1 place holder for image center for sustainable landscapes pittsburgh, pa daniel zartman |...

36
1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction Advisor : Dr. Robert Leicht Images courtesy of the Design Alliance Architects

Upload: leona-simpson

Post on 03-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

1

PLACE HOLDER FOR IMAGE

Center for Sustainable Landscapes Pittsburgh, PA

Daniel Zartman | ConstructionAdvisor : Dr. Robert Leicht

Daniel Zartman | ConstructionAdvisor : Dr. Robert Leicht

Images courtesy of the Design Alliance Architects

Page 2: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | ConstructionProject Background

2

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Presentation Outline:I. Project Background

I. General Information

II. Building Information

II. Analysis 1: Critical Industry Issue

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final Recommendations

VII.Acknowledgements

General Project Information: Owner: Phipps Conservatory Contractor: Turner Construction Location: Schenley Park,

Pittsburgh, PA Function: Mixed Use

(Office/Education)

Building Size : Area: 24,350 GSF Height: 40’- 4” (3 Stories)

Project Size: Contract Value: $10 Million ($410

per SF) Project Type: New Construction Project Duration: 11 Months

Images Courtesy of Microsoft Corporation

Images Courtesy of Turner Construction

Page 3: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | ConstructionProject Background

3

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Structural System: Substructure: Concrete Strip/Spread Footing Superstructure: Braced Steel Frame

Building Envelope: Exterior Walls: 8” Metal Stud w/ Reclaimed Barn Wood Facade 7,600 SF Green Roof

Sustainable Achievements: LEED Platinum Living Building Challenge SITES Certification for Landscapes Net-Zero Annual Energy Consumption Net-Zero Annual Water Consumption

Images Courtesy of Turner Construction

Presentation Outline:I. Project Background

I. General Information

II. Building Information

II. Analysis 1: Critical Industry Issue

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final Recommendations

VII.Acknowledgements

Page 4: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

4

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

State requirements for publicly funded projects: Traditional Design – Bid – Build Hard-bid Multiple Prime Contracts

Problems: Does not adequately address the needs of complex projects Does not incentivize the contractor to minimize schedule and

cost growth

Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII. Results/Conclusion

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Images courtesy of the Design Alliance Architects

Page 5: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

5

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Funding Types: Private Public Combination

Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.

Research Goal: To create a decision tree that illustrates the progressive alternatives available to Penn State’s OPP.

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII. Results/Conclusion

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Images courtesy of the Design Alliance Architects

Page 6: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

6

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Project Features Analyzed: Funding Type Delivery System Contract Type Procurement Method

Industry Members Interviewed: John Bechtel – Asst. Director of Design and Construction at

Penn State‘s OPP James Hostetler – Director of Construction and Design at

Bucknell University Kristine Retetagos – VP Preconstruction Turner Construction

Pittsburgh Tim Gilotti – Radner Property Group Jeff Sandeen - Hensel Phelps Construction Co Mike Arnold – Foreman Group Elizabeth O’Reilly - Deputy Secretary of Pennsylvania’s Public

Works

Critical Industry Issue: Legislation in Pennsylvania prevents public projects from utilizing progressive delivery systems.

Research Goal: To create a decision tree that illustrates the progressive alternatives available to Penn State’s OPP.

Research Method: Analyze projects completed in PA by public and private owners using public funding.

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII. Results/Conclusion

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Images courtesy of the Design Alliance Architects

Page 7: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

7

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Penn State’s Office of Physical Plant:

Operates as an extension of DGS Public funding types most

commonly received: Delegated (most common) – OPP

is given money with specific use Non-Delegated (uncommon) –

DGS stays heavily involved

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII. Results/Conclusion

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 8: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

8

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Projects Researched: SCI Benner: Design-Build, GMP Bucknell University Bookstore: Design-Bid-Build, CM At-Risk,

GMP Center for Sustainable Landscapes: Design-Bid-Build, CM At-

Risk, GMP

The Decision Tree: Illustrates the influence funding has on procurement, delivery and contract methods

