10 planning, land use and property - hdp-au-prod-app
TRANSCRIPT
Planning, Land Use and Property
143
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
10 Planning, Land Use and Property 10.1 Introduction A review of the existing land use, planning context and tenure has been undertaken for the B2N Project, including both the Project Area and a 50m buffer area. Whilst the implementation of the B2N Project is expected to proceed under Schedule 6 of the Planning Regulation 2017 as ‘Development local categorising instrument is prohibited from stating is assessable development’ and therefore not subject to assessment against a planning scheme, a review of the SCC Planning Scheme has been undertaken to provide context to the potential changes in land use and zoning as a result of the B2N Project.
10.2 Assessment Methods This land use and planning assessment has included consideration of the following:
• SCC Planning Scheme, 2014 • State Development Assessment Provisions • available land use mapping and zoning mapping (Queensland Globe and SCC Local Area Maps and interactive
“MyMaps”) • SARA and SPP Mapping (DSDMIP) • Native Title Assessments, undertaken by TMR for Building Queensland • review of aerial imagery, 2019 • Key Resource Area Reports, DILGP 2016 • review of previous land use impacted identified in the Beerburrum to Landsborough and Landsborough to
Nambour studies.
The residual impact assessment adopted elsewhere in this REF has not been applied to this Chapter due to the nature of the impacts and ongoing actions that will be part of future stages of B2N Project delivery.
10.3 Existing Environment 10.3.1 The Protected Corridor and Works Areas
The Protected Corridor between Beerburrum and Landsborough was identified and formally preserved as ‘future railway land’ by way of Government Gazette in 2011. Rail duplication works between Beerburrum and Landsborough will be conducted within this Protected Corridor. Works north of Landsborough will be undertaken utilising the existing rail reserve (lands leased) and not utilise the corridor protected as ‘future public passenger transport corridor’.
The SCC Planning Scheme Regional Infrastructure Overlay Maps show the Protected Corridor between Beerburrum and Landsborough within the ‘Railway Corridor and Buffer Zone’. This designation also covers the existing railway and ‘future public passenger transport corridor’ between Landsborough and Nambour.
10.3.2 Local Plan Areas and Land Use
Land use in the Project Area comprises a mix of rural, natural and hinterland township uses.
The SCC Planning Scheme includes local plan area zoning maps for Beerburrum, Glass House Mountains, Beerwah, Landsborough, Mooloolah Valley, Eudlo, Palmwoods, Woombye and Nambour. Areas outside these Local Plan areas are covered by Rural Area zone maps.
The Local Plan Area for Beerburrum, as described in part 7.2.1 of the SCC Planning Scheme (2014) encompasses the village of Beerburrum and residential areas immediately to the south. This Local Plan Area covers approximately 69 hectares and incorporates the Beerburrum Station and station cark park. The Beerburrum State School is located on the western side of the existing rail corridor. Parrot Park is located between the school and Beerburrum Road, providing public rest facilities and signage about the local area. Commerce and retail includes the general store/ post office/ newsagent, motor vehicle repair shop and cafe. The SCC Planning Scheme notes that limited residential urban services include reticulated water, but not sewerage, with the large lot size essential for on-site treatment of residential waste water. The Beerburrum Cemetery is located to the north of the Primary School, zoned as community facilities zone, located on the west of the existing railway.
Planning, Land Use and Property
144
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
The area between the Beerburrum Local Plan and the Glass House Mountains Local Plan is covered by the Rural Area Plan no 53. This includes areas of Beerburrum State Forest (east and west), Glass House Mountains National Park, the Matthew Flinders Rest Area and monument, and a residential subdivision and community facilities zone encompassing the “Twin Cedars Lifestyle Villas” on the eastern side of Steve Irwin Way. Other land uses within this area include fruit and vegetable market, plant nursery, caravan park, the former State Forest nursery, cropping and the Beerburrum Quarry (Key Resource Area no 51). This resource area is a source of quarry rock, supplying crushed rock products (KRA Reports and Maps 41 to 80, DILGP April 2016). The Burrum Key Resource Area (KRA no 147) is located to the west of the Beerburrum Local Plan Area, with the transport route identified off Beerburrum-Woodford Road.
The Local Plan Area for Glass House Mountains covers 474ha, including the developed areas to the east and west of the railway, and the town centre immediately surrounding the existing rail station. The Glass House Mountains Local Plan Elements map shows east – west green corridors (local ecological links) on the north and south sides of the station, associated with Coonowrin Creek. Glass House Mountains State School is located approximately 900m to the south west of Glass House Mountains Station, on Coonowrin Road. Other community facilities within Glass House Mountains include the Glass House Mountains Sports Club, the medical centre, information centre. Commercial and services include the IGA, post office, mechanic, strip shopping complex, bakery, café and real estate agency. Surrounding land uses include residential, agriculture including pineapples and poultry. The Local Plan Code (Planning Scheme Section 7.2.12) also notes that further residential development opportunities are located to the south of Fullertons Road and Coonowrin Road. Reticulated water and sewerage is available within the urban zoned land within the Local Plan area, with rural residential areas provided access to reticulated water only.
The Glass House Key Resource Area (KRA no 48) is located to the west of the Glass House Mountains township, with the transport route for this resource area along Coonowrin Road, across the Burgess St bridge and onto Steve Irwin Way. This resource area is a source of quarry rock, with uses included concrete and asphalt aggregates, manufactured sand, road base, rip rap and coarse aggregates (KRA Reports and Maps 41 to 80, DILGP, April 2016).
The SCC Rural Map tile 48 covers the area between Glass House Mountains and Beerwah Local Plan Areas. Zoning of the Project Area is rural, with the rail corridor shown as community facilities zone.
The Beerwah Local Plan Area map covers the Beerwah township and adjacent residential areas, covering approximately 775 hectares. The Beerwah Local Plan Code, part 7.2.2 of the Sunshine Coast Planning Scheme 2014, signals that Beerwah is intended to function as a major regional activity centre providing a mix of business, retail, community and administrative functions, but remain at a smaller scale than other regional activity centres across the Sunshine Coast. Beerwah State High School and Glasshouse Christian College are located to the west of the railway, with Beerwah State Primary School located further to the west on Peachester Road. Both Aldi and Woolworths are located at Beerwah, with numerous retail services located on both sides of the railway. The Beerwah and Districts Golf Course is located on the east side, along with areas of industrial use. Australia Zoo is located to the north of the Beerwah Plan area, with access via Steve Irwin Way.
The Beerwah Plan Code indicates that new development providing for retail and commercial functions is intended to be consolidated on the western side of the railway, with the eastern side to emerge as high density residential accommodation and local convenience shopping. The code also identifies an industrial estate on the eastern side of the railway. An employment growth area, located outside the local plan area, is also identified to the east of Steve Irwin Way, on the south side of Coochin Creek. This area is identified in the Local Plan Code so that the area can be ‘protected from fragmentation and inappropriate land use until decisions about long term land use are made’.
The future CAMCOS rail link to Caloundra and Maroochydore is identified in the SCC Planning Scheme 2014 Regional Infrastructure Overlay Maps as ‘dedicated transit corridor and buffer’, branching off from the existing North Coast Line, approximately 1km to the north of Beerwah Station, and south of Australia Zoo.
The SCC Rural Map tile 48 also covers the area between the Beerwah and Landsborough Local Plan Areas. Zoning of the Project Area is rural, with the rail corridor shown as community facilities zone. The area to the east of the Project Area is identified as ‘Tourism Zone’, Precinct TOU1 (Australia Zoo).
The Landsborough Local Plan Area covers approximately 880ha and includes the Landsborough town centre, surrounding urban areas and adjacent rural residential areas. The Landsborough Local Plan Code (Planning Scheme Section 7.2.16), highlights the historic significance of the Landsborough town, and the intent to develop an ‘Arts, Community and Heritage Precinct’ south of the town centre around Maleny Street.
Land uses within Landsborough are described in the Local Plan Code as including a range of community activities and sport and recreation areas including Landsborough State School, emergency services, local utilities, the Landsborough
Planning, Land Use and Property
145
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Museum, places of worship and district sports grounds. The Landsborough and District Sports Ground is located north of the Landsborough township, directly adjacent to the existing rail corridor and Project Area. This significant community facility has been the subject of master planning with future plans for capacity and car parking improvements identified. Landsborough Primary School is also located to the north of the town centre, with its school oval located across the street from the School premises on Gympie Street North. Significant commercial development is located on both the east and west sides of the railway, with the Caloundra Street level crossing and Gympie Street North level crossings providing for east –west connectivity. Dularcha National Park is located to the north of Landsborough, just outside the limits of the Local Plan Area.
Land use in the vicinity of works at Mooloolah Station include the Mooloolah Recreation Reserve and Pony Club to the east of the station and station car park, with commercial and residential on the western side. A level crossing on Mooloolah/ Bray Road provides for east – west connectivity, with a timber pedestrian bridge also providing pedestrian access when the boom gates are down.
At Eudlo Station and surrounds, land uses include Eudlo State Primary School on the east, Olsen Mill Park to the north east, and Federation Walk, located on railway land, on the west facing the existing station. The Landsborough to Nambour Rail Project EIS identifies these areas of key significance to the local community, with significant effort and time invested by volunteers in the revegetation and ongoing maintenance of the area.
At Palmwoods, land uses surrounding the station precinct include open space, commercial and residential. Kolora Park, Palmwoods Memorial Hall and the Palmwoods Bowls Club are located to the north of the station precinct. SCC is progressing a master plan process for the Palmwoods town centre, called Place Making Palmwoods. This includes the publication of an implementation plan identifying intersection improvements, potential car parking areas, streetscape improvements and improvements to the Palmwoods Memorial Hall precinct. This plan also identifies the corridor protected in 2011, with the existing rail corridor identified as ‘land for potential alternate uses following rail corridor upgrade (subject to future planning)’.
Land uses in the vicinity of the Woombye Station and passing loop extension include residential, commercial along Blackall Street, with open space comprising the soccer club, netball club and pony club on the west of the station precinct. Residential areas are located on the south east of the railway. A new stabling yard has been constructed south of the station, and is located on the west of the existing railway.
