11 october 2006basic layout of ler g. de rijk1 basic layout of ler the basic idea vlhc type...
TRANSCRIPT
11 October 2006
Basic Layout of LER G. de Rijk 1
Basic Layout of LERBasic Layout of LER
The basic ideaThe basic idea VLHC type magnetsVLHC type magnets LER in the LHC tunnelLER in the LHC tunnel LayoutLayout LER experiment bypass and injection schemeLER experiment bypass and injection scheme SPS-LER-LHC injection sequenceSPS-LER-LHC injection sequence
11 October 2006
Basic Layout of LER G. de Rijk 2
The basic ideaThe basic idea LER is a two beam machineLER is a two beam machine Two-in-one superferric combined function magnets Two-in-one superferric combined function magnets Inject beam from SPS into LER Inject beam from SPS into LER Accumulate and shape the two beams in LERAccumulate and shape the two beams in LER Accelerate from 0.45 TeV up to 1.5 TeVAccelerate from 0.45 TeV up to 1.5 TeV Transfer the two beam simultaneously in a single Transfer the two beam simultaneously in a single
turn transfer into the LHCturn transfer into the LHCSo:So: Beam coasting time in LHC at injection energy Beam coasting time in LHC at injection energy
(0.45 TeV) is reduced to the minimum (~10 ms)(0.45 TeV) is reduced to the minimum (~10 ms) Starting at 1.5 TeV the LHC can ramp fasterStarting at 1.5 TeV the LHC can ramp faster Beam is coasting at 0.45 TeV in LER in a “clean” Beam is coasting at 0.45 TeV in LER in a “clean”
machingmaching
11 October 2006
Basic Layout of LER G. de Rijk 3
Pre-accelerator LERPre-accelerator LER Pre-accelerator of Pre-accelerator of
0.45 TeV => 1 TeV-0.45 TeV => 1 TeV-1.5 TeV in the LHC 1.5 TeV in the LHC tunnel.tunnel.
Ring of small Ring of small transverse transverse dimensions dimensions
Cheap magnetsCheap magnets
Using VLHC Using VLHC ‘pipetron’ magnets.‘pipetron’ magnets.
11 October 2006
Basic Layout of LER G. de Rijk 4
Pipetron - VLHC magnets Pipetron - VLHC magnets FNALFNAL
0.45 TeV injection at 0.48 T0.45 TeV injection at 0.48 T 1.5 TeV top at 1.595 T 1.5 TeV top at 1.595 T
(72kA)(72kA) Gradient ~ 3%Gradient ~ 3% Enlarged magnet aperture Enlarged magnet aperture
v 28 mm x h 40 mmv 28 mm x h 40 mm
VLHC
LER
H. Piekarz et al.
11 October 2006
Basic Layout of LER G. de Rijk 5
Pipetron - VLHC magnets Pipetron - VLHC magnets FNALFNAL
1 m prototype tested at 1 m prototype tested at FNALFNAL
Reported at MT19Reported at MT19
H. Piekarz et al.
11 October 2006
Basic Layout of LER G. de Rijk 6
Feasibility study - Feasibility study - tunnel spacetunnel space
Fits above the LHC ring at a Fits above the LHC ring at a 1.35 m beam-to-beam 1.35 m beam-to-beam vertical distancevertical distance
(some cabling exceptions in (some cabling exceptions in straight sections)straight sections)
11 October 2006
Basic Layout of LER G. de Rijk 7
Feasibility study - Feasibility study - tunnel spacetunnel space
11 October 2006
Basic Layout of LER G. de Rijk 8
Feasibility study - Feasibility study - tunnel spacetunnel space
11 October 2006
Basic Layout of LER G. de Rijk 9
Layout (1)Layout (1) Arc cells match the LHC cell lengthArc cells match the LHC cell length 4 Combined function magnets (12 m) per half cell 4 Combined function magnets (12 m) per half cell
Bmax 1.595 T, G = ± 4.969 T/mBmax 1.595 T, G = ± 4.969 T/m Dispersion suppressor with combined function Dispersion suppressor with combined function
magnets (8 m).magnets (8 m). Short straight sections with corrector magnets are Short straight sections with corrector magnets are
similar to those for VLHCsimilar to those for VLHC Straight sections have 4 m long quadsStraight sections have 4 m long quads Low beta insertion is common with the LHCLow beta insertion is common with the LHC
talk by J. Johnstone FNALtalk by J. Johnstone FNAL
11 October 2006
Basic Layout of LER G. de Rijk 10
The challenge: Experiment The challenge: Experiment bypassesbypasses
There are:There are:
2 large (ATLAS & 2 large (ATLAS & CMS) CMS)
2 less big (ALICE & 2 less big (ALICE & LHCb) LHCb)
experiments to experiments to bypassbypass
For this study we For this study we assume that after assume that after an upgrade only an upgrade only ATLAS and CMS ATLAS and CMS will remainwill remain
