1-s2.0-s0142061599000356-main

Upload: madhumitha-rajasekaran

Post on 03-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 1-s2.0-S0142061599000356-main

    1/8

    An adaptive load shedding method with time-based design for isolatedpower systems

    S.-J. Huang*, C.-C. Huang

    Department of Electrical Engineering, National Cheng Kung University, Tainan, Taiwan, 70101

    Abstract

    When an isolated power system encounters a serious disturbance or a large generator unit trip, the system frequency may drop if total

    generating power is not able to supply the load demand sufficiently. Since an isolated power system possesses a lower inertia with limited

    reserves, load shedding becomes a critical solution to restore system frequency. In this paper, the initial rate of change of frequency is firstdetected. A designated time interval and a modification algorithm that considers the maximum frequency change at the last step are

    integrated to complete a load shedding task. Features of the method include the easy determination of shedding loads and fast trip of the

    load in anticipation of avoiding the occurrence of over-shedding or under-shedding. Numerical simulations have solidified the effectiveness

    of the proposed method for the application. 1999 Elsevier Science Ltd. All rights reserved.

    Keywords: Load shedding; Isolated power system

    1. Introduction

    When an isolated power system encounters a serious

    disturbance or a large generator trip, the system frequency

    may drop once the total generating power could not supply

    the load demand sufficiently. It is known that an isolatedpower system should be self-sufficient to provide security,

    reliability and economy of electricity. In such a system, the

    speed of frequency decay due to loss of generation is parti-

    cularly significant. Therefore, more attention should be paid

    to the load shedding scheme design [13].

    Several studies have been proposed to restore the system

    operation frequency after serious disturbances. One of these

    strategies is throughthe under-frequencyloadshedding design

    [4,5]. This approach is simple and easy to implement;

    however, its poor coordination capability may deteriorate the

    overall performance. Efforts to improve under-frequency load

    shedding using the rate of change of frequency as additional

    control variables have been suggested [610]. These methods

    primarily shed the load when therate of change offrequency is

    higher than a designated value. Among these methods, a low-

    order linear system frequency response model based on the

    idea of average frequency was proposed, where the essential

    characteristics of the system frequency response was seen

    accurately estimated in their test cases [6]. This is followed

    by an adaptive methodology that was applied for the setting of

    under-frequency relays based on the initial rate of change of

    the frequency at the relay [7]. Because conventional under-

    frequency loadshedding schemes canonlyhandle a maximum

    of 50% load, a hybrid load-shedding scheme was also

    suggested. This hybrid system includes at least one time-coor-

    dinated step in addition to several frequency-coordinatedsteps. By this hybrid, it is able to shed 70% and more of the

    loadfrom the system[11]. On accountof tediouscomputations

    required for determining the amount of overload and the load

    shed per step, a neural network approach has also been

    employed to calculate the minimum frequency during a forced

    outage of a generating unit [12].

    This paper proposes the detection of the initial rate of

    change of frequency with predetermined time intervals to

    formulate an appropriate load shedding strategy. Mean-

    while, to avoid load-shedding failures, a modification

    method considering the maximum change of frequency at

    the last step is embedded in order to adjust the required total

    amount of shed load. By this modification, the load-shed-

    ding scheme can be more effective in restoring the system

    frequency, which also overcomes the coordination difficulty

    of the problems. Numerical simulations support the

    proposed method in good agreement.

    2. Problem formulation

    2.1. Analysis model

    Fig. 1 shows the linear frequency response model that

    Electrical Power and Energy Systems 22 (2000) 5158

    0142-0615/00/$ - see front matter 1999 Elsevier Science Ltd. All rights reserved.

    PII: S0142-0615(99) 00035-6

    www.elsevier.com/locate/ijepes

    * Corresponding author. Tel.: 886-6-276-0711; fax: 886-6-234-

    5482.

    E-mail address:[email protected] (S.-J. Huang)

  • 8/12/2019 1-s2.0-S0142061599000356-main

    2/8

    represents the frequency characteristics of an isolated power

    system, where all parameters are in per unit on an MVA

    base equal to the total rating of the generating units in the

    island. This frequency response model is formulated based

    on neglecting non-linearity and all but the largest time

    constants in the generating unit inertia and reheat time

    constant of generating units in the isolated system. Note

    that in modeling, the generation is assumed dominated by

    reheat steam turbine generators. In Fig. 1, the change in thespeed changer setting Prefand the change in load demand

    PLare two inputs. Other parameters in this model are FHP,

    GM and s, where FHP is the high-pressure turbine power

    fraction, GM the mechanical power gain factor and s the

    differential operator. Most steam turbine generators in

    service today are of the reheating type, in which about

    one-third of the power is developed in the high-pressure

    section. When the steam leaves the high pressure turbine,

    it returns to the reheater and then flows to the intermediate

    and low pressure sections of the turbine, where the remain-

    ing two-thirds of the power is developed.

