11 policies bilingual

216
7/30/2019 11 Policies Bilingual http://slidepdf.com/reader/full/11-policies-bilingual 1/216 Organization and Management Fadwa Bawazir, CPHQ Director, TQM Dept. Hera General Hospital

Upload: tahat22

Post on 14-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 1/216

Organization and

Management

Fadwa Bawazir, CPHQ

Director, TQM Dept.

Hera General Hospital

Page 2: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 2/216

Objectives

To understand theeffect of organizationand management ondaily operations

To link O&M to thedevelopment of policies andprocedures

Discussion is within thescope of hospitals.

 

    

Page 3: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 3/216

Introduction

Hospitals are corporateentities

Hospitals include

supporting elements,such as

income,

operating expenses,

politics,

reporting levels,

and vast interactions withthe public, patients,employees, and physicians.

 .

 :

 

 

 / 

Page 4: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 4/216

Regulatory and

competitivepressures arerequiring hospitalsand other healthcare

providers to examine their

organizationalstructures, and

to realign thosestructures to enablethem to competeflexibly.

 

:

 

 

Page 5: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 5/216

Key Issues

Health transition

Medical Technology

Consumer

expectations andquality of care

Demographic andepidemiologicalpressures

 

 

 

 

Page 6: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 6/216

Key Issues

New innovations

Informationsuperhighway

Organization of services aroundspecialized expertise

 

 

Page 7: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 7/216

Shift from inpatient today care facilities

Changing patterns of care

Reallocation of spaceto meet changingneeds

 

 

 

Page 8: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 8/216

Many modernorganizations arefunctional and

hierarchical; theysuffer from isolateddepartments, poorcoordination, andlimited lateralcommunication.

 

Page 9: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 9/216

To eliminateinefficiencies work

processes should beredesigned

Process improvement =

Process management 

 /

  .

 

Page 10: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 10/216

Operational andadministrativeprocesses shareseveral

characteristics. Both involve

sequences of linked,interdependent

activities that togethertransform inputs intooutputs.

 

 

.

Page 11: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 11/216

Both have beginningsand ends, withboundaries that canbe defined with

reasonable precisionand minimal overlap.

And both havecustomers, who may

be internal or externalto the organization.

 

 

()

Page 12: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 12/216

Typically, operational processes producegoods and services thatexternal customers

consume,

while administrative processes generate

information and plansthat internal groups use.

 

 

Page 13: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 13/216

 

Both must be aligned and

mutually supportive if theorganization is tofunction effectively

 

Page 14: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 14/216

the need to redesignprocesses is to

improve quality,

cut costs, reduce cycle times, or

otherwise enhanceoperating

performance

 :

 

 

 

Page 15: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 15/216

To govern thoseadministrative andoperational processes

Policies andprocedures are

developed 

 

Page 16: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 16/216

Accreditation bodies

require that policies

are:

Documented  Approved

Communicated/educated

Implemented

 :

/

Page 17: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 17/216

 Types of Policies

Philosophical 

Code of Ethics

Mission Vision

Organizational values

Code of Conduct

Dress Code

Communication culture

Page 18: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 18/216

 Types of Policies

Resources Deployment

Allocation of resources:

Manpower: staff distribution Equipment

Space

Financial

Page 19: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 19/216

 Types of Policies

Working /Departmental/Multidisciplinary policies

Processes Guidelines

Daily work/ services 

Page 20: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 20/216

 Types of Policies

Administrative 

General Rules and regulations

Leaves, personnel processes Smoking policy

Security policies

Staff development

TQM policies

Page 21: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 21/216

 Types of Policies

Memo policies

Management notification,

general distribution,

delegation of authority

Self Operation ProgramDirector - Dr.Talal Karima

M di l Ad i i t ti

Page 22: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 22/216

Director Dr.Talal Karima

Medical Director 

DR. Waleed Hussain

Anesthesia

Dr. Somya Mansoor 

Dermatology

Dr. Mohamad Fatane

Emergency

Dr. Belal Mostafa

ICU

Dr. Khaled Hakim

Pediatrics & NICU

DR. Mohamad Basamad

Medicine

Dr. Samih Chakalli

Ophthalmology

Dr. Amna Falata

OB/GYN

Dr. Samih Emam

Medical

Departments

Clinical

Ancillaries

Pharmacy

Dr. Azza Shaban

Laboratory

Dr. Ahmad Ashshi

Radiology

Dr.Bothyna Abd Alshakoor 

Clinical Dietary

Mrs.Marie Eden Agot

OPD

Mr. Abdulrhman Linga 

Infection Control

Dr. Sayed Bukhari

CSSD

Ms. Liza Baylon

Public Health

Dr. Mohd. Anas Nashwati

Physiotherapy

Dr. Ayman Aboalftooh

TQM

Ms. Fadwa Bawazer

Nursing Services

Mrs. Sharifa Zeannat Ali

Nursing Education

Social Services

Mr.Adel Aljmaan

Surgery

Dr. Omar Abohmdan

Business Center (SMCC)

Dr. W aleed Hussain

Public Relations &Health

Education

Mr. Zohair Melibari

Training (PG&CMEC)

Mrs. Manal Karima

ENT Unit

Dr. Mahmoud Alshora

Dental

Dr. Mohamad Samy

Neurology Unit

Dr. Mousa Mejally

Endoscopy Unit

Dr. Ayman Ghaith

Medical Administration Organization Structure 2005

Cardiology Unit

Dr. Salwa Ghuneim

ECG Unit

I.V.F

Dr. Mohamad Khan

 Approved

 __________________ 

Dr. Waleed Hussain

Medical Director 

Nursing Admin

Mr. Hussein Chenini

Health Educators

Ms. Wessam Ramzy

Pediatrics & NICU

Ms. Emma De Villa

ICU

Ms. Cherry Ofelia Manigo

Emergency

Ms. Balqees Sultana

Male Medical Ward

Mr. Sherawin Culajara

Female Medical Ward

Mrs. Mariama Jayan

Female Surgical Ward

Mrs. Rosalina Y Parraguirre

Male Surgical Ward

Mrs. Emma de Villa

Operating Room

Mrs. Ofelia Liedo

Obstetrics and Gunecology

Ms. Disy Lao Nashrie

SMCC

Ms. Huda Othman

Out-Patient DepartmentMs. Marian Duque

Ms. Norma Mendez

Ms. Erlinda Duncombe

Ms. Asela Bea

Endoscopy

Ms. Sharifa Rohani Barazar 

Page 23: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 23/216

 All processes and activities

in the hospital should be

guided by policies and

procedures inline with theorganizational structures

 

Page 24: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 24/216

 Why do we need Policies and

Procedures?

