Pre-Bid Conference & Site Tour
State Library and Courts Building Renovation
2
Project Management Overview
Department of General Services –Owner, Building Manager, Contract Authority, and InspectionCarey & Co. – ArchitectVanir Construction Management - On-site Construction ManagerCalifornia State Library, Supreme Court, Court of Appeals - Tenants
3
Project Funding
Pre-sold Lease Revenue BondsState’s Estimate: $ 50,000,000
4
NeighborhoodParade/Demonstration Routes
State Historic Preservation Office (SHPO)
Jesse Unruh Building
Library & Courts Building
State Capitol Building
Capitol Park
Capitol Extension Group
Parade/Demonstration RoutesParade/Demonstration RoutesParade/Demonstration RoutesParade/Demonstration Routes
5
Project Overview
188,000 GSFSix stories plus basementComplete fire, life and safety upgradeMEP and telecom infrastructure replacementHazardous materials abatement. Registered State Historic Landmark and on the National Register of Historic Places
6
General Requirements & Conditions
Building is vacant.Special Project Procedures include:
Intensive coordination requirementsMethod of proceduresInterval schedules, work plans & coordination drawing submittals
Requirement for qualified designated historic preservationist on GC staff.LEED accredited professional
7
Decorative Elements
8
Historic Fabric & Fine Art
9
Project Overview - Site
~ 3.90 AcresWithin the jurisdiction of Capitol ParkSeveral memorial statuary, placards, and plantingsMature tree and landscape protectionLandscape irrigation replacementReplacement of aged shrubberyMiscellaneous signage
10
Site Views
11
Memorials & Statuary
12
Exterior Improvements
Repair and re-point granite and terra cottaRepair windowsReplace roofRemove and replace mechanical penthousesRestore light wellsImprove accessibility
13
Façades
14
Fine Art Fenestrations
15
Fine Art Statuary & Detail
16
Interior Improvements
Abate hazardous materialsReplace MEPReplace telecommunicationNew fire suppression & alarmReplace or refresh most finishesNew access, security, and controlsTenant Improvements
17
Interiors
18
Typical Interiors
19
Plant Rooms
20
Elaborate Ceilings
21
Light Fixture Restoration
22
Maynard Dixon Mural – Rm 301
23
Dixon Paintings - Second Floor North Corridor
24
Memorial Vestibule History of War Panels
25
Decorative Arts
26
Decorative Arts
27
Review of Bid Instructions
Bid Date: August 17, 2010Bid Time: 2:00 PMBid Location: Third Floor PMB Reception Desk, 707 3rd Street, West SacramentoAnticipated NTP: Late 2010Project Duration: 670 calendar days
28
Bid Forms:
The bid proposal forms will be distributed at the conclusion of the conference. All Contractors bidding as a Prime Contractor must sign-in and receive bid forms today!
29
Request for Bidders Information
Please submit bid questions on form included in project manual E-file is available from Project Director & on BidsyncEmail to: [email protected]
Cut-off date: 10 days prior to bid date
30
Bidding & Contracting Requirements
Lump sumPrevailing wage February 2010Disable Veteran Business EnterpriseReference documents available
Original 1920s documentsHazardous Materials Survey DataHistoric Structures Survey
DGS General ConditionsAugust 2009 Edition
31
Disable Veterans Business Enterprise Program
Good Faith Effort has been discontinued!Bidders must meet or exceed 3% DVBE participation or bid will be non-responsive.Incentives for exceeding DBVE requirement and stated SBE goal are calculated based on lowest responsive bidder.
32
Disable Veteran & Small Business Enterprise Requirements
James Frolich, Contract OfficerContract Management Section916-376-1770
33
Supplementary Conditions
Contract time 670 Calendar DaysLiquated Damages on completion dateInsurance
Commercial General Liability = $10,000,000Employer Liability = $1,000,000Pollution Liability = $2,000,000Builder’s Risk = Contract Sum
Escrow Bid Documents
34
Supplementary Non-Mandatory Bid Walks
July 28, 2010:9:30 to 11:30: Architectural Protection, Restoration, Exterior Restoration, Hazardous Materials Abatement and Demolition1:00 to 3:00: Electrical, Telecommunication, and Security Systems and Historic Light Fixture Restoration
July 29, 2010:9:30 to 11:30: Mechanical and Plumbing1:00 to 3:00: Fire Suppression and Elevator renovation
No new Prime Contractors admitted to bid!
Questions?
Last Chance!
Prime contractors must sign-in and receive bid proposal forms before
leaving this area.