    In the above model, the inertia constant of H and thereheater time constant ofTRH are important. For the inertia

    constant of H, it is defined as the ratio of the moment of

    inertia of the generator rotating components to the generat-

    ing capacity of the unit. This constant is available from the

    manufacturer of generating units, with the typical value of

    28 s. Calculation of this constant in a system is also

    expressed as follows:

    HH1MVA1 H2MVA2 HnMVAn

    MVA1 MVA2 MVAn1

    The other time constant that is critical to the system is the

    reheater time constant, TRH. This constant is usually of therange between 6 and 12 s, and tends to dominate the

    response of the largest fraction of turbine power output

    [6]. The remaining parameters of this model shown in Fig.

    1 are the incremental frequency off, the damping factor of

    D, and the inverse of the governor regulation of 1R

    2.2. Formulation

    With the above analysis model, let us now consider a

    simple situation where Pref 0 and a step change happens

    in load demand of PL. The frequency variation in the

    frequency domain is then calculated as follows:

    fs bR1 TRHs

    ss2 2ns 2n

    PL 2

    where

    b 2HRtRH1

    n bDR GM05

    b2n

    2HR DR GMFHPTRH3

    By applying the inverse Laplace transform, the change of

    frequency as function of time when a step of change in the

    load can be written:

    ft bR

    2n1 rent cosht PL 4

    where

    r1 2nT

    2RH 2nTRH

    1 2

    05

    h n1 2

    05

    tan1 nTRH

    1 2

    Since Eq. (4) is expressed in the closed form, we can readily

    compute the initial slope of the response at t 0Therefore,

    m0 dft

    dt t0

    PL

    2H 5

    By differentiating Eq. (4) with respect to the time variable of

    tand let the post-differentiated result be equal to zero, the

    result oftmreveals the time when the variation of frequencyis maximum. This result is also expressed as below:

    tm 1

    htan1

    hTRH

    nTRH 1

    6

    Substitutetminto Eq. (4), the outcome can be simplified as:

    fmax kPL 7

    where k is a constant. This equation illuminates that the

    maximum frequency variation can be deemed proportional

    to the system disturbances.

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 515852

    frefP

    -

    +

    sT

    F

    RH

    HP

    +

    1

    1

    R

    1

    MG

    +

    +

    -

    +

    LP

    DHs+2

    1

    HPF

    Fig. 1. Analysis model.

  • 8/12/2019 1-s2.0-S0142061599000356-main

    3/8

    3. Design of load-shedding scheme

    The load-shedding scheme is designed to determine a

    workable balance between providing maximum system

    protection and minimal service interruption. The design

    procedure for the proposed load-shedding scheme is listed

    as follows:

    Step1 (obtain system parameters): As an example of the

    computation of the proposed method, consider an isolated

    area whose system parameters are D 10R 006H

    45 GM 090 FHP 033 and TRH 75 We can then

    calculate the following values, including b 02469 n

    04869 08158 r 50046 h 02816 and

    13696By substituting these values into Eq. (4), we can

    obtain the frequency variations in the function of time:

    ft 00625PL1 50046e03972t cos02816t

    13696 8

    Moreover, by Eq. (6), the value oftm can be calculated as2.9044 s. By substituting thistminto Eq. (8) and comparing

    the results with Eq. (7), the value of k was found to be

    0.1196.

    Step 2 (select the first shedding frequency(f1) and mini-

    mum allowable operating frequency (fmin)): Many utilities

    have set the first step of load shedding at 59.5 Hz. This

    choice was made based on several reasons [7,14]. First, all

    of the larger turbine-generators on the system are not rated

    for continuous operation below 59.5 Hz. Thus, setting the

    initial load shedding frequency at a relatively high value,

    such as 59.5 Hz, tends to limit the maximum frequency

    deviation. Second, a load-shedding program starting at59.5 Hz would be more effective in minimizing the depth

    of the under-frequency response for a heavy overload than

    would a similar program which had a lower first shedding

    frequency. Third, the first shedding frequency should not be

    too close to normal frequency. In this way, the tripping on

    severe but non-emergency frequency swings can be

    avoided. In this paper, the 59.5 Hz was also selected as

    shedding frequency at the first step shedding frequency.

