PA Function: Mixed Use
(Office/Education)
Building Size : Area: 24,350 GSF Height: 40’- 4” (3 Stories)
Project Size: Contract Value: $10 Million ($410
per SF) Project Type: New Construction Project Duration: 11 Months
Images Courtesy of Microsoft Corporation
Images Courtesy of Turner Construction
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | ConstructionProject Background
3
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Structural System: Substructure: Concrete Strip/Spread Footing Superstructure: Braced Steel Frame
Building Envelope: Exterior Walls: 8” Metal Stud w/ Reclaimed Barn Wood Facade 7,600 SF Green Roof
Sustainable Achievements: LEED Platinum Living Building Challenge SITES Certification for Landscapes Net-Zero Annual Energy Consumption Net-Zero Annual Water Consumption
Images Courtesy of Turner Construction
Presentation Outline:I. Project Background
I. General Information
II. Building Information
II. Analysis 1: Critical Industry Issue
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final Recommendations
VII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
4
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
State requirements for publicly funded projects: Traditional Design – Bid – Build Hard-bid Multiple Prime Contracts
Problems: Does not adequately address the needs of complex projects Does not incentivize the contractor to minimize schedule and
cost growth
Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII. Results/Conclusion
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Images courtesy of the Design Alliance Architects
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
5
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Funding Types: Private Public Combination
Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.
Research Goal: To create a decision tree that illustrates the progressive alternatives available to Penn State’s OPP.
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII. Results/Conclusion
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Images courtesy of the Design Alliance Architects
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
6
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Project Features Analyzed: Funding Type Delivery System Contract Type Procurement Method
Industry Members Interviewed: John Bechtel – Asst. Director of Design and Construction at
Penn State‘s OPP James Hostetler – Director of Construction and Design at
Bucknell University Kristine Retetagos – VP Preconstruction Turner Construction
Pittsburgh Tim Gilotti – Radner Property Group Jeff Sandeen - Hensel Phelps Construction Co Mike Arnold – Foreman Group Elizabeth O’Reilly - Deputy Secretary of Pennsylvania’s Public
Works
Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.
Research Goal: To create a decision tree that illustrates the progressive alternatives available to Penn State’s OPP.
Research Method: Analyze projects completed in PA by public and private owners using public funding.
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII. Results/Conclusion
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Images courtesy of the Design Alliance Architects
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
7
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Penn State’s Office of Physical Plant:
Operates as an extension of DGS Public funding types most
commonly received: Delegated (most common) – OPP
is given money with specific use Non-Delegated (uncommon) –
DGS stays heavily involved
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII. Results/Conclusion
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
8
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Projects Researched: SCI Benner: Design-Build, GMP Bucknell University Bookstore: Design-Bid-Build, CM At-Risk,
GMP Center for Sustainable Landscapes: Design-Bid-Build, CM At-
Risk, GMP
The Decision Tree: Illustrates the influence funding has on procurement, delivery and contract methods
Black Diamonds: Represent questions that can be answered by OPP project staff
Red Diamonds: Represent decisions that are made by the Government
Green Boxes: Display the conditional procurement methods
Penn State’s Office of Physical Plant:
Operates as an extension of DGS Public funding types most
commonly received: Delegated (most common) – OPP
is given money with specific use Non-Delegated (uncommon) –
DGS stays heavily involved
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII. Results/Conclusion
III. Analysis 2: Constructability
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
9
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Project: SCI Benner Project Synopsis: $174 million new
construction of a 2,000 bed medium security prison
Location: Bellefonte, PA Owner: Department of General
Services Delivery Method: Design-Build Contract Type: GMP Procurement Method: Best Value
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII.Results/
ConclusionIII. Analysis 2:
Constructability IV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly
Funded Projects
10
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Project: SCI Benner Project Synopsis: $174 million new
construction of a 2,000 bed medium security prison
Location: Bellefonte, PA Owner: Department of General