Land uses in the vicinity of the Nambour Station car park upgrades include commercial industrial and retail.
10.3.3 Zoning
The North Coast Line is zoned as ‘community facilities zone’. This includes areas associated with the rail corridor, station and station car parks.
Areas of State Forest and National Park are zoned as ‘Environmental Management and Conservation Zone’.
Zoning of the areas designated as part of the ‘protected corridor’ are generally rural. The hinterland townships are zoned for more intensive uses including ‘local centre zone’, ‘specialised centre zone’, ‘sport and recreation zone’ and ‘residential zone’. These zones are broadly illustrated on Figure 10.
10.3.4 Tenure
The tenure of the existing rail corridor is lands lease. The tenure of the areas under the Protected Corridor include lands lease (existing rail corridor) freehold, reserve, road reserve and State Forest.
Tenure of the Project Area is illustrated on Figure 11.
N
N
N:\
Proj
ects
\300
3243
6 - B
eerb
urru
m t
o N
ambo
ur\1
40 G
IS\3
0032
436_
B2N
__Re
f2_1
_Rev
isio
n_20
1911
21.q
gz|F
igur
e 10
: Zon
ing|
_Fig
02_R
E
PAGE SIZE
Figure 10: ZoningA3
Rail sta ons
Current rail line
Project Area
Addi onal Project Areas
CREATED BY EH11799
SOURCES QLD Govt
© SMEC Australia Pty Ltd 2019.All Rights Reserved
Disclaimer: While all reasonable care has been taken to ensure theinforma on contained on this map is up to date and accurate, thismap contains data from a number of sources - no warranty is giventhat the informa on contained on this is free from error or omission.Any reliance placed on such informa on shall be at the sole risk of theuser. Please verify the accuracy of all informa on prior to using it. Thismap is not a design document.
SMEC AUSTRALIA PTY LTDABN 47 065 475 149
Community Facili es Zone
District Centre Zone
Emerging Community Zone
Environmental Management and Conserva on Zone
High Density Residen al Zone
High Impact Industry Zone
Limited Development (Landscape Residen al) Zone
Local Centre Zone
Low Density Residen al Zone
Low Impact Industry Zone
Major Centre Zone
Medium Density Residen al Zone
Medium Impact Industry Zone
Open Space Zone
Principal Centre Zone
Rural Residen al Zone
Rural Zone
Specialised Centre Zone
Sport and Recrea on Zone
Tourism Zone
Tourist Accommoda on Zone
Waterfront and Marine Industry Zone
Zoning Classifica ons Sunshine Coast Overlays Planning Scheme
DATE 21-11-2019
N
N
N:\
Proj
ects
\300
3243
6 - B
eerb
urru
m t
o N
ambo
ur\1
40 G
IS\3
0032
436_
B2N
__Re
f2_1
_Rev
isio
n_20
1911
21.q
gz|F
igur
e 11
: Ten
ure|
_Fig
02_R
E
PAGE SIZE
Figure 11: TenureA3
Rail sta on
Current rail line
Project AreaAddi onal Project Areas
CREATED BY EH11799
SOURCES QLD Govt
© SMEC Australia Pty Ltd 2019.All Rights Reserved
Disclaimer: While all reasonable care has been taken to ensure theinforma on contained on this map is up to date and accurate, thismap contains data from a number of sources - no warranty is giventhat the informa on contained on this is free from error or omission.Any reliance placed on such informa on shall be at the sole risk of theuser. Please verify the accuracy of all informa on prior to using it. Thismap is not a design document.
SMEC AUSTRALIA PTY LTDABN 47 065 475 149
Forest Reserve
Na onal Park
State Forest
Reserve
Covenant
Easement
Freehold
Lands Lease
Housing Land
Main Road
Profit-a-Prendre
Railway
State Land
Tenure
DATE 21-11-2019
Planning, Land Use and Property
148
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
10.3.5 Native Title
The Project Area is located within the Kabi Kabi First Nation Traditional Owners Native Title Claim Group claim area, registered on 8 February 2019. Native Title assessments have been undertaken by Building Queensland for properties identified as being impacted by the Protected Corridor.
Native Title is the recognition in Australian law that some Indigenous people continue to hold rights to their lands and waters which come from their traditional laws and customs. Native Title applies to any areas in respect of which Native Title has not been extinguished.
The Native Title Act 1993 (NTA) provides for the recognition and protection of Native Title, establishes ways in which future dealings affecting native title (called “future acts”) may validly proceed. It also establishes a mechanism for determining native title claims and provides for the validation of “past acts” and “intermediate period acts”.
As part of the Business Case phase of the B2N Project, the department has carried out a total of 122 Native Title Assessments to ascertain the extent to which native title may continue to exist in the B2N Project Area as indicated in Table 53.
Table 53: Native Title Assessments Undertaken
TENURE TOTAL NO. OF NATIVE TITLE ASSESSMENTS
Freehold 61
Perpetual Head Lease 15
Roads 34
Reserve 5
State Forest 2
Unallocated State Land (USL) / Waterways 5
The Native Title Assessment investigation revealed the proposed alignment crosses areas where registered Native Title Claims exist. The Kabi Kabi First Nation currently have a registered Native Title claim over the B2N Project Area.
Under the NTA, before a determination is made by the Federal Court, registered Native Title claimants have access to certain procedural rights while any application is being considered for activities that affect their Native Title rights and interests.
The procedural rights include the right to be consulted, the opportunity to comment, or the same rights as a freehold landowner. The Project will therefore be required to consult with the registered native title claimant in accordance with either section 24KA of the NTA and/or section 24MD of the NTA.
Section 24KA of the NTA provides for the validation of future acts that permit the construction, operation, use, maintenance and repair of a railway for the general public. Native Title rights and interests would not be extinguished but only be suppressed for the duration of the B2N Project.
Section 24KA of the NTA does not permit the inclusion of land and waters into the State’s Perpetual Head Lease. The grant of a Perpetual Head Lease is a separate “future act” which requires Native Title to be extinguished. Native Title can be extinguished either by a voluntary ILUA (Indigenous Land Use Agreement) with the Native Title party, or through compulsory acquisition under section 24MD. The Native Title claimants will be entitled to the same procedural rights that a freehold landowner receives under the Acquisition of Land Act 1967.
The Native Title Assessments undertaken have identified five waterways and two non-freehold lands over which Native Title still exist, shown in Table 54.
Planning, Land Use and Property
149
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Table 54: Land/ Water where Native Title exists
LAND / WATERWAY TENURE PROCEDURAL RIGHTS
Tibrogargan Creek USL s.24KA
Coonowrin Creek USL s.24KA
Coochin Creek USL s.24KA
Mellum Creek USL s.24KA
Addlington Creek USL s.24KA
Lot 301 on M332061 Reserve s.24KA
Lot 611 on FTY1877 Beerburrum State Forest s.24KA and s.24MD
Five waterways will be subject to section 24KA of the NTA. The Kabi Kabi First Nation claimants will be notified in writing and given the opportunity to comment.
A section of the Beerburrum State Forest located to the North of Beerburrum Railway Station is required for the railway alignment and will ultimately be included into the State’s Perpetual Head Lease. Native Title rights and interests will need to be extinguished under section 24MD of the NTA.
The Department of Transport and Main Roads will fully examine any legal requirements concerning any registered Native Title Claims as part of the judicial process.
10.3.6 Observed and Impacted Land Uses
The rail upgrade and associated road works have been designed to minimise changes to the Protected Corridor between Beerburrum and Landsborough. However, grade separation at Barrs Road and Landsborough (Caloundra Street) will result in property impacts identified in the B2N Project Grade Separation Options Report.
Track duplication commences to the north of Beerburrum Station, with a proposed extension to the station car park located on the eastern side of the existing station. This area is zoned as community facilities, with the exception of the residential property identified as ‘precinct LDR1 (Protected Housing Area). As noted in Chapter 8, this property is of local heritage significance. It is assumed to be the former station masters’ house and requires further consideration in future stages of design refinement. Currently the area surrounding this property is cleared and in use as station car parking.
Continuing north, the duplicated track crosses under a new bridge for Beerburrum Road, and traverses an area of Beerburrum State Forest, comprising native vegetation. Works also include a realignment of the intersection of Beerburrum Road/ Steve Irwin Way/ Red Road, within the existing road reserve.
Approximately 1.2km north of the Beerburrum Road bridge, the Project Area crosses the existing rail corridor and the Matthew Flinders Rest Area on Tibrogargan Creek. It then continues on the west side of the existing rail corridor, traversing sections of Beerburrum West State Forest, including the former Forestry Nursery site. Reconfiguration of Caves Road/ Evans Road and Berteaus Road will be required in this area.
The Project Area then crosses back over the existing rail corridor and continues on the eastern side, with realignment of approximately 1.3km of Steve Irwin Way. The rail and associated road realignment impacts a number of rural zoned, agricultural properties and a caravan park zoned as community facilities area. These property impacts area contained within the previously identified upgrade corridor.
The duplication works continue north, avoiding impacts to the Glass House Mountains National Park, and generally fitting within the existing rail reserve.
The proposed closure of the existing Barrs Road open level crossing will require construction of a new road link along the existing Barrs Road alignment, connecting to Coonowrin Road. This extension of Barrs Road will be predominantly within an unformed road reserve. However, it will impact a large parcel of freehold land and include a bridge over Coonowrin Creek. The realignment of the Burgess Street bridge will also impact several freehold private properties.
Planning, Land Use and Property
150
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
The duplicated track then aligns to the existing short section of dual track that passes through Glass House Mountains Station. No changes to this station are proposed. The upgrade continues online for a short distance, before shifting east, impacting the edge of several rural properties, historically used for growing pineapples. The duplication works then shift back predominantly within the existing corridor, with some further minor edge effects to rural properties on the west, just prior to the crossing of Coochin Creek. A residential subdivision, with an existing noise barrier, is located on the east side of the railway prior to the crossing of Coochin Creek. Approaching Beerwah, the works will be contained within the existing rail reserve and passing through Beerwah Station. No changes are proposed to the Beerwah Station. North of Beerwah Station, there may be some minor impacts to Mill Park.