    As for the selection of minimum allowable frequency,

    because the TPC limits system frequency deviation within

    ^ 4% (i.e. ^ 2.4 Hz for 60 Hz base), the minimum allow-

    able operating frequency of fmin is equal to 57.6 Hz. Thus,

    the value of the maximum change of frequency fmaxbecomes576 595595 00319 pu

    Step 3 (determine the number of steps (N) and the time

    interval between consecutive steps (t)): Steps of the shed

    load should be carefully chosen. Over- or under-shedding

    might happen under a small disturbance when a large step

    size is selected, while coordination problems might happen

    when many steps are decided. Experience has shown that

    three to five steps are adequate selections [13,14]. Hence, in

    this paper, the three, four and five steps were all adopted for

    the evaluation of the proposed method.

    An under-frequency relay is often incorporated with a

    time delay in order to decrease the impact caused by the

    system surges. This time delay may result in a longer trip

    reaction such that the frequency may decline, and hence

    result in unnecessary generator protection relay trips. To

    deal with this problem, a time-based procedure was

    proposed to shed the load in each predetermined time inter-

    val. By this method, because each length of time step was

    known, the time delay will not be required and the coordi-

    nation problem can also be solved. This time interval can be

    determined based on the system characteristics and types of

    under-frequency relays. The length of each time step is not

    necessarily equal to each other; while in this paper, time

    intervals were all set at t 01 s for easy manipulation.

    Step 4 (calculate the total amount of load shed PLS):

    The worst possible disturbance is subject to the speculation,

    while the load-shedding plan is inherently limit based on

    this assumption. Although the larger system upsets are seen

    less probable than small upsets, there is a certain probability

    that a large disturbance happens [15,16]. In the load-shed-

    ding study, once the frequency deviation curve is known, wecan obtain the initial rate of change of frequency ofm0based

    on this curve. The overload calculated by using Eq. (5)

    becomes PL 2Hm0

    With the time tm obtained in Step 1 and the maximum

    change of frequency fmaxin Step 2, we can solve the PL,minwith the aid of Eq. (8); and then, the total amount of load

    shed can be obtained by the following equation:

    PLS 2Hm0 PLmin 9

    Step 5 (determine the amount of load shed per step

    (PLS,i)): Once the total amount of load to be shed is

    known, the load shed per step can be obtained throughdividing by the number of shedding steps. In the method,

    each successive step was designed to shed a larger amount

    of load than the preceding step [17,18]. This design feature

    allows the protection scheme to drop smaller amounts of

    load when the degree of overload is less serious. Note that

    for an isolated system, fewer steps and larger load shed per

    step are required when compared with the interconnected

    systems.

    Step6 (plot the system frequency change curve): By the

    information on the amount of load shed per step, the over-

    load PL, and the time interval t, the system frequency

    change curve off(t) and f(t) can be plotted through the aid

    of Eqs. (4) and (9), respectively. Therefore, we can evaluatethe minimal operation frequency value. If the minimum

    operation frequency is seen higher than the minimum allow-

    able value offmin, the load shedding is claimed accomplished

    and the system has reached a new steady state. Otherwise,

    an additional modification step should be activated. As for

    the modification task, it will be discussed in the next step.

    Step7 (modification) A modification task is required for

    the case when the minimum operation frequency is lower

    than the minimum allowable operation frequency fmin.

    Under this scenario, it reveals that the amount of load to

    be shed is still insufficient to restore the system frequency.

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 5158 53

  • 8/12/2019 1-s2.0-S0142061599000356-main

    4/8

    To justify the total amount of shed load, a necessary task is

    to get the shedding frequency fi at each step. When the

    frequency at the last step is termed as fL, this value can be

    computed by the following Eqs. (10)(12) iteratively:

    PL1 PL PLS1 10

    PLi1 PLi PLSi1 i 1 2 3 N 1 11

    fi1 fi1

    f

    ti i 1 2 3 N

    1 12where PLis the initial system overload, PL,ithe overload

    after thei-th step, PLS,ithe amount of shed load at the i-th

    step, fti frequency variation after the i-th step during

    time interval t, andfi the frequency at the i-th step.

