1 presentation on indian power sector : key issues by r.v. shahi secretary (power), government of...
TRANSCRIPT
1
PresentationPresentation on on
Indian Power Sector : Indian Power Sector : Key IssuesKey Issues
ByBy
R.V. SHAHIR.V. SHAHISecretary (Power) , Government of IndiaSecretary (Power) , Government of India
November 16, 2006November 16, 2006
Power Ministers’ Conference on Capacity Power Ministers’ Conference on Capacity AdditionAddition
2
Growth in Electricity Generation (%)
3.1
5.1 5.2 5.2
6.0
7.1
3.2
0
2
4
6
8
2001-02 '02-03 '03-04 '04-05 '05-06 Target 06-07
06-07(Apr-Oct)
* 2005-06 (Apr- Oct) : 5.1%
3
Capacity Addition as % of Target
54.0
75.0
47.0
0
20
40
60
80
VIII IX X
Plan
%
4
Growth in PLF of Thermal Stations (%)
69.9
72.1 72.7
74.873.6
70.8
73.774.3
77.178.7
81.7 82.1
79.480.4
60
65
70
75
80
85
2001-02 '02-03 '03-04 '04-05 '05-06 05-06(Apr-Oct)
06-07(Apr-Oct)
All India Central
5
Electrification of Villages
11000
55000
29000
14000
0
10,000
20,000
30,000
40,000
50,000
60,000
VIII IX X(Target) X (Achvmnt)*
Plan
* 26,000 under execution
6
Likely Capacity Addition During X Plan (MW)
Sector Mid Term
Appraisal
Target
Units
Commissioned
Units Expected
During Nov’06-
Mar’07
Total
Capacity
Anticipated
Central 19,817 10,865 5,314 16,179
State 12,240 4,948 6,060 11,008
Private 4,899 1,931 1,524 3,455
Total 36,956 17,744 12,898* 30,642
* Based on latest reviews with CEA/ BHEL
7
Meeting Target – Steps Taken
Commissioning 12,898 MW in 4½ months require
intensified coordination between Central sector and States.
Nodal officers identified from CEA for each project being
posted to respective project sites.
Daily monitoring of progress in Ministry of Power
Equipment for 8291 MW capacity supplied by BHEL.
Supplies from Trichy, Ranipet and Chennai Piping Centre
periodically reviewed with BHEL.
States to take steps to ensure adherence of commissioning
schedule in respect of projects under state/ private sectors.
8
Capacity Addition - Perspective Programme
Present installed capacity - 1,28,000 MW.
Installed capacity by March,2007 ~ 1,41,000 MW.
Targeting economic growth rate of 8-10% pa
• Projected installed capacity by 2012 - 2,07,000 MW
• Thereafter, doubling of capacity every 10 years.
• Projected installed capacity by 2030 - 8,00,000 MW.
9
Capacity Addition Programme During XI Plan (2007-2012)
Fuel- Mix Central Sector
State Sector Private Sector
Total
Thermal 25,860 16,152 4,102 46,114
Hydro 11,289 2,637 3,263 17,189
Nuclear 3,160 0 0 3,160
Total 40,309 18,789 7,365 66,463
In addition, 14,000 MW through Non- Conventional
Energy Sources.
Captive capacity not included.
(MW)
10
XI Plan Capacity Addition – Advance Action
At present about 43,700 MW capacity is under
construction. Investment of about Rs, 2,05,000 crore
committed.
Commissioning in this year, and in next 3 years.
30,967 MW to be added in first three years of XI plan.
11
Completion Schedule of Ongoing Projects (MW)
Type Nov’06-
Mar’07
2007-08 2008-09 2009-10 Total
Hydro 2,000 2,450 2,328 2,055 8,833
Thermal 10,678 4,407 6,737 10,330 32,152
Nuclear 220 1,440 1,220 0 2,880
Total 12,898 8,297 10,285 12,385 43,865
12
XI Plan Capacity Addition – Pipeline Projects
XI Plan projects list includes only those hydro and super
critical technology based projects in which LOA is expected
by March, 2007.
Projects for over 35,600 MW capacity identified for
commissioning during XI Plan.
Fuel- Mix Central Sector
State Sector Private Sector
Total
Thermal 18,660 10,300 1,500 30,460
Hydro 3,567 530 1,072 5,169
Nuclear 0 0 0 0
Total 22,227 10,830 2,572 35,629
13
States – Action Required Only projects with adequate preparation to be included in
the XI plan list.
• All hydro projects for which TEC is not available by
June’06 and LOA is not expected by Mar’07 to be
excluded. Projects included if TEC is expected at a later
date but parallel actions taken on EPC contract
and LOA is expected by Mar’07.
• Greenfield thermal projects for which land acquisition,
fuel linkages and other clearances are expected by
Dec’07 to be included.Contd..
14
States – Action Required contd.. Expansion projects to be considered for development
through negotiation with BHEL. Benchmarks for 250/ 500
MW unit ratings - a basis for negotiations . CEA may
facilitate states negotiating better price through bulk
ordering.
• Since the meeting of May 30,2006, generation projects
aggregating 3695 MW ordered to BHEL through
negotiated route by states of Maharashtra, U.P.,
Rajasthan, Karnataka and West Bengal.
• Negotiation for 5250 MW is currently on and is to be
fianlised shortly. Contd..
15
States – Action Required contd.. To avoid skewed project commissioning at the tail end of
the programme, expedite orders for thermal power
projects.
Gas not available at appropriate price. States not advised
to make provision for gas based power projects. Position to
be reviewed during mid- XI plan.
Private sector projects to be developed through tariff
based competitive bidding. MoU route not available. States
may use basic documentation for competitive bidding
developed for UMPPs . Projects to be finalised by March,
2007. Contd..
16
States – Action Required contd..
To back up the capacity addition programme, financial
plans for the required equity support to be drawn.
Issues related to coal linkages/ coal blocks and
Environment clearance to be immediately sent to Ministry
of Power for taking up in Secretary level coordination
meetings.
Suitable intra state transmission network for power
evacuation and grid strengthening during XI plan to be
drawn and implemented .
Contd..
17
States – Action Required contd..
Expression of Interest for procurement of power through
competitive bidding in accordance with guidelines issued
by Ministry of Power, to be invited .
The requirements projected in 16th EPS to be reassessed, in
view of 8-9% economic growth and changes in rural
electrification parameters.
18
Demand Management- Action by States
Greater grid discipline. SLDCs to reduce overdrawal by
50% in case frequency falls below 49.5 Hz.
Ensure operation of Under Frequency Relays.
Full utilisation of Gas based stations on liquid fuel.
Surplus captive power to be tapped. Model of Pune city
for making it a load shed free city to be considered.
Bilateral purchase of power to be tied up well in advance.
Load sanctioning commensurate with availability of power.
19
Actions by States for Demand Management
Implementation of Intra -State ABT, TOD metering and
differential tariffs.
Energy Conservation saving target to be fixed.
Campaign of Energy Conservation at state level. Utilities/
States to provide budget. A separate EC fund in each state.
State level Energy Conservation award scheme. Special
award scheme for Small and Medium Industries.
Energy Audit in all Government buildings.
Compulsory use of CFLs in Government Buildings.
Automatic switching of street lights.
20
THANK YOU