The duplication works are located within the existing rail/ protected corridor between Beerwah and Landsborough. However, there may be some impacts to Railway Parade, which runs along the western edge of the existing rail corridor.
In Landsborough, the duplication works and western park and ride extension are within existing rail reserve. The proposed grade separation of Caloundra Street has the potential to impact freehold and reserve lands. These include the parkland reserve where Morris House and the CWA hall are located and an area of reserve along Mellum Creek. Properties zoned for community facilities and low density residential will also be impacted by the grade separation on the western side. Commercial properties including the service station would be impacted by the east. Further consultation with council will be required to optimise the grade separation and ensure it does not adversely impact the proposed Arts, Community and Heritage Precinct south of Maleny Street.
Expansion of the park and ride on the eastern side of Landsborough Station has been identified on properties zoned medium impact industry zone.
North of Landsborough station, the duplication works are proposed to continue for approximately 1.3km. This may result in some edge impacts to the Landsborough Sportsfield, but is not anticipated to require land requirements from the Dularcha National Park.
Station works at Mooloolah Station will be contained within the existing rail reserve and will not significantly alter the current land use in that area.
Station works and passing loop extensions at Eudlo are within existing rail reserve or railway lands. The station upgrade will result in land requirement from the area known as ‘Federation Walk’, and will require further detailed planning and consultation with stakeholders and the community to address the impacts to the edge of this area.
Station works at Palmwoods are within the existing rail reserve, and have been designed to avoid impacts to the heritage buildings discussed in Chapter 8.
Station works and the extension of the passing loop Woombye will occur within the existing rail reserve, with potential for impacts to one private property. The proposed closure of a section of Back Woombye Road and realignment of Barts Street will divert traffic along a previously dead end road. Further consultation and planning will be required to address the changes resulting from this road realignment.
The expansion of car parking at Nambour is proposed to be within existing rail lands, and no impacts are anticipated to property or existing or proposed land uses.
10.3.7 Property Impacts
Property impacts associated with the protected corridor were identified during previous phases of investigation (Caboolture to Landsborough Rail Study and Trackstar 2007). New property impacts have been defined, associated with:
• new grade separations not identified in previous phases of work • station upgrades and park and ride expansions.
Table 56 lists the properties identified as being located within the B2N Project Area. It is noted that three national park lots were identified as intersecting the Project Area, but a visual inspection indicated that this was due to poor geometry in the GIS spatial layers, so these lots have been excluded from Table 56. As noted above, the B2N Project will avoid the Glass House Mountains and Dularcha National Parks.
There are also a number of properties located outside the Project Area, but within a 50m buffer, which may be impacted by Project activities. A list of these properties is provided in Appendix H.
Planning, Land Use and Property
151
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Table 55: Properties located within the Project Area
LOT NUMBER SUNSHINE COAST PLANNING SCHEME ZONING TENURE
Beerburrum
853SP168402 Rural Zone Freehold
896SP168402 Rural Zone Freehold
611FTY1877 Rural Zone State Forest
Beerwah
751CG6070 Community Facilities Zone Reserve
3RP217235 Environmental Management and Conservation Zone Reserve
10SP183159 Low Density Residential Zone Freehold
11SP183159 Low Density Residential Zone Freehold
12SP183159 Low Density Residential Zone Freehold
13SP183159 Low Density Residential Zone Freehold
14SP183159 Low Density Residential Zone Freehold
15SP183159 Low Density Residential Zone Freehold
1SP183161 Low Density Residential Zone Freehold
22RP183306 Low Density Residential Zone Freehold
23RP183306 Low Density Residential Zone Freehold
26RP183306 Low Density Residential Zone Freehold
27RP183306 Low Density Residential Zone Freehold
28RP183306 Low Density Residential Zone Freehold
29RP183306 Low Density Residential Zone Freehold
2SP183161 Low Density Residential Zone Freehold
30RP183306 Low Density Residential Zone Freehold
31RP183306 Low Density Residential Zone Freehold
3SP183161 Low Density Residential Zone Freehold
4SP183161 Low Density Residential Zone Freehold
5SP183160 Low Density Residential Zone Freehold
7SP183160 Low Density Residential Zone Freehold
8SP183160 Low Density Residential Zone Freehold
13SP229833 Freehold
417B4414 Open Space Zone Reserve
2RP107762 Rural Zone Freehold
2RP123640 Rural Zone Freehold
2SP229834 Specialised Centre Zone Freehold
Glass House Mountains
11RP174795 Limited Development (Landscape Residential) Zone Freehold
12RP174795 Limited Development (Landscape Residential) Zone Freehold
31CG3387 Limited Development (Landscape Residential) Zone Freehold
32CG3458 Limited Development (Landscape Residential) Zone Freehold
5RP127108 Local Centre Zone Freehold
7RP127108 Local Centre Zone Freehold
898CG4790 Local Centre Zone Freehold
9RP168054 Local Centre Zone Freehold
77RP223272 Medium Density Residential Zone Freehold
Planning, Land Use and Property
152
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
LOT NUMBER SUNSHINE COAST PLANNING SCHEME ZONING TENURE
136CG757 Rural Zone Freehold
1RP167515 Rural Zone Freehold
1RP177687 Rural Zone Freehold
1RP214941 Rural Zone Freehold
1RP7660 Rural Zone Freehold
21RP153799 Rural Zone Freehold
2RP177687 Rural Zone Freehold
2RP72081 Rural Zone Freehold
3RP222399 Rural Zone Freehold
48CG3132 Rural Zone Freehold
49CG2193 Rural Zone Freehold
4RP222399 Rural Zone Freehold
5RP222399 Rural Zone Freehold
777CG1135 Rural Zone Freehold
793SP149904 Rural Zone Freehold
8CG105 Rural Zone Freehold
589FTY1876 Rural Zone State Forest
Landsborough
1RP76609 Community Facilities Zone Freehold
2RP111079 Community Facilities Zone Freehold
2RP76609 Community Facilities Zone Freehold
3RP76609 Community Facilities Zone Freehold
455CG2348 Community Facilities Zone (Landsborough state school) Freehold
4CG4024 Community Facilities Zone Reserve
711CG6392 Community Facilities Zone Reserve
763CG6262 Community Facilities Zone Reserve
999CG6008 Environmental Management and Conservation Zone Reserve
99SP126335 Environmental Management and Conservation Zone Reserve
101SP290341 Low Density Residential Zone Freehold
16L2588 Low Density Residential Zone Freehold
1RP177390 Low Density Residential Zone Freehold
1RP81152 Low Density Residential Zone Freehold
1SP201520 Low Density Residential Zone Freehold
1SP248298 Low Density Residential Zone Freehold
21L2589 Low Density Residential Zone Freehold
22SP129708 Low Density Residential Zone Freehold
236RP864765 Low Density Residential Zone Freehold
23RP213968 Low Density Residential Zone Freehold
24RP213968 Low Density Residential Zone Freehold
25RP213968 Low Density Residential Zone Freehold
28RP213968 Low Density Residential Zone Freehold
2RP177390 Low Density Residential Zone Freehold
2RP81152 Low Density Residential Zone Freehold
2SP201520 Low Density Residential Zone Freehold
Planning, Land Use and Property
153
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
LOT NUMBER SUNSHINE COAST PLANNING SCHEME ZONING TENURE
2SP248298 Low Density Residential Zone Freehold
37L2589 Low Density Residential Zone Freehold
4RP168075 Low Density Residential Zone Freehold
4SP195902 Low Density Residential Zone Freehold
4SP201520 Low Density Residential Zone Freehold
55RP45367 Low Density Residential Zone Freehold
61SP159196 Low Density Residential Zone Freehold
62SP159196 Low Density Residential Zone Freehold
63SP159196 Low Density Residential Zone Freehold
65SP159196 Low Density Residential Zone Freehold
66SP159196 Low Density Residential Zone Freehold
67SP159196 Low Density Residential Zone Freehold
68RP45367 Low Density Residential Zone Freehold
68SP159196 Low Density Residential Zone Freehold
0BUP5392 Medium Density Residential Zone Freehold
74RP8439 Medium Density Residential Zone Freehold
15RP201396 Medium Impact Industry Zone Freehold
16RP201396 Medium Impact Industry Zone Freehold
17RP201396 Medium Impact Industry Zone Freehold
18RP201396 Medium Impact Industry Zone Freehold
43RP45367 Medium Impact Industry Zone Freehold
9RP201396 Medium Impact Industry Zone Freehold
512CP835985 Open Space Zone Reserve
17RP45367 Specialised Centre Zone Freehold
18RP45367 Specialised Centre Zone Freehold
19RP45367 Specialised Centre Zone Freehold
42RP45367 Specialised Centre Zone Freehold
301M332061 Sport and Recreation Zone/Environmental Management and Conservation Zone Reserve
Eudlo
1RP140250 Rural Zone Freehold
2SP145971 Rural Zone Freehold
Nambour
10SP110903 Community Facilities Zone Freehold
9SP110903 Community Facilities Zone Freehold
5RP907803 Limited Development (Landscape Residential) Zone Freehold
1SP263819 Major Centre Zone Freehold
Woombye
1RP159791 Low Density Residential Zone Freehold
7RP56696 Low Density Residential Zone Freehold
1SP295563 State Land
543CG3620 Rural Zone Freehold
Planning, Land Use and Property
154
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
10.4 Addressing Land Use Impacts Feedback from community information sessions in 2016 identified land use and planning concerns associated with the proposed grade separation option at Landsborough. Other issues raised include the impact to Matthew Flinders Rest Area north of Landsborough, and integration with existing SCC planning and Place Making projects in the area.
Ongoing consultation with newly affected landowners and business owners, as well as continuation of consultation with landowners impacted by the Protected Corridor, will be required.
Ongoing consultation with SCC Councillors and Officers will be necessary to ensure the optimum outcome for these hinterland townships and surrounding areas. Opportunities for master planning in station precincts should be aligned with council master planning and street scape treatment plans, so that benefits can be optimised.