Services Delivery Method: Design-Build Contract Type: GMP Procurement Method: Best Value
Conclusions: Project Exemption is Plausible Provided exemption is approved by DGS Provided exemption is authorized by Legislation
Recommendations 2 out of 3 owners analyzed utilized a traditional delivery
system despite exemption Pursue the use of contemporary delivery methods when
necessary
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueI. OverviewII. ResearchIII.Results/
ConclusionIII. Analysis 2:
Constructability IV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
11
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste
Images courtesy of the Design Alliance Architects
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
12
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste
Research Goal: Develop an alternative atrium design that: Improves Constructability at a minimal cost Maintains the spaces passive performance Aesthetically pleasing
Images courtesy of the Design Alliance Architects
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
13
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste
Research Goal: Develop an alternative atrium design that: Improves Constructability at a minimal cost Maintains the spaces passive performance Aesthetically pleasing
Proposed Solution: Structural steel stair Transfer thermal mass to atrium walls
Images courtesy of the Design Alliance Architects
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
14
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Changes to Original Design in Alternative Design Alternative Stair
Structural Steel Rectilinear Self-supporting
Imagery based off of one provided by The Design Alliance Architects
Alternative Design (Below)
Original Design (Below)
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative
Design III. Results/Conclusion
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
15
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Changes to Original Design in Alternative Design: Alternative Stair
Structural Steel Rectilinear Self-supporting
Alternative Design (Below)
Original Design (Below)
Alternative Wall Design Inc. thickness of concrete by
3 inches Net decrease in concrete: 3
cubic yards
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative
Design III. Results/Conclusion
IV. Analysis 3: Value Engineering
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
16
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased
with steel erection) Not located on critical path
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III.Results/
Conclusion IV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
17
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased
with steel erection) Not located on critical path
Cost Comparison
Original Design - Cost of Concrete Stair $ 49,950.00
Alternative Design - Total Cost $ 119,707.63
Alternative Design - Cost of Steel Stair $ 105,603.65
Alternative Design - Increase in Wall Thicknesses
$ 14,103.98
Net Increase in Alternative Design over Original Design
$ 69,757.63
Cost Summary: Net Increase: $70,000 Resulting from:
No central support added approximately $25,000 Increased connections costs Increased structural steel costs
Terrazzo finishes added approximately $15,000
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III.Results/
Conclusion IV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 2: Constructability – Alternative Design of Atrium
18
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased
with steel erection) Not located on critical path
Alternative Design Conclusions: Not Recommended Pros
Comparably Sustainable Minimizes Construction Waste Improves Aesthetics Reduces Schedule by 10 days
Cons Significantly increased material cost
Recommendations Make adjustments to reduce cost:
Replace terrazzo Add column
Cost Comparison
Original Design - Cost of Concrete Stair $ 49,950.00
Alternative Design - Total Cost $ 119,707.63
Alternative Design - Cost of Steel Stair $ 105,603.65
Alternative Design - Increase in Wall Thicknesses
$ 14,103.98
Net Increase in Alternative Design over Original Design
$ 69,757.63
Cost Summary: Net Increase: $70,000 Resulting from:
No central support added approximately $25,000 Increased connections costs Increased structural steel costs
Terrazzo finishes added approximately $15,000
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII.Analysis 2:
ConstructabilityI. OverviewII. Alternative Design III.Results/
Conclusion IV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
19
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Images courtesy of kingspan.com/raised_flooring/full.jpg
Images courtesy of accessfloorsystems.com
Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III. Results/Conclusion
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
20
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Images courtesy of kingspan.com/raised_flooring/full.jpg
Images courtesy of accessfloorsystems.com
Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces
Research Goal: Reduce system cost without compromising performance Improve constructability
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III. Results/Conclusion
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
