10 capital budgeting

Upload: rakshit-bapna

Post on 07-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 10 Capital Budgeting

    1/24

    The Basics of Capital Budgeting

    Should webuild this

    plant?

  • 8/4/2019 10 Capital Budgeting

    2/24

    10-1

    What is capital budgeting?Analysis of potential additions to

    fixed assets.

    Long-term decisions; involve largeexpenditures.

    Very important to firms future.

  • 8/4/2019 10 Capital Budgeting

    3/24

    10-2

    Steps to capital budgeting1. Estimate CFs (inflows & outflows).

    2. Assess riskiness of CFs.

    3. Determine the appropriate cost of capital.

    4. Find NPV and/or IRR.

    5. Accept if NPV > 0 and/or IRR > WACC.

  • 8/4/2019 10 Capital Budgeting

    4/24

    10-3

    What is the difference betweenindependent and mutually exclusive

    projects?

    Independent projects if the cash flows of oneare unaffected by the acceptance of the other.

    Mutually exclusive projects if the cash flowsof one can be adversely impacted by theacceptance of the other.

  • 8/4/2019 10 Capital Budgeting

    5/24

    10-4

    What is the difference between normal

    and nonnormal cash flow streams? Normal cash flow stream Cost (negative CF)

    followed by a series of positive cash inflows.

    One change of signs. Nonnormal cash flow stream Two or more

    changes of signs. Most common: Cost(negative CF), then string of positive CFs, then

    cost to close project. Nuclear power plant,strip mine, etc.

  • 8/4/2019 10 Capital Budgeting

    6/24

    10-5

    What is the payback period? The number of years required to

    recover a projects cost, or How long

    does it take to get our money back?

    Calculated by adding projects cashinflows to its cost until the cumulative

    cash flow for the project turns positive.

  • 8/4/2019 10 Capital Budgeting

    7/24

    10-6

    Calculating payback

    PaybackL = 2 + / = 2.375 years

    CFt -100 10 60 100

    Cumulative -100 -90 0 50

    0 1 2 3

    =

    2.4

    30 80

    80

    -30

    Project L

    PaybackS = 1 + / = 1.6 years

    CFt -100 70 100 20Cumulative -100 0 20 40

    0 1 2 3

    =

    1.6

    30 50

    50

    -30

    Project S

  • 8/4/2019 10 Capital Budgeting

    8/24

    10-7

    Strengths and weaknesses of

    payback Strengths

    Provides an indication of a projects risk

    and liquidity. Easy to calculate and understand.

    Weaknesses

    Ignores the time value of money.

    Ignores CFs occurring after the paybackperiod.

  • 8/4/2019 10 Capital Budgeting

    9/24

    10-8

    Discounted payback period Uses discounted cash flows rather than

    raw CFs.

    Disc PaybackL = 2 + / = 2.7 years

    CFt -100 10 60 80

    Cumulative -100 -90.91 18.79

    0 1 2 3

    =

    2.7

    60.11

    -41.32

    PV of CFt -100 9.09 49.59

    41.32 60.11

    10%

  • 8/4/2019 10 Capital Budgeting

    10/24

    10-9

    Net Present Value (NPV) Sum of the PVs of all cash inflows and

    outflows of a project:

    n

    0tt

    t

    )k1(

    CFNPV

  • 8/4/2019 10 Capital Budgeting

    11/24

    10-10

    What is Project Ls NPV?Year CFt PV of CFt

    0 -100 -$100

    1 10 9.09

    2 60 49.59

    3 80 60.11

    NPVL = $18.79

    NPVS = $19.98

  • 8/4/2019 10 Capital Budgeting

    12/24

    10-11

    Rationale for the NPV methodNPV = PV of inflows Cost= Net gain in wealth

    If projects are independent, accept if theproject NPV > 0.

    If projects are mutually exclusive, acceptprojects with the highest positive NPV,those that add the most value.

    In this example, would accept S ifmutually exclusive (NPVs > NPVL), and

    would accept both if independent.