Black Diamonds: Represent questions that can be answered by OPP project staff

Red Diamonds: Represent decisions that are made by the Government

Green Boxes: Display the conditional procurement methods

Penn State’s Office of Physical Plant:

Operates as an extension of DGS Public funding types most

commonly received: Delegated (most common) – OPP

is given money with specific use Non-Delegated (uncommon) –

DGS stays heavily involved

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII. Results/Conclusion

III. Analysis 2: Constructability

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 9: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

9

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Project: SCI Benner Project Synopsis: $174 million new

construction of a 2,000 bed medium security prison

Location: Bellefonte, PA Owner: Department of General

Services Delivery Method: Design-Build Contract Type: GMP Procurement Method: Best Value

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII.Results/

ConclusionIII. Analysis 2:

Constructability IV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 10: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly

Funded Projects

10

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Project: SCI Benner Project Synopsis: $174 million new

construction of a 2,000 bed medium security prison

Location: Bellefonte, PA Owner: Department of General

Services Delivery Method: Design-Build Contract Type: GMP Procurement Method: Best Value

Conclusions: Project Exemption is Plausible Provided exemption is approved by DGS Provided exemption is authorized by Legislation

Recommendations 2 out of 3 owners analyzed utilized a traditional delivery

system despite exemption Pursue the use of contemporary delivery methods when

necessary

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueI. OverviewII. ResearchIII.Results/

ConclusionIII. Analysis 2:

Constructability IV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 11: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

11

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste

Images courtesy of the Design Alliance Architects

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 12: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

12

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste

Research Goal: Develop an alternative atrium design that: Improves Constructability at a minimal cost Maintains the spaces passive performance Aesthetically pleasing

Images courtesy of the Design Alliance Architects

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 13: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

13

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 2-Story radiused cast-in-place concrete atrium stair Labor intensive Produces a large amount of onsite waste

Research Goal: Develop an alternative atrium design that: Improves Constructability at a minimal cost Maintains the spaces passive performance Aesthetically pleasing

Proposed Solution: Structural steel stair Transfer thermal mass to atrium walls

Images courtesy of the Design Alliance Architects

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III. Results/Conclusion

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 14: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

14

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Changes to Original Design in Alternative Design Alternative Stair

Structural Steel Rectilinear Self-supporting

Imagery based off of one provided by The Design Alliance Architects

Alternative Design (Below)

Original Design (Below)

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative

Design III. Results/Conclusion

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 15: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

15

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Changes to Original Design in Alternative Design: Alternative Stair

Structural Steel Rectilinear Self-supporting

Alternative Design (Below)

Original Design (Below)

Alternative Wall Design Inc. thickness of concrete by

3 inches Net decrease in concrete: 3

cubic yards

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative

Design III. Results/Conclusion

IV. Analysis 3: Value Engineering

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 16: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

16

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased

with steel erection) Not located on critical path

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III.Results/

Conclusion IV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 17: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

17

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased

with steel erection) Not located on critical path

Cost Comparison

Original Design - Cost of Concrete Stair $ 49,950.00

Alternative Design - Total Cost $ 119,707.63

Alternative Design - Cost of Steel Stair $ 105,603.65

Alternative Design - Increase in Wall Thicknesses

$ 14,103.98

Net Increase in Alternative Design over Original Design

$ 69,757.63

Cost Summary: Net Increase: $70,000 Resulting from:

No central support added approximately $25,000 Increased connections costs Increased structural steel costs

Terrazzo finishes added approximately $15,000

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III.Results/

Conclusion IV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 18: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 2: Constructability – Alternative Design of Atrium

18

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 20 days Alternative Design: 10 days (phased

with steel erection) Not located on critical path

Alternative Design Conclusions: Not Recommended Pros

Comparably Sustainable Minimizes Construction Waste Improves Aesthetics Reduces Schedule by 10 days