Resumption, tenure, Native Title and State Forest revocation activities will need to be progressed as part of the corridor acquisition in future stages of B2N Project delivery.
Landscape and Visual Amenity
155
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
11 Landscape and Visual Amenity 11.1 Introduction A review of the landscape context has been undertaken for the B2N Project, particularly focusing on new B2N Project elements with the potential to alter the existing hinterland / railway township environment.
11.2 Assessment Methods The landscape and visual amenity review was undertaken with reference to the following:
• SCC Planning Scheme, 2014 • available land use mapping (Queensland Globe and SCC Local Area Maps and interactive “MyMaps”) • review of aerial imagery, 2019 • review of previous landscape and visual impact commentary from the Beerburrum to Landsborough and
Landsborough to Nambour studies.
The residual impact assessment adopted elsewhere in this REF has not been applied to this Chapter due to the nature of the impacts and ongoing actions that will be part of future stages of B2N Project delivery.
11.3 Existing Environment The B2N Project is located within the Sunshine Coast hinterland in a region characterised by semi-rural agricultural holdings, small townships, and tracts of National Park and State Forests. Key landscape characteristics include:
• distinctive topographic mix of coastal plains to the east leading into the steep undulating land of the Great Dividing Range to the west
• National Parks, State Forests, native vegetation and farmland • settlement areas particularly around the existing railway stations • scattered individual rural dwellings and rural residential subdivisions • minor roads connecting small settlements to regional civic centres, tourist attractions, individual properties and
railway stations • the peaks of the Glass House Mountains as a visible backdrop to the immediate west of the Project Area.
A section by section description of the landscape and surrounds is provided in Table 56.
Table 56: Landscape Context
SECTION DESCRIPTION
Beerburrum to Glass House Mountains township
This section of the Project Area traverses a gently undulating landscape at the base of Mount Beerburrum and Mount Tibrogargan, crossing over Tibrogargan Creek near the Matthew Flinders Rest Area. The existing line passes through cuttings and on embankments, running parallel to the Steve Irwin Way.
Glass House Mountains to Beerwah
This section of the Project Area is relatively flat, characterised by farmland, semi-rural holdings, tracts of bushland and medium-density residential developments.
Beerwah to Landsborough The Beerwah to Landsborough section is comparatively flat, and runs parallel to Steve Irwin Way.
Landsborough The Landsborough township is relatively flat, and characterised by several heritage precincts, a commercial precinct to the west and some industrial land uses to the east. The station and level crossing are prominent features in the townscape.
Mooloolah Station Mooloolah Station is located to the south east of the Mooloolah town centre, fringed by open space (the Pony Club) with a significant feature being the timber pedestrian footbridge to the north of the Station.
Eudlo Station Eudlo Station is tucked between the village centre, and an area locally known as ‘Federation Walk’ This area was a community planting project and provides a bushland backdrop to the minor Eudlo Station infrastructure.
Landscape and Visual Amenity
156
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
SECTION DESCRIPTION
Palmwoods Station Palmwoods township is located on a hill side, sloping from Kolora Park leading up to the commercial centre and surrounding residential areas. Palmwoods Station is adjacent to Kolora Park, with the main town entrance statement the existing low height rail bridge.
Woombye Station Woombye Station is located on the western fringe of the Woombye commercial centre, dropping off to the west where playing fields and the new stabling facility are located.
Nambour Station Nambour station is located adjacent to Petrie Creek, with the township of Nambour a mix of commercial, industrial and residential outlooks.
11.4 Potential Impacts Potential impacts associated with the B2N Project are likely to occur during both construction and operation and are outlined below. Opportunities for landscape and amenity improvements are identified, however these will require further consideration and confirmation in future stages of design.
11.4.1 Construction
Temporary laydown areas and work sites will be active during construction, introducing a mix of different visual elements into the local landscape. This will be most noticeable from urban edges and the local road network.
11.4.2 Operation
Potential landscape and visual impacts and opportunities as a result of the B2N Project implementation are described in Table 57.
Table 57: Potential visual impacts and opportunities
SECTION DESCRIPTION
Beerburrum to Glass House Mountains township
The B2N Project will result in the realignment of this section of the railway, with corresponding realignment of sections of the Steve Irwin Way. The Matthew Flinders Rest Area will be impacted by the B2N Project, resulting in the loss of a scenic rest stop. Expansion of the Beerburrum Station park and ride should be subject to further urban design and landscaping, as it is proposed to occur around an existing residential property. The extension of Barrs Road, bridge over Coonowrin Creek and reconstruction of Burgess Street will require further design development to address visual impacts and loss of recreational amenity. No changes are proposed to the Glass House Mountains Station or the existing Beerburrum Station infrastructure.
Glass House Mountains to Beerwah
Rail upgrades on this section are not anticipated to significantly alter existing views and vistas as the rail will continue at similar grade and follow similar alignment.
Beerwah to Landsborough
Similar to the Glass House Mountains to Beerwah section, rail upgrades on this section are not anticipated to significantly alter existing views and vistas as the rail will continue at similar grade and follow similar alignment. Mill Park and Simpson Park are adjacent to the western side of the existing rail corridor north of Beerwah Station, with minor edge impacts anticipated during construction. No changes are proposed to Beerwah Station.
Landsborough
The proposed grade separation at Landsborough, involving a new road bridge over rail, approximately 6-7m above the existing rail level, is expected to significantly alter the local landscape and character. Further urban design, master planning and consultation with the community, businesses and key stakeholders will be necessary to develop the best possible outcome for Landsborough. Upgrades to the Landsborough park and ride facilities may also alter views and vistas within the station precinct. While not likely to be viewed from residences within the community given the flat topography, the eastern car park extension will be a prominent feature at the juncture of Maleny Street (Landsborough Maleny Road) and Steve Irwin Way. Existing heritage features (air raid shelter and locomotive turning triangle) will be retained. Further urban design, master planning and consultation with the community, businesses and key stakeholders should be undertaken in association with the progression of the grade separation and
Landscape and Visual Amenity
157
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
SECTION DESCRIPTION
park and ride urban design. No changes are proposed to the Landsborough station infrastructure or heritage elements.
Mooloolah Station
Works at Mooloolah Station include duplication of the platform, lifts, and an overbridge. This will introduce new visual elements, and should be undertaken in a manner sympathetic to the existing tin and timber structures at the station. Retention of the existing timber footbridge should be addressed in future stages of design.
Eudlo Station
Works at Eudlo Station include duplication of the platform, lifts, and an overbridge. This will introduce new visual elements, and should be undertaken in a manner sympathetic to the regenerated bushland on the western side (Federation Walk), and the character of the Eudlo township.
The passing loop extensions south of Eudlo station are within existing rail reserve or railway lands and will follow similar alignment and grade. It is not expected to alter the current landscape or visual amenity in that area.
Palmwoods Station
Works at Palmwoods Station include duplication of the platform, lifts, and an overbridge. This will introduce new visual elements, and should be undertaken in a manner sympathetic to the surrounding townscape. This includes consideration of the existing heritage structures at the station. The car park is directly adjacent to residential properties, works at this station are likely to alter views for those properties that currently overlook the station and car park.
Woombye Station
Station works and the extension of the passing loop at Woombye will follow a similar alignment and grade to the existing line and will occur within the existing rail reserve with potential for visual impacts to one private property. The proposed closure of a section of Back Woombye Road and realignment of Barts Street will divert traffic along a previously no through road. Works at Woombye Station include duplication of the platform, lifts, and an overbridge. This will introduce new visual elements, and should be undertaken in a manner sympathetic to the character of the Woombye area.
Nambour Station The expansion of car parking at Nambour is proposed to be within existing rail lands, with marginal changes anticipated on the fringes of the rail corridor. Station upgrade works at Nambour are being progressed by Queensland Rail.
Resource Use and Management
158
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
12 Resource Use and Management 12.1 Introduction This Chapter provides a summary of information relevant to the identification and investigation of potential risks associated with the use and management of resources, and of the generation of waste as a result the proposed Project activities.
12.2 Assessment Methods This aspect documents the potential impacts to resources, their use and management during the life of the B2N Project and the potential to create wastes and how these are to be managed. Information is drawn from the B2N Project design including a review of general construction activities, construction materials and ancillary activities anticipated.
12.3 Potential Impacts Generally, the potential resource impacts fall under a limited number of categories including wastage of resources, missed opportunities to salvage or re-use resources, generation of avoidable wastes and contamination.
12.3.1 Planning and Detailed Design
No impacts associated with the planning and design of the B2N Project are anticipated. However, the planning and design stage allows for the consideration and management of potential impacts during later stages of the B2N Project. Consideration should be given to:
• Balancing the earthwork cut and fill and minimising where possible the distance travelled between cut and fill locations. Where fill is to be brought onsite, designing the receipt of that fill to be the shortest possible distance to the source.
• Designing water management structures to capture sufficient water for use onsite and access to these areas so the water can be collected and used.
12.3.2 Construction
Construction Materials and Natural Resources
Construction materials will need to be brought onsite, the following opportunities to incorporate sustainability initiatives into the B2N Project will be considered:
• energy efficient measures to reduce fuel and energy usage • conservation of water resources • reuse of materials and the use of recycled construction materials • minimisation of the generation of waste.
Resources are finite and are often expensive to acquire or relocate. Resources likely to be available and that could be considered for recovery during construction activities include:
• mature vegetation including large timbers which could be recovered for use in fauna furniture and/or mulched for use in landscaping and revegetation
• topsoil which could be reused in landscaping and revegetation • earthwork spoil which could be used as fill in locations along the corridor where excess is required.
Other natural resources are likely to be required to be brought to site (i.e. aggregate materials such as sand, gravel, cement, steel and petroleum products). Consideration could be given to reusing recovered materials or using recycled materials where possible.
Demolition of the existing rail would produce ballast rock. QR has a program where ballast rock is reclaimed and the larger rock is cleaned and reused, and smaller rock is crushed and recycled as road base or fill material.
