Page 1: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

1

Submitting a RARF

Art Deller, P.E.Supervisor, Model Administration New Generation WorkshopNovember 4, 2014

Page 2: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

2

Process

Page 3: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

3

Process

• Prerequisites:

– Must be registered as a Resource Entity

– Must have received and installed Digital Certificate

Page 4: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

4

Process

Go to MIS and select Applications

Page 5: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

5

Process

Select Service Requests

Page 6: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

6

Process

Submit the request

Page 7: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

7

Process

…then add the RARF workbooks and attachments

Page 8: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

8

Process

Page 9: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

9

Timelines

Page 10: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

10

Timelines

Page 11: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

11

Timelines

• ERCOT suggests submitting RARF a minimum of 130 days before the projected MRD

• Interim updates for new resources are not being approved

Page 12: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

12

Completing the RARF

Ed Geer, P.E.Network Model Engineer, Sr. New Generation WorkshopNovember 4, 2014

Page 13: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

13

Stage 1 RARF forInterconnection Studies and

Planning Cases

Page 14: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

14

Completing the RARF – Stage 1

Page 15: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

15

• Interconnecting Entity (IE) begins submitting the RARF in Stage 1 of the generation interconnection process (refer to Interconnection Handbook at http://www.ercot.com/services/rq/re/index)

• Stage 1 RARF submitted for Screening Study and Full Interconnection Study using the currently posted version (RARF v 5.2)

Completing the RARF – Stage 1

Page 16: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

16

• Planning Guide Section 6.9 (2) requirement:

• “The IE shall provide to ERCOT the data necessary to model the Generation Resource in the base cases created and maintained by SSWG, SPWG, and the DWG, as directed by ERCOT.”

Completing the RARF – Stage 1

Page 17: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

17

• Planning Guide Section 6.9 (1) ERCOT will include a proposed Generation Resource in the planning cases – SSWG, SPWG, DWG if below criteria are met:– Signed SGIA– Air Permit (if necessary)– Water rights (if necessary)– Notice to proceed with construction of interconnection

to TSP– Financial security required to fund the interconnection

facilities

Completing the RARF – Stage 1

Page 18: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

18

• What RARF data is required?

• RDWG is working on an updated RARF Glossary that will state the details of the required planning data by item.

• For now, refer to the “Screening/Full Interconnection Study Guides” – “Spreadsheet Map” – column D posted by Resource Integration at the below link.

• Screening Study/Full Interconnection Study Guides (.zip)

Completing the RARF – Stage 1

Page 19: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

19

• “Each Generation Resource…shall provide accurate modeling information …” (Operating Guides 5.1(c) )

• For the Stage 1 RARF – “Typical or representative information may be provided for planned facility additions or modifications for use in the SSWG, DWG, and SPWG base cases…” (Operating Guides 5.1(d) )

Completing the RARF – Stage 1

Page 20: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

20

• Stage 1 RARF data examples include: Generator type, fuel, nameplate ratings, voltage,

county, planned COD Generator net seasonal ratings, reactive capability,

impedances and aux. load Transformer impedances, ratings, taps and AVR

settings Capacitors, reactors, STATCOMs, DVARs and

associated AVR settings POI name, PTI bus number, TSP Line data for connecting line to POI

Completing the RARF – Stage 1

Page 21: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

21

Stage 2 RARF forRegistration and Modeling

Page 22: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

22

Completing a RARF – Stage 2

Page 23: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

23

• Stage 2 RARF is submitted by registered Resource Entity (RE) only.

• Requires a fully completed RARF submittal for new resource(s) and associated equipment to provide the needed data for the new resource(s) to be added to ERCOT Network Operations Model

Completing the RARF – Stage 2

Page 24: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

24

Completing the RARF – Stage 2

• Operating Guide 5.1 (d) “Typical or representative information may be provided for planned facility …such information shall be revised using actual design or construction information in accordance with the time line for Network Operations Model changes outlined in Protocol Section 3.10.1, Time Line for Network Operations Model Changes.”

Page 25: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

25

• Select a target date for the addition of your RARF data into the ERCOT Network Operations Model at least 30 days before desired energization date.

• Refer to the ERCOT Network Operations Model Change Schedule for listing of available model load dates and associated deadlines.

Completing the RARF – Stage 2

Page 26: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

26

•IMPORTANT -- Start preparing the added RARF data early: 5 - 6 months before desired addition to ERCOT Network Operations Model (MRD).

•Contact us at [email protected] to discuss the details of your resource RARF data.

Completing the RARF – Stage 2

Page 27: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

27

• Don’t let your RARF submittal be on your new resource’s critical path.

• It’s better for your RARF data to be added to the model 2 months early than cause a slip in your energization because the RARF missed a deadline.

