1 project control & risk n purpose of control n control process n cost/schedule/technical...

20
1 PROJECT CONTROL & RISK Purpose of Control Control Process Cost/Schedule/Technical Control Introduction to Earned Value Project Changes and Change Control Importance of Managing Risk

Upload: thomas-hall

Post on 14-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

1

PROJECT CONTROL & RISK Purpose of Control

Control Process

Cost/Schedule/Technical Control Introduction to Earned Value

Project Changes and Change Control

Importance of Managing Risk

Page 2: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

2

Purpose of Control

To make the actual meet the plan

The Process 1. Key performance areas 2. Set standards 3. Measure performance 4. Compare 5. Fix

Page 3: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

3

A Question of Balance Too little control? Too much control?

$

Amount of Control

CControl

CMistakes

Page 4: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

4

What Forms do these “Standards” Take?

Cost

Schedule

Performance

Page 5: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

5

A Control Example

You’re two months into a three month project. You’ve spent 90% of your budget.

Defend yourself.

Page 6: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

6

Three Important Terms BCWS: The plan, integrating schedule

and budget

BCWP: What you planned to spend for work actually done

ACWP: Actual dollars spent at a point in time, for the work actually done

Page 7: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

7

More Terms BAC: Original budget at completion

TAC: Original time at completion

ECAC: Estimated cost at completion

ETAC: Estimated time at completion

Page 8: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

8

Four Relationships Cost Variance = BCWP - ACWP

Schedule Variance = BCWP - BCWS

ECAC = ACWP X BAC BCWP

ETAC = BCWS X TAC BCWP

Page 9: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

9

Changes and Change Control

The last step of the control process: FIX

Two Types: Business and Technical Changes

Page 10: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

10

Business Changes (aka CCPs) Business related Driven by such things as:

Spec relief Deliverables changes Funding shifts Schedule changes Acts of God Subcontractor changes

Page 11: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

11

Technical Changes (aka ECPs)

Technological issues, such as: New technologies Laws of physics Competitor response Threat changes Changes in user requirements (real

or political)

Page 12: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

12

Change Control

Changes cost $, usually big $ So they need control

PM responsibility Signed baselines High levels of authority

Some tools: Zero sum/DTC/caps

Page 13: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

13

PROJECT RISK MANAGEMENT

Risk defined A brief history Types of project risk The PMBOK sequence Tools

Page 14: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

14

RISK DEFINED

The likelihood (probability) and the impact of an undesirable event

“Fear of harm ought to be proportional not only to the gravity of the harm, but also to the probability of the event.” (Antoine Arnauld, 1665)

Both matter Examples

Page 15: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

15

A BRIEF HISTORY

The management of risk forms the boundary between the old world and modern times

Old world Fates and gods Short time horizons Man’s role: accept, maybe react

Page 16: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

16

SO WHAT CHANGED? Rise of rational man

Man can plan and influence the future

Development of math, probability, forecasting

Multiply XII times VIII Rise of zero and Arabic numerals

Rise of trade, business, shipping Longer time horizons Large commercial ventures mean more at stake

Page 17: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

17

THE CRITICAL QUESTIONS To what extent does the past foretell

the future? Can we extrapolate from the past to

predict a future event?“Nature has established patterns originating in the

return of events, but only for the most part.”

(von Leibnitz to Bernoulli, who then developed the Law of Large Numbers, 1703)

Page 18: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

18

TYPES OF PROJECT RISK

PeopleTime

Political Financial

Technical

A Question: Is “Risk Reduction” really possible?

Page 19: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

19

THE PMBOK RISK MANAGEMENT SEQUENCE

Risk identification Risk quantification Risk response development Risk response control

Page 20: 1 PROJECT CONTROL & RISK n Purpose of Control n Control Process n Cost/Schedule/Technical Control n Introduction to Earned Value n Project Changes and

20

TOOLS FOR RISK MANAGEMENT (more or less in order) Expert opinion Simulation Historical Analysis/ “Lessons Learned” “Risk Reduction” Contracting/Procurement Strategy

CPFF, FFP, “Make or Buy,” Sole Source, etc.

Insurance, bonding Multiple paths Management attention (e.g., “Top 10” Lists) Workarounds