Water
Water is an expensive and finite resource that could be considered regarding the opportunity to harvest to supplement construction requirements, and also to reduce the risks associated with contaminated discharge from the site. The following management opportunities could be considered:
Resource Use and Management
159
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
• where possible, use of potable water where non-potable water could be used should be avoided • construction of sediment basins as part of the erosion and sediment control management measures:
− for use as a source of non-potable water in dust suppression and construction activities − to avoid the need for treatment and discharge of collected surface water to nearby watercourses and the
environmental risks associated with this. • use of waterless techniques where possible.
Waste
Current waste facilities in the Sunshine Coast region provided by the SCC include:
• Beerwah Resource Recovery Centre • Buderim Resource Recovery Centre • Caloundra Landfill and Resource Recovery Centre • Kenilworth Transfer Station • Mapleton Transfer Station • Nambour Landfill and Resource and Recovery Centre • Witta Resource Recovery Centre • Yandina Transfer Station.
These facilities offer a range of disposal options. However, not all waste streams can be disposed at all facilities.
Key waste streams likely to be generated during construction including available facilities for disposal are provided in Table 58.
Table 58: Construction Waste Streams
WASTE STREAM DESCRIPTION AVAILABLE DISPOSAL FACILITY
Demolition wastes from roads, rail and buildings
Existing structures located within the corridor and associated works that will be demolished. Wastes will include wood, pipe work, concrete and bitumen, steel and other metals, glass and plastics. Building materials could possibly contain asbestos (a regulated waste).
Buderim, Caloundra and Nambour
Shrubs and trees From the clearing of vegetated areas including both native and exotic vegetation species. All locations except Yandina
Excavation waste
Excavated material will be used as earth-fill embankments or structures where the material is suitable which will minimise spoil generated. After geotechnical appraisal, some sections of subsoil may require removal and replacement due to engineering unsuitability.
Caloundra and Nambour
Packaging materials
Materials delivered to site often come with packaging materials. This consists largely of pallets, crates, cartons, plastics and wrapping materials, all of which need to be disposed of once the product has been utilised. It should be noted that minimisation of packaging of raw products will be strongly encouraged.
Buderim, Caloundra and Nambour
Wastes from construction equipment maintenance
Various heavy vehicles and construction equipment will be utilised for the duration of the construction phase. Liquid hazardous wastes from cleaning, repairing and maintenance of this equipment will be generated. Likewise, leakage or spillage of fuels/oils within the site need to be managed and disposed of appropriately. These are all likely to be regulated wastes.
All locations.
Domestic quantities (20L) maximum) free, commercial quantities (>20L) accepted with charges.
Contaminated soil There may be contaminated waste from one or more of the potentially contaminated land parcels (refer section 6.3.5).
Caloundra and Nambour.
By application only.
General Wastes This includes site office waste, scrap materials and biodegradable wastes. All locations.
Resource Use and Management
160
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Where wastes are not accepted by facilities within the Sunshine Coast, these materials may require transport to the greater Brisbane area for disposal at a licenced facility.
Where wastes are deemed to be ‘regulated’ under the Environmental Protection Regulation 2019, wastes are to be managed and tracked in accordance with the associated requirements.
Potential impacts associated with these waste streams could include:
• unnecessary consumption of materials and generation of wastes • ground contamination and water quality impacts as a result of the generation of general wastes, demolition and
construction wastes • water quality impacts due to vegetation removal, topsoil removal, earthworks, overburden, and stockpiling • ground contamination as a result of contaminated soils and overburden (from spills or reuse of excavated
material from contaminated sites) • water quality impacts and ground contamination as a result of hazardous wastes • increased energy/fuel use as a result of double handling of materials or inefficient transportation of the
materials.
Energy
The primary sources of energy use during construction will be electricity for ancillary activities such as lighting, workplace cooling and heating and general power requirements, and non-renewable fossil fuels for operating vehicles, plant and equipment.
This is both a cost to the B2N Project and a source of greenhouse gas emissions to the atmosphere. Consideration should be given to the reduction of energy use wherever possible.
12.3.3 Operation and Maintenance
Impacts to environmental values are anticipated to be low resulting from inappropriate use and management of resources as a consequence of operation of the rail. QR has an Environment Policy and a documented Safety and Environmental Management System to communicate environmental requirements to staff.
QR monitors its energy use and emissions and provides annual reporting to the Federal Government. The largest portion of carbon emissions arise from the supply of traction electricity to electric trains. QR have accordingly developed measures to minimise and optimise the supply and use of energy along the network.
QR has all waste disposed of by licensed waste contractors. Waste is recycled where possible, including scrap metal, timber, paper, industrial waste, waste oils, as well as some hazardous waste.
Very large volumes of ballast rock are used to provide a foundation for the network’s track and sleepers. Over time, ballast rock becomes worn down meaning that its drainage capacity is reduced, due to the build-up of dust and soil fines. Large ballast renewal machines work to help to turn over the ballast to increase the service life of the ballast. At the end of its service life ballast needs to be removed and replaced.
QR segregates and stores ballast spoil. The ballast spoil is then sieved, screened and separated into re-usable product. The large ballast spoil is screened and cleaned for reuse. The smaller ballast rock is crushed down and used as road base or fill material.
12.4 Proposed Mitigation Measures Mitigation measures proposed to minimise the impacts are listed below.
• wastage of resources − recover mature vegetation including large timbers for use in fauna furniture and/or mulched for use in
landscaping and revegetation − recover topsoil for use in landscaping and revegetation − recover spoil for use as fill where the spoil is geotechnically appropriate − construct sediment basins as part of the erosion and sediment control management measures for use of
collected water during construction − incorporate energy reduction initiatives for management of lighting, workplace cooling and heating and
general power requirements
Resource Use and Management
161
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
− incorporate fuel use reduction/efficiency initiatives to reduce the use of non-renewable fossil fuels. • missed opportunities to salvage or re-use resources
− where viable, import recovered or recycled materials for use during construction − recover ballast rock for recycling by QR.
• generation of avoidable wastes − implement Waste and Resource Management hierarchy principle in managing all wastes: Avoid, Reduce,
Re-use, Recycle, Recover, Treat, Dispose − no burning or burial of wastes onsite − disposal is to be offsite and undertaken by an adequately licenced sub-contractor to an appropriately
licensed facility − during construction, provide for recycling as well as general waste collection − during operation, provide adequate waste and recycling receptacles at stations.
• contamination − ensure sufficient waste storage facilities are available onsite, with appropriate bunding / protection and
access to spill kits − locate waste storage areas appropriately, i.e. away from watercourses − regular removal of waste to appropriate facility − no burning or burial of waste onsite.
12.5 Residual Impact Assessment With the implementation of the mitigation measures outlined in Table 59, it is anticipated that the B2N Project’s potential impacts will be minor and manageable and may make positive contributions in some regards.
Resource Use and Management
162
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Table 59: Residual Impact Assessment, Resource Use and Management
FACTOR PHASE POTENTIAL IMPACT (WITHOUT MITIGATION)
MITIGATION AND MANAGEMENT RESIDUAL EFFECTS DURATION LIKELIHOOD IMPACT
ASSESSMENT
Wastage of resources including mature vegetation and topsoil
Construction Lost resource that could be freely incorporated into landscaping and revegetation
Recover mature vegetation including large timbers for use in fauna furniture and/or mulched for use in landscaping and revegetation
Recover topsoil for use in landscaping and revegetation
Minimised waste generation.
Improved revegetation outcomes.
Reduced handling/transport requirements.
Reduced need for imported resources.
Short term Possible Positive
Wastage of resources including earthwork spoil
Construction Lost resource that could be freely used as fill
Recover spoil for use as fill where the spoil is geotechnically appropriate and contaminated lands procedures allow.
Minimised waste generation.
Reduced handling/transport requirements.
Reduced need for imported resources.
Short term Possible Positive
Use of virgin natural resources when recovered or recycled materials would suffice
Construction Use of additional resources with associated extraction impacts
Where viable, import recovered or recycled materials for use during construction
Reduced waste to landfill.
Reduced impacts associated with extraction of virgin material.
Long term Possible Positive
Viable ballast rock sent to landfill Construction
Loss of resource
Missed opportunity to reclaim a resource
Recover ballast rock for recycling by QR
Recovered resource that would otherwise be used as fill material or sent to landfill.
Long term Possible Positive
Use of potable water where non-potable would suffice
Construction Loss of resource
Missed opportunity to reclaim a resource
Construct sediment basins as part of the erosion and sediment control management measures for use in construction
Reduced use of potable water
Reduced discharge of surface water to nearby watercourses
Short term Possible Positive
Generation of avoidable wastes Construction
Increased waste to landfill.
Increased handling and transport.
Implement Waste and Resource Management hierarchy principle in managing all wastes across the site: avoid, reduce, reuse,
Reduced waste generated Short term Possible Positive
Resource Use and Management
163 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
FACTOR PHASE POTENTIAL IMPACT (WITHOUT MITIGATION)
MITIGATION AND MANAGEMENT RESIDUAL EFFECTS DURATION LIKELIHOOD IMPACT
ASSESSMENT
Missed opportunity for recovery of a resource
recycle, recover, treat, dispose
Demolition wastes
Recycle materials
Recover concrete for use in earthworks
Offsite disposal to a recycling facility if opportunities for beneficial reuse on site not identified
Reduced waste generated Short term Possible Positive
Shrubs and trees
Minimise clearing extents
Reuse cleared vegetation onsite
Remove to composting facility if not suitable for reuse onsite
No burning or burial of wastes onsite
Reduced waste generated Short term Possible Positive
Excavation waste
Reuse onsite where suitable
Offsite disposal by adequately licenced sub-contractor to a licensed facility, in accordance with Soil Disposal Permit
Reduced waste generated Short term Possible Positive
Packaging materials
Select products with minimal packaging or recyclable packaging where practical, seek opportunities to purchase in bulk where this
Reduced landfill waste generated Short term Possible Positive
Resource Use and Management
164 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
FACTOR PHASE POTENTIAL IMPACT (WITHOUT MITIGATION)
MITIGATION AND MANAGEMENT RESIDUAL EFFECTS DURATION LIKELIHOOD IMPACT
ASSESSMENT
reduces waste packaging material
Offsite recycling or disposal
No burning of wastes onsite
Wastes from construction equipment maintenance
Where unable to reuse, offsite disposal by adequately licensed (ERA) subcontractor to a licensed facility
Reduced waste generated Short term Possible Positive
Non-hazardous liquid wastes
Offsite disposal by adequately licensed (ERA) sub-contractor to a licensed facility
Reduced waste generated Short term Possible Positive
Contaminated soils
Offsite disposal by adequately licensed sub-contractor to a licensed facility, in accordance with Soil Disposal Permit
Reduced waste generated Short term Possible Positive
General Wastes
Provide for recycling as well as general waste collection
No burning or burial of wastes to occur on the Project.