    Now, the frequency at the last step is obtained; therefore,

    we can immediately calculate the maximum allowable

    change of frequency at the last step, namely, fmax

    fmin fLfL in p.u./s. Similar to Eq. (7), the modified

    expression can be rewritten as below:

    fmin fL

    fLkPmax 13

    Eq. (13) can be also rearranged as:

    Pmax

    1

    k

    fmin

    fL 1

    14

    At this stage, the modified amount of shed of load is calcu-

    lated as follows:

    PLS PL Pmax 15

    By Eqs. (5) and (14), Eq. (15) can be further formulated as

    follows:

    P

    LS

    2Hm0

    1

    k

    fmin fL

    fL

    16

    whereP LSrepresents the total amount of shed load after the

    modification, and Pmax the maximum allowable overload

    after the last step. This equation informs the new amount of

    load to be shed in anticipation of restoring the system

    frequency.

    4. Numerical simulations

    To verify the proposed algorithm, numerical simulations

    have been performed. For an isolated system, the maximum

    load subject to a shedding schedule may include all loads.

    Therefore, in the simulation, the maximum disturbance at

    100% of the generation (i.e. PL 10 pu) in an isolated

    power system was investigated. Under this situation, the

    initial rate of change of frequency m0 can be obtained

    through Eq. (5),m0 01111 pusThe value ofPL,minwas thus computed as 0.267 p.u. By Eq. (9), the total

    amount of shed load PLS was concluded to be 0.733 p.u.

    As mentioned above, the 3, 4 and 5 steps were selectedas the number of shedding steps. In each case, two

    strategies (Strategy A, B) for shedding the load are

    considered:

    Strategy A: The loads are shed equally in each step.

    Strategy B: The loads are shed in the geometry mean

    form. Namely, the load shed at the second step is of the

    half amount of load shed at the first step.

    Tables 1 and 2 tabulate the load shed by strategy A and

    strategy B, respectively. In Table 1, the load can be seen

    shed equally at each step. For example, if the 3-step shed-

    ding-load is selected, the amount of the shed load at eachstep is equal to 07333 0244 pu While in Table 2, by

    strategy B, each step of shed load will be 0733 47

    0419 pu 0733 27 0209 pu and 0733 17

    0105 pu In these tables, we use the scheme 1A-3 to

    symbolize the 3-step load-shedding by strategy A, and the

    scheme 1B-3 to symbolize the 3-step load-shedding by strat-

    egy B. Figs. 2 and 3 plot the frequency change curve by

    these strategies, respectively. From these figures, the mini-

    mum frequency is seen lower than fmin 576 Hz by both

    strategies. The load shedding process was not successfully

    accomplished.

    To improve the above load-shedding process, the Step 7

    mentioned in Section 3 has been adopted. In this modifica-tion process, the shedding frequency at the last step, fL, was

    first calculated. Table 3 shows the shedding frequency at

    each step. In the table, the fL of 58.694, 58.294 and

    57.899 Hz that is seen for the scheme 1A-3, 1A-4 and 1A-

    5 at their individual final step. Similarly, the fL values of

    58.895, 58.648 and 58.431 Hz is seen for the scheme 1B-3,

    1B-4 and 1B-5, respectively. Now, by substituting these

    values of fL into Eq. (16), the amount of total shed load

    can be determined. Table 4 lists the required shed-load

    before and after modification. For example, after the modi-

    fication process, the new amount of load required to shed for

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 515854

    Table 1

    Amount of load shed per step by Strategy A

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    1A-3 0.245 0.244 0.244

    1A-4 0.184 0.183 0.183 0.1831A-5 0.147 0.147 0.147 0.146 0.146

    Table 2

    Amount of load shed per step by Strategy B

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    1B-3 0.419 0.209 0.105

    1B-4 0.391 0.195 0.098 0.049

    1B-5 0.378 0.189 0.095 0.047 0.024

  • 8/12/2019 1-s2.0-S0142061599000356-main

    5/8

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 5158 55

    Fig. 2. Load frequency curve of Scheme 1A.

    Fig. 3. Load frequency curve of Scheme 1B.

    Table 3

    Shedding frequency of Strategy A

    Strategy Shedding frequency at each step (Hz)

    1 2 3 4 5

    1A-3 59.5 59.018 58.694

    1A-4 59.5 58.979 58.578 58.294

    1A-5 59.5 58.955 58.508 58.157 57.899

    1B-3 59.5 59.129 58.895

    1B-4 59.5 59.111 58.848 58.648

    1B-5 59.5 59.103 58.828 58.614 58.431

    Table 4

    Required shed load before and after modification

    Strategy Total amount of load shed (p.u.)