To make systems work

Consistently

Continuously

Uniformed manner 

 

 

Page 25: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 25/216

 Why do we need P&P?

To protect the staff 

To ensure patient safety

To ensure competency

To establish systems

 

  

Page 26: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 26/216

Hera General Hospital PolicyManagement System

Page 27: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 27/216

Purpose

To define and outline the policyand procedure development and

up keep system.

 

Page 28: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 28/216

Policy:

the rules and regulations.

Definitions 

Procedures:

are the steps to be

followed inimplementing certain

policy.

:

 

:

 

Page 29: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 29/216

Policy

1.  All policy and procedures of Hera

General Hospital will be governed by

the rules and regulations outlined in this

policy.

Page 30: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 30/216

2 . All departments should establish and

develop their policies and procedure togovern their functions and activities

according to their scope of services.

Policy

 / 

Page 31: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 31/216

3 . All policies and procedures should notcontradict with the government rules and

regulations and MOH policies and procedures.

Page 32: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 32/216

Policy

4. According to theapproved formatpolicies andprocedures should

include thefollowing headings:

:

Page 33: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 33/216

KING FAISAL SPECIALIST

HOSPITAL

AND RESEARCH CENTER  INTERNAL POLICY AND/OR PROCEDURE (IPP) 

TITLE/DESCRIPTION : 

MORTALITY AND MORBIDITY REVIEW

APPROVED

BY : 

ISSUE DATE: 

JUNE 2000

POLICY NUMBER: 

QM 004

APPLIES TO: 

QUALITY

MANAGEMENT

Page 34: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 34/216

APP  ADMINISTRATIVE POLICY AND/OR PROCEDURE 

NUMBER: PR 001 TITLE: Handling and Processing patient complaints 

PUBLICATION

DATE: January 2001 

EFFECTIVE

DATE: To:  All Hospital staff 

Chief of Medical staff 

Patient Relations/Executives on duty 

Clinical Review Analysts 

Page 35: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 35/216

SUBJ

ECT:

 ADMISSION FOR OUTPATIENT

SURGICAL

REFERENCE

#1005

PROCEDURE PAGE: 1

DEPARTMENT: OUTPATIENT SURGERY OF: 3

EFFECTIVE:

 APPROVED BY: REVISED:

Medical Consultant Network

Page 36: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 36/216

4.1 Department Name

4.2 Index Number 

4.3 Date Issued:4.4 Replaces Policy

No:

4.5 Effective Date:

4.6 Pages: _x_ of _y__ 4.7 Title/Description:

4.8 Applies To:

4/14/2

4/3

4/4 4/5

4/6 __  ____ 

4/74/8

Page 37: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 37/216

 

4.9 Statement of Purpose:

4.10 Definitions:

4.11 Policy: 

4.12 Procedure:

4.13 Equipments andforms

4.14 Responsibilities4.15 References

4/9 /

4/10

 4/114/12

4/13

4/14 4/15

Page 38: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 38/216

5. All items mentioned in the

policy should benumbered as follows:

1.1

1.1.1

1.1.21.2

1.2.1

1.2.2

2.1

2.1.1

:

 1/1

 1/1/1

1/2

 1/2/1

 1/2/2

 

Page 39: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 39/216

Page 40: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 40/216

 

   / 

 

  

 

Page 41: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 41/216

6. The headingsand the footageshould becompleted in

every page of the policy.

Page 42: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 42/216

7. Any revisions which arerecommended for the policyshould follow the samepattern of authority.

Page 43: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 43/216

8. All policies andprocedures aresubject for

review everytwo (2) yearsand revised asneeded.

 

Page 44: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 44/216

9. To ensuremultidisciplinaryapproach to theservices provided

in the hospital, allpolicies shall bereviewed by amulti-disciplinary

team.

 (

 ) 

.

Page 45: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 45/216

An essential reviewingbody is the Policy andProcedure ReviewCommittee.

Other standing committees shallreview policies

pertinent to theirscope.

 

 

Page 46: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 46/216

 

Policies that are

reviewed by astanding committeedo not requirereview and approval

of the Policy andProcedure ReviewCommittee.

 

Page 47: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 47/216

flow charts are developed to show allthe steps in a process;

the process is then made moreefficient by eliminating multipleapprovals and checkpoints,

Page 48: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 48/216

finding opportunities to reduce waitingtime,

smoothing the hand-offs betweendepartments, and

grouping related tasks andresponsibilities

Page 49: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 49/216

PROCEDURE

1. Department Head/Supervisor should review the existing policyand procedures and identifyfunctions carried out in thedepartment/service

Page 50: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 50/216

PROCEDURE

2. Department Head and/or Employee:

2.1 Identify the need for policy

2.2 Identify involved people/ department in the

implementation of policy.

 /:

2/1 

2/2/ 

Page 51: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 51/216

2.3 Contact Total Quality Management Dept. (or 

the organizations’ office in charge of the P&P 

system) to verify the existence of the policy.2.4 Draft the policy in cooperation with the

involved staff/section/ department.

PROCEDURE

2/3 

2/4  /

 / 

Page 52: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 52/216

2.5 Forward policy draft to the Policy and Procedure

Review Committee

2.6 Policy and Procedure Review Committee reviews

the policy and procedure and forwards comments

and recommends corrections to the initiating

department.

PROCEDURE 

2/5 (

 )

2/6 

Page 53: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 53/216

PROCEDURE

2.7 Department carries out the recommended

changes.

2.8 Policies and Procedures are forwarded toPolicy and Procedure Review Committee for 

final review and approval.

 

 

Page 54: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 54/216

2.9 Policies andProcedures isforwarded to theTQM Dept. fornumbering and

circulated togoverningauthorities forapproval.

Page 55: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 55/216

2.10 Policies and Procedures is

communicated to the department

responsible for implementation.2.11 In-service training and education is

organized for the staff.

 

 

Page 56: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 56/216

3. Numbering System:

3.1 The numbering system for the policies andprocedures is an alpha numeric oneconsisting of 6 digits, 3 letters followed bythree numbers.