11 October 2006
Basic Layout of LER G. de Rijk 11
Experiment bypass optionsExperiment bypass options1.1. Bypass the experiments in a tunnelBypass the experiments in a tunnel
typically be at least 2 x 300 long Digging a bypass requires to empty the main tunnel at the
junctions An extra shaft is probably needed for each bypass At least a year shutdown Very costly: >20 MCHF per tunnel Remark: the optics could be very problematic
2.2. Bypass the experiments through the detectorsBypass the experiments through the detectors Drilling a hole through the detectors is probably a very bad idea There is a hybrid option with (1) passing in between the muon
chambers : to be studied later Remark: the optics could be very problematic
3.3. Bypass the experiments through the LHC beampipeBypass the experiments through the LHC beampipe Bump beam down (and back up) into beam experimental beam
pipe Study concentrates on this option
11 October 2006
Basic Layout of LER G. de Rijk 12
Injection / bypass schemeInjection / bypass scheme
Use existing Use existing injection injection channelchannel
Fast switched Fast switched transfer lines transfer lines in IP1 and IP5in IP1 and IP5
RF, dump and RF, dump and cleaning cleaning separate from separate from LHCLHC
11 October 2006
Basic Layout of LER G. de Rijk 13
Injection / bypass scheme (2)Injection / bypass scheme (2)
Beam train of 89 Beam train of 89 s + gap of 3 s + gap of 3 ss To inject in LHC switch Fast Switching Dipole off during 3 To inject in LHC switch Fast Switching Dipole off during 3 s gaps gap The following FSD go off in sequence when the gap passesThe following FSD go off in sequence when the gap passes
LER ops:LER ops:D and FSD onD and FSD on
LHC ops:LHC ops:D and FSD offD and FSD off
11 October 2006
Basic Layout of LER G. de Rijk 14
Transfer between LER and Transfer between LER and LHC (1)LHC (1)
Horizontal separation 150 ==> 0 mmHorizontal separation 150 ==> 0 mm Vertical separation 1350 ==> 0 mmVertical separation 1350 ==> 0 mm
- One set of fast One set of fast switched dipoles switched dipoles only at the LHC only at the LHC side of a transfer side of a transfer lineline
- horizonal bend 2 horizonal bend 2 is made by tilting is made by tilting the vertical bends the vertical bends
Talks: J. Johnstone and H. Piekarz
11 October 2006
Basic Layout of LER G. de Rijk 15
Transfer between LER and Transfer between LER and LHC (2)LHC (2)
Talks: J. Johnstone and H. Piekarz
11 October 2006
Basic Layout of LER G. de Rijk 16
Timing sequenceTiming sequence Injection plateau of ~ 400 sInjection plateau of ~ 400 s Ramp up time from 0.45 TeV to 1.5 TeV is 300 s.Ramp up time from 0.45 TeV to 1.5 TeV is 300 s. Fast Pulsed Dipoles ramp down in 3 Fast Pulsed Dipoles ramp down in 3 ss
11 October 2006
Basic Layout of LER G. de Rijk 17
Timing sequenceTiming sequence Neighbouring fast switching magnets switch off at Neighbouring fast switching magnets switch off at
different timesdifferent times Timing sequencing and magnetic decoupling of Timing sequencing and magnetic decoupling of
FSDs are importantFSDs are important
11 October 2006
Basic Layout of LER G. de Rijk 18
Machine set-up optionMachine set-up option
After an LHC dump:After an LHC dump: If the low beta insertions can be ramped down fast Then LER can setup while the LHC main magnets are still
ramping down
11 October 2006
Basic Layout of LER G. de Rijk 19
Conclusing remarksConclusing remarks LER fits into the LHC arcs (with ease).LER fits into the LHC arcs (with ease). The main two-in-one superferric combined function The main two-in-one superferric combined function
magnets are of an existing technologymagnets are of an existing technology The bypass through the experimental beam pipe is The bypass through the experimental beam pipe is
possible.possible. Dipole magnets which can be switched off fast, are Dipole magnets which can be switched off fast, are
crucial.crucial. LER is a dedicated injector for the LHC.LER is a dedicated injector for the LHC. A future application is LER as DLHC injectorA future application is LER as DLHC injector