10072-02 rq protocol line-1 tunnel-001
TRANSCRIPT
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Details of Equipment/ System
User Department ProductionSystem ID PN/TUNNL-001Equip. Location/ Room No. Vial washing area Line-1 / PN025Equip. Make/ Model IMA-LIBRA / BLUE GALAXY 870 FLSEquip. Serial No. (Supplier) LD 8015Document Effective DateQualification Start DateQualification Completion DateRequalification due date
Table of Contents
S. No. Details Page No.
1. Pre-Approval 022. Scope 033. Objective 034. Abbreviations 035. Responsibility 046. Intended use of equipment 047. Equipment / system description 048. Safety Precautions 059. Training Record 0510. Equipments/ Materials Required for Qualification 0611. Verification of calibration status 0712. Verification of operational controls 0813. Qualification requirements & observations 0814. Qualification Tests & Results 2815. Requalification criteria 3016. Details of Discrepancies 3017. Summary / Conclusion 3118. References 3219. Annexure 3220. Post Approval 33
Page 1 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
1. PRE APPROVAL:
Name Designation Department Signature /date
Prepared by
Reviewed by
Approved by
Page 2 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
2. SCOPE:
This qualification protocol is applicable for the requalification of depyrogenation tunnel in
vial washing room of manufacturing Line-1 as per the Qualification Plan 20017.
3. OBJECTIVE:
The objective of this protocol is to ensure the consistency, repeatability and reproducibility of
the depyrogenation tunnel machine in the following conditions.
Measurement of airflow velocity
Verification of Differential pressures across zones.
Installed filter system integrity / Leakage test.
Air flow pattern test.
Non-viable particle count.
Verification of Conveyor Speed.
Heat Penetration Study with biological qualification.
Heat Penetration Study with biological qualification by increasing set speed.
Physical observation of vials during qualification run.
4. ABBREVIATIONS:
ID No. - Identification Number
MOC - Material of Construction
NA - Not Applicable
OQ - Operational Qualification
PQ - Performance Qualification
QA - Quality Assurance
QC - Quality Control
RQ - Re-Qualification
S. No. - Serial Number
PN - Production
AISI - American Iron And Steel Institute
Page 3 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
5. RESPONSIBILITY:
Department/ Function
Responsibility
Validation group
Preparation & Execution of the protocol and collection of samples.
Engineering / Instrumentation
Review the activity and provide required technical support.
Quality Control To perform testing of samples, wherever applicable.User department
To provide necessary support For the execution of activity
Quality Assurance
To review and approve the executed protocol with supporting data
6. INTENDED USE OF EQUIPMENT
Depyrogenation tunnel is used for the preparation/processing (depyrogenation) of containers
for the filling of sterile drug product. Depyrogenation process shall be done by using filtered
dry hot air.
7. EQUIPMENT/ SYSTEM DESCRIPTION
Depyrogenating Tunnel is located at Vial washing room Line-1 of Ground Floor Production
Department. The purpose of Depyrogenating Tunnel is to depyrogenate the Vials coming out
from the Vial washing Machine. The tunnel, constructed in AISI 304, consists of three
laminar flow zones such as inlet zone, heating zone and cooling zone. The clean and slighty
containers are arranged and automatically deposited by the washer on to the tunnel conveyor
belt at the in-feed zone. The tunnel inlet zone is protected by sterile laminar air flow which
protects the washed vials discharged by washing machine and prevents any hot, saturated air,
released from the heating zone because of higher pressure. The vials coming out from the
heating zone enter into the cooling zone where they struck by the cooling laminar flow and
brought to temperature required for the successive working.
Page 4 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
With the principle of communicating vessel, assisted by the make up of the hot zone tunnel
permits operation with difference in pressure between the sterile chamber and the tunnel area
of 50 Pascal with variation of ±15 of such value are absorbed and balanced automatically
with out altering the operating parameters.