21
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Images courtesy of kingspan.com/raised_flooring/full.jpg
Images courtesy of accessfloorsystems.com
Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces
Research Goal: Reduce system cost without compromising performance Improve constructability
Proposed Solution: Relocated HVAC distribution to above the ceiling
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III. Results/Conclusion
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
22
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Original Design 14” Raised Access Floor System In-floor electrical distribution
Alternative Design Lowered the ceiling 6” Reduced building height by 8” Maintained High Volume/Low
Velocity flow rate
Alternative Design: Above Ceiling Distribution Original Design: Raised Floor Distribution
Alternative Design: First Floor
Alternative Design: Second FloorPresentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative
Design III. Results/Conclusion
V. Analysis 4: Schedule Acceleration
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
23
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the
Critical PathSchedule Durations for Raised Floor Analysis
SystemSchedule Duration
(Days)Total Man
HoursCrew Size
Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III.Results/
Conclusion V. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
24
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the
Critical Path
Cost Impacts 46% Decrease in cost Indirect Costs
Reduction in building height (credit)
Flooring Cost Schedule Durations for Raised Floor Analysis
SystemSchedule Duration
(Days)Total Man
HoursCrew Size
Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3
Total System ComparisonsRaised Floor Distribution System - Total Cost $ 110,000.00 Raised Floor - Material Cost $ 76,000.00 Raised Floor - Labor Cost $ 34,000.00 Ceiling Distribution System $ 50,838.00 Ceiling - Material Cost $ 7,696.00Ceiling - Labor Cost $ 19,620.00 Indirect Costs $ 23,521.00Net Decrease in System Cost: $ 59,162.00 Total Man Hours: 581 hrs
Electrical Distribution Contingency
Sales Tax Credit
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III.Results/
Conclusion V. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the
Critical Path
Cost Impacts 46% Decrease in cost Indirect Costs
Reduction in building height (credit)
Flooring Cost Schedule Durations for Raised Floor Analysis
SystemSchedule Duration
(Days)Total Man
HoursCrew Size
Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3
Total System ComparisonsRaised Floor Distribution System - Total Cost $ 110,000.00 Raised Floor - Material Cost $ 76,000.00 Raised Floor - Labor Cost $ 34,000.00 Ceiling Distribution System $ 50,838.00 Ceiling - Material Cost $ 7,696.00Ceiling - Labor Cost $ 19,620.00 Indirect Costs $ 23,521.00Net Decrease in System Cost: $ 59,162.00 Total Man Hours: 581 hrs
Alternative Design Conclusions: Added 100 hours of work Reduced cost by approximately $59,000 Recommendations: Met analysis goal to increase project’s value Pursue alternative design based on significant decrease
in system cost Marginal compromises in value
Electrical Distribution Contingency
Sales Tax Credit
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV.Analysis 3: Value
EngineeringI. OverviewII. Alternative Design III.Results/
Conclusion V. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
26
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite
Images courtesy of sips.org
Images courtesy of sips.org
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
27
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite
Research Goal: Develop alternative design Decreases the project schedule
Images courtesy of sips.org
Images courtesy of sips.org
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
28
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite
Research Goal: Develop alternative design Decreases the project schedule
Proposed Solution: Structural Insulated Panel System (SIPS) High performance wall type composed of:
OSB Sheathing EPS (Expanded Polystyrene) Foam Core
Increase superstructure to accommodate additional load
Images courtesy of sips.org
Images courtesy of sips.org
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
29
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Original Design 8” Metal Stud Framing 2” Rigid Board Insulation 5/8” Fiberglass-matt gypsum
board
Alternative Design 10 ¼” SIP Panel
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative
DesignIII. Structural Breadth IV. Results/Conclusion
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
30
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Structural Impacts: Structural Breadth Original Stud Wall: 45 PLF Alternative SIP Wall: 75 PLF
Results: W12x19 Spandrel Beams were
found to be inadequate Max. Allowable Def. = 1.07”
Deflection = 1.3” Max. Allowable Bending Moment
= 55.9 ft-kips Bending Moment = 82.2 ft-
kips W12x26 Spandrel Beams were
found to be adequate HSS 6x6x5/8 Columns were found
to be adequate
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative DesignIII.Structural
Breadth IV. Results/Conclusion
VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
31