Reduced waste generated Short term Possible Positive
Wastage of Energy Resources Construction Increased GHG emissions.
Incorporate energy reduction initiatives for management of lighting, workplace cooling and heating and general power requirements
Reduced GHG emissions Short term Possible Positive
Resource Use and Management
165 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
FACTOR PHASE POTENTIAL IMPACT (WITHOUT MITIGATION)
MITIGATION AND MANAGEMENT RESIDUAL EFFECTS DURATION LIKELIHOOD IMPACT
ASSESSMENT
Incorporate fuel use reduction/efficiency initiatives to reduce the use of non-renewable fossil fuels
Reduced GHG emissions Short term Possible Positive
Contamination of land or waterways Construction
Onsite storage of waste and/or hazardous materials releases contaminants or pollutants to land or waterways
Ensure sufficient waste storage facilities are available onsite, with appropriate bunding / protection and access to spill kits
Locate waste storage areas appropriately, i.e. away from watercourses
Regular removal of waste
No contamination or pollution of waterways as a result of waste management practices.
Short Term to Long Term
Unlikely Negligible
Contamination of land or waterways from rail activities including station, sub-stations and stabling yard
Operation
Onsite storage of waste and/or hazardous materials releases contaminants or pollutants to land or waterways
Ensure sufficient waste storage facilities are available onsite, with appropriate bunding / protection, and are regularly maintained
Regular removal of waste to appropriate facility
No burning or burial of waste onsite
No contamination or pollution of waterways as a result of waste management practices
Long term Unlikely Negligible
Waste at stations Operation Waste is generated during operation of rail stations and stabling
Provide adequate waste and recycling receptacles at stations
Implement operational waste management plan
Waste deposited at stations requires regular collection Long Term Certain Negligible
Legislative Requirements
166 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
13 Legislative Requirements 13.1 Commonwealth Approvals 13.1.1 Environment Protection and Biodiversity Conservation Act 1999
The Beerburrum to Landsborough Project was referred under the EPBC Act by QR- SEQIP Rail in November 2006 and was determined to be ‘not a controlled action’. The Landsborough to Nambour Rail Project was also referred under the EPBC Act by Queensland Transport (now TMR), and similarly determined to be ‘not a controlled action’ in 2008.
The environmental approvals report prepared for the Preliminary Evaluation phase discussed the previous EPBC Act referrals for the Beerburrum to Landsborough and Landsborough to Nambour Rail Projects. Although both projects were determined to not be controlled actions at the time of referral, the Preliminary Evaluation Environmental Approvals Report also identified some EPBC Act Referral triggers (i.e. the koala and the Giant Barred Frog).
Targeted fieldwork and research identified potential habitat for MNES in the Project Area; these MNES and the likelihood of occurrence are described in Chapter 7 of the REF. Based on desktop mapping it was previously thought the koala would be the key threatened species triggering assessment. However, as noted in Chapter 7, targeted surveys did not identify koala presence although suitable habitat is located in the Project Area. Further survey will be required to comply with the EPBC Act Referral Guidelines for the Vulnerable koala.
Confirmation was sought from the Department of the Environment (now Department of the Environment and Energy - DoEE) during the preparation of the Preliminary Evaluation regarding the status of the previous EPBC Act referrals. The advice was provided verbally and indicated that the B2N Project would likely be considered a ‘different action’ to the action previously referred for the Landsborough to Nambour Project, as it was not commenced within the nominated timeframes. Verbal advice from DoEE also indicated that as the Beerburrum to Landsborough Project was not constructed within the original timeframe, it would likely be considered a ‘different action’ to the action that was originally referred. In addition, the proponent for the Beerburrum to Landsborough section and the spatial extents of the projects have both changed since these referrals.
For the B2N Project, it is recommended that:
• targeted field and desktop assessment is undertaken to confirm the presence of MNES, identify specificmanagement strategies, and conclusively assess whether significant impacts are likely
• a referral under the EPBC Act is submitted to provide legal and program certainty• options for staged consideration of the B2N Project (i.e. separate referrals, under section 74A of the EPBC Act)
should also be explored.
Submission of a new referral under the EPBC Act is recommended for the B2N Project on the basis that:
• advice indicates that DoEE would consider the B2N Project a new action• species distributions change over time (i.e. some species/habitat may no longer be present in the project area,
while others may now occur), and there have been changes in the species included in the EPBC Act since 2006and 2008
• a review of the Significant Impact Assessment would be prudent given the changes in the Project Area and theabove
• there is a public interest in the project and its status as a controlled action, and submitting a new referral willmitigate risks associated with this interest.
13.2 State Approvals The Queensland Planning Act 2016 (Planning Act) provides a framework of land use planning (planning), development assessment, and related matters that facilitates the achievement of ecological sustainability. The Planning Regulation 2017 is established under the Planning Act and declares development that cannot be made assessable by a planning scheme (Schedule 6). Of relevance, that development includes "Development for the construction of the following infrastructure, if the infrastructure is government supported transport infrastructure:
(a) an aid to navigation;(b) a public marine facility;
Legislative Requirements
167
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
(c) road transport infrastructure; (d) transport infrastructure."
This would include the B2N Project.
Development approval requirements may be triggered for other aspects of the development or works, depending on the location and particular impacts of works.
The environmental aspects listed in Table 60 are accepted or assessable development under Schedule 7 and Schedule 10 of the Planning Regulation 2017, respectively. Table 60 also lists exemptions and other environmental approvals identified that are applicable to the Project.
13.2.1 State Development and Public Works Organisation Act 1971
An Environmental Impact Statement (EIS) was completed for the Landsborough to Nambour Project in 2010, with the Coordinator-General’s report released in November 2011. The EIS process under the State Development and Public Works Organisation Act 1971 (SDPWO Act) is typically used to provide a coordinated facilitation process for projects that have complex approvals requirements under legislation such as the EPBC Act, Planning Act and Environmental Protection Act 1994. It is not a statutory requirement that any given project be assessed under the SDPWO Act and proponents who enter the coordinated project process do so voluntarily. The reasons for completing an EIS for Landsborough to Nambour were outlined in the Initial Advice Statement, and related to a recommendation in the preliminary scoping study.
The Coordinator-General’s report for the approved Landsborough to Nambour Project EIS states that:
“The Coordinator-General is not expected to be involved in future phases of the project. In accordance with 35A of the SDPWO Act, this report will lapse four years after its completion. Given the scheduled timing of the project, the requisite approvals to construct and operate the railway are anticipated to be sought by the proponent well after the four-year currency of this report. Accordingly, no conditions are stated for the project in this report.
The Coordinator-General recommends that the Landsborough to Nambour Rail project should proceed.”
This statement indicates that the approvals were expected to be applied for after the EIS approval was no longer current, which is now the case. Further, there were no conditions placed on the Landsborough to Nambour Project due to this issue. As such a change report for the Landsborough to Nambour Project EIS would not be required.
As the EIS process is typically used for projects that have complex approvals requirements and as TMR has exemptions under a number of other Acts it is generally not necessary for a TMR project to go through an EIS under the SDPWO Act – a direct approvals approach is usually more efficient. Based on the approval requirements identified in Table 60, a direct approvals approach is recommended for the B2N Project.
Legislative Requirements
168 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Table 60: State Approvals Identified
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
Assessable Development
Operational Works Vegetation Management Act 1999
Planning Regulation 2017
For clearing native vegetation
Planning Regulation, Schedule 21 Exempt Clearing Work —not assessable development under Schedule 21, part 1, item 14:
Clearing vegetation for the construction or maintenance of infrastructure stated in schedule 5, if—
(a) the clearing is on designated premises; or
(b) the infrastructure is government supported transportinfrastructure.
Schedule 5 refers to transport infrastructure (part 1, item 2), which is defined in the Regulation as including rail infrastructure.
Clearing of REs for the B2N Project and ancillary infrastructure requirements is therefore not assessable development and is exempt from requiring a permit.
Schedule 21 (16) also lists activities including geotechnical investigations and cadastral survey as exempt subject to defined clearing limits.
Exempt
Water Act 2000
Water Regulation 2016
For taking or interfering with water, excavation or placement of fill in a watercourse, destruction of vegetation in a watercourse
Water Act 2000, s 206: A Water Licence may be required for a watercourse diversion if a creek realignment is required.
All other works are exempt in accordance with the Riverine Protection Permit exemption requirements WSS/2013/726 (2018). TMR is an approved entity in accordance with Schedule 2 of the guideline.
Potentially required if creek realignments occur.
All other works likely to be exempt.
Water Act 2000
Water Regulation 2016
For taking or interfering with water
Under the Water Regulation 2016, a water authority is not required for the taking of water by a constructing authority for the purpose of constructing or maintaining infrastructure that the constructing authority may lawfully construct or maintain (part 3, division 1, item 23) and is exempt if it complies with Exemption requirements
Likely to be exempt.
Legislative Requirements
169 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
for constructing authorities for the take of water without a water entitlement WSS/2013/666 (2018).
Fisheries Act 1994 For constructing or raising waterway barrier works
Guidelines from the DAF website detail the following:
• New single span bridges are not waterway barrierworks when:
− the abutments do not extend into thewaterway beyond the high bank;
− the bank revetment works do not extendbeyond the toe of the bank; and
− no scour protection is placed on the bed of thewaterway upstream, downstream or under the structure.