The tunnel sterilizer equipped with anemometer, DP meters, hot zone air flow measurement
system and Automatic adjustment of air speed basing on the density.
8. SAFETY PRECAUTIONS:
Personnel involved in autoclave qualification shall follow proper written procedures for equipment operation.
Personnel shall wear necessary gloves, wherever applicable.
Do not touch the hot surfaces during validation.
Care should be taken while handling with electrical cables.
9. TRAINING RECORD:
Purpose To train all the personnel involved in execution of qualification, on following attributes: System Description Protocol, applicable SOPs and documentation.
Doc. Ref. No(s).
Training by
S. No. Name of the participant Area of Operation Sign and Date
Page 5 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Trainer (Sign and Date):
10. INSTRUMENT/ MATERIALS REQUIRED FOR QUALIFICATION:
10.1 Details of Instruments
S. No.
Instrument Name Instrument IDCalibration certificate
No./ Done dateCalibration Due
date
1Anemometer
IN/ANMTR-001
2 IN/ANMTR-002
3 Digital manometer IN/DMNMR-001
4 Aerosol Photometer IN/APHMR-001
5
Non-Viable particle counter
PN/PLCTR-001
6 PN/PLCTR-003
7 PN/PLCTR-004
8 PN/PLCTR-005
9 PN/PLCTR-006
10 Data logger
11 Smoke generator
13 Stop watch
Sensor details
S. No.
Instrument Name Pre calibration datePost calibration
date
1 Temperature mapping probesChecked By: (Sign and Date)
Reviewed By:
(Sign and Date)
Page 6 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
10.2 Details of materials
Endotoxin spiked container
Specific size & quantity of the container as per requirement
Minicolt-4 smoke refill canister / Dry Ice
PAO
11. VERIFICATION OF CALIBRATION STATUS:
Equipment Name
Instrument Name Instrument ID No.Calibration
DateCalibration Due Date
Tunnel
Magnehelic Gauge
PN/TUNNL-001-MG001
PN/TUNNL-001-MG002
PN/TUNNL-001-MG003
PN/TUNNL-001-MG004
PN/TUNNL-001-MG005
PN/TUNNL-001-MG006
DP TransmitterPN/TUNNL-001-DPT001
PN/TUNNL-001-DPT002
Temperature Sensor
PN/TUNNL-001-TS001
PN/TUNNL-001-TS002
PN/TUNNL-001-TS003
PN/TUNNL-001-TS004
Strip chart Recorder
PN/TUNNL-001-SC001
Anemometer
PN/TUNNL-001-AM001
PN/TUNNL-001-AM002
PN/TUNNL-001-AM003
Remarks:
Page 7 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Equipment Name
Instrument Name Instrument ID No.Calibration
DateCalibration Due Date
Checked By:(Sign and Date)
Reviewed By:(Sign and Date)
12. VERIFICATION OF OPERATIONAL CONTROLS:
S. No. Description of Control Document Ref. No. Status/ Remarks
1 Availability of approved operation, cleaning and monitoring SOPs
2 Availability of approved PM SOP 3 Availability of log books for recording
the activities4 Implementation of gowning practices
with SOPsRemarks:
Checked By:(Sign and Date)
Reviewed By:(Sign and Date)
13. QUALIFICATION REQUIREMENTS & OBSERVATIONS:
13.1 Measurement of airflow velocity:
13.1.1 Procedure
Switch on the tunnel fans in maintenance mode.
The tunnel should be stabilized at least 15 min prior to start the activity and heaters should be OFF.
Perform the air velocity measurement test as per SOP # FU4-QA-GEN-040 and record the observations.
Calculate minimum, maximum & average velocity of all locations.
Page 8 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Diagram.1 HEPA Filter location drawing
Diagram.2 Air velocity sampling locations of filter
13.1.2 Acceptance criteria:
Air velocity should be with 79-118 FPM (0.4-0.6 m/s) at conveyer level in infeed zone, hot zone and cool zone.