    P LS PLS Increment

    1A-3 0.733 0.8442 0.1112

    1A-4 0.733 0.9005 0.1675

    1A-5 0.733 0.9568 0.2238

    1B-3 0.733 0.8162 0.0832

    1B-4 0.733 0.8506 0.1176

    1B-5 0.733 0.8811 0.1481

  • 8/12/2019 1-s2.0-S0142061599000356-main

    6/8

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 515856

    Fig. 4. Load frequency curve of Scheme 2A.

    0 2 4 6 8 10 12 14 1657.5

    58

    58.5

    59

    59.5

    60

    60.5

    Time [Sec]

    Frequen

    cy[Hz]

    Scheme 2B-5

    Scheme 2B-4Scheme 2B-3

    Fig. 5. Load frequency curve of Scheme 2B.

    Table 5

    Modified amount of load shed per step by Strategy A

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    2A-3 0.2814 0.2814 0.2814

    2A-4 0.2252 0.2251 0.2251 0.2251

    2A-5 0.1914 0.1914 0.1914 0.1913 0.1913

    Table 6

    Modified amount of load shed per step by Strategy B

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    2B-3 0.4824 0.2412 0.1206

    2B-4 0.4803 0.2401 0.1201 0.0600

    2B-5 0.4939 0.2469 0.1235 0.0617 0.0308

  • 8/12/2019 1-s2.0-S0142061599000356-main

    7/8

    the scheme 1A-3, P LS, will be:

    1A-3 P LS 10 1

    01196

    576 58694

    58694

    08442 pu

    Hence, the increment amount of total shed load becomes

    08442 0733 01112 puSimilarly, the new amount of

    load required to shed for the scheme 1B-3, P LS, can be

    computed:

    1B-3 P

    LS

    10 1

    01196

    576 58895

    58895

    08162 pu

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 5158 57

    Fig. 6. Load frequency curve of Scheme 3A.

    Fig. 7. Load frequency curve of Scheme 3B.

    Table 7

    Modified amount of load shed per step by Strategy A

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    3A-3 0.2721 0.2721 0.2720

    3A-4 0.2127 0.2127 0.2126 0.2126

    3A-5 0.1763 0.1762 0.1762 0.1762 0.1762

    Table 8

    Modified amount of load shed per step by Strategy B

    Scheme Amount of load shed per step (p.u.)

    1 2 3 4 5

    3B-3 0.4664 0.2332 0.1166

    3B-4 0.4537 0.2268 0.1135 0.0566

    3B-5 0.4548 0.2274 0.1137 0.0568 0.0284

  • 8/12/2019 1-s2.0-S0142061599000356-main

    8/8

    Now, because the total amount of load to be shed is

    different from the above case, the above scheme 1A is modi-

    fied to be schemes 2A and 2B, while the scheme 1B is

    modified to be 3A and 3B. Tables 5 and 6 list the newly

    determined amount of load shed per step after the modifica-

    tion by strategy A and strategy B, respectively. By this new

    amount of shed load, Figs. 4 and 5 plot the respective

    frequency curve by strategy A and strategy B.

    Similarly, for the modified amount of shed load from

    Scheme 1B, Tables 7 and 8 list the amount of shed load

    per step by strategy A and strategy B, respectively. By the

    new amount of shed load, Figs. 6 and 7 individually plot the

    frequency curve by strategy A and strategy B.

    From the above results, the operation frequency of Figs.

    4, 5 and 7 is seen higher than 57.6 Hz, which have demon-

    strated the effectiveness of the proposed method. However,

    seen from Fig. 6, it does not complete the load-shedding

    task. The reason why Fig. 6 failed is that Scheme 3A was

    modified from Scheme 1B, and the shed load of Scheme 3A

    is less drastic than Scheme 1B. Therefore, the load may notbe shed sufficiently in time, and the frequency drops down

    to be lower than the value offmin. The frequency restoration

    was thus not successfully accomplished. This outcome also

    explains the critical importance of the load-shedding

    scheme to the system protection performance.

    5. Conclusions

    A time-based load shedding protection scheme is

    proposed in this paper. In the method, the rate of change

    of frequency was detected as the initial value. A predeter-

    mined time interval and a modification algorithm thatincludes the maximum frequency change at the last step

    are embedded to organize a load shedding strategy. By

    case studies with numerical simulations, the proposed

    method is verified with simplicity, flexibility, and success

    for load shedding problems considering power system

    dynamics nature and protection component nature. It can

    be a useful integration of load shedding algorithm with a

    practical value. Currently, by the assistance of Taiwan

    Power Company engineers, a research project is carried

    on the extension of the proposed method to cover the control

    of pump-storage generating units in Taiwan Power Systems.