Completing the RARF – Stage 2

Page 28: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

28

• ERCOT suggests that you submit a first attempt at completing your RARF at least 130 days before the desired model load to allow time to resolve any RARF data issues.

• Send first attempt at a completed RARF to [email protected] with subject line indicating “TEST RARF submittal” and your site name.

Completing the RARF – Stage 2

Page 29: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

29

• The RE must complete the appropriate forms for the type of resource – using the currently posted RARF forms at the time of the submittal (currently RARF v 5.2).

• Changes must not be made to the names of the .xls RARF forms nor the structure of the forms in order for the RARF Audit Report to be run.

Completing the RARF – Stage 2

Page 30: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

30

• Wind, Combined Cycle, Conventional and Solar PV generation need three forms and Battery/Storage requires four forms. Wind – General Site ESIID, Wind, Transmission CC – General Site ESIID, Combined Cycle,

Transmission Generation - General Site ESIID, Gen, Transmission Solar PV – General Site ESIID, Gen, Transmission Battery or storage - General Site ESIID, Gen,

Transmission, and Load Resource

Completing the RARF – Stage 2

Page 31: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

31

• RARF – Parameters - Gen, Parameters -Wind or Parameters -CC tab – Seasonal Net Max. Sustainable Ratings need to match the Interconnection Agreement and the FIS studies.

• RARF - Reactive Capability tab – enter the gross leading and lagging reactive capability of the resource, specified at four MW output levels covering the full range of resource operation.

• Be sure that the data matches the reactive capability that was stated in the reactive study for your resource(s) provided to the Resource Integration engineer.

Completing the RARF – Stage 2

Page 32: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

32

• Substation capacitors, reactors or other reactive devices are modeled separately and are NOT included in the Reactive Capability tab.

• Enter the substation capacitors, reactors on the Capacitor and Reactor Data tab.

• Enter the dynamic reactive devices on the Static_Var_Compensator Data tab.

Completing the RARF – Stage 2

Page 33: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

33

• Suggest submittal of the reactive study at least 6 months before desired energization to allow time for approval so the RARF can be submitted with the correct resource reactive capability and reactive devices.

• Note: It may be necessary to submit the reactive study earlier than 6 months prior to energization depending on lead times for installing the required reactive equipment at the new resource site in time for the initial synchronization.

Completing the RARF – Stage 2

Page 34: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

34

• RARF - Transmission form – enter the lines, breakers, switches, transformers, capacitors, reactors, loads, series devices and static var compensators (STATCOMs, DVARs, SVCs) for the new resource site.

• All transmission voltage devices must be entered.

• Lower voltage devices are entered as needed to model the resource’s connection(s) and associated equipment.

• Telemetry is required for all RARF transmission form equipment as well as for the resource(s).

Completing the RARF – Stage 2

Page 35: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

35

For Wind and Solar sites:•Enter transmission voltage equipment and lines•Enter station transformer(s)•Enter a pseudo breaker for each resource (representing a group of feeder breakers)•Enter bus tie breaker/switch and transformer breakers and switches•Enter a load on the low side of each station transformer (with or without a breaker or switch)•Enter all reactive devices with associated breakers/switches.

Completing the RARF – Stage 2

Page 36: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

36

Completing the RARF – Stage 2

For Wind resources:•NPRR 425 – covers (1) WGR grouping and (2) aggregation of WTGs into a WGR•Submit requested grouping of WGRs on the RARF “Turbine Details” tab•Submit requested aggregation of WTGs for a WGR on the RARF “Turbine Details” tab•Grouping of WGRs and aggregation of WTGs in a WGR require ERCOT approval – allow 2 weeks for the approval before the RARF submittal deadline. •Section 3.10.7.2 (9), Modeling of Resources and Transmission Loads

Page 37: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

37

For Solar PV resources:•Enter the inverter information on the GEN form – “Unit Info – AGR” tab.•Telemetry is required for number of generators (inverters) on-line, number off- line and the number unknown.•Provide separate files for the Solar PV resource collection system data (raw file, sequence file and collector one-line)

Completing the RARF – Stage 2

Page 38: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

38

• If requesting “Non-Modeled Generator” on the RARF refer to Protocol Section 2 definition: A generator that is: (a) Capable of providing net output of energy to the ERCOT

System; (b) Ten MW or less in size; or greater than ten MW and

registered with the PUCT according to P.U.C. SUBST. R. 25.109, Registration of Power Generation Companies and Self-Generators, as a self-generator; and

(c) Registered with ERCOT as a Non-Modeled Generator, which means that the generator may not participate in the Ancillary

Service or energy markets, RUC, or SCED.

Completing the RARF – Stage 2

Page 39: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

39

• Required RARF files are either embedded or added to the zip file on each RARF submittal.