Page 9 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
2
34
5
1
TITLE : PERFORMANCE/ RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.1.3 Result:
Name of the instrument used: Calibration due Date:
Instrument Id: Calibration certificate no:
Filter No
Grill Location & Velocity in m/s
L1 L2 L3 L4 L5 Acc. limit Min Max Average
Filter-1
0.4-0.6 m/s
Filter-2
Filter-3
Filter-4
Filter-5
Filter-6
Filter-7
Remarks:
Done by : Checked By: Reviewed By:
Page 10 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : PERFORMANCE/ RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
(Sign/Date) (Sign/Date) (Sign/Date)
Page 11 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.2 Verification of Differential pressures across zones:
13.2.1 Procedure :
Monitor & record the pressure differential values from the calibrated magnehelic gauge across zones.
Perform the differential pressure test as per SOP # FU4-QA-GEN-040 and record the observations for the various zones using manometer.
While measuring DP between zone to zone and zone to room, place manometer positive end in high pressure zone and negative in low pressure zone.
Diagram .3 Differential pressure representations
Page 12 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.2.2 Acceptance criteria & Results
Description Acceptance criteria Observation Result Remarks
Filter-1 (Across filter) 120 pa -350 pa. Pass/Fail
Filter-2 (Across filter)
120 pa -400 pa.
Pass/Fail
Filter-3 (Across filter) Pass/Fail
Filter-4 (Across filter) Pass/Fail
Filter-5 (Across filter) Pass/Fail
Filter-6 (Across filter)120 pa -350 pa.
Pass/Fail
Filter-7 (Across filter) Pass/Fail
DP between Infeed zone and washing room
Infeed zone DP should be higher than washing room Pass/Fail
DP between Depyrogenation zone and Infeed zone
Depyrogenation zone DP should be higher than Infeed zone
Pass/Fail
DP between depyrogenation zone and cool zone
Depyrogenation zone DP should be higher than cool zone
Pass/Fail
DP between filling room and cool zone
Filling room DP should be higher than cool zone Pass/Fail
Done by:(Sign/Date)
Checked By:
(Sign/Date)
Reviewed By:
(Sign/Date)
Note: √ whichever is correct in result column.
Page 13 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.3 Installed filter system integrity / Leakage test:
13.3.1 Test Procedure:
Perform the filter integrity test as per SOP # FU4-QA-GEN-040 and record the observations.
13.3.2 Acceptance criteria:
The downstream concentration of aerosol from each HEPA filter should not be more than 0.01%, while upstream PAO concentration is set as 100%.
13.3.3 Results:
Filter ID No.Upstream
Concentration %Downstream
Concentration %Mounting joints
%Result Done By
Sign/Date:
Filter-1 Pass/Fail
Filter-2 Pass/Fail
Filter-3 Pass/Fail
Filter-4 Pass/Fail
Filter-5 Pass/Fail
Filter-6 Pass/Fail
Filter-7 Pass/Fail
Remarks if any:
Checked by :(Sign / Date)
Reviewed by: (Sign / Date)
Note: √ whichever is correct in result column.
13.4 Air flow pattern test:
13.4.1 Procedure:
Ensure that the tunnel air velocities and pressure differential are maintained.
Perform the air flow pattern test as per SOP # FU4-QA-GEN-040 and record the observations.
Page 14 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Attach the air flow pattern visual record to the executed protocol.
13.4.2 Acceptance criteria & Results
Description of test Acceptance criteria Observation
Generate the fog near Infeed zone towards panels
The air flow should be fromInfeed zone to washing room Complies / Not complies
Generate the fog in Depyrogenation zone
The air flow should be towards Infeed zone and cool zone Complies / Not complies
Generate the fog in Filling room near turn table panel
The airflow should be towards cooling zone Complies / Not complies
Generate the fog near filters in Infeed zone
Laminarity should be observe until Working height level. Complies / Not complies
Generate the fog near filters in cooling zone
Laminarity should be observe until Working height level. Complies / Not complies
Remarks:
Checked by :(Sign / Date)
Reviewed by:
(Sign / Date)
Note: √ whichever is correct in result column.