 /:

 3/1 

Page 57: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 57/216

3. Numbering System:

3.2 Eachdepartment/unit willbe designated threeletters to reflect itsname as well as ablock of numbersfrom 001 to 999. 

3/2 001999

 

Page 58: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 58/216

Departments  Assigned Acronyms 

Hospital Administration   APP 

Total Quality Management  TQM 

Infection Control  ICS Management of Information  MIS 

Education and Training  ETD 

Public Relations  PRD 

Numbering System:

Numbering System:

Page 59: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 59/216

Medical Services  MDS 

Internal Medicine  IMD 

Intensive Care  ICU 

Emergency Dept.  EMD 

Surgery  SUD 

OB/Gyne  OBG 

Pediatrics  PED Nursery  NIC 

 Anesthesia   ANE 

Dental  DEN 

Ophthalmology  OPH Neurology  NEU 

ENT  ENT 

Nursing  NSG 

Numbering System:

Page 60: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 60/216

Administrative Affairs   AAP 

Recruitment  REC 

Personnel Services  PER 

Finance Services  FIN 

Legal Affairs  LEG 

Government Relations  GOV 

Religious Affairs  REL 

Numbering System:

Numbering System:

Page 61: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 61/216

Ancillary Clinical Services   ACS 

Physiotherapy  PHY 

Radiology  RAD 

Pharmacy  PHA 

Endoscopy  END 

Public Health  PUB 

Clinical Dietary  DIT Laboratory  LAB 

Medical Supplies  MSP 

Medical Records  MRD 

Medical Coordination  MCD 

Patient Affairs  PAD 

Medical Reports  MRP 

Social Services  SOC 

 Admissions and Discharge   AND 

Numbering System:

Page 62: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 62/216

Support Services  SUP 

Maintenance  MAN Biomedical  BMD 

Security  SEC 

Safety  SAF 

Housekeeping  HKS 

Laundry  LAU 

Food Services  FDS 

Housing  HSG 

Transportation TRP 

Property Control  PCL 

Central Supplies & Sterilization  SSD 

Numbering System:

Page 63: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 63/216

8. Approvals

8.1. The one who prepared the policy

should sign. If prepared by a

group then an additional

approval sheet is attached to thepolicy with the signature of all

members of the group. The

leader of the group signs on

every page of the policy.

8/1 . 

.

 .

 

Page 64: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 64/216

8. Approvals

8.2. Interdepartmental policies

should be reviewed and

singed by all departmentheads concerned.

 - - 

Page 65: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 65/216

8. Approvals

8.3. All policies and procedures are reviewed and signed by

the Total Quality Management Department

8.4. All policies and procedures should be approved by the

following division heads as applicable and their official

stamp affixed as appropriate

 

 

Page 66: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 66/216

9.1. Minimum of two (2)

weeks between the

date of issue and the

date of effect shall

be given for 

orientation and in-service training

 

Policy Implementation 

Page 67: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 67/216

9.2. Implementation

process involves a

period of three (3)

months to give time

for distribution,

familiarization, actual practice and

monitoring

 

 /

 

Policy Implementation 

Page 68: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 68/216

9.3. All the hospital staff shallsign in the

 Acknowledgement Sheet

to signify that they have

read and understood thePolicies and Procedures

(Hospital Wide,

Departmental, Safety,

Infection Control, etc.).

Original Copy filed as

page 3 in the Manual kept

in every department

 

)...

 

 

Policy Implementation 

Acknowledgement Sheet

Page 69: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 69/216

g

KINGDOM OF SAUDI ARABIA 

Ministry of Health 

Directorate of Health Affairs 

Holy Makkah 

HOSPITALWIDE POLICIES AND PROCEDURE STAFF ACKNOWLEDGEMENT SHEET

I, the undersigned, have read and understood the contents of this Hospital-wide Policy and Procedure Manual.

NAME  ID NO.  SIGNATURE  DATE 

Note: Original Copy in the Hospital Wide Policies and Procedure Manual.Duplicate Copy to be forwarded to the Total Quality Management

(TQM) Department.

Page 70: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 70/216

Policy Termination

10.1. Policies should be

terminated when cancelled

by a later policy

10.2. A policy may beterminated by authority of 

the Program Director 

   /  

Page 71: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 71/216

RESPONSIBILITY 

1. It is the responsibility of each Department

Head to develop policy and procedure within

their scope of service

2. The Department Head shall cooperate and

coordinate inter-related departmental

policies.

 

 .

Page 72: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 72/216

RESPONSIBILITY 

3. TQM Department isresponsible to provideassistance to the

departments to developtheir policy andprocedures.

Page 73: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 73/216

4. TQM Department

is responsible for the upkeep andmonitoring of thepolicy and

proceduressystem of thedepartment.

Page 74: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 74/216

EQUIPMENTS AND FORMS

1. Policy and Procedure Form

2. Acknowledgement Sheet

3. Policy Review Sheet4. Policy Revision Sheet

Page 75: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 75/216

Thank you

Page 76: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 76/216

Practical ProjectManagement

October 2006

Page 77: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 77/216

77

Overview 

Introduction to Project Management Project Management Context Integration Management Scope Management Time Management Cost Management Quality Management

Human Resource Management Communications Management Risk Management Procurement Management

Module 1: Introduction to Project

Page 78: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 78/216

78

j

Management 

Objectives 

Define what project is and describe projectmanagement

Understand the history of projectmanagement

Understand the growing need for betterproject management

Discuss key elements of the projectmanagement framework

Discuss recent trends in project

management research and software

Page 79: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 79/216

79

Project Management Defined

Project management is the application of knowledge, skills, tools, and techniques toproject activities in order to meet projectrequirements

A project is a temporary endeavorundertaken to achieve a particular aim.Project management knowledge and

practices are best described in terms of their component processes

Page 80: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 80/216

80

History of Project Management

Some people argue that building theEgyptian pyramids was a project, as wasbuilding the Great Wall of China

Most people consider the ManhattanProject to be the first project to use “modern” project management 

This three-year, $2 billion (in 1946

dollars) project had a separate projectmanager and a technical manager

Page 81: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 81/216

81

Project Management Framework 

A set of processes, tools and templates,designed to be used together to manage aproject through its lifecycle

Page 82: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 82/216

82

Define your project  

Select a real-life project

Define the project

Discuss within group

Select spokesperson Share with the rest

Page 83: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 83/216

83

Recent Trends in Research and Software

7 Actions for Success: broaden views,communicate in 3D, political operative,assert yourself, be flexible, & sharpensocial skills

Five major challenges of today: globalteams, moving parts, development,partners, and project portfolios

Five levels of excellence: Level 1 is ad-

hoc, (2) planned, (3) managed, (4)integrated, and (5) sustained

Software: Microsoft Project

Page 84: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 84/216

84

Develop a framework  

Briefly outline your PM framework usingthe real-life project previously described.