Cons Significantly increased material cost

Recommendations Make adjustments to reduce cost:

Replace terrazzo Add column

Cost Comparison

Original Design - Cost of Concrete Stair $ 49,950.00

Alternative Design - Total Cost $ 119,707.63

Alternative Design - Cost of Steel Stair $ 105,603.65

Alternative Design - Increase in Wall Thicknesses

$ 14,103.98

Net Increase in Alternative Design over Original Design

$ 69,757.63

Cost Summary: Net Increase: $70,000 Resulting from:

No central support added approximately $25,000 Increased connections costs Increased structural steel costs

Terrazzo finishes added approximately $15,000

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII.Analysis 2:

ConstructabilityI. OverviewII. Alternative Design III.Results/

Conclusion IV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 19: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

19

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Images courtesy of kingspan.com/raised_flooring/full.jpg

Images courtesy of accessfloorsystems.com

Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III. Results/Conclusion

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 20: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

20

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Images courtesy of kingspan.com/raised_flooring/full.jpg

Images courtesy of accessfloorsystems.com

Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces

Research Goal: Reduce system cost without compromising performance Improve constructability

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III. Results/Conclusion

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 21: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

21

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Images courtesy of kingspan.com/raised_flooring/full.jpg

Images courtesy of accessfloorsystems.com

Problem Identification: Raised Floor Distribution Plenum Higher system costs Increased building height from redundant plenum spaces

Research Goal: Reduce system cost without compromising performance Improve constructability

Proposed Solution: Relocated HVAC distribution to above the ceiling

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III. Results/Conclusion

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 22: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

22

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Original Design 14” Raised Access Floor System In-floor electrical distribution

Alternative Design Lowered the ceiling 6” Reduced building height by 8” Maintained High Volume/Low

Velocity flow rate

Alternative Design: Above Ceiling Distribution Original Design: Raised Floor Distribution

Alternative Design: First Floor

Alternative Design: Second FloorPresentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative

Design III. Results/Conclusion

V. Analysis 4: Schedule Acceleration

VI. Final RecommendationsVII.Acknowledgements

Page 23: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

23

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the

Critical PathSchedule Durations for Raised Floor Analysis

SystemSchedule Duration

(Days)Total Man

HoursCrew Size

Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III.Results/

Conclusion V. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 24: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

24

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the

Critical Path

Cost Impacts 46% Decrease in cost Indirect Costs

Reduction in building height (credit)

Flooring Cost Schedule Durations for Raised Floor Analysis

SystemSchedule Duration

(Days)Total Man

HoursCrew Size

Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3

Total System ComparisonsRaised Floor Distribution System - Total Cost $ 110,000.00 Raised Floor - Material Cost $ 76,000.00 Raised Floor - Labor Cost $ 34,000.00 Ceiling Distribution System $ 50,838.00 Ceiling - Material Cost $ 7,696.00Ceiling - Labor Cost $ 19,620.00 Indirect Costs $ 23,521.00Net Decrease in System Cost: $ 59,162.00 Total Man Hours: 581 hrs

Electrical Distribution Contingency

Sales Tax Credit

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III.Results/

Conclusion V. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 25: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Original Design: 16 days Alternative Design: 24 days Neither designs were located on the

Critical Path

Cost Impacts 46% Decrease in cost Indirect Costs

Reduction in building height (credit)

Flooring Cost Schedule Durations for Raised Floor Analysis

SystemSchedule Duration

(Days)Total Man

HoursCrew Size

Raised Floor Dist. 16 480 6Ceiling Dist. 24 581 3

Total System ComparisonsRaised Floor Distribution System - Total Cost $ 110,000.00 Raised Floor - Material Cost $ 76,000.00 Raised Floor - Labor Cost $ 34,000.00 Ceiling Distribution System $ 50,838.00 Ceiling - Material Cost $ 7,696.00Ceiling - Labor Cost $ 19,620.00 Indirect Costs $ 23,521.00Net Decrease in System Cost: $ 59,162.00 Total Man Hours: 581 hrs

Alternative Design Conclusions: Added 100 hours of work Reduced cost by approximately $59,000 Recommendations: Met analysis goal to increase project’s value Pursue alternative design based on significant decrease

in system cost Marginal compromises in value

Electrical Distribution Contingency

Sales Tax Credit

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV.Analysis 3: Value

EngineeringI. OverviewII. Alternative Design III.Results/

Conclusion V. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Page 26: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

26

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite

Images courtesy of sips.org

Images courtesy of sips.org

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion

VI. Final RecommendationsVII.Acknowledgements

Page 27: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

27

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite

Research Goal: Develop alternative design Decreases the project schedule

Images courtesy of sips.org

Images courtesy of sips.org

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion

VI. Final RecommendationsVII.Acknowledgements

Page 28: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

28

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Problem Identification: 8” Metal Stud Exterior wall Time and Labor intensive Located on the Critical Path Produces a large amount of waste onsite

Research Goal: Develop alternative design Decreases the project schedule

Proposed Solution: Structural Insulated Panel System (SIPS) High performance wall type composed of:

OSB Sheathing EPS (Expanded Polystyrene) Foam Core

Increase superstructure to accommodate additional load

Images courtesy of sips.org

Images courtesy of sips.org

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative Design III. Structural BreadthIV. Results/Conclusion

VI. Final RecommendationsVII.Acknowledgements

Page 29: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

29

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Original Design 8” Metal Stud Framing 2” Rigid Board Insulation 5/8” Fiberglass-matt gypsum

board

Alternative Design 10 ¼” SIP Panel

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative

DesignIII. Structural Breadth IV. Results/Conclusion

VI. Final RecommendationsVII.Acknowledgements

Page 30: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

30

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Structural Impacts: Structural Breadth Original Stud Wall: 45 PLF Alternative SIP Wall: 75 PLF

Results: W12x19 Spandrel Beams were

found to be inadequate Max. Allowable Def. = 1.07”

Deflection = 1.3” Max. Allowable Bending Moment

= 55.9 ft-kips Bending Moment = 82.2 ft-

kips W12x26 Spandrel Beams were

found to be adequate HSS 6x6x5/8 Columns were found

to be adequate

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative DesignIII.Structural

Breadth IV. Results/Conclusion

VI. Final RecommendationsVII.Acknowledgements

Page 31: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

31

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Structural Impacts: Structural Breadth Original Stud Wall: 45 PLF Alternative SIP Wall: 75 PLF

Results: W12x19 Spandrel Beams were

found to be inadequate Max. Allowable Def. = 1.07”

Deflection = 1.3” Max. Allowable Bending Moment

= 55.9 ft-kips Bending Moment = 82.2 ft-

kips W12x26 Spandrel Beams were

found to be adequate HSS 6x6x5/8 Columns were found

to be adequate

Sustainability Provides superior conductive and

convective performance No additional LEED points gained

Relative R-Value ComparisonR-Value Original Design 25.3 2" Rigid Board Insulation 8 5/8” Fiberglass-mat 8 8" Wall Cavity 9.3R-Value Alternative Design 35 (2) 7/16" OSB Sheathing 1 10 1/4" SIP w/ EPS Core 34

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/

Conclusion VI. Final RecommendationsVII.Acknowledgements

Page 32: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

32

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Reduced the project schedule by a

total of 8 days Allowed Glazing to begin 8 days

earlier than the original scheduleSchedule Durations for Façade Analysis

SystemSchedule

Duration (Days)Total Man

HoursCrew Size

8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/

Conclusion VI. Final RecommendationsVII.Acknowledgements

Page 33: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

33

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Reduced the project schedule by a

total of 8 days Allowed Glazing to begin 8 days

earlier than the original schedule

Cost Impacts: SIP System Cost w/ General Conditions Savings:

$74,920 Includes increased cost of superstructure of $2,578

Schedule Durations for Façade Analysis

SystemSchedule

Duration (Days)Total Man

HoursCrew Size

8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5

Façade Estimate SummaryTotal Original Metal Stud Wall System

$ 71,216

Original Design Labor Cost $

42,508

Original Design Material Cost $

25,708Adjusted Total Alternative Wall System Cost

$ 74,920

Total Alternative SIP Wall System $

88,382

Alt. Design Labor Costs $

37,594

Alt. Design Material Costs $

50,789

Estimated General Conditions Savings $

(13,462.00)

Net Increase in Cost $

3,704

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/

Conclusion VI. Final RecommendationsVII.Acknowledgements

Page 34: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 4: Schedule Acceleration –Alternative Wall System

34

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Schedule Impacts: Reduced the project schedule by a

total of 8 days Allowed Glazing to begin 8 days

earlier than the original schedule

Cost Impacts: SIP System Cost w/ General Conditions Savings:

$74,920 Includes increased cost of superstructure of $2,578

Schedule Durations for Façade Analysis

SystemSchedule

Duration (Days)Total Man

HoursCrew Size

8” Metal Stud Framing 16 770 6SIP Wall Panel 8 320 5

Façade Estimate SummaryTotal Original Metal Stud Wall System

$ 71,216

Original Design Labor Cost $

42,508

Original Design Material Cost $

25,708Adjusted Total Alternative Wall System Cost

$ 74,920

Total Alternative SIP Wall System $

88,382

Alt. Design Labor Costs $

37,594

Alt. Design Material Costs $

50,789

Estimated General Conditions Savings $

(13,462.00)

Net Increase in Cost $

3,704

Alternative Wall Construction Design Conclusions: Reduces project schedule by 8 days Increases Superstructure Improves the performance of the building envelope Marginal increase in cost Recommendations: Met analysis goal to reduce project schedule Pursue alternative design as specified due to significant

schedule savings

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationI. OverviewII. Alternative DesignIII. Structural Breadth IV.Results/

Conclusion VI. Final RecommendationsVII.Acknowledgements

Page 35: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | ConstructionRecommendation/Conclusion

35

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Analysis 1: Critical Industry Issue - Avoiding Traditional Delivery Methods on Publicly Funded Projects Project exemption can be gained by OPP

Analysis 2: Constructability – Alternative Design of Atrium Rejected alternative design due to substantial increases in cost

Analysis 3: Value Engineering – Redesign of Raised Floor Distribution System Accepted above ceiling distribution system as a result of the

significant cost savings

Analysis 4: Schedule Acceleration –Alternative Wall System Accepted Structural Insulated Panel System as a result of

reduced schedule and marginal increase in cost

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI.Final

RecommendationsVII.Acknowledgements

Images courtesy of the Design Alliance Architects

Images courtesy of the Design Alliance Architects

Page 36: 1 PLACE HOLDER FOR IMAGE Center for Sustainable Landscapes Pittsburgh, PA Daniel Zartman | Construction Advisor : Dr. Robert Leicht Daniel Zartman | Construction

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | ConstructionQuestions

36

Center for Sustainable LandscapesPittsburgh, PA

Daniel Zartman | Construction

Special Acknowledgements:Dr. Robert Leicht – CM Faculty AdvisorMegan Corrie, Kristine Retetagos of Turner Construction contacts and project sponsors Owner Phipps Conservatory David Zartman and staff of Zartman ConstructionJames Hostetler Director of Construction and Design Bucknell UniversityJohn Bechtel Assistant Director of Design and Construction of Penn State OPPTim Gilotti of Radner Property GroupJeff Sandeen of Hensel Phelps Construction Co.

Presentation Outline:I. Project BackgroundII. Analysis 1: Critical

Industry IssueIII. Analysis 2:

ConstructabilityIV. Analysis 3: Value

EngineeringV. Analysis 4: Schedule

AccelerationVI. Final RecommendationsVII.Acknowledgements

Images courtesy of the Design Alliance Architects

Images courtesy of the Design Alliance Architects