• New multi-span bridges are not waterway barrierworks when:
− in all waterways, the abutments do not extendinto the waterway beyond the high bank, andthe abutment revetment works do not extendinto the waterway beyond the toes of thebanks;
− in all waterways, bed scour protection isplaced at, or below the natural bed level of thewaterway, and does not change thecharacteristics of the low flow channel;
− in Purple, Red, Amber and Green waterways, bed scour protection cannot extend more than20m upstream, or 20m downstream beyondthe footprint of the bridge.
− in Grey waterways, bed scour protectioncannot extend more than 5m upstream, or 5mdownstream beyond the footprint of thebridge.
Further design detail and liaison with DAF will be required to determine if requirements for waterway barrier works approval are triggered. This includes a review of the DAF design guidelines current at the time of design development.
Legislative Requirements
170 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
− in Amber and Green waterways, the pier/pileand/or pier/pile platform are completelyoutside the low flow channel
− in Purple, Red and Grey waterways, thepier/pile and/or pier/pile platform can bewithin the low flow channel, but does notchange the characteristics of the low flowchannel (i.e. cause scouring of the low flowchannel banks or bed).
Both permanent and a number of temporary waterway barrier works may be required for the Project.
Temporary works are considered accepted development if they meet the criteria in DAF’s ‘Accepted development requirements for operational work that is constructing or raising waterway barrier works’ (DAF 2018 or most recent version).
Water Act 2000 For removal of quarry material from a watercourse or lake
Required if a permit under the Water Act 2000 (Part 5) is triggered, for beneficial use of material won from the watercourse.
Landowners consent would also be required.
Unlikely to be required, as material extracted would likely be treated as unsuitable/waste.
Queensland Heritage Act 1992
Development on a Queensland Heritage place
Part 6: Approval for Development by the State (ss71) or exemption certificate (Division 2) is required for works over a Queensland heritage place.
Approval for Development by the State and/or exemption certificate is unlikely to be required based on Project Area. However, if this changes, development will be assessed under the Queensland Heritage Act 1992.
Queensland Heritage Act 1992
Development on a local heritage place
Part 6 Division 2: Development on a local heritage place will be exempt development under the Planning Regulation.
Likely to be exempt.
Legislative Requirements
171 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
Accepted Development under Planning Regulation 2017
Building work Building Act 1975
Planning Act 2016
Planning Regulation 2017
Building work for station sites.
On behalf of the State, a public sector entity or a local government
Building Act 1975, section 21, building work is accepted development if undertaken for or on behalf of the State or a public sector entity (Planning Regulation, Schedule 7, part 1, item 2).
Development on a registered State heritage place will require approval, unless an exemption certificate has been issued (Planning Regulation 2017, Division 2, Subdivision 1, Part 15, s1(a)). If an approval is required, the process will depend on whether or not the development is "by the State".
Accepted development.
Operational works Fisheries Act 1994
Planning Act 2016
Planning Regulation 2017
Fisheries Regulation 2008
For waterway barrier works and temporary waterway barrier works
Some works may be conducted in accordance with accepted development requirements under the Fisheries Act 1994: ‘Accepted development requirements for operational work that is constructing or raising waterway barrier works’ (DAF 2018 or most recent version).
Development permit is not required, unless unable to comply with the Accepted development requirements.
Other Cultural Heritage Aboriginal Cultural Heritage Act 2003
Cultural Heritage Management Plan and Agreement with Kabi Kabi First Nation
The Project Area traverses the Kabi Kabi First Nation claim area. Compliance with the Aboriginal Cultural Heritage Act Duty of Care Guidelines (2004) may require a Cultural Heritage Management Plan (CHMP) or Agreement, including consultation and any field investigation and monitoring necessary with the involvement of the Kabi Kabi First Nation representatives.
Cultural Heritage Risk Assessment and subsequent Cultural Heritage Management Plan and/or Agreement.
Other Contaminated Land Environmental Protection Act 1994
Movement or disposal of contaminated soil
Chapter 7 Part 8 Division 2 (s 371): Properties in the Project Area are listed on the Environmental Management Register (EMR).
Identification and disposal permit requirement for contaminated soil in accordance with the requirements of the EP Act, in particular tracking as regulated waste.
A Soil Disposal Permit will be required for any
Legislative Requirements
172 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
material moved from an EMR listed lot.
Protected Plants Nature Conservation Act 1992
Nature Conservation (Wildlife Management) Regulation 2006
Permit to Clear protected plants
Some sections of the B2N Project are located in the ‘high risk’ areas mapped under the Protected Plants Survey Trigger map.
Nature Conservation (Wildlife Management) Regulation 2006 Chapter 4, Division 4: A protected plant survey in accordance with the DES Protected Plant Flora Survey Guidelines (2019) will be required in the mapped high risk areas (clearing impact area), and should be undertaken for any other area of likely disturbance (i.e. within the construction footprint). A flora survey report and either a Clearing Permit or an Exempt Clearing Notification should then be prepared and submitted. The flora survey report cannot be submitted more than 12 months after completion of the flora survey. The clearing start date and end date must also be nominated in the application.
Clearing Permit (Protected Plants) or an Exempt Clearing Notification.
EVNT flora surveys required, and potentially permits, and offsets under the Environmental Offsets Act 2014.
Species Management Program (SMP)
Nature Conservation Act 1992
Nature Conservation (Wildlife) Regulation 2006
SMP - Low Risk Impact – Least Concern
A low risk SMP species would be required if breeding habitat is only identified for least concern species (Nature Conservation (Wildlife) Regulation 2006, Schedule 6). This excludes special least concern species and colonial breeders.
Likely to be required.
SMP – High Risk Impact – All protected wildlife
A high risk SMP would be required if breeding habitat for colonial breeders, special least concern, extinct in the wild, endangered, vulnerable or near threatened species is identified. This SMP could also be used to apply to least concern species.
Likely to be required.
Other Koala Planning Regulation 2017 (Schedule 10)
State Government Supported Infrastructure, Koala
Clearing of non-juvenile koala habitat trees
The B2N Project is within the South East Queensland Koala Protection Area (SEQKPA) and is self-assessable under the provisions of the DERM (now DES)-TMR MOA.
Schedule 10 of the Planning Regulation 2017 will not apply as the works are not assessable under a planning scheme. Self-assessment is to be undertaken in
No external approval required; however, documentation of findings would need to be included in annual reporting by
Legislative Requirements
173 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
Conservation Policy July 2017
TMR DERM (now DES) Memorandum of Agreement (MOA) June 2010, SEQIPP
accordance with TMR Compliance reporting requirements. This involves surveys of any area mapped as SEQKPA, including number of non-juvenile koala habitat trees (NJKHTs).
The B2N Project will trigger offsets under the Environmental Offsets Act 2014 and Policy. The B2N Project is not exempt from this requirement as it was not identified as a committed project at the time the MOA was signed by the last party.
TMR. A survey of NJKHTs will be required.
EVNT species
State Forest
Environmental Offsets Act, Regulation and Policy 2014
Clearing of EVNT species or habitat for EVNT Species
Requirements for offsets or will need to be determined through completion of updated flora and fauna surveys. Surveys completed to inform this review of environmental factors provides a base from which these can be calculated, however more detailed investigations will be required to ensure offsets are commensurate with impacts identified.
Revocation of areas of State Forest will require agreement regarding appropriate offsets.
Likely to be required, though only in the event that protected plants or MSES are impacted.
Restricted and prohibited weeds and pest animals
Biosecurity Act 2016 Weed and pest animal management during construction
Construction works will be required to comply with the Biosecurity Act 2016 and general biosecurity obligation (GBO) for management of restricted biosecurity matter occurring in the Project Area.
The Project Area is not currently in a Red Fire Ant biosecurity zone.
Requirements to be incorporated into the CEMP. Review biosecurity zones in the lead up to construction.
State Forest Revocation
Tenure Forestry Act 1959
Environmental Offsets Act 2014
Change in tenure to State Forest
Several portions of the Beerburrum State Forest will need to be revoked under Forestry Act 1959 Part 3, Division 2, Section 26(2), including the nursery (no longer operational). Once land requirements are finalised, process should commence. This process can take up to 12 months.
Documentation will require a land requirement plan, assessment detailing the reasons for the revocation, and also consideration of offset requirements in accordance with the Environmental Offsets Act, Part 6.
Legislative Requirements
174 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
Native Title Tenure Native Title (Qld) Act 1993 (NT Act)
Acquisition/suppression of Native Title
s 144: Several local roads and waterways will require native title acquisition or suppression. Where native title has not been extinguished, notification procedures, acquisition of native title or suppression of native title in accordance with the NT Act will need to be considered in accordance with the policy position of the State at the time.
Required.
Environmental Authority
ERA 16 – extraction and screening activities
Environmentally Relevant Activity
Environmental Protection Act 1994
Environmental Protection Regulation 2019
Extracting material The Environmental Protection Regulation 2019 lists the following activities that are not considered to be environmentally relevant activities under the regulation:
Schedule 2, Part 4, s16(2)(c): extracting material from a place for constructing a road or railway at the place (e.g. cutting and filling land for constructing a road or railway).
Requirements to be documented in any subsequent CEMP as a construction contractor requirement, subject to the arrangement for materials sourcing. The requirements for this approval will be determined and addressed by the construction contractor at the time of construction.
Compliance Management Plan
Construction Transport Infrastructure Act 1994
May include vegetation clearing, noise management, air quality management
Chapter 16, sections 477G – 477H of the Transport Infrastructure Act 1994 relate to making and approving Compliance Management Plans. These may be prepared and approved by TMR or prepared by contractor and approved by TMR. Compliance Management Plans establish how construction and maintenance of infrastructure will comply with relevant legislative requirements.
Requirements to be confirmed.
Road Corridor Permit
Works on a State Controlled Road
Transport Infrastructure Act 1994
Transport Infrastructure (State-Controlled Roads) Regulation 2006
Activities or works within State Controlled road corridor
This will apply for any temporary or permanent works within a State Controlled road corridor.