Module 2: The Project Management

Page 85: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 85/216

85

j g

Context

Objectives  Understand the systems view of project

management Explain the differences among functional, matrix,

and project organizational structures Explain why stakeholder management and top

management commitment are critical for aproject’s success

Understand the initiation, planning, execution,and closure phases of the project life cycle

Understand effective project initiation, planning,execution, control, and closing

Distinguish between project development andproduct development

Discuss the unique attributes and diverse natureof information technology projects

Page 86: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 86/216

86

Systems View 

Systems philosophy: View things assystems, interacting components workingwithin an environment to fulfill some purpose

Systems analysis: problem-solving approach

Systems management: Address business,technological, and organizational issues beforemaking changes to systems

Page 87: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 87/216

87

Formal Organizational Frames

Structural frame: Focuses on roles andresponsibilities, coordination, and control.Organization charts help define this frame.

Human resources frame: Focuses onproviding harmony between needs of theorganization and needs of people.

Political frame: Assumes organizations

are coalitions composed of variedindividuals and interest groups. Conflictand power are key issues. 

Symbolic frame: Focuses on symbols

Page 88: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 88/216

88

Organizational Structures

Page 89: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 89/216

89

Organizational Structures

Stakeholder and Top Management

Page 90: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 90/216

90

Commitment

Top management can help projectmanagers:

Secure adequate resources.

Get approval for unique project needs in atimely manner.

Receive cooperation from peoplethroughout the organization.

Learn how to be better leaders.

Page 91: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 91/216

91

Project Life Cycle Phases

Project Development vs Product 

Page 92: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 92/216

92

Development  

Discuss the similarities and differences of project development versus productdevelopment within your specific career. 5minutes. Share with your peers.

Page 93: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 93/216

93

What makes a good project manager? 

Discuss the skills and characteristicsneeded to be a good and successfulproject manager. 10 minutes. Share withthe rest of your peers.

Module 3: Project Integration

Page 94: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 94/216

94

Management

Objectives  Describe an overall framework for project

integration management as it relates to the otherproject management knowledge areas and theproject life cycle

Understand the integrated change controlprocess, planning for and managing changes, andusing a change control system

Explain tools and techniques to assist in project

plan execution of integrated projects such asGantt Charts, S-Curves, and PERTs

Explain project plan execution, its relationship toproject planning, the factors related to successfulresults

Page 95: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 95/216

95

Project Integration Management

Project Plan Development: taking theresults of other planning processes andputting them into a consistent, coherentdocument—the project plan

Project Plan Execution: carrying out theproject plan

Integrated Change Control: coordinating

changes across the entire project

Page 96: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 96/216

96

Integrated Change Control

Integrated change control involvesidentifying, evaluating, and managingchanges throughout the project life cycle

Three main objectives of change control: Influence the factors that create

changes to ensure they arebeneficial

Determine that a change hasoccurred

Manage actual changes when and

Page 97: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 97/216

97

 Tools and Techniques

Page 98: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 98/216

98

 Tools and Techniques

Page 99: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 99/216

99

 Tools and Techniques

Page 100: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 100/216

100

 Tools and Techniques

Importance of Project  Planning the 

Page 101: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 101/216

101

Execution  

Discuss the reason and importance of preparing a plan before executing it usingcases specific to your area of responsibility. 10 minutes. Share withyour peers.

S k h ld A l i

Page 102: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 102/216

102

Stakeholder Analysis

Documents important (often sensitive)information about stakeholders such as

stakeholders’ names and organizations 

roles on the project

unique facts about stakeholders

level of influence and interest in the project

suggestions for managing relationships

Identify, Prioritize, Understand

S k h ld A l i

Page 103: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 103/216

103

Stakeholder Analysis

conduct a brief stakeholder analysis categorize their relation and advocating of 

the project

Module 4: Project Scope

Page 104: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 104/216

104

Management

Objectives  Describe the strategic planning process,

apply different project selection methods,such as a net present value analysis, a

weighted scoring model, and a balancedscorecard, and understand the importanceof creating a project charter

Explain the scope planning process and

contents of a scope statement Discuss the scope definition process and

construct a work breakdown structure

Understand the importance of scope

S i Pl i P

Page 105: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 105/216

105

Strategic Planning Process

S i Pl i P

Page 106: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 106/216

106

Strategic Planning Process

Scope Planning and Definition

Page 107: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 107/216

107

Processes

Scope planning: Deciding how the scopewill be defined, verified, and controlled.

Scope definition: Reviewing the project

charter and preliminary scope statementand adding more information asrequirements are developed and changerequests are approved.

S S

Page 108: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 108/216

108

Scope Statement  

In your group, place the initial project tobe managed in the Scope Statementformat. 10 minutes. Share with the rest of your peers.

W k B kd S (WBS)

Page 109: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 109/216

109

Work Breakdown Structure (WBS )  

Using the same project as before andbuilding on previous activities, develop aWBS chart with your group. 10 minutes.Share with the rest of your peers.

B i P i i l f C i WBS

Page 110: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 110/216

110

Basic Principles for Creating WBSs

1. A unit of work should appear at only one place in the WBS.2. The work content of a WBS item is the sum of the WBSitems below it.

3. A WBS item is the responsibility of only one individual, eventhough many people may be working on it.

4. The WBS must be consistent with the way in which work is

actually going to be performed; it should serve the projectteam first and other purposes only if practical.5. Project team members should be involved in developing the

WBS to ensure consistency and buy-in.6. Each WBS item must be documented to ensure accurate

understanding of the scope of work included and not

included in that item.7. The WBS must be a flexible tool to accommodate inevitable

changes while properly maintaining control of the workcontent in the project according to the scope statement.

Scope Verification and Scope ChangeC l

Page 111: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 111/216

111

Control

Suggestions for Reducing Incomplete and ChangingRequirements 

Develop and follow a requirements managementprocess.

Use techniques such as prototyping, use casemodeling.

Put requirements in writing and keep themcurrent.

Create a requirements management database for

documenting and controlling requirements. Conduct adequate testing throughout the project

life cycle.

Review changes from a systems perspective.

Emphasize completion dates to help focus on

Module 5: Project Time

M

Page 112: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 112/216

112

Management 

Objectives  Understand the importance of project schedules

and good project time management Define activities as the basis for developing

project schedules

Explain how various tools and techniques helpproject managers perform activity durationestimating and schedule development

Understand and use critical path analysis andcritical chain scheduling

Describe how to use several techniques forshortening project schedules

Use a Gantt chart for schedule planning andtracking schedule information

Discuss how reality checks and people issues are

involved in controlling and managing changes to

S h d l d Ti M

Page 113: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 113/216

113

Schedules and Time Management

Activity definition: Identifying the specific activities thatthe project team members and stakeholders must performto produce the project deliverables. 

