11 december 2008 energynetworks.org 1 common methodology group work presented by george moran,...

9
11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN , CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation from Workstream 2 Development of the distribution reinforcement model 11 December 2008

Upload: reynard-miller

Post on 14-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

11 December 2008 energynetworks.org •1

Common Methodology Group Work

PRESENTED BY GEORGE MORAN , CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2

Presentation from Workstream 2

Development of the distribution

reinforcement model11 December 2008

Page 2: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 2

Scope

Workstream 2 have the responsibility for:• Producing an overall timetable for the development of a

charging model that can be adopted by the DNO’s;• Supporting and advising the consultants that have to deliver

the suite of charging models that cover the full spectrum of charges for all voltage levels, by the end of January 2009;

• Ensuring that the model is cognisant of decisions coming out of workstream 3 (tariff structures); and

• Identifying any issues with the proposed implementation and to provide alternative solutions.

ToR from: http://2008.energynetworks.org/structure-of-charges/

Page 3: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 3

Deliverables

Workstream 2 have the responsibility for:• Identifying the main differences between DNO’s existing

charging models to assist with the development of a common DRM model;

• Producing a process map detailing an overview of the model functionality;

• Developing spreadsheets which capture the requirements of the common methodology set out in Ofgem’s October decision document; and

• Documentation of the methodology.

Page 4: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 4

Areas under consideration

DRM

Network Costs (500MW model)

DRM strawman

Operational Costs (Opex)

IDNO’s

Revenue Reconciliation Scaling (Fixed Adder)

Allocation of costs for availability charges

Tariff structures

Reactive power charges

EHV Modelling

Time of day and time of year cost

signals

Generation charges

Load & coincidence factor

template

Split of allowed revenue

EHV sole use asset template

Connection boundary

Cost matrices

Page 5: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 5

Progress

• DRM strawman• A strawman based on the most recently updated DRM model has been

chosen as the basis for illustrating the concepts and principles for the modelling.

• The model has then been updated to better reflect different aspects of Ofgem’s decision letter.

• The consultant will interact with DNOs to select the most desirable charging principles.

• Reactive power charges• A sheet calculating reactive charges based on the ENW approach has been

included in the strawman, although how the weighting factors (or “step 7 in ENW’s methodology) are to be applied is still to be resolved.

Page 6: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 6

Progress

• DG yardsticks • DG yardsticks have been added to the strawman, based on the DNO’s current

interpretation of the decision document and the use of F-factors rather than coincidence factors (see presentation on Cost and Benefit to DG).

• Areas still to be resolved include whether benefits at the level of connection should be counted; the choice of F-factors per technology type and the final tariff structure.

• Coincidence factor template• A template (separate from the strawman) has been prepared to allow companies to

calculate the coincidence factor per yardstick group at time of system peak and the associated load factor.

• An alternative method to use the coincidence factors and load factors based on the use of DECs and peaking probabilities is being developed as a possible alternative or as a possible complimentary approach for STOD costing.

Page 7: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 7

Progress

• Time of day and time of year cost signals • The group has compiled the current approached used by all companies.

• A template has been presented to allocate costs on a day/night split basis and an alternative proposal has been offered that could include an allocation based on the time of year.

• Further work is being is been undertaken to understand if the use of the G3 DECs as another potential solution in this area.

• 500MW model• One DNO has presented its 500MW model, for others to use it as a template for

presenting their own.

• Discussions are still ongoing as to whether the charging model should include the replacement of services as well as reinforcement.

• It should be noted that this model excludes that part of the network whose costs are recovered normally through the connection charge.

Page 8: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 8

Progress

• Allocation of costs for availability charges • The group has compiled the current approaches used by all companies and looked at

previous (academic and industry) reports on how to allocate the costs for availability charges. A decision is still to be reached.

• Split of allowed revenue• The group received two worked examples on how the EHV/HV-LV split of the allowed

revenue should be done (on the basis of MEAV) and will look at alternatives. This is still to be incorporated in the model.

Page 9: 11 December 2008 energynetworks.org 1 Common Methodology Group Work PRESENTED BY GEORGE MORAN, CENTRAL NETWORKS, ON BEHALF OF WORKSTREAM 2 Presentation

December 11, 2008 energynetworks.org 9

Future areas of work

• Calculation of forecast O&M costs

• IDNO charges

• EHV sole use asset charges

• Representation of the network and tariff yardsticks as “cost-matrices”

• Allocation of scaling, as £/kVA or £/kW, into the customer/tariff yardsticks

• Incorporation of the tariff and tariff components, as specified by WS3

• Minimum cost connection/Service models - discuss the possibility of having a generic network model representing HV and LV service assets. This will assist in the calculation of some cost elements of the fixed charge