13.5 Non-viable particle count
13.5.1 Procedure:
Page 15 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
A discrete particle counting, light scattering instrument is used to determine the concentration of air borne particles, equal to and larger than the specified sizes, at designated sampling locations.
Perform the non viable particle count test as per SOP # FU4-QA-GEN-040 and attach the non viable particle count data printout to the executed protocol.
13.5.2 Acceptance criteria:
All the readings of test should pass the below mentioned criteria.
Maximum permitted number of particles/m3 is mentioned in following table.At rest
Maximum permitted number of particles/m3
0.5μm/ m3 5μm/ m3
≤ 3520 ≤ 20
Diagram.5 NVPC location drawing
13.5.3 Results;
Location Observation Results
0.5μm / m3 5μm / m3
Infeed zone location-1
Infeed zone location-2
Infeed zone location-3
Depyrogenation zone location-1
Depyrogenation zone location-2
Depyrogenation zone location-3
Page 16 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Cool zone location-1
Cool zone location-2
Cool zone location-3
Done by Sign/DateChecked By :(Sign/Date)
Reviewed By :(Sign/Date)
13.6 Verification of conveyor speed :
13.6.1 Procedure:
Perform the conveyor speed verification for all the set speeds.
During qualification verification of conveyor speed shall be done as per SOP # FU4-QA-GEN-040.
Operate the tunnel as per SOP # FU4-PR-MF-OPI-002
13.6.2 Acceptance criteria:
Conveyor speed should be within ± 5% of set speed
13.6.3 Results:
S. No. Container sizeSet Conveyor
SpeedObserved conveyor
SpeedResults
Done by Sign / Date
Remarks if any:
Checked By:(Sign/Date )
Reviewed By:(Sign/Date)
Page 17 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.7 Heat Penetration Study with Endotoxin Spiked Vials
13.7.1 Procedure
Heat penetration study with endotoxin spiked containers shall be performed for following containers
2 mL vial with 13 mm neck
3 mL vial with 13 mm neck
5 mL vial with 20 mm neck
10 mL vial with 20 mm neck
20 mL vial with 20 mm neck
30mL vial with 20 mm neck
The tunnel when operated with fully loaded glass vials on the conveyor is capable of producing the temperature profiles in side the vials distributed across the conveyor belt as per the temperature set points set in the PLC of the equipment.
Operate the tunnel as per SOP # FU4-PR-MF-OPI-002 & perform the heat penetration study as per SOP # FU4-QA-GEN-040.
The placement of spiked Endotoxin vials and temperature sensors in empty vial are depicted in the below diagram.
Note: The tunnel conveyor should not stop when SS zigs are in depyrogenation zone
Left side conveyor edge In feed zone Depyrogenation zone Cool zone
Page 18 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Right side conveyor edge
Vial with temperature sensor Endotoxin Spiked Vial
13.7.2 Acceptance criteria:
Each temperature sensor of the row should be more than 300°C for minimum of 3 minutes (Considered as residence time) during Depyrogenation period of each run.
The temperature variation across all sensors in any row shall not be more than 20°C at any stage in passage of load during calculated residence time.
Depyrogenation zone temperature during Depyrogenation period shall be at 330 ± 6°C and the same shall be confirmed through strip chart to ensure the equipment functionality.
Minimum 3- log reduction should be achieved for endotoxin spiked vials.