Activity sequencing: Identifying and documenting therelationships between project activities. 

Activity resource estimating: Estimating how many

resources a project team should use to perform projectactivities.  Activity duration estimating: Estimating the number of 

work periods that are needed to complete individualactivities. 

Schedule development: Analyzing activity sequences,

activity resource estimates, and activity duration estimatesto create the project schedule.  Schedule control: Controlling and managing changes to

the project schedule.

S h d li d Ti M

Page 114: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 114/216

114

Scheduling and Time Management  

Why are project schedules important?What sort of schedule conflicts could withexpect in your specific project? 10minutes. Share with the rest of yourpeers.

A ti it D ti E ti ti

Page 115: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 115/216

115

 Activity Duration Estimating 

After defining activities and determiningtheir sequence, the next step in timemanagement is duration estimating

Duration includes the actual amount of 

time worked on an activity plus elapsedtime

Effort is the number of workdays or workhours required to complete a task. Effort

does not equal duration People doing the work should help create

estimates, and an expert should reviewthem

S h d l D l pm t

Page 116: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 116/216

116

Schedule Development

Schedule development uses results of theother time management processes todetermine the start and end date of theproject and its activities

Ultimate goal is to create a realisticproject schedule that provides a basis formonitoring project progress for the timedimension of the project

Important tools and techniques includeGantt charts, PERT analysis, critical pathanalysis, and critical chain scheduling

Criti l P th Meth d

Page 117: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 117/216

117

Critical Path Method

CPM is a project network analysistechnique used to predict total projectduration

A critical path for a project is the series of activities that determines the earliest time by which the project can be completed

The critical path is the longest path 

through the network diagram and has theleast amount of slack or float

Finding the Critical Path

Page 118: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 118/216

118

Finding the Critical Path

First develop a good project networkdiagram

Add the durations for all activities on eachpath through the project network diagram

The longest path is the critical path

Schedule Trade offs

Page 119: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 119/216

119

Schedule Trade-offs

Shorten a Project Schedule

Page 120: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 120/216

120

Shorten a Project Schedule

Overlapped

Tasks or fast

tracking

Shortened

duration thru

crashing

Originalschedule

Critical Chain Scheduling

Page 121: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 121/216

121

Critical Chain Scheduling 

Critical chain scheduling is a method of scheduling that takes limited resourcesinto account when creating a projectschedule and includes buffers to protect

the project completion date

Critical chain scheduling assumesresources do not multitask because it

often delays task completions andincreases total durations

Example of Critical Chain Scheduling

Page 122: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 122/216

122

Example of Critical Chain Scheduling 

Scheduling using PERT

Page 123: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 123/216

123

Scheduling using PERT

PERT weighted average formula: optimistic time + 4X most likely time + pessimistic time

6

Example:

PERT weighted average =

8 workdays + 4 X 10 workdays + 24 workdays = 12 days6

where 8 = optimistic time, 10 = most likely time, and 24 =pessimistic time

Scheduling

Page 124: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 124/216

124

Scheduling  

Develop a schedule for your project usingsome of the tools presented thus far.There is no rule against combiningtechniques. If fact, pulling the best from

each may be advantageous. 15 minutes.Share with the rest of your peers.

Controlling and Managing Change

Page 125: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 125/216

125

Controlling and Managing Change

Review the draft schedule or estimatedcompletion date in the project charter.

Prepare a more detailed schedule with theproject team.

Make sure the schedule is realistic andfollowed.

Alert top management well in advance if 

there are schedule problems.

Managing Change

Page 126: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 126/216

126

Managing Change  

Using the recently created schedules,assess their reality. What things havebeen adjusted to the schedule to helpmanage change? 10 minutes. Share with

peers.

Module 6: Project Cost Management

Page 127: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 127/216

127

Module 6: Project Cost Management 

Objectives  Explain basic project cost management

principles, concepts, and terms

Understand the importance of good

project cost management Explain cost estimating using definitive,

budgetary, and rough order of magnitude(ROM) estimates

Understand the processes involved in costbudgeting and preparing a cost estimate

Understand the benefits of earned value

management and project portfolio

Cost management

Page 128: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 128/216

128

Cost management

Resource planning: determining whatresources and quantities of them shouldbe used

Cost estimating: developing an estimateof the costs and resources needed tocomplete a project

Cost budgeting: allocating the overall cost

estimate to individual work items toestablish a baseline for measuringperformance

Cost control: controlling changes to the

Cost Management

Page 129: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 129/216

129

Cost Management  

Why is good cost management important?Why bother with it?

Methods of Cost Estimating

Page 130: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 130/216

130

Methods of Cost Estimating 

Earned Value Management

Page 131: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 131/216

131

Earned Value Management

Earned Value - Planned Costs = ScheduleVariance (SV)

Earned Value - Actual Costs = CostVariance (CV)

Cost Control

Page 132: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 132/216

132

Cost Control

Project cost control includes monitoring cost performance

ensuring that only appropriate project changesare included in a revised cost baseline

informing project stakeholders of authorizedchanges to the project that will affect costs

Earned value management is an importanttool for cost control

Project Portfolio Management

Page 133: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 133/216

133

Project Portfolio Management

Five levels for project portfoliomanagement

Put all your projects in one database

Prioritize the projects in your database

Divide your projects into two or three budgetsbased on type of investment

Automate the repository

Apply modern portfolio theory, including risk-return tools that map project risk on a curve

Cost Plan View

Page 134: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 134/216

134

Cost Plan View 

Module 7: Project Quality

Management

Page 135: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 135/216

135

Management

Objectives  Define project quality management

Describe quality planning and itsrelationship to project scope management

Discuss the importance of qualityassurance

Understand the importance of projectquality management

List the three outputs of the qualitycontrol process

Understand the tools and techniques for

quality control such as Pareto analysis

Quality Management Program

Page 136: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 136/216

136

Quality Management Program

Quality management planning andimplementing policies, procedures, andrequirements.

Quality control ensuring that work is being

performed and that work is being checkedprior to its acceptance.

Quality assurance verifying that qualitycontrol tasks are being performed.

Continuous quality improvementcontinually pursuing improvement in thequality of the project process.

Quality costs redoing a project item even

'

Quality Planning and Quality Assurance

Page 137: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 137/216

137

Quality Planning and Quality Assurance

Quality Definitions Quality Materials

Quality Events

 Importance of Quality Management  

Discuss the importance of qualitymanagement and assurance. How maythey vary from project to project?

