1. project management
TRANSCRIPT
Introduction
‘Death marches’ are common features that characterise projects with circumstances
necessary for the successful completion of the project are greatly compromised and therefore
posing high possibilities for failure. Ranging from funding to management, the issues
responsible for death marches in project management need to be seriously considered before
any project is commenced if chances of failure are to be reduced. The cost for failure can be
immense depending on the level of compromise of the issues. Experienced management and
appropriate application are of project management principles some of the reasons that can
avert or lessen the risk of failure of the projects.
The USA Government committed to constructing a sewerage system in Iraq in the
aftermath of the war that ravaged most of its infrastructure including water and sewage
system. The project that was scheduled to take three years and be completed in 2006 ended
being a fiasco, adding to a series of failures that the USA faced. Initially budgeted to cost
$32.5-million, the project in Fallouja, Iraq cost the Government almost triple the amount to
almost $ 100 million besides being delayed. The audit report discovered communication
barriers that led to the failure of the project. Being a project that was managed by high profile
officials of the countries, bureaucracy and long chains of communication made supervision a
challenge. Thus management and progress of the project were compromised in the process.
According to Pritchard (2004), communication is the most important and powerful tool that a
manager can use to assess and determine the success rate of the project. Constant
communication in a free and coherent fashion can help identify loopholes early enough and
the solution be rendered before the whole project tumbles down.
Inexperience in management by overseers of the Fallouja project in Iraq were from
USA and had little conceptualised the whole issue of management and terrain in the country.
The project had o redesigned in twice, meaning more cost was committed for each
redesigning assignment. Individuals assigned the duties had no experience in designing
similar projects in the area and that was the reason design had to be redrawn. Gido and
Clements (2009) advise that a contractor needs to present experience of prior successful
completion of similar projects before awarding the contract. There was also an element of
little agreement between the stakeholders on the terms and conditions of the project for the
parties involved to be bound to the terms and conditions of the contract while at the same
time focussing on the deliverables on successful completion of the project (Gido & Clements,
2009). The charter failed to outline all the essential elements that ought to have been noted
for the both stakeholders, i.e. the contractor and US government. The charter also failed to
outline full responsibilities of all the stakeholders. When the USA Government required
residents to contribute US $ 10000 to cater for the stretched budget, an article that was not
identified in the article initially, it emerges that poor planning and poor identification of
responsible parties or stakeholders were not identified in the project. The charter should have
been specific enough in terms of deliverables, functions and responsibilities of the
stakeholders and the scope prior to commencement of the project (Rad & Anantatmula,
2010). With all these failures, the project ran a high risk of failure like was witnessed in the
audit report.
Another project that failed on almost similar grounds is The Secure Border Initiative
Project in the USA between the Government and SBInet. The project was supposed to
supplement to the existing 600 miles f physical border fence by adding a 2000 mile security
wall. Of these, only 53 miles was constructed at a cost of US $ 1 billion in four years. Key
principles in management of projects were also overlooked by the parties involved. The key
stakeholders in the project were the Department of Home Security with SBInet and Boeing as
the main contractors. In the report by GAO (2010), key failures are noted that refer to the
scope, poor monitoring and management of the issues were identified responsible for the
failed project.
Management issues emerged after GAO discovered that DHS did not adequately
monitor the progress and what was expected to be achieved by the contractors. This is
important to ensure what was planned for and documented in the charter is actually what is in
the progress of achievement by the contractor. Both stakeholders ought to have understood
the quality of deliverables. It was the duty of the contract manager or the break down the
activities into deliverables, distribute and delegate them, follow up on the progress and
review them after designated periods (Means & Adams, 2005). DHS had the duty of
following up the project manager to ensure individual activities were delivered as agreed.
Failure of this resulted in realising important aspects of the project had not been achieved
when it was too late.
The scope of the project were also not agreed upon and adhered to strictly. For
example, whereas it was envisaged that strategic geographic locations would be equipped
with operational equipment, the exact operationalisation and exact points were not specified
and thus they diminished with time. The scope changes also affected the type of project from
being a cost-plus-award-fee to cost-plus-fixed-fee. The contactor did not define what was to
be achieved when and where and quality of the technology deployments at surveillance
locations. This left the team to work in a haphazard manner, low success rate of deployed
system, delays and increased cost to the financier. Poor documentation in the charter and
expectation from both parties led to failure of the Secure Border Initiative Project.
Conclusion
Most of the projects that fail have common weaknesses in them that are not difficult
to identify should any audit be carried out. The two separate cases present classic and typical
weaknesses in management, setting up a clear and succinct charter, identification of
stakeholders and key deliverables in the progress and at final completion of the project.
Failure to appreciate all key principles have led to widespread project failures as evidenced in
the two projects that were considered ‘death marches’.
Reference List
Pritchard, C L (2004). The Project management communications toolkit. Norwood: Artech
House
Gido, J. & Clements, J. P. (2009). Successful project management. New York: Cengage
Learning.
Rad, P. F. & Anantatmula, V. S. (2010). Successful Project management practises. Bingley:
Emarald Group Publishing.
Mean, J & Adams, A. (2005). Facilitating the project lifecycle: Skills and tools to
facilitators, and six sigma project teams, New York: John Wiley and Sons.
GAO (2010). Report to Congressional Requesters: Secure Border Initiative, retrieved 5
September 2011, from http://www.gao.gov/new.items/d116.pdf