Page 19 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.7.3 Results:
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
Date of cycle
Cycle Start Time
Cycle End Time
Set conveyor speed
Observed conveyor speed (max)Depyrogenation hold start time for set -1
Depyrogenation hold end time for set-1
Calculated residence time for set-1
Depyrogenation hold start time for set -2
Depyrogenation hold end time for set-2
Calculated residence time for set-2
Page 20 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
Depyrogenation hold start time for set -3
Depyrogenation hold end time for set-3
Calculated residence time for set-3Minimum temperature during depyrogenation hold period for set-1Maximum temperature during depyrogenation hold period for set-1Maximum temperature variation across the probes in any row during Depyrogenation hold period for set-1Minimum temperature during depyrogenation hold period for set-2Maximum temperature during depyrogenation hold period for set-2Maximum temperature variation across the probes in any row during
Page 21 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mmDepyrogenation hold period for set-2Minimum temperature during depyrogenation hold period for set-3Maximum temperature during depyrogenation hold period for set-3Maximum temperature variation across the probes in any row during Depyrogenation hold period for set-3Maximum variation (± °C) of temperature from set point (330°C) in strip chartDone by sign/Date
Remarks if any:
Checked by : (Sign/Date)
Reviewed by :
(Sign/Date)
Page 22 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Page 23 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.8 Heat Penetration Study with Endotoxin Spiked Vials with increased set speed
13.8.1 Procedure:
Perform the one heat penetration run with endotoxin spiked vials by increasing 5% of set speed and followed same procedure as mentioned in 13.7.1.
13.8.2 Acceptance criteria :
Each temperature sensor of the row should be more than 300°C for minimum of 3 minutes (considered as residence time) during Depyrogenation period of each run.
The temperature variation across all sensors in any row shall not be more than 20°C at any stage in passage of load during calculated residence time.
Depyrogenation zone temperature during Depyrogenation period shall be at 330 ± 6°C and the same shall be confirmed through strip chart to ensure the equipment functionality.
Minimum 3- log reduction should be achieved for endotoxin spiked vials.
Page 24 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.8.3 Result:
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
Date of cycle
Cycle Start Time
Cycle End Time
Actual conveyor speed
Increased set conveyor speed
Observed conveyor speed (max)
Depyrogenation hold start time for set -1
Depyrogenation hold end time for set-1
Page 25 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
Calculated residence time for set-1
Depyrogenation hold start time for set -2
Depyrogenation hold end time for set-2
Calculated residence time for set-2
Depyrogenation hold start time for set -3
Depyrogenation hold end time for set-3
Calculated residence time for set-3
Minimum temperature during depyrogenation hold period for set-1Maximum temperature during
Page 26 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
depyrogenation hold period for set-1Maximum temperature variation across the probes in any row during Depyrogenation hold period for set-1Minimum temperature during depyrogenation hold period for set-2Maximum temperature during depyrogenation hold period for set-2Maximum temperature variation across the probes in any row during Depyrogenation hold period for set-2Minimum temperature during depyrogenation hold period for set-3Maximum temperature during depyrogenation hold period for set-3Maximum temperature variation across
Page 27 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Parameters Observations
ResultsContainer details
vial size 2 mL 3mL 5 mL 10 mL 20 mL 30 mL
Neck Size 13 mm 13 mm 20 mm 20 mm 20 mm 20 mm
the probes in any row during Depyrogenation hold period for set-3Maximum variation (± °C) of temperature from set point (330°C) in strip chartDone by sign/Date
Remarks if any:
Checked by : (Sign/Date)
Reviewed by :
(Sign/Date)
Note-1: If 1 probe gets opened during depyrogenation consider remaining 11 sensors data. At least 11 sensors should be functional throughout the cycle to consider it satisfactorily.
Page 28 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
13.9 Physical observation of vials during heat penetration study:
13.9.1 Procedure:
Physical observation of the containers shall be done by viewing through the glass window of the tunnel (cool zone) for following parameters.
Movement of the vial, tilting of vial on conveyor, breakage of the vial, charring of the vial.
