Page 1: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

1

TRAIL BRIDGE INSPECTION TRAIL BRIDGE INSPECTION 101101

TRAIL BRIDGE INSPECTION TRAIL BRIDGE INSPECTION 101101

Page 2: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

2

Mission Mission StatementStatement

•This PowerPoint is intended to familiarize This PowerPoint is intended to familiarize the budding inspector with bridge the budding inspector with bridge terminology and concepts so they are terminology and concepts so they are ready and able to participate in a more in-ready and able to participate in a more in-depth discussions during the classroom depth discussions during the classroom sessions.sessions.

Page 3: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

3

Trail Bridges 101Trail Bridges 101•Why do we inspect trail Why do we inspect trail bridges?bridges?

•Who can inspect trail bridges?Who can inspect trail bridges?•What is a trail bridge?What is a trail bridge?•What does that bridge term What does that bridge term mean?mean?

•What are checks, splits, etc? What are checks, splits, etc? •What tools do I need for What tools do I need for inspection?inspection?

•What should I wear for safety?What should I wear for safety?

Page 4: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

4

It’s just water over the bridge…☺

Safety!! National

Bridge Inspection Standards

Why do we inspect trail bridges?

Page 5: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

5

Bridge Inspection History

• During the bridge construction boom of the 1950’s and 1960’s, little emphasis was placed on safety inspection and maintenance of bridges. This changed when the 2,235 foot Silver Bridge at Point Pleasant, WV, collapsed into the Ohio River, on Dec. 15, 1967. 46 people were killed.

Page 6: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

6

Bridge Inspection History

• The Federal Highway Act of 1968 required the Secretary of Transportation to establish a national bridge inspection standard and develop a program to train bridge inspectors.

• National Bridge Inspection Standards were developed for Road Bridges.

Page 7: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

7

Forest Service Trail BridgeInspector Qualifications

• FSM 7736.33 - Qualifications of Personnel Responsible for Trail Bridges Inspection and Condition Assessment

• Qualification and certification requirements shall be established by Regional guidance (FSH 7709.56b, sec. 05).

Page 8: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

8

General Definition of a Trail Bridge from the

TRAIL BRIDGE MATRIX:

A trail structure, including supports, erected over a depression or obstruction such as water, roadway, trail, or railway that provides a continuous pathway and has a deck for carrying traffic or other loads.

What is a Trail Bridge?

Page 9: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

9

Trail Bridge Matrix

Page 10: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

10

Trail Bridge Matrix

Page 11: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

11

TRAIL BRIDGE MATRIX:• Complex

• Major • Minor

* Inspection interval for all trail bridge classifications is every 5 years

Classification of Trail Bridges

Page 12: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

12

Complex Trail Bridge• Whose failure likely would put the

public at risk • Made of wood, concrete, fiberglass,

steel, suspension, or trusses• Usually greater than 20 ft long &• Greater than 5 ft height• Single or multiple span• Any bridge that requires higher

inspection skills• Requires a technical inspection

by an engineer or engineering technician certified road bridge inspector

Page 13: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

13

Example: Steel Deck Truss

COMPLEX TRAIL BRIDGE

Page 14: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

14

Example: Fiberglass

COMPLEX TRAIL BRIDGE

Page 15: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

15

Example: Steel Thru Truss

COMPLEX TRAIL BRIDGE

Page 16: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

16

Example: Old Railroad Trestle

COMPLEX TRAIL BRIDGE

Page 17: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

17

Example: Suspension

COMPLEX TRAIL BRIDGE

Page 18: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

18

Other Examples of

Complex Trail Bridges:

Concrete

Masonry

Arches

Multi-Span Structures

Complex Designs

COMPLEX TRAIL BRIDGE

Page 19: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

19

Major Trail Bridge• Whose failure likely would put the

public at risk• Made of wood (log/timber/glulam)• Greater than 20 ft long &• Greater than 5 ft height• Single span• Requires a technical inspection by

a person:1. Trained specifically for log and/or

timber trail bridge inspections; and

2. Deemed qualified, based on Regional Guidance.

Page 20: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

20

MAJOR TRAIL BRIDGEWood and >20 ft long and >5 ft high and single

spanExample: Treated Log

Stringer

Page 21: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

21

MAJOR TRAIL BRIDGEWood and >20 ft long and >5 ft high and single

spanExample: Untreated Log Stringer

Page 22: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

22

MAJOR TRAIL BRIDGEWood and >20 ft long and >5 ft high and single

spanExample: Glulam Beam

Page 23: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

23

MAJOR TRAIL BRIDGEWood and >20 ft long and >5 ft high and single

spanExample: Sawn Lumber

Page 24: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

24

Minor Trail Bridge

– Whose failure poses no significant risk to the public

– Made of wood (log/timber/glulam)– Less than 20 ft long or– Less than 5 ft height– Requires a condition

assessment by a person trained and qualified, based on Regional Guidance.

Page 25: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

25

MINOR TRAIL BRIDGE

Example: Sawn Lumber

Wood and <20 ft long or <5 ft above stream

Page 26: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

26

MINOR TRAIL BRIDGEWood and <20 ft long or <5 ft above stream

Example: Log Stringer

Page 27: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

27

WHY WE INSPECT TRAIL BRIDGES SAFETY!!!!

WHAT IS A BRIDGE?

A structure erected over a depression or obstruction such as water that provides a continuous pathway and has a deck for carrying traffic or other loads.

WHAT ARE THE THREE CLASSIFICATIONS OF TRAIL BRIDGES?

* Complex *Major *Minor

This class is only for Minor and Major trail bridges

Quick Summary so Far

Page 28: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

28

Bridge Terminology

Clear Span – Distance between face of support.

Page 29: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

29

LEFT

RIGHT

UPSTREAM

DOWNSTREAM

Bridge Orientation Terminology

APPROACH

Page 30: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

30

Span Arrangements

• SINGLE or SIMPLE SPAN

Page 31: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

31

• MULTIPLE SIMPLE SPANSimple Span – many spans, but each acts independently

Span Arrangements

Page 32: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

32

• MULTIPLE CONTINUOUS SPANContinuous Spans – 1 girder spans across 2 or more supports

Span Arrangements

Page 33: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

33

Approach Types

Gravel and Steps Gravel

Page 34: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

34

Rail System

Curbs, rails, posts, and bracing provided for user Safety

Page 35: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

35

Deck

The Deck supports loads applied to the bridge

Page 36: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

36

Decking Types & Terms

• Planks • Glulam panels • Split logs • Puncheon

•Wearing Surface •Running plank •Non-skid •Gravel

Page 37: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

37

Superstructure

The Superstructure carries loads from the deck to the substructure.

Page 38: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

38

Superstructure Components

Girders or stringers or beams – main load carrying members

Diaphragms or bridging or cross bracing – provide lateral support to girders (help stabilize the girders)

Backwalls – attached to the ends of the girders or stringers.

GLULAM GIRDER

LOG STRINGER

SAWN BEAM

Is it a girder or a stringer?

Page 39: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

39

Superstructure

Diaphragms (*), Bridging, Cross Bracing

*

Page 40: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

40

Superstructure

Log Stringer, aka Footlog

Page 41: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

41

Substructure

The Substructure carries loads to the ground

Page 42: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

42Sills or Ledgers

Substructure Types

Page 43: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

43Cribs and Gabions

Substructure Types

Page 44: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

44

Columns, piers, piles, bents

Substructure Types

Page 45: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

45

Stream Channel

But stream channels may have problem with aggradation, degradation and floating debris.

This stream channel is fairly stable

Page 46: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

46

Stream Channel

Bank and bank protection, debris in the waterway, streambed movement

Page 47: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

47

Stream Channel

Aggradation is the accumulation of sediment in rivers

Page 48: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

48

Stream Channel

Degradation is erosion of the streambed

Page 49: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

49

Stream Channel

Floating Debris can be trees and/or vegetation

Page 50: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

50

SCOUR is loss of ground support

Scour

Page 51: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

51

Scour

“Undermining”

is localized scour under a Substructure

Page 52: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

52

Scour failure is most common in bridges that are too short

Scour

Page 53: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

53

Scour

Scour failure is also common in areas where the banks are weak and unprotected by vegetation or riprap

Page 54: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

54

Scour

Is this substructure fully supported?

Page 55: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

55

• Railing

• Deck

• Approach

• Substructure (Sill)

• Superstructure(Log Stringer)

Reviewing Bridge Terminology Isn’t this fun?

Page 56: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

56

HOW A BRIDGE WORKSLive Loads are applied to the DECK.The DECK transmits live loads and

deck dead load to the SUPERSTRUCTURE. The SUPERSTRUCTURE transmits these loads and

the superstructure dead load to the SUBSTRUCTURE.

Deck

SuperstructureSubstructure

Earth

Page 57: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

57

The SUBSTRUCTURE transmits all these loads and the substructure dead load to the EARTH.

The EARTH supports the bridge and all its loads

It’s all about LOAD PATHS.

Deck

SuperstructureSubstructure

Earth

HOW A BRIDGE WORKS

Page 58: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

58

Loads and Forces Acting on the Bridge

• Dead Load – weight of bridge and its components• Live Load – temporary loads• Soil Reaction – support from the earth

Page 59: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

59

are determined by bridge materials and design

Dead Loads

Page 60: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

60

Dead Loadsinclude weight of stringers, decking, and railing

Page 61: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

61

Live Loadsare loads placed on the bridge

People, pack animals, ATV’s, groomers…

Page 62: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

62

… also include snow, wind, and earthquakes…

Live Loads

Page 63: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

63

is the ground supporting the structure

Soil Reaction

Page 64: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

64

How does a bridge react to loads?

Is there going to be math?

Page 65: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

65

• MOMENT, or BENDING, forces are greatest in the middle of the bridge. They are critical in the design of LONG bridges.

SHEAR and MOMENT• SHEAR forces are

greatest at the ends of the bridge. They are critical in the design of SHORT bridges.

compression

tension

Page 66: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

66

Shear• SHEAR FORCES are highest at the ends of a

bridge. Shear failure is common in short spans

Page 67: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

67

• MOMENT FORCES are highest at the middle of

the bridge. Bending failure is common in long spans

Moment

Page 68: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

68

Wood Terminology

• We can break the terminology for wood into three groups:– Basic Wood Definitions– Natural Defect of Wood– Evaluation or Inspection Terms

Page 69: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

69

Basic Wood Definitions

• Different timber shapes are used for different applications.

• Beams can either be rectangular for sawn or glulam beam bridges or round for log stringer bridges.

Page 70: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

70

Basic Wood Definitions• Dimension Lumber. Lumber with a nominal

thickness of from 2 inches up to, but not including, 5 inches and having a nominal width of 2 inches or greater.

• Rough Lumber. Lumber that has not been dressed but that has been sawn, edged, and trimmed.

• Sawn Lumber. The product of a sawmill not further manufactured other than by sawing, re-sawing and cross-cutting to length.

Page 71: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

71

Basic Wood Definitions

• Glued Laminated Timber (glulam). An engineered, stress-rated product of a timber laminating plant comprised of assemblies of specially selected and prepared wood laminations securely bonded together with adhesives.

• Log Stringer. Round logs that are used as beams or stringers that have been debarked.

• Timbers. Lumber that is nominally 5 inches or more in least dimension.

Page 72: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

72

Basic Wood Definitions

• Dressed Size. The dimensions of lumber after being surfaced with a planing machine. The dressed size is usually 1/2 to 3/4 in. less than the nominal or rough size. A 2- by 4-in. stud, for example, actually measures about 1-1/2 by 3-1/2 in.

• Nominal Size. As applied to timber or lumber, the size by which it is known and sold in the market i.e, 2x4, 2x6,4x4,etc. (often differs from the actual size).

Page 73: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

73

Wood Related Definitions• Fastener. Generic term for individual

mechanical devices such as bolts, nails, etc., used in a connection.

• Oil-Borne Preservative. A preservative that is introduced into wood in the form of an oil-based solution.

• Waterborne Preservative. A preservative that is introduced into wood in the form of a water-based solution.

Page 74: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

74

Natural Defects of Wood• Check – A separation of the wood normally

occurring across or through the rings of annual growth and usually as a result of seasoning.

• Split – A separation of the wood through the piece to the opposite surface or to an adjoining surface due to the tearing apart of wood cells.

• Shake – A lengthwise separation of the wood which occurs between or through the rings of annual growth.

Page 75: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

75

Natural Defect of Wood

Page 76: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

76

ChecksSeasoning checks may occur in the wide side of a member at or near the neutral axis.

The cracks form because the wood near the surface dries and shrinks first.

In larger pieces of lumber, the inner core of the member loses moisture and shrinks much slower.

Checking relieves the stresses caused by non-uniform drying.

Page 77: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

77

Checks

Page 78: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

78

Checks

Page 79: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

79

Split

Page 80: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

80

Shake

Page 81: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

81

Inspection Terms• Crack – Complete separation of wood fibers

across short axis of wood cells

• Decay*** - Decomposition of wood substance by fungi. Some people refer to it as “rot”

• Delamination. The separation of layers in laminated wood or plywood because of failure of the adhesive, either within the adhesive itself or at the interface between the adhesive and the adhered.

*** Will be covered in the classroom in more detail.

Page 82: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

82

Crack

Page 83: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

83

Other Inspection Terms• Moisture Content (MC). The amount of water

contained in the wood, usually expressed as a percentage of the weight of the oven dry wood.

• Twist. A distortion caused by the turning or winding of the edges of a board so that the four corners of any face are no longer in the same plane.

• Warp. Any variation from a true or plane surface. Warp includes bow, crook, cup, and twist, or any combination thereof.

• Weathering. The mechanical or chemical disintegration and discoloration of the surface of wood caused by exposure to light, the action of dust and sand carried by winds. Weathering does not include decay.

Page 84: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

84

Inspection Tools & Equipment

Basic inspection tools & equipment consists of:

• Backpack

• Light

• Boots

• Pick

• Awl

Page 85: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

85

Backpack

A good backpack is needed to store and carry your tools to the bridge site.

Page 86: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

86

Boots or WadersA set of waders or boots are required for walking in the water to inspect the underside of bridges.

Boots with felt soles work well walking in areas with slippery rocks.

Page 87: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

87

Prospector’s Pick

A prospector’s pick works well for sounding logs and beams with the hammer side and checking for decay with the pick side.

Page 88: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

88

Probes

Narrow screw drivers and awls work best for checking for decay in wood members.

Locking knives may be used, but are strongly discouraged. Knives that do not lock should not be used.

Page 89: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

89

Lights

A good light for use under bridges is highly recommended.

Both for safety and to perform a good bridge inspection.

Shining the light under a bridge before entering is a good safety practice, while it helps the inspector see animals and other obstacles that may cause problems.

Page 90: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

90

Optional Tools

A pair of binoculars is good for looking at the underside of a bridge when you can not get right up on the member you need to look at.

A telescoping pole can be used to look for scour holes and help to steady the inspector while walking in the stream.

Page 91: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

91

Optional Tools

A mirror can be used for inspecting hard to reach locations or around corners.

A plumb bob will help to check if things are perpendicular to the ground.

A wrench can be used for checking bolt tightness.

Page 92: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

92

Essential Items

Don’t forget the essentials!!!

Duck tape for fixing everything and toilet paper for when nature calls.

Page 93: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

93

Record KeepingBasic record keeping tools are:

• Clipboard

• Inspection Forms

• Write-in-rain notebook

• Pencils

• Camera

• Maps

Page 94: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

94

Maps

Maps are a necessity for working for the Forest Service.

Getting lost is not fun.

Taking the time to mark the location of the trail bridges on the map makes them easier to find in the field

Page 95: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

95

Bridge Inspection Forms & Tools

Make sure you have enough pencils, write-in-the-rain paper, forms and a clipboard to write on before going into the field.

Page 96: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

96

Camera

Take a camera along and take lots of pictures and document any deficiencies or problems.

Page 97: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

97

Optional Recording Tools

Other optional tools maybe a straight edge, triangles, compass and scale for drawing up sketches of the bridge.

Who knows, a calculator may even be handy to have.

Page 98: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

98

Surveying Equipment

Surveying equipment will be used for taking measurements of the bridge. The basics are a 6-foot rule, 25-foot tape, 100-foot cloth tape, a level and a GPS unit.

Page 99: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

99

GPS or Compass

A GPS unit will help you from getting lost and to get the coordinates of the site.

Some people still like to use a compass in the woods.

Page 100: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

100

Levels

Levels or a pocket level & ruler are not required, but maybe useful for checking slope of the bridge and settlement of the structure.

Page 101: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

101

Measuring Devices

Tapes and rulers should be used to take measurements of the bridge and problems. At minimum, the inspector should carry a 6-foot rule and a 100-foot cloth tape.

Page 102: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

102

Safety Equipment

Basic Safety Equipment consists of:• Hard Hat• Safety Glasses• Orange Vest• Gloves• Cell Phone• Hiking Boots

Page 103: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

103

Hard Hat

Hard Hats protect your head from sharp or protruding objects under the bridge.

Page 104: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

104

Safety Glasses & Gloves

Glasses protects eyes from flying debris when sounding timbers and sharp objects when walking under bridge

Gloves protect hands from blisters, slivers and cuts. They also protect against biting insects and poisonous plants.

Page 105: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

105

BootsBoots should provide ankle support to prevent sprains and twisted ankles

The treads should provide good traction

Page 106: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

106

Safety Vests

Safety vests are needed to provide visibility from traffic using the trail

Page 107: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

107

CommunicationsA proper communication device should be carried at all times in case of emergency

Examples are Forest Service Radios, cell and satellite phones

Page 108: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

108

First Aid Kit

A first aid kit should be carried into the field for emergency use.

Page 109: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

109

Optional Safety Equipment

Optional safety equipment can include:

• Snake Chaps

• Bear Spray

• Insect Repellent

• Sun Screen

• Rain Gear

• Coveralls

Page 110: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

110

Snake Chaps (optional)

Snake chaps should be worn in areas where poisonous snakes are known to live.

Do not provoke or handle snakes.

Page 111: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

111

Insect Repellent & Sunscreen (optional)

Insect repellent should be used when mosquitoes, flies and other biting bugs are present.

In addition, long sleeve shirts and pants should be worn. Gloves and head nets may also be a good idea.

The same holds true for sun screen. Prevent sunburn by wearing long sleeves and hard hat. Use sun screen if needed.

Page 112: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

112

Rain Gear (optional)

A light weight packable rain coat is a great way to go.

You need to wear clothing suited to the weather.

A layering approach works best for working in unpredictable weather conditions.

Page 113: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

113

Acknowledgments

• Thanks to R6 & R10 bridge engineers for their past training presentations and information to help develop this training.

• Thanks to Michael Knutson and John Kattell for reviewing the training.

Page 114: 1 TRAIL BRIDGE INSPECTION 101. 2 Mission Statement This PowerPoint is intended to familiarize the budding inspector with bridge terminology and concepts

114

References• FHWA Bridge Inspection Reference Manual• FHWA Field Manual for Timber Bridge Inspection,

Draft• FPL Timber Bridges Design, Construction,

Inspection and Maintenance• FSM 7736 • FSH 7709.56b, Chapter 8• R1 Major Trail Bridge Inspection Form & Minor

Trail Bridge Condition Assessment Form• R2 Trail Bridge Inspection Guidelines• R4 Trail Bridge Inspection Guidelines• R6 Trail Bridge Inspection• R10 Training PowerPoints