  • 8/4/2019 10 Capital Budgeting

    13/24

    10-12

    Internal Rate of Return (IRR) IRR is the discount rate that forces PV of

    inflows equal to cost, and the NPV = 0:

    n

    0tt

    t

    )IRR1(

    CF0

  • 8/4/2019 10 Capital Budgeting

    14/24

    10-13

    Rationale for the IRR method If IRR > WACC, the projects rate of

    return is greater than its costs.

    There is some return left over toboost stockholders returns.

  • 8/4/2019 10 Capital Budgeting

    15/24

    10-14

    IRR Acceptance Criteria If IRR > k, accept project.

    If IRR < k, reject project.

    If projects are independent, acceptboth projects, as both IRR > k =

    10%. If projects are mutually exclusive,

    accept S, because IRRs > IRRL.

  • 8/4/2019 10 Capital Budgeting

    16/24

    10-15

    NPV Profiles

    A graphical representation of project NPVs atvarious different costs of capital.

    k NPVL NPVS0 $50 $405 33 29

    10 19 2015 7 1220 (4) 5

  • 8/4/2019 10 Capital Budgeting

    17/24

    10-16

    Drawing NPV profiles

    -10

    0

    10

    20

    30

    40

    50

    60

    5 10 15 20 23.6

    NPV($)

    Discount Rate (%)

    IRRL = 18.1%

    IRRS = 23.6%

    Crossover Point = 8.7%

    SL

    .

    .

    . ...

    .

    ..

    . .

  • 8/4/2019 10 Capital Budgeting

    18/24

    10-17

    Comparing the NPV and IRRmethods

    If projects are independent, the twomethods always lead to the same

    accept/reject decisions. If projects are mutually exclusive

    If k > crossover point, the two methods lead tothe same decision and there is no conflict.

    If k < crossover point, the two methods lead todifferent accept/reject decisions.

    Ifprofiles dont cross, one project dominates the

    other.

  • 8/4/2019 10 Capital Budgeting

    19/24

    10-18

    Reinvestment rate assumptions

    NPV method assumes CFs are reinvestedat k, the opportunity cost of capital.

    IRR method assumes CFs are reinvestedat IRR.

    Assuming CFs are reinvested at theopportunity cost of capital is morerealistic, so NPV method is the best. NPV

    method should be used to choosebetween mutually exclusive projects. Perhaps a hybrid of the IRR that assumes

    cost of capital reinvestment is needed.

  • 8/4/2019 10 Capital Budgeting

    20/24

    10-19

    Since managers prefer the IRR to the NPVmethod, is there a better IRR measure?

    Yes, MIRR is the discount rate thatcauses the PV of a projects terminal

    value (TV) to equal the PV of costs. TVis found by compounding inflows atWACC.

    MIRR assumes cash flows arereinvested at the WACC.

  • 8/4/2019 10 Capital Budgeting

    21/24

    10-20

    Calculating MIRR

    66.012.1

    10%10%

    -100.0 10.0 60.0 80.0

    0 1 2 310%

    PV outflows

    -100.0 $100

    MIRR = 16.5%158.1

    TV inflows

    MIRRL = 16.5%

    $158.1(1 + MIRRL)

    3=

  • 8/4/2019 10 Capital Budgeting

    22/24

    10-21

    Why use MIRR versus IRR?

    MIRR correctly assumes reinvestmentat opportunity cost = WACC. MIRR

    also avoids the problem of multipleIRRs.

    Managers like rate of return

    comparisons, and MIRR is better forthis than IRR.

  • 8/4/2019 10 Capital Budgeting

    23/24

    10-22

    Project P has cash flows (in 000s): CF0 =-$800, CF1 = $5,000, and CF2 = -$5,000.

    Find Project Ps NPV and IRR.

    NPV = -$386.78.

    IRR = 25% & 400%

    -800 5,000 -5,000

    0 1 2k = 10%

  • 8/4/2019 10 Capital Budgeting

    24/24

    10-23

    Multiple IRRs

    NPV Profile

    450

    -800

    0 400100

    IRR2 = 400%

    IRR1 = 25%

    k

    NPV