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Structural Impacts: Structural Breadth Original Stud Wall: 45 PLF Alternative SIP Wall: 75 PLF
Results: W12x19 Spandrel Beams were
found to be inadequate Max. Allowable Def. = 1.07”
Deflection = 1.3” Max. Allowable Bending Moment
= 55.9 ft-kips Bending Moment = 82.2 ft-
kips W12x26 Spandrel Beams were
found to be adequate HSS 6x6x5/8 Columns were found
to be adequate
Sustainability Provides superior conductive and
convective performance No additional LEED points gained
Relative R-Value ComparisonR-Value Original Design 25.3 2" Rigid Board Insulation 8 5/8” Fiberglass-mat 8 8" Wall Cavity 9.3R-Value Alternative Design 35 (2) 7/16" OSB Sheathing 1 10 1/4" SIP w/ EPS Core 34
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/
Conclusion VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
32
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Reduced the project schedule by a
total of 8 days Allowed Glazing to begin 8 days
earlier than the original scheduleSchedule Durations for Façade Analysis
SystemSchedule
Duration (Days)Total Man
HoursCrew Size
8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/
Conclusion VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
33
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Reduced the project schedule by a
total of 8 days Allowed Glazing to begin 8 days
earlier than the original schedule
Cost Impacts: SIP System Cost w/ General Conditions Savings:
$74,920 Includes increased cost of superstructure of $2,578
Schedule Durations for Façade Analysis
SystemSchedule
Duration (Days)Total Man
HoursCrew Size
8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5
Façade Estimate SummaryTotal Original Metal Stud Wall System
$ 71,216
Original Design Labor Cost $
42,508
Original Design Material Cost $
25,708Adjusted Total Alternative Wall System Cost
$ 74,920
Total Alternative SIP Wall System $
88,382
Alt. Design Labor Costs $
37,594
Alt. Design Material Costs $
50,789
Estimated General Conditions Savings $
(13,462.00)
Net Increase in Cost $
3,704
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/
Conclusion VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 4: Schedule Acceleration –Alternative Wall System
34
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Schedule Impacts: Reduced the project schedule by a
total of 8 days Allowed Glazing to begin 8 days
earlier than the original schedule
Cost Impacts: SIP System Cost w/ General Conditions Savings:
$74,920 Includes increased cost of superstructure of $2,578
Schedule Durations for Façade Analysis
SystemSchedule
Duration (Days)Total Man
HoursCrew Size
8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5
Façade Estimate SummaryTotal Original Metal Stud Wall System
$ 71,216
Original Design Labor Cost $
42,508
Original Design Material Cost $
25,708Adjusted Total Alternative Wall System Cost
$ 74,920
Total Alternative SIP Wall System $
88,382
Alt. Design Labor Costs $
37,594
Alt. Design Material Costs $
50,789
Estimated General Conditions Savings $
(13,462.00)
Net Increase in Cost $
3,704
Alternative Wall Construction Design Conclusions: Reduces project schedule by 8 days Increases Superstructure Improves the performance of the building envelope Marginal increase in cost Recommendations: Met analysis goal to reduce project schedule Pursue alternative design as specified due to significant
schedule savings
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/
Conclusion VI. Final RecommendationsVII.Acknowledgements
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | ConstructionRecommendation/Conclusion
35
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly Funded Projects Project exemption can be gained by OPP
Analysis 2: Constructability – Alternative Design of Atrium Rejected alternative design due to substantial increases in cost
Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System Accepted above ceiling distribution system as a result of the
significant cost savings
Analysis 4: Schedule Acceleration –Alternative Wall System Accepted Structural Insulated Panel System as a result of
reduced schedule and marginal increase in cost
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI.Final
RecommendationsVII.Acknowledgements
Images courtesy of the Design Alliance Architects
Images courtesy of the Design Alliance Architects
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | ConstructionQuestions
36
Center for Sustainable LandscapesPittsburgh, PA
Daniel Zartman | Construction
Special Acknowledgements:Dr. Robert Leicht – CM Faculty AdvisorMegan Corrie, Kristine Retetagos of Turner Construction contacts and project sponsors Owner Phipps Conservatory David Zartman and staff of Zartman ConstructionJames Hostetler Director of Construction and Design Bucknell UniversityJohn Bechtel Assistant Director of Design and Construction of Penn State OPPTim Gilotti of Radner Property GroupJeff Sandeen of Hensel Phelps Construction Co.
Presentation Outline:I. Project BackgroundII. Analysis 1: Critical
Industry IssueIII. Analysis 2:
ConstructabilityIV. Analysis 3: Value
EngineeringV. Analysis 4: Schedule
AccelerationVI. Final RecommendationsVII.Acknowledgements
Images courtesy of the Design Alliance Architects
Images courtesy of the Design Alliance Architects