 Tools and Techniques for Quality Control

Page 138: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 138/216

138

Control

Pareto Analysis Steps to identify the important causes using

Pareto analysis  Step 1: Form a table listing the causes and their 

frequency as a percentage . 

Step 2 : Arrange the rows in the decreasing order of importance of the causes i.e. the most important cause first  

Step 3: Add a cumulative percentage column tothe table 

Step 4: Plot with causes on x- and cumulative percentage on y-axis 

Step 5 : Join the above points to form a curve 

Step 6 : Draw line at 80% on y-axis parallel to x-axis. Then drop the line at the point of 

intersection with the curve on x-axis This point

Pareto Analysis Sample

Page 139: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 139/216

139

Pareto Analysis Sample

Six Sigma

Page 140: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 140/216

140

Six Sigma

It requires an organization-widecommitment

Six Sigma organizations have the abilityand willingness to adopt contraryobjectives, like reducing errors andgetting things done faster

It is an operating philosophy that is

customer-focused and strives to drive outwaste, raise levels of quality, and improvefinancial performance at breakthrough levels

Six Sigma

Page 141: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 141/216

141

Six Sigma

Quality Control Chart

Page 142: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 142/216

142

Quality Control Chart

 Testing 

Page 143: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 143/216

143

Test g

Unit test Integration testing

System testing

A test plan is simply a high-level summaryof the areas (functionality, elements,regions, etc.)

Quality Control Plan  

Page 144: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 144/216

144

Q y

What sort of tools would you use and whatwill you be looking for when assessingquality in a project?

Module 8: Project Human Resource

Management

Page 145: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 145/216

145

g

Objectives  Discuss the importance of good human resource

management on projects Summarize key concepts for managing people by

understanding the theories of Abraham Maslow, FrederickHerzberg, David McClelland, and Douglas McGregor onmotivation, H. J. Thamhain and D. L. Wilemon oninfluencing workers, and Stephen Covey on how people andteams can become more effective

Discuss organizational planning and be able to create aproject organizational chart, responsibility assignmentmatrix, and resource histogram

Understand important issues involved in project staff acquisition and explain the concepts of resourceassignments, resource loading, and resource leveling

Assist in team development with training, team-buildingactivities, and reward systems

Project Human Resources

Page 146: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 146/216

146

j

Human resource planning: Identifyingand documenting project roles,responsibilities, and reportingrelationships. 

Acquiring the project team: Getting theneeded personnel assigned to and workingon the project. 

Developing the project team: Building

individual and group skills to enhanceproject performance. 

Managing the project team: Trackingteam member performance, motivating

team members rovidin timel

Keys to Managing People

Page 147: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 147/216

147

y g g p

Psychologists and management theoristshave devoted much research and thoughtto the field of managing people at work

Important areas related to projectmanagement include

motivation (intrinsic and extrinsic)

influence and power

effectiveness

 Abraham Maslow on Motivation

Page 148: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 148/216

148

Herzberg’s Motivational and Hygiene

Factors

Page 149: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 149/216

149

McClelland’s Acquired-Needs

Page 150: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 150/216

150

q

Achievement: People with a high needfor achievement seek to excel and thustend to avoid both low-risk and high-risksituations . 

Affiliation: Those with a high need foraffiliation need harmonious relationshipswith other people and need to feel

accepted by other people. 

Power: A person's need for power can beone of two types - personal andinstitutional . 

McGregor’s Theory X and Theory Y  

Page 151: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 151/216

151

g y y

 Thamhain and Wilemon’s Ways to Have

Influence on Projects

Page 152: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 152/216

152

j

1. Authority: the legitimate hierarchical right toissue orders2. Assignment: the project manager's perceived

ability to influence a worker's later workassignments

3. Budget: the project manager's perceived abilityto authorize others' use of discretionary funds4. Promotion: the ability to improve a worker's

position5. Money: the ability to increase a worker's pay and

benefits6. Penalty: the project manager's ability to causepunishment

7. Work challenge: the ability to assign work thatcapitalizes on a worker's enjoyment of doing a

particular task

Improving Effectiveness - Covey’s 7Habits

Page 153: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 153/216

153

Project managers can apply Covey’s 7habits to improve effectiveness onprojects

Be proactive

Begin with the end in mind

Put first things first

Think win/win

Seek first to understand, then to beunderstood

Synergize

Sharpen the saw

Creating a Motivating Environment 

Page 154: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 154/216

154

g g

Discuss various instances where you havebeen motivated and where you havemotivated others. Try to associate it toone or more of the principles discussed in

this module.

Organizational Planning 

Page 155: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 155/216

155

g g

Organizational planning involvesidentifying, documenting, andassigning project roles,

responsibilities, and reportingrelationships

Outputs and processes include

project organizational chartswork definition and assignment

process

responsibility assignment matrixes

Project Organizational Charts

Page 156: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 156/216

156

j g

 Work Definition and AssignmentProcess

Page 157: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 157/216

157

Responsibility Assignment Matrix

Page 158: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 158/216

158

p y g

Resource Histogram

Page 159: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 159/216

159

g

Project Staff Acquisition

Page 160: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 160/216

160

Staffing plans and good hiring proceduresare important in staff acquisition, as areincentives for recruiting and retention

Research shows that people leave their jobs because they don’t make adifference, don’t get proper recognition,

aren’t learning anything new, don’t liketheir coworkers, and want to earn moremoney

Resource Loading and Leveling 

Page 161: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 161/216

161

Resource loading refers to the amount of individual resources an existing projectschedule requires during specific timeperiods

Resource leveling is a technique forresolving resource conflicts by delaying

tasks. The main purpose of resourceleveling is to create a smootherdistribution of resource usage and reduceoverallocation

 Team Development Activities

Page 162: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 162/216

162

Different types of people

Page 163: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 163/216

163

Meyers-Briggs Type Indicator (MBTI) Extrovert/Introvert (E/I)

Sensation/Intuition (S/N)

Thinking/Feeling (T/F)

Judgment/Perception (J/P) Social Styles Profile

Drivers

Expressives

Analyticals Amiables

General Advice on Teams

Page 164: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 164/216

164

Be patient and kind with your team. Fix the problem instead of blaming people.

Establish regular, effective meetings.

Allow time for teams to go through the basicteam-building stages.

Limit the size of work teams to three to sevenmembers.

Plan some social activities to help project teammembers and other stakeholders get to know

each other better. Stress team identity.

Nurture team members and encourage them tohelp each other.