• Dynamic data/models – PSSe v33, site one-lines, collector system one-lines and data files, and transformer test reports (showing positive and zero sequence impedances, windings and taps)

• All supporting files need to be submitted every time you submit a RARF update (we don’t have an incremental update system)..

• Each RARF submittal must be a complete stand-alone package - zip file with all forms and associated files.

Completing the RARF – Stage 2

Page 40: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

40

Completing the RARF – Stage 2 – Example Time-line

The below time-line is for illustration purposes only.•Planned Energization Date (PED): 8/15/2015•Select MRD (30+ days prior to PED): 7/1/2015•Start updating RARF: 1/1/2015•Complete RE registration: 2/1/2015•Submit initial RARF for test: 2/1/2015•Submit RARF 4 weeks before deadline: 3/2/2015•Re-submit RARF with corrections: 3/9/2015•Receive ERCOT approval of RARF: 3/13/2015•Receive ERCOT confirmation of MRD: 3/13/2015

Page 41: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

41

Stage 3 RARF forCommissioning and Ongoing

Operations

Page 42: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

42

Completing the RARF – Stage 3

Page 43: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

43

Completing the RARF – Stage 3

• Planning Guide Section 6.8.2 (9) The Resource Entity must submit updated Resource Registration data containing changes made for the reasons below for an All-Inclusive Generation Resource. (a) Within ten Business Days of ERCOT approval of a Net

Dependable Capability test to reflect the results of the test; (b) Within ten Business Days of ERCOT approval of a reactive

capability test to reflect the results of the test; (c) Within ten Business Days of a request by ERCOT to check or

update specific Resource Registration data; and (d) Within ten Business Days of a known change to any

Resource Registration data.

Page 44: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

44

Questions about Completing the RARF ?

Page 45: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

45

Where does it go

Page 46: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

46

Where does it go?

• RARF Data feeds:– Network Operations Model– Steady State Planning Model– Dynamic Planning Model– CRR Model– Registration– Settlements– EMS– Market Manager

Page 47: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

47

• Data on RARF necessary for proper:

– Operation of a unit– Limits on parameters– Topology– Registration and Settlement– CRRs

Where does it go?

Page 48: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

48

Model Ready Date

Page 49: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

49

Model Ready Date

• MRD is the date the site is loaded into the Network Operations Model

• It precedes Energization, Synchronization and Commercial Operation

Page 50: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

50

Model Ready Date

• Based on the Model Load calendar

• Change must be submitted 90+ days prior to MRD

• Calendar does not include time to process RARF, submit RARF in time to complete processing

Page 51: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

51

Model Ready Date

Network Operations Model calendar can be found on the ERCOT website:

http://www.ercot.com/gridinfo/transmission/opsys-change-schedule

Page 52: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

52

Model Ready Date

• Timeline for submission of RARF follow the model load calendar specified in the Protocols, section 3.10.1

Deadline to Submit Information to ERCOT

Note 1

Model Complete and Available for Test

Note 2

Updated Network Operations Model Testing Complete

Note 3

Paragraph (5)

Update Network Operations Model Production Environment

Target Physical Equipment included in Production Model

Note 4

Jan 1 Feb 15 March 15 April 1 Month of AprilFeb 1 March 15 April 15 May 1 Month of MayMarch 1 April 15 May 15 June 1 Month of JuneApril 1 May 15 June 15 July 1 Month of JulyMay 1 June 15 July 15 August 1 Month of AugustJune 1 July 15 August 15 September 1 Month of SeptemberJuly 1 August 15 September 15 October 1 Month of OctoberAugust 1 September 15 October 15 November 1 Month of NovemberSeptember 1 October 15 November 15 December 1 Month of DecemberOctober 1 November 15 December 15 January 1 Month of January (the

next year)November 1 December 15 January 15 February 1 Month of February (the

next year)December 1 January 15 February 15 March 1 Month of March (the

next year)

Page 53: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

53

• Interim updates allowed for existing resources, but not new resources:

3.10.4(6) “ERCOT may update the model on an interim basis, outside of the timeline described in Section 3.10.1, Time Line for Network Operations Model Changes, for the correction of temporary configuration changes in a system restoration situation, such as after a storm, or correction of impedances and ratings.“

3.10.4 (7) “Interim updates to the Network Operations Model caused by unintentional inconsistencies of the model with the physical transmission grid may be made. If an interim update is implemented, ERCOT shall report changes to the PUCT Staff and the IMM. ERCOT shall provide Notice via electronic means to all Market Participants and post the Notice on the MIS Secure Area detailing the changed model information and the reason for the interim update within two Business Days following the report to PUCT Staff and the IMM.”

Model Ready Date

Page 54: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

54

Model Ready Date

• Transmitted back to RE in the Service Request after RARF is approved

Page 55: 1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014

55