13.9.2 Acceptance criteria & Results:
S.No.Parameters / Acceptance criteria
Observation
2 mL 3mL 5mL 10mL 20mL 30mL
1
Vial should move on the conveyor belt in erect condition. No vial should be tilted
2No breakage of vials should be observed
3
No charring spot should be observed on the surface of the vials
4Observed by sign /date
Remarks if any:
Checked by Sign/Date :
Reviewed by
Sign/Date :
Page 29 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
14 QUALIFICATION TESTS & RESULTS:
S. No. Test Item/ StageReference
Document No.Acceptance Criteria Results
Sign & Date
1. Measurement of Air flow velocity
SOP # FU4-QA-GEN-040
Refer point no.13.1.2
2.Differential pressure test
SOP # FU4-QA-GEN-040
Refer point no.13.2.2
3. Filter integrity / Leakage test
SOP # FU4-QA-GEN-040
Refer point no.13.3.2
4.Air flow pattern test
SOP # FU4-QA-GEN-040
Refer point no.13.4.2
5.Non viable particle
SOP # FU4-QA-GEN-040
Refer point no.13.5.2
6. Verification of conveyor speed
SOP # FU4-QA-GEN-040
Refer point no.13.6.2
7. Heat penetration study with Endotoxin spiked
SOP # FU4-QA-GEN-040
Refer point no.13.7.2
Page 30 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
S. No. Test Item/ StageReference
Document No.Acceptance Criteria Results
Sign & Date
vials
8.Heat penetration study with Endotoxin spiked vials with increased set speed
NA Refer point no.13.8.2
9.Physical observation of vials during Heat penetration study
SOP # FU4-QA-GEN-040
Refer point no.13.9.2
Page 31 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
15 REQUALIFICATION CRITERIA
15.1 Scheduled re-qualification:
Heat Penetration and Endotoxin challenge trials shall be done as part of a time-related re-qualification programme for every tunnel.
Re-qualification shall be performed once in six months at minimum.
One heat penetration with endotoxin challenge trail shall be done on every process specification / container size combination on each tunnel at least once per 2-years.
Where HEPA filter in situ integrity testing in the hot zone of LAF tunnels is required to be done twice per year at approximately 6 month intervals.
15.2 Unscheduled re-qualification:
Any modification in the depyrogenation process parameters or any major maintenance of equipment which has impact on depyrogenation, shall be properly investigated. Based on out come of the investigation results requalification shall be performed.
Introduction of any new container (specifications/source) shall be qualified, based on the impact assessment on the depyrogenation efficiency.
16 DETAILS OF DISCREPANCIES:
Description Notification
Ref. No.Proposed/ Performed
Corrective ActionsRecorded By
(Sign and Date)
Impact on Qualification/ Further Actions to be taken (if any):
Reviewed By (User):(Sign and Date)
Approved By (QA):(Sign and Date)
Page 32 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
17 SUMMARY/ CONCLUSION:
Prepared by: Reviewed by:
Page 33 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
Sign/Date : Sign/Date :
18 REFERENCES:
SOP # FU4-QA-GEN-040 - Qualification/ Re-Qualification of Depyrogenation Tunnel
SOP # FU4-PR-MF-OPI-002 - Cleaning and Operation of Depyrogenating Tunnel (Make-IMA).
SOP # FU4-EN-OPI-007- Operation of digital temperature data logger.
SOP # FU4-QC-MIC-GEN-029 - Handling and Maintenance of Endotoxin Indicators
19 ANNEXURES:
S. No. Title/ Description of Annexure No. of Pages
Page 34 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307
TITLE : RE QUALIFICATION PROTOCOL
REFERENCE SOP : FU4-QA-GEN-035/ FU4-QA-FORM-120-1
Protocol No.:10072-02 Equipment No.: PN/TUNNL-001
20 POST APPROVAL:
Name Designation Department Signature/ Date
Executed by
Reviewed by
Approved by
Page 35 of 35
Formulations Unit-IV, AUROBINDO PHARMA LIMITED, Plot No’s - 4, 34 to 48, EPIP, IP-Pashamylaram, Medak(Dist.), Hyderabad – 502307