Take additional actions to work with virtual team

Module 9: Project

Communications Mgmt 

Page 165: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 165/216

165

g

Objectives  Understand the importance of goodcommunication on projects and describe themajor components of a communicationsmanagement plan

Discuss the elements of project communicationsplanning, including information distribution,performance reporting, and administrativeclosure

Discuss various methods for project informationdistribution and the advantages anddisadvantages of each

List various methods for improving projectcommunications, such as managing conflicts,running effective meetings, using e-maileffectively, and using templates

Communications Management Plan

Page 166: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 166/216

166

A description of a collection and filingstructure for gathering and storing varioustypes of information

A distribution structure describing what

information goes to whom, when, and how A format for communicating key project

information

A project schedule for producing the

information Access methods for obtaining the

information

A method for updating the

Project Communications ManagementProcesses

Page 167: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 167/216

167

Communications planning: determiningthe information and communicationsneeds of the stakeholders

Information distribution: making needed

information available in a timely manner Performance reporting: collecting and

disseminating performance information

Administrative closure: generating,

gathering, and disseminating informationto formalize phase or project completion

Communications Planning 

Page 168: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 168/216

168

Information Distribution

Page 169: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 169/216

169

Getting the right information to the rightpeople at the right time and in a usefulformat is just as important as developingthe information in the first place

Important considerations include using technology to enhance information

distribution

formal and informal methods for distributinginformation

Information Distribution  

Page 170: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 170/216

170

Discuss various methods for projectinformation distribution and theadvantages and disadvantages of each.

Media Choice Table

Page 171: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 171/216

171

Performance Reporting 

Page 172: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 172/216

172

Performance reporting keeps stakeholdersinformed about how resources are beingused to achieve project objectives

Status reports describe where the project

stands at a specific point in time Progress reports describe what the project

team has accomplished during a certain periodof time

Project forecasting predicts future projectstatus and progress based on past informationand trends

Status review meetings often include

erformance re ortin

 Administrative Closure

Page 173: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 173/216

173

A project or phase of a project requiresclosure

Administrative closure produces

project archives

formal acceptance

lessons learned

Suggestions for Improving ProjectCommunications

Page 174: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 174/216

174

Manage conflicts effectively Develop better communication skills

Run effective meetings

Use e-mail effectively Use templates for project communications

Conflict Handling Modes, in Preference

Order

Page 175: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 175/216

175

Confrontation or problem-solving: directlyface a conflict

Compromise: use a give-and-takeapproach

Smoothing: de-emphasize areas of differences and emphasize areas of agreement

Forcing: the win-lose approach Withdrawal: retreat or withdraw from an

actual or potential disagreement

Running Effective Meetings

Page 176: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 176/216

176

Determine if a meeting can be avoided Define the purpose and intended outcome

of the meeting

Determine who should attend the meeting

Provide an agenda to participants beforethe meeting

Prepare handouts, visual aids, and makelogistical arrangements ahead of time

Run the meeting professionally

Build relationships

Using E-Mail Effectively Tips

Page 177: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 177/216

177

Ensure it is an appropriate medium forwhat you want to communicate Be sure to send the e-mail to the right

people Use meaningful subjects Limit the content to one main subject, and

be as clear and concise as possible Limit the number and size of attachments Delete e-mail you don’t need, and don’t

open it if you question the source Make sure your virus software is up to

date Respond to and file e-mails quickly

Using Templates for ProjectCommunications

Page 178: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 178/216

178

Many people are afraid to ask for help Providing examples and templates for

project communications saves time andmoney

Organizations can develop their owntemplates, use some provided by outsideorganizations, or use samples from

textbooks Recall that research shows that companies

that excel in project management makeeffective use of templates

Communication Channels  

Page 179: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 179/216

179

Discuss various individual communicationneeds and how to determine the numberof communications channels.

Module 10: Project Risk Management

Page 180: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 180/216

180

Objectives  Understand what risk is and the importance of 

good project risk management Discuss the elements involved in risk

management planning

Describe the risk identification process and toolsand techniques to help identify project risks Discuss the qualitative risk analysis process and

explain how to calculate risk factors, useprobability/impact matrixes, the Top Ten RiskItem Tracking technique, and expert judgment torank risks

Explain the quantify risk analysis process andhow to use decision trees and simulation toquantitative risks

Discuss what is involved in risk monitoring and

 The Importance of Project Risk Management

Page 181: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 181/216

181

Project risk management is the art andscience of identifying, assigning, andresponding to risk throughout the life of aproject and in the best interests of 

meeting project objectives Risk management is often overlooked on

projects, but it can help improve projectsuccess by helping select good projects,determining project scope, and developingrealistic estimates

Risk Management Planning 

Page 182: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 182/216

182

The main output of risk managementplanning is a risk management plan

The project team should review projectdocuments and understand the

organization’s and the sponsor’s approachto risk

The level of detail will vary with the needs

of the project

Risk Management Planning 

Page 183: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 183/216

183

Risk Identification

Page 184: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 184/216

184

Risk identification is the process of understanding what potentialunsatisfactory outcomes are associatedwith a particular project

Several risk identification tools andtechniques include Brainstorming

The Delphi technique

Interviewing SWOT analysis

Risk Identification

Page 185: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 185/216

185

 Activity – Identify Risks 

Page 186: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 186/216

186

Identify the risks using the project youhave been working on for each area of project management covered thus far.

Qualitative Risk Analysis

Page 187: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 187/216

187

A risk analysis assesses the likelihood andimpact of identified risks to determinetheir magnitude and priority. Riskquantification tools and techniques

include: Probability/Impact matrixes

The Top 10 Risk Item Tracking technique

Expert judgment

Probability/Impact Matrices 

Page 188: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 188/216

188

 Top 10 Risk Item Tracking 

Page 189: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 189/216

189

Quantitative Risk Analysis

Page 190: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 190/216

190

Often follows qualitative risk analysis, butboth can be done together or separately

Large, complex projects involving leadingedge technologies often require extensive

quantitative risk analysis

Main techniques include

Simulation

Decision tree analysis

Page 191: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 191/216

Decision Trees and Expected Monetary  Value (EMV)

Page 192: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 192/216

192

Risk Response Planning 

Page 193: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 193/216

193

Risk avoidance: eliminating a specificthreat or risk, usually by eliminating itscauses

Risk acceptance: accepting the

consequences should a risk occur Risk transference: shifting the

consequence of a risk and responsibilityfor its management to a third party

Risk mitigation: reducing the impact of arisk event by reducing the probability of its occurrence

Risk Monitoring and Control

Page 194: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 194/216

194

Monitoring risks involves knowing theirstatus

Controlling risks involves carrying out therisk management plans as risks occur

Workarounds are unplanned responses torisk events that must be done when thereare no contingency plans

The main outputs of risk monitoring andcontrol are corrective action, projectchange requests, and updates to otherplans

Good Project Risk Management

Page 195: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 195/216

195

Unlike crisis management, good projectrisk management often goes unnoticed

Well-run projects appear to be almosteffortless, but a lot of work goes into

running a project well Project managers should strive to make

their jobs look easy to reflect the results

of well-run projects

Module 11: Project ProcurementManagement

Obj ti

Page 196: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 196/216

196

Objectives  Understand the importance of project

procurement management and the increasing useof outsourcing for information technologyprojects

Describe the procurement planning process,procurement planning tools and techniques,types of contracts, and statements of work

Discuss what is involved in solicitation planningand the difference between a request for proposaland a request for quote

Explain what occurs during the solicitationprocess

Describe the source selection process anddifferent approaches for evaluating proposals orselecting suppliers

Procurement Management

Page 197: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 197/216

197

Procurement means acquiring goodsand/or services from an outside source.

We outsource for the following reasons:

To reduce both fixed and recurrent costs

To allow the client organization to focus on itscore business

To access skills and technologies

To provide flexibility

To increase accountability

Project Procurement ManagementProcesses

P t l i d t i i h t

Page 198: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 198/216

198

Procurement planning: determining whatto procure and when

Solicitation planning: documentingproduct requirements and identifyingpotential sources

Solicitation: obtaining quotations, bids,offers, or proposals as appropriate

Source selection: choosing from amongpotential vendors

Contract administration: managing therelationship with the vendor

Contract close-out: completion andsettlement of the contract

Project Procurement ManagementProcesses

Page 199: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 199/216

199

Procurement Planning 

Page 200: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 200/216

200

Procurement planning involves identifyingwhich project needs can be best met byusing products or services outside theorganization. It includes deciding

whether to procure how to procure

what to procure

how much to procure

when to procure

Make-or-buy analysisMake or Buy Example: Assume you can lease an item you

Page 201: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 201/216

201

Make or Buy Example: Assume you can lease an item you

need for a project for $150/day. To purchase the item, theinvestment cost is $1,000, and the daily cost would beanother $50/day. How long will it take for the lease cost tobe the same as the purchase cost? If you need the item for12 days, should you lease it or purchase it?

Set up an equation so the “make” is equal to the “buy.” In thisexample, use the following equation. Let d be the numberof days to use the item.

$150d = $1,000 + $50dSolve for d as follows:

Subtract $50d from the right side of the equation to

get$100d = $1,000

Divide both sides of the equation by $100d = 10 days

Th l t i th th h t t 10 d If

 Types of Contracts

Page 202: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 202/216

202

Fixed-price or lump-sum: involve afixed total price for a well-defined productor service 

Cost-reimbursable: involve payment to

the seller for direct and indirect costs  Time and material contracts: hybrid of 

both fixed-price and cost-reimbursable,

often used by consultants  Unit price contracts: require the buyer

to pay the seller a predetermined amountper unit of service

Cost Reimbursable Contracts

Page 203: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 203/216

203

Cost plus incentive fee (CPIF): thebuyer pays the seller for allowableperformance costs plus a predeterminedfee and an incentive bonus 

Cost plus fixed fee (CPFF): the buyerpays the seller for allowable performancecosts plus a fixed fee payment usuallybased on a percentage of estimated costs 

Cost plus percentage of costs (CPPC): the buyer pays the seller for allowableperformance costs plus a predetermined

Contract Types Versus Risk 

Page 204: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 204/216

204

Statement of Work 

Page 205: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 205/216

205

A statement of work is a description of thework required for the procurement

Many contracts, or mutually bindingagreements, include SOWs

A good SOW gives bidders a betterunderstanding of the buyer’s expectations 

Statement of Work 

Page 206: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 206/216

206

Solicitation planning 

Page 207: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 207/216

207

Solicitation planning involves preparingseveral documents:

Request for Proposals: used to solicitproposals from prospective sellers

Requests for Quotes: used to solicitquotes for well-defined procurements

Invitations for bid or negotiation and initial

contractor responses are also part of solicitation planning

Solicitation planning Outline for a Request for Proposal:

Page 208: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 208/216

208

Outline for a Request for Proposal:

I. Purpose of RFPII. Organization’s Background III. Basic RequirementsIV. Hardware and Software Environment

V. Description of RFP ProcessVI. Statement of Work and Schedule InformationVII. Possible Appendices

A. Current System OverviewB. System RequirementsC. Volume and Size DataD. Required Contents of Vendor’s

Response to RFPE. Sample Contract

Solicitation

Page 209: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 209/216

209

Solicitation involves obtaining proposals orbids from prospective sellers

Organizations can advertise to procuregoods and services in several ways

approaching the preferred vendor

approaching several potential vendors

advertising to anyone interested

A bidders’ conference can help clarify thebuyer’s expectations 

Source selection

Page 210: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 210/216

210

Source selection involves: evaluating bidders’ proposals 

choosing the best one

negotiating the contract

awarding the contract

It is helpful to prepare formal evaluation

procedures for selecting vendors. Buyersoften create a “short list.”  

Sample Proposal Evaluation Sheet

Page 211: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 211/216

211

Detailed Criteria for Selecting Suppliers

Page 212: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 212/216

212

Contract Administration

Page 213: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 213/216

213

Contract administration ensures that theseller’s performance meets contractualrequirements

Contracts are legal relationships, so it is

important that legal and contractingprofessionals be involved in writing andadministering contracts

Many project managers ignore contractualissues, which can result in seriousproblems

Suggestions on Change Control forContracts

Changes to any part of the project need to

Page 214: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 214/216

214

Changes to any part of the project need tobe reviewed, approved, and documentedby the same people in the same way thatthe original part of the plan was approved

Evaluation of any change should includean impact analysis. How will the changeaffect the scope, time, cost, and quality of the goods or services being provided?

Changes must be documented in writing.Project team members should alsodocument all important meetings andtelephone calls

Contract Close-out

Page 215: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 215/216

215

Contract close-out includes product verification to determine if all work

was completed correctly and satisfactorily

administrative activities to update records to

reflect final results archiving information for future use

Procurement audits identify lessonslearned in the procurement process

Review / Summary 

Page 216: 11 Policies Bilingual

7/30/2019 11 Policies Bilingual

http://slidepdf.com/reader/full/11-policies-bilingual 216/216