    The results will be reported in the near future.

    References

    [1] Jones JR, Kirkland WD. Computer algorithm for selection of

    frequency relays for load shedding. IEEE Computer Applications in

    Power 1988;1(1):2125.

    [2] Concordia C, Fink LH, Poullikkas G. Load shedding on an isolated

    system. IEEE Transactions on Power Systems 1995;10(3):1467

    1472.

    [3] Thompson JG, Fox B. Adaptive load shedding for isolated power

    systems. IEE ProceedingsGeneration, Transmission and Distribu-

    tion 1994;141(5):491496.

    [4] Maliszewski RM, Dunlop RD, Wilson GL. Frequency actuated load

    shedding and restoration Part Iphilosophy. IEEE Transactions on

    Power Apparatus and Systems 1971;PAS-90(4):14521459.

    [5] Horowitz SH, Polities A, Gabrielle AF. Frequency actuated load

    shedding and restorationPart IIimplementation. IEEE Transactions

    on Power Apparatus and Systems 1971;PAS-90(4):14601468.[6] Anderson PM, Mirheydar M. A low-order system frequency response

    model. IEEE Transactions on Power Systems 1990;5(3):720729.

    [7] Anderson PM, Mirheydar M. An adaptive method for setting under-

    frequency load shedding relays. IEEE Transactions on Power Systems

    1992;7(2):647655.

    [8] Lokay HE, Burtnyk V. Application of under-frequency relays for

    automatic load shedding. IEEE Transactions on Power Apparatus

    and Systems 1968;PAS-87(5):13621366.

    [9] Chuvychin VN, Gurov NS, Venkata SS, Brown RE. An adaptive

    approach to load shedding and spinning reserve control during

    under-frequency conditions. IEEE Transactions on Power Systems

    1996;11(4):18051810.

    [10] Shilling SR. Electrical transient stability and under-frequency load

    shedding analysis for a large pump station. IEEE Transactions on

    Industry Applications 1997;33(1):194201.[11] Hicks KL. Hybrid load shedding is frequency based. IEEE Spectrum

    1983;02:5256.

    [12] Kottick D, Or O. Neural-networks for predicting the operation of an

    under-frequency load shedding system. IEEE Transactions on Power

    Systems 1996;11(3):13501358.

    [13] Taylor CW, Nassief FR, Cresaf RL. Northwest power pool transient

    stability and load shedding controls for generation load imbalances.

    IEEE Transactions on Power Apparatus and Systems 1981;PAS-

    100(7):34863495.

    [14] Smaha DW, Rowland CR, Pope JW. Coordination of load conserva-

    tion with turbine-generator under-frequency protection. IEEE Trans-

    actions on Power Apparatus and Systems 1980;PAS-99(3):1137

    1150.

    [15] Prasetijo D, Lachs WR, Sutanto D. A new load shedding scheme for

    limiting under-frequency. IEEE Transactions on Power Systems1994;9(3):13711378.

    [16] Halevi Y, Kottick X. Optimization of load shedding system. IEEE

    Transactions on Energy Conversion 1993;8(2):207213.

    [17] IEEE Committee Report. Dynamic models for steam and hydro

    turbines in power system studies. IEEE Transactions on Power Appa-

    ratus and Systems 1973;PAS-92:19041915.

    [18] Nagrath IJ, Kothari DP. Power system engineering, New Delhi: Tata

    McGraw-Hill, 1994. p. 339376.

    S.-J. Huang, C.-C. Huang / Electrical Power and Energy Systems 22 (2000) 515858

    Shyh-Jier Huang received his PhD degree in Electrical Engineering

    from the University of Washington, Seattle, in 1994. Currently, he is

    with Department of Electrical Engineering and is the project manager

    in Computational Intelligence Applied to Power (CIAP) laboratory at

    National Cheng Kung University, Taiwan. He has worked research

    projects at the University of California, Berkeley from 1989 to 1991.

    He received Research Awards from National Science Council, Taiwan,

    from 1996 to 1999. He is a member of IEEE PES, CSS, CS and SMC.

    His main areas of interest are power system analysis, neural networks

    and fuzzy control.

    Chin-Chyr Huang received his MS degree from National Cheng Kung

    University in 1992. He is pursuing his PhD degree in the same univer-

    sity. His major interests are power system analysis and fuzzy controls.