12 07 i 91 newsletter

Upload: owenfd

Post on 05-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 12 07 I 91 Newsletter

    1/4

    interchange19

    A public meeting was held in June 2010 to present information on all

    the improvement alternatives (10 build, plus a No Build, and a Trans-

    portation Demand Management (TDM) package) that were considered

    up until that point in time. The purpose of the meeting was to allow

    members of the local community to comment on all proposed consid-

    erations early in the study process (before decisions are made). After

    the meeting, the study team (with the PACs support) recommended

    that the following concepts move forward for further analysis: 13, 13A,

    13B, the No Build, and the TDM package.

    Working with the Project Advisory Committee, the project team began

    the effort of further developing and analyzing the alternatives that

    were still under consideration. However, just prior to the completion

    of the analysis phase, additional population and economic growth

    rate factors became available from the latest census. The project

    team, in consultation with the PAC, decided that these changes were

    signicant enough to warrant a reevaluation of the alternatives. While

    this was a small setback for the study (timing-wise), the project

    team and the PAC felt that it was more important to make decisions

    based on the latest data available. With this data, the project team

    reassessed the alternatives and added one additional alternative to

    be considered, Alternative 13C. For more information on this and the

    other alternatives, see page 2 of this newsletter.

    What has happened since thelast public meeting?

    Summer 2012

    Volume 2, Issue 1

    www.mass.gov/massdot/interchange19

    Study Background

    In Spring 2009, the Massachusetts Depart-

    ment of Transportation (MassDOT) began

    the process of studying the I-91 Exit 19

    Interchange area. The purpose of the study

    is to nd ways to improve trafc congestion

    in the I-91 Exit 19 area, particularly on Route

    9. The project includes a trafc and transit

    analysis, roadway design, environmental

    analysis, and an effort to seek community

    input. The nal product could be a completed

    highway design, a series of smaller recom-

    mended improvements, or a recommenda-

    tion to make no improvements.

    The study is being conducted by MassDOT

    and a consultant team. TranSystems is the

    lead rm of the consultant team and is sup-

    ported by McMahon Associates and Fitzger-

    ald & Halliday, Inc. In addition, a Project

    Advisory Committee (PAC) advises MassDOT

    on all major elements to be included in

    any improvement option pursued. The PACconsists of representatives from the Ward 3

    neighborhood, environmental interests, state

    legislature, local colleges and universities, re-

    gional planning and transit agencies, bicycle

    advocacy groups, MassDOT, and Federal

    Highway Administration, as well as from the

    municipalities of Northampton, Hadley, and

    Hateld. The PAC has met 10 times with the

    study team since November 2009.

    See page 2:

    Remaining Alternatives...

    at a Glance

  • 7/31/2019 12 07 I 91 Newsletter

    2/4

    Summer 2012interchange19

    2

    Study Schedule

    The Remaining AlternativesAt a Glance

    Data Collection &

    Existing Conditions Analysis

    Alternatives Development

    Alternatives Evaluation

    Alternatives Report

    Preparation

    Interchange Justication,Design & Structures Report

    Environmental Analysis

    Design

    Public Meetings

    Project Advisory Committee

    Meetings

    Newsletters/Fact Sheets

    Summer

    2009

    Fall

    2009

    Winter

    2009 -2010

    Spring

    2010

    Summer

    2010

    Fall

    2010

    Winter

    2010 - 2011

    Spring

    2011

    Summer

    2011

    Fall

    2011

    Winter

    2011 -2012

    Spring

    2012

    Summer

    2012

    Fall

    2012

    START

    START

    START

    There are currently 6 alternatives (called

    concepts) that are being considered for

    the I-91 Interchange 19 study area. The

    alternatives include a No Build, four

    build alternatives and one TDM pack-

    age alternatives. (Note: Alternatives

    are numbered in reference to the CT River

    Crossing Study (an earlier study) concepts,

    which included concepts at locations other

    than Interchange 19.

    No Build - consists of making no engi-

    neering improvements in the study area.

    Concept 13

    - includes lanewidening to the existing

    intersection and ramps.

    Specically, it includes

    adding an additional

    westbound left turn lane

    from Route 9 onto the I-91

    southbound on-ramp and

    an additional northbound

    through lane to Damon Road

    from the I-91 northbound

    off-ramp. The left turn lane

    onto I-91 southbound will

    be extended under the

    bridge by relocating sidewalk

    or replacing the overpass

    structures. Improvements

    are also made to the merges

    of the on- and off- ramps

    with the highway.

  • 7/31/2019 12 07 I 91 Newsletter

    3/4

    3

    Summer 2012 interchange19

    Concept 13A - converts

    the signalized intersection

    of Route 9 and Damon

    Road into a two- lane

    roundabout. It generally

    stays within the existing

    state highway layout. In

    addition, a second left-

    turn lane to enter the

    I-91 southbound on-ramp

    is added.

    Concept 13B includes

    two roundabouts along

    Route 9. It converts the

    Damon Road / Route 9

    signalized intersection

    into a roundabout and

    the Route 9 / I-91

    southbound on-ramp

    intersection into a

    roundabout.

    TDM Concept

    intended to reduce congestion in

    the study area by reducing vehicular

    trafc volume includes consideration

    of infrastructure as well as some

    operational improvements. Elements

    under consideration include more

    frequent bus service on Route 9,

    transit signal priority to speed buses

    through trafc signals, an employer-

    based universal pass system to

    offer deeply discounted bus fares

    beyond the academic community,

    enhanced bus shelters, and improved

    connections to and maintenance of the

    Norwottuck Rail Trail.

    Concept 13C converts only the

    Route 9 / I-91 southbound on-ramp

    intersection into a roundabout. At the

    I-91 Northbound Exit 19 off-ramp, it

    includes adding an additional westboundleft turn lane from Route 9 onto the I-91

    southbound on-ramp and an additional

    northbound through lane to Damon Road

    from the I-91 northbound off-ramp.

  • 7/31/2019 12 07 I 91 Newsletter

    4/4

    4

    One of the project teams main goals is to involve the public at the highest leveland make the study process as transparent as possible. Ways to get more infor-

    mation about the study and provide comments include:

    Visit the Project Website There is a project website for the I-91 Exit

    19 Interchange Study at www.mass.gov/massdot/interchange19. This

    website includes background information on the study as well as detailed

    information such as PAC and public meeting scheduling information and

    materials. In addition, you can submit written comments on the Contact

    Us page.

    Attend a Project Advisory Committee or Public Meeting This

    is a great place to learn more about the study through viewing andlistening to study update presentations. There is an opportunity for you to

    comment at all meetings, which are scheduled regularly throughout the

    study process. Meeting information is posted on the project website.

    Email Us You can email Bao Lang, of MassDOT, directly at

    [email protected] for more information or to express your concerns.

    A public meeting is scheduled for September 2012 to discuss the

    six alternatives under analysis. The meeting is an opportunityfor members of the community to learn about the most recent

    happenings in the study and remaining six alternatives, as well

    provide input on their desired outcome.

    The meeting, which will be Tuesday, September 18, 2012, will

    begin at 6:00 PM in the Bridge Street School Cafeteria. We hope

    to see you there!

    Summer 2012interchange19

    Public Meeting - Get Involved!

    Lookingformoreinfo

    rmation?

    Let us know what you think!