Consultation with TMR (North Coast)
Completion of Road Corridor Permit Application
Legislative Requirements
175
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
APPROVAL TYPE ASPECT RELEVANT ACT OR POLICY
RELEVANT ACTIVITIES COMMENTS REQUIREMENT
Road Closures Temporary and Permanent Road Closures
Land Act 1994 Temporary road closures to facilitate works
Permanent road closures for sections of road reserve impacted by the works
Temporary road closures may be required to facilitate construction or construction access.
In some cases, unformed road reserves will be required to facilitate construction and operation of the corridor. These areas may be leased to adjacent landowners.
Consultation with DNRME
Application for road closure (LA18)
Preparation of traffic management plans
Road Opening/ application to dedicate State Land as a road
Opening of new road
Land Act 1994 Required where road realignment is on land acquired by the State for the purpose of road realignment
Road openings will be required where realigned sections of State and local roads are required to facilitate the B2N Project.
Application to dedicate State land as a road (LA17)
Legislative Requirements
176 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
13.3 Other Relevant Processes In addition to the heritage listings under State and Local government registers, there are several QR heritage listed items including:
• Mooloolah Railway Shelter (also listed under Local register as Mooloolah Waiting Shed)• Mooloolah Railway Station• Eudlo Railway Station• Woombye Passenger Station• Palmwoods Passenger Station (also listed under Local register)• Palmwoods Good Shed (also listed under Local register)• Palmwoods Locomotive remains.
Impacts to these listed rail elements are to be addressed in accordance with the heritage listing details.
The relocation and installation of services / public utility plant (PUP) has been considered at a high level in this assessment, however it is possible that separate approvals may be required. This aspect should be considered as part of future PUP relocation planning.
Temporary works within a local road corridor or footpath are expected to require a Road and Footpath Permit under the Local Government Act 2009, Local Laws 1 (Administration) and 4 (Local Government Controlled Areas, Facilities, Infrastructure and Roads) and Subordinate Local Laws 1 (Administration) and 4 (Local Government Controlled Areas, Facilities, Infrastructure and Roads). Further consultation with SCC will be required in future stages of design and construction to confirm requirements.
13.4 Future Changes to Legislation There is a potential for future changes to legislation or new requirements to alter the legislative requirements discussed in this Chapter. It is therefore recommended that permits and approval requirements, as well as policies and guidelines of the relevant Queensland and Commonwealth agencies are reviewed during detailed design and prior to commencement of construction.
References
177
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
14 References Aecom (2011) Adaptation of Melbourne’s Metropolitan Rail Network in Response to Climate Change
Arup (1998) Stage 2 Corridor Assessment Report - An options analysis assessment of the proposed Caboolture to Maroochydore Corridor Project Area.
Arup, for the Department of Transport and Main Roads (2009) Landsborough to Nambour Rail Project EIS
Arup, for Queensland Transport (2007) Caboolture to Landsborough rail upgrade study: Beerburrum to Landsborough Corridor
Australian and New Zealand Environment and Conservation Council (ANZECC) (2000) Australian and New Zealand Guidelines for Fresh and Marine Water Quality
Bureau of Meteorology (BOM), Australian Groundwater Explorer http://www.bom.gov.au/water/groundwater/explorer/index.shtml accessed May 2016
Bureau of Meteorology, Climate Data Online http://www.bom.gov.au/climate/data/index.shtml accessed September 2019
Cameron M. (2006) Nesting habitat of the glossy black-cockatoo in central New South Wales. Biological Conservation 127, 402-10.
Clout M.N. (1989) Foraging behaviour of Glossy Black-cockatoos. Australian Wildlife Research 16, 167-73.
CSIRO (1991) Atlas of Australian Soils: Broad-scale soils mapping
CSIRO (2010) Adaptation Science: Opportunities and Responses to Climate Change Impacts
CSIRO (2014) Australian Soil Resource Information System http://www.asris.csiro.au/ accessed June 2016
CSIRO and Bureau of Meteorology, Climate Change in Australia http://www.climatechangeinaustralia.gov.au/en/ accessed September 2019
Department of Agriculture and Fisheries (DAF), 2016, GIS layer: Queensland Waterways for Waterway Barrier Works
Department of Climate Change (2009) Climate Change Risks to Australia’s Coast: A First Pass National Assessment, Department of Climate Change, Canberra
Department of Defence, 2016, Where is Unexploded Ordnance? http://www.defence.gov.au/UXO/WhereIs.asp accessed June 2016.
Department of Environment and Heritage Protection (2014) Flora Survey Guidelines - Protected Plants: Nature Conservation Act 1992 Department of Environment and Heritage Protection, Brisbane
Department of Environment and Heritage Protection (2014) Wildlife Online WildNet database.
Department of Environment and Resource Management (2009) Climate Q: toward a greener Queensland
Department of Environment and Resource Management (2010) Environmental Protection (Water) Policy 2009 Maroochy River environmental values and water quality objectives
Department of Environment and Resource Management (2010) Environmental Protection (Water) Policy 2009 Mooloolah River environmental values and water quality objectives
Department of Environment and Resource Management (2010) Environmental Protection (Water) Policy 2009 Pumicestone Passage environmental values and water quality objectives
Department of Infrastructure, Local Government and Planning (2016) State Development Assessment Provisions v 1.9
Department of Infrastructure, Local Government and Planning (2016) State Planning Policy (April 2016) and SPP mapping
Department of Natural Resources, Mines and Energy (DNRME), Groundwater Database – Queensland https://data.qld.gov.au/dataset/groundwater-database-queensland accessed March 2016
Department of Environment and Science(2019) Queensland Air Monitoring Report 2018 for the NEPM Measure
Department of the Environment (DoEE) 2016 Species Profile and Threats Database
References
178 REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Department of the Environment and Energy, National Pollution Inventory, http://www.npi.gov.au/npi-data accessed September 2019
Department of Transport and Main Roads (2013) Environmental Processes Manual.
Department of Transport and Main Roads (2016) South East Queensland’s Rail Horizon Blueprint
Geological Survey of Queensland (1977) 1:100,000 series Nambour geological map sheet
Healthy Waterways (2015) SEQ Healthy Waterways Ecosystem Health Monitoring Program (EHMP): 2015 Report Card
Lemckert F. (1999) Impacts of selective logging on frogs in a forested area of northern New South Wales. Biological Conservation 89, 321-8.
Lunney D., Gresser S. M., O'Neill L. E., Matthews A. & Rhodes J. (2007) The impact of fire and dogs on Koalas at Port Stephens, New South Wales, using Population Viability Analysis. Pacific Conservation Biology 13, 189-201.
Lunney D., O’Neill L., Matthews A. and Sherwin W.B. (2002) Modelling mammalian extinction and forecasting recovery: koalas at Iluka (NSW, Australia). Biological Conservation 106, 101-13.
Moreton Bay Regional Council Pumicestone Passage Overview https://www.moretonbay.qld.gov.au/general.aspx?id=141044 accessed May 2016
National Environment Protection Council (1998) National Environment Protection Measures (NEPMs) for Ambient Air Quality
National Environment Protection Council (2019) Draft Variation to the National Environment Protection (Ambient Air Quality) Measures for sulfur dioxide, nitrogen dioxide and ozone Impact Statement May 2019.
Neldner, V.J., Wilson, B.A., Thompson, E.J. and Dillewaard, H.A. (2012) Methodology for Survey and Mapping of Regional Ecosystems and Vegetation Communities in Queensland. Version 3.2. Updated August 2012. Queensland Herbarium, Queensland Department of Science, Information Technology, Innovation and the Arts, Brisbane.
O'Brien, A. & Marsden, T., Peterken, C. and Draper, I. (2016). Risk Management of Waterways: Impact Determination of Barrier Works for Fish Passage in Queensland. Conference paper: 11th International Symposium on Ecohydraulics, Melbourne, Australia
Oli M.K. (2004) “The fast-slow continuum and mammalian life-history patterns: an empirical evaluation”. Basic and Applied Ecology 5, 449-63.
Phillips, Stephen and Callaghan, John. “The Spot Assessment Technique: A Tool for Determining Localised Levels of Habitat Use by Koalas Phascolarctos Cinereus.” Australian Zoologist 35, no. 3 (November 2011): 774–80.
Queensland Government Environmental Protection Policy (Air) 2019.
Queensland Government South East Queensland Infrastructure Plan 2007-2026(SEQIP)
Queensland Government Water Resource (Mary Basin) Plan 2006.
Queensland Government Water Resource (Moreton) Plan 2007.
Queensland Herbarium Regional Ecosystem Description Database. Version 9.0
Queensland Land Use Mapping Program February 2016 Queensland Land Use Mapping
Queensland Rail MD-15-316 Specification – Noise assessment (Environment)
Queensland Rail MD-15-317 Procedure – Noise Management (Environment)
SEQwater (2017) Seqwater Development Guidelines: Water Quality Management in Drinking Water Catchments.
Shuker J.D. and Hero J.-M. (2013) “Perch substrate use by the threatened wallum sedge frog (Litoria olongburensis) in wetland habitats of mainland eastern Australia”. Australian Journal of Zoology 60, 219-24.
SMEC (2016a) Hydrologic & Hydraulic Modelling Beerburrum to Nambour Reference Design Phase. Report completed for Building Queensland in December 2016.
SMEC (2016b) Beerburrum to Nambour (B2N) Rail Upgrade Project Geotechnical Investigations Report. Report completed for Building Queensland in December 2016.
Sunshine Coast Council (2014) Sunshine Coast Planning Scheme 2014 and overlay maps
References
179
REVIEW OF ENVIRONMENTAL FACTORS – UPDATE Beerburrum to Nambour Rail Upgrade Prepared for Department of Transport and Main Roads
SMEC Internal Ref. 30032436 22 November 2019
Sunshine Coast Council and Moreton Bay Regional Council (2013) Pumicestone Passage and Catchment Action Plan 2013-2016
Trackstar Alliance (2008) Beerburrum to Landsborough Rail Upgrade Project
Trackstar Alliance (2008) Beerburrum to Landsborough Final Geotechnical Report
WBM and BAAM (2007) Caboolture to Landsborough Rail Upgrade – Beerburrum to Landsborough Ecological Assessment