1 plans of vienna slhc proposal workshop 20. february 2008

15
1 Plans of Vienna SLHC Proposal Workshop 20. February 2008

Upload: whitney-dean

Post on 31-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

1

Plans of Vienna

SLHC Proposal Workshop

20. February 2008

2

Facilities

3

Strip-by-strip Test Setup• Sensor in Light-tight Box

• Vacuum support jig is carrying the sensor– Mounted on freely movable table in

X, Y and Z

• Needles to contact sensor bias line – fixed relative to sensor

• Needles to contact:– DC pad (p+ implant)

– AC pad (Metal layer)

– Can contact ever single strip while table with sensor is moving

3

4

Strip-by-Strip CharacterizationWhat do we test?• Global parameters:

– IV-Curve: Dark current, Breakthrough

– CV-Curve: Depletion voltage, Total Capacitance

• Strip Parameters e.g.– strip leakage current Istrip

– poly-silicon resistor Rpoly

– coupling capacitance Cac

– dielectric current Idiel

4

5

Test structures Measurement Setup

• Instruments– Source Measurement Unit (SMU)

– Voltage Source

– LCR-Meter (Capacitance)

• Heart of the system: Crosspoint switching box, used to switch instruments to different needles

• Labview and GPIB used to control instruments and switching system

• Cold chuck will be provided by Karlsruhe

5

617 Sept. 2006 Thomas Bergauer

PQC Setup @ Vienna

7

CMS Test Structures

• TS-CAP:– Coupling capacitance CAC to

determine oxide thickness– IV-Curve: breakthrough voltage of

oxide

• Sheet:– Aluminium resistivity– p+-impant resistivity– Polysilicon resistivity

• GCD: – Gate Controlled Diode– IV-Curve to determine surface

current Isurface

– Characterize Si-SiO2 interface

• CAP-TS-AC: – Inter-strip capacitance Cint

• Baby-Sensor: – IV-Curve for dark current– Breakthrough

• CAP-TS-DC: – Inter-strip Resistance Rint

• Diode:– CV-Curve to determine depletion

voltage Vdepletion – Calculate resistivity of silicon bulk

• MOS: – CV-Curve to extract flatband voltage

Vflatband to characterize fixed oxide charges

– For thick interstrip oxide (MOS1)– For thin readout oxide (MOS2)

7

8

Example of identified problems

8

• Limit: Rint > 1GΩ to have a good separation of neighbouring strips

• Each dot in the left plot shows one measurement

• Value started to getting below limit

• We reported this to the company• Due to the long production

pipeline, a significant amount of ~1000 sensors were affected

Inter strip resistance issue during CMS sensor production

9

Other Facilities

• Longterm Setup – Dark current characterization for

hours/days/weeks

• Wire bonding Machines– Semi-automatic Kulicke & Soffa (old)– Fully automatic Delvotec 6400

• 3D coordinate measurement machine– Mitutoyo Euro-C apex 776

10

Sensor Design

• Electronic Design Automation Tool

• Mentor Graphics– ICstudio– ICstation– Physical design not drawn

but “programmed” using simple language called AMPLE

• Status: We can draw simple strip sensors

11

Vienna Plans for SLHC

Main topic:

• Sensor Design

• Connectivity: – Sensor design for dual metal layer– test structures for dual metal layer readout– Have 1st test structures with dual metal layers

processed with fab (ITE Warsaw, ON Semi)

12

Connectivity

• Occupancy reduction by segmentation of strips => Strixels

• Conventional pitch adapter and wire bonding not applicable anymore

• Readout chip has to be bump-bonded directly onto sensor– Cooling?

13

Connectivity

• TODO:– Reliable design for

routing lines: short distances, low crosstalk

– calculation of additional capacitance caused by routing lines (causing noise in the readout)

– simulation of overhangs– Test structures with dual

metal layers to verify optimal geometry experimentally

14

Bump-/Stud- bonding

• Readout chip must be connected upside down onto sensor (flip-chip bonding)

• Two methods:– Indium Bump-bonding needs

treatment of both chip and sensor with indium

• Advantage: fine pitch

– Stud-bonding doesn’t need special treatment

• 1st step: Design to enable both, wire or flip-chip bonding with same chips and sensors

• Open point: Cooling

15

Summary– We cannot competitive with RD50, which works since years on new

rad-hard materials. We should concentrate on other issues.

– Intermediate Tracker will need strixels– Routing lines should be integrated into sensor– Flipchip-bonding of readout chip necessary, cheap stud-bonding preferred.– Effect on noise caused by increased strip length has to be investigated

• Capacitance of strip together with routing line unknown and complicated to calculate (Simulation?)

– Correlation of this project with Tracker-Trigger ambitions unclear (to me)

– We will not afford many wafer processing runs within this consortium (no external funding)

• Many things have to be tested cost-effective, e.g. test structures with dual metal layers by ITE Warsaw

• Extensive simulations before starting processing