![Page 1: 1 Update on Run Schedule R. Raman NSTX Team Meeting PPPL, Princeton, NJ, 08 February, 2006 Work supported by DOE contract numbers DE-FG02-99ER54519 AM08,](https://reader031.vdocument.in/reader031/viewer/2022033106/56649efb5503460f94c0d9e1/html5/thumbnails/1.jpg)
1
Update on Run Schedule
R. Raman
NSTX Team MeetingPPPL, Princeton, NJ,
08 February, 2006
Work supported by DOE contract numbers DE-FG02-99ER54519 AM08, DE-FG03-96ER54361
Supported byOffice ofScience
College W&MColorado Sch MinesColumbia UComp-XGeneral AtomicsINELJohns Hopkins ULANLLLNLLodestarMITNova PhotonicsNew York UOld Dominion UORNLPPPLPSIPrinceton USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU MarylandU RochesterU WashingtonU Wisconsin
Culham Sci CtrU St. Andrews
York UChubu UFukui U
Hiroshima UHyogo UKyoto U
Kyushu UKyushu Tokai U
NIFSNiigata UU Tokyo
JAERIHebrew UIoffe Inst
RRC Kurchatov InstTRINITI
KBSIKAIST
ENEA, FrascatiCEA, Cadarache
IPP, JülichIPP, Garching
ASCR, Czech RepU Quebec
![Page 2: 1 Update on Run Schedule R. Raman NSTX Team Meeting PPPL, Princeton, NJ, 08 February, 2006 Work supported by DOE contract numbers DE-FG02-99ER54519 AM08,](https://reader031.vdocument.in/reader031/viewer/2022033106/56649efb5503460f94c0d9e1/html5/thumbnails/2.jpg)
2
Start date of NSTX Run to be finalized soon
• Note: Decision on Baking vessel will revise the present Draft schedule
• First Week of research focus is in pre-Li experiments– Obtain reliable plasmas in NSTX (2 days) and conduct piggy back activities
• Test the Supersonic gas injector• Get all diagnostics working• Test high-k scattering and RWM systems
• Second week devoted to evaluating Li capability and to develop suitable plasma targets for other experiments
• Third week will develop tools needed for RWM system and high-k scattering diagnostic
– Supporting experiments in these areas would be conducted
• Then we will evaluate Li capability and assess impact on NSTX Run
• Early next week, the updated schedule will be posted on the NSTX web page
![Page 3: 1 Update on Run Schedule R. Raman NSTX Team Meeting PPPL, Princeton, NJ, 08 February, 2006 Work supported by DOE contract numbers DE-FG02-99ER54519 AM08,](https://reader031.vdocument.in/reader031/viewer/2022033106/56649efb5503460f94c0d9e1/html5/thumbnails/3.jpg)
3
![Page 4: 1 Update on Run Schedule R. Raman NSTX Team Meeting PPPL, Princeton, NJ, 08 February, 2006 Work supported by DOE contract numbers DE-FG02-99ER54519 AM08,](https://reader031.vdocument.in/reader031/viewer/2022033106/56649efb5503460f94c0d9e1/html5/thumbnails/4.jpg)
4
Maintenance Breaks
• We expect week of April 3-7 (TTF Meeting) and May 8-12 (HTPDC) to be used as maintenance breaks
• NSTX is planned to operate during the weeks April 10-14 (ITPA meeting at MIT) and April 24-28 (ITPA meeting at PPPL)– Operations support staff who plan to attend
